rancho cucamonga 2009-2014 implementation plan
DESCRIPTION
The Rancho Cucamonga Redevelopment Agency's Five-Year Implementation Plan (2009-2014) has been prepared to comply with Assembly Bill 1290, entitled the Community Redevelopment Law Reform Act of 1993, which took effect January 1, 1994, and Senate Bill 732, which was signed into law by the governor on September 26, 1994. The California Health and Safety Code Section 33490 requires redevelopment agencies to adopt an Implementation Plan to carry out the goals and objectives of the Redevelopment Plan.TRANSCRIPT
Five-Year Implementation Plan
2009-2014
RANCHO CUCAMONGA REDEVELOPMENT AGENCY
ADOPTED DECEMBER 2009
FIVE-YEAR IMPLEMENTATION PLAN
2
Rancho Cucamonga Redevelopment Agency
Board Members
Donald J. Kurth, M.D., Chairman
L. Dennis Michael, Vice-Chairman
Rex Gutierrez, Agency Member
Sam Spagnolo, Agency Member
Diane Williams, Agency Member
With Executive Staff
Jack Lam, AICP, Agency Executive Director Linda D. Daniels, Agency Deputy Director
FIVE-YEAR IMPLEMENTATION PLAN
3
Table of Contents
Introduction………………………………………………………………………………………………………………………………….. 5
The Redevelopment Agency……………………………………………………………………………………………………….9
The Environment – conditions prevalent at the time of plan adoption……………………………….. 11
Implementation Plan Goals ………………………..……………………………………………………………………………… 13
Agency Accomplishments
Capital Improvement Projects………………………………………………………………… 15
Economic Development and Enhancement Programs………………………. 17
Community/Cultural Facilities………………………………………………………………… 25
Affordable/Workforce Housing……………………………………………………………… 28
Ongoing and Potential Projects for 2009-2014
Capital Improvement Projects………………………………………………………………… 31
Economic Development and Enhancement Programs………………………. 40
Community/Cultural Facilities………………………………………………………………… 44
Affordable/Workforce Housing……………………………………………………………… 45
Housing Requirements……………………………………………………………………………………………………………….. 51
Housing Compliance…………………………………………………………………………………………………………………… 59
Conclusion……………………………………………………………………………………………………………………………………. 62
Comments…………………………………………………………………………………………………………………………………….. 63
Figures & Tables
Figure I. Redevelopment Project Area Map……………………….……………………………….. 10
Figure II. Percent of Community Under/Over 65……………………………………................53
Table I. ERAF Payments ……………………………….…………………………………………................ 7
Table II. Ongoing and Potential Capital Improvement Projects………………………..38
Table III. Ongoing and Potential Economic Development Programs………………..43
FIVE-YEAR IMPLEMENTATION PLAN
4
Table IV. Ongoing and Potential Community and Cultural Projects………….……..45
Table V. Ongoing and Potential Affordable Housing Projects ……………..……..…..49
Table VI. Affordable Housing Unit Summary……………………………………………….……….51
Table VII. 2006-2014 Regional Housing Needs Assessment…………………................ 52
Table VIII. Rancho Cucamonga Assessment 2009………………………………………………….52
Table IX. FY 2004-2005 Housing Fund Expenditures…..………………………………………54
Table X. FY 2005-2006 Housing Fund Expenditures……….………………….………………55
Table XI. FY 2006-2007 Housing Fund Expenditures……………………………………….. 56
Table XII. FY 2007-2008 Housing Fund Expenditures….………………….……………………57
Table XIII. FY 2008-2009 Housing Fund Expenditures….………………….……………………58
Table XIV. Housing Estimated Revenues and Expenditures 09-14..……………………..61
FIVE-YEAR IMPLEMENTATION PLAN
5
Introduction
I. Purpose of the Five-Year Implementation Plan
The Five-Year Implementation Plan is the Redevelopment Agency’s policy
statement as to the type of projects and programs it has completed and intends to
undertake over a five year period; this Implementation Plan will cover the period from
December 2009 to December 2014. It is prepared to assist the Agency in setting
priorities and allocating resources during this period for redevelopment activities within
and benefiting the redevelopment project area. The Implementation Plan includes an
explanation of how the goals, objectives, projects, programs and expenditures for the
next five years will promote revitalization, eliminate blight, foster economic
development/growth/sustainability and create affordable/workforce housing. The Plan
is a dynamic document thus adjustments can be made to reflect changing project
conditions or other factors to ensure positive outcomes.
II. Legislative Requirements
Assembly Bill 1290 and Senate Bill 732 were enacted by the California Legislature
in 1993 and 1994, respectively. These legislative acts were comprehensive reforms of
California Redevelopment Law (CRL) which established regulations requiring each
redevelopment agency to adopt an Implementation Plan no later than December 31,
1994 and to update the plan every five years. The Rancho Cucamonga Redevelopment
Agency has been and continues to be in compliance with these requirements. Each
Implementation Plan is required to contain the following four elements:
1. A description of the redevelopment agency’s goals and objectives, including housing related goals and objectives for the redevelopment project area.
2. A description of the programs and expenditures proposed for the next five
years. 3. An explanation of how these goals, objectives, programs and expenditures
will eliminate blight within the project area.
FIVE-YEAR IMPLEMENTATION PLAN
6
4. An explanation of how the housing-related goals, objectives, programs and expenditures, including the use of housing set-aside funds and an annual housing program, will implement State affordable housing requirements and replacement housing requirements.
III. The Implementation Plan Cycle
The City of Rancho Cucamonga adopted previous Implementation Plans and completed mid-cycle reviews as highlighted below:
• The Rancho Cucamonga Redevelopment Agency adopted the first Five-Year Implementation Plan in December 1994 covering the period from December 1994 to December 1999.
• A mid-cycle Review of the Plan was completed by the Agency in 1997.
• A second Five-Year Implementation Plan was adopted in December 1999 covering the period from December 1999 to December 2004.
• A mid-cycle review of the Plan was completed by the Agency in 2002.
• A third Five-Year Implementation Plan was adopted in December 2004 covering the period from December 2004 to December 2009.
• A mid-cycle review of the Plan was completed by the Agency in 2007.
• This is the fourth Five-Year Implementation Plan and it will cover the period from December 2009 to December 2014.
Agencies are required by Assembly Bill 315 to also prepare a detailed Housing
Production Plan as part of the Implementation Plan or Housing Element. The Planning
department generates the Housing Element and Housing Production Plan on behalf of
the Agency. The City revised the General Plan in 2001 and is currently in the process of
updating it and is scheduled to complete the process in 2010. The Housing Element
and Production Plan are in draft form and are schedule to be completed in 2010.
Prior to adoption of the Five-Year Implementation Plan by the Redevelopment
Agency, a public hearing must be conducted to gather public input. A public hearing
was duly noticed (published in the paper on November 25, December 2, and December
9 and posted at four locations within the project are) pursuant to the requirements of
Section 6063 of the Government Code, as required by Health and Safety Code Section
33490(d).
The Implementation Plan is intended to be a planning document only.
Redevelopment is a very fluid process, subject to a myriad of changing issues and
FIVE-YEAR IMPLEMENTATION PLAN
7
market dynamics; therefore, the law does not require an amendment to the
Implementation Plan to conform to every change. Recognizing that new opportunities
arise and markets change, during the mid-cycle review, which is required within three
years from adoption of the Plan, changes can be made if necessary.
Adoption of the Implementation Plan does not constitute approval of any specific
program, potential project, or estimated expenditure and does not commit the Agency
to complete or construct any identified projects or improvements. Any one of the
programs, potential projects or estimated expenditures identified may be eliminated by
the Redevelopment Agency upon subsequent study or review. Furthermore, identified
projects, programs and expenditures remain subject to review by any and all
discretionary bodies, including environmental review pursuant to California
Environmental Quality Act, Division 13, of the Public Resources Code.
IV Financial Impacts from the State of California
The financial impacts of the California Education Relief Augmentation Fund
(ERAF) have been negative to the Agency’s mission to remove blight and redevelop the
project area. The ERAF Fund was established by the State and requires Agencies
throughout the state to return tax increment revenues to a special fund to assist
California schools. Over the years, the Rancho Cucamonga Redevelopment Agency has
been required to make several ERAF payments to the State. The table below lists the
amounts and year that funds were “shifted” to the State.
Table I. Education Relief Augmentation Fund Payments
Although initially intended as an occasional take, the State continued to lean on
local jurisdictions without signs of ending the practice. In 2008, the State proposed and
Fiscal Year ERAF Payment 2002-2003 $1,161,173
2003-2004 $2,075,904
2004-2005 $3,971,929
2005-2006 $4,094,069
FIVE-YEAR IMPLEMENTATION PLAN
8
assessed another ERAF take, which was legally challenged by CRA on behalf of all
agencies. CRA prevailed and preserved $6.5 million of the Agency’s revenue.
In 2009, the State Legislature boldly sought to relieve the Sate budget crisis by
passing Assembly Bill X4-26, the State budget trailer bill which authorized a $2.05 billion
raid of local redevelopment funds. These funds will be given to education through a
Supplemental Education Relief Augmentation Fund (SERAF) account. The impact to the
Rancho Cucamonga Redevelopment Agency will be $32.1 million in FY2009-2010 and
$6.9 million in FY 2010-2011. A lawsuit has been filed in an attempt to void the illegal
“taking” of the funds, however, if the lawsuit is unsuccessful and the taking occurs, it will
severely impede the Agency’s ability to perform and complete many of the projects and
programs described in the Implementation Plan.
V Contents of the Implementation Plan
The Implementation Plan consists of the following sections:
Introduction
Overview of the Rancho Cucamonga Redevelopment Agency
Accomplishments during the previous periods
• Capital Improvement Projects • Economic Development and Enhance Programs • Community and Cultural Facilities • Housing Projects and Programs
Ongoing and Potential Projects/Expenditures for 2009-2014
• Capital Improvement Projects • Economic Development and Enhance Programs • Community and Cultural Facilities • Housing Projects and Programs
Housing Requirements
Housing Compliance
FIVE-YEAR IMPLEMENTATION PLAN
9
The Redevelopment Agency
Background
The Rancho Cucamonga Redevelopment Plan was adopted in 1981, and
amended three times; Plan Amendment #1 in 1987, which increased the Agency’s
bonding and tax increment capacity, Plan Amendment #2 in 2001, extending the
Agency's time limit as it relates to incurring debt and Plan Amendment #3 in 2002, for
reinstatement of the Agency's eminent domain authority for a specific portion of the
project area. The project area was created to ensure a healthy and growing economic
base and affordable housing for the citizens and businesses in Rancho Cucamonga by
eliminating blighting conditions that had become a deterrent to private investment. The
Redevelopment Project area includes approximately 8,500 acres of land generally
located in the central and southern portion of the City (see Figure #1, map of the project
area).
The Redevelopment Agency is a legal and public body, with powers and budget
separate from the City of Rancho Cucamonga. The five City council members serve as
the Redevelopment Agency board members. The City Manager and Deputy City
Manager serve as the Executive Director and Deputy Director, respectively. The Agency
plays a facilitating role, acting as a liaison between developers, businesspersons and
residents within the project area and the City. The Agency is proactive in seeking
desirable new development that will provide employment and revenue for the
community.
The Redevelopment Agency receives funding through tax increment revenue
generated from property tax revenues from assessments of properties located within the
project area. These revenues are based on the increased assessed valuation of those
properties, which occurred after 1981 (base year), the year the Redevelopment Plan was
adopted. Inclusion of property within the project area boundaries does not increase the
amount of tax assessed to the property. As properties are improved or sold, the property
tax valuation increase above the base year valuation is distributed to the Redevelopment
Agency and other eligible public agencies. The Agency uses these revenues to fund
projects and programs described in the Redevelopment Plan and further defined in the
FIVE-YEAR IMPLEMENTATION PLAN
10
Implementation Plan to promote and finance revitalization efforts, eliminate blight and
provide affordable housing. The Agency leverages redevelopment funds to revitalize
neighborhood and commercial areas of the City through bond financing and
cooperative partnerships with private and other public sectors.
Project Area Boundaries
Figure I. Redevelopment Project Area
Since its initial formation in 1981, the Redevelopment Agency has aggressively
coordinated efforts to eliminate blight in the City. Rancho Cucamonga's success in
attracting quality jobs, new commercial development and increasing the supply of safe,
affordable housing is the result of an active redevelopment program. Through the
Agency's assistance in the construction of major infrastructure improvements, the
FIVE-YEAR IMPLEMENTATION PLAN
11
economic strength of the project area has been enhanced. The Agency's assistance has
also resulted in the maintenance and development of high-quality affordable housing,
both for sale and rental.
The Five-Year Implementation Plan is intended to focus on the Redevelopment
Agency's programs, projects and resources over the next five years most beneficial to the
project area. Through the creative use of the tools and mechanisms provided by State
Law, the Redevelopment Agency will continue to coordinate public and private
investment to maximize benefits to the project area. As outlined by AB 1290 and SB 732
requirements, this report will consider the following:
Summary of the blighting conditions present at the time the Plan was
adopted.
Summary of Agency activities since the adoption of the Plan that have
eliminated some of the identified causes of the blight.
Summary of current conditions within the project area.
Statement of goals and objectives for programs targeted to remove blight.
Summary of anticipated programs and expenditures over the next five
years, and blight alleviated.
Summary of Agency activities to provide housing affordable to low- and
moderate-income citizens.
The Environment
Conditions at the Time of Plan Adoption
The selection of the Rancho Cucamonga Redevelopment project area was
generally based on a desire to eliminate the potential health and safety hazards within
the proposed project area caused by lack of public improvements, which are essential to
service anticipated growth. These deficiencies included a number of deterrents to
development, such as inadequate flood control channels and circulation system
throughout the project area, along with physical and economic blighting conditions,
FIVE-YEAR IMPLEMENTATION PLAN
12
such as deteriorated and substandard structures and the lack of safe, affordable housing.
The high cost associated with these improvements had deterred property owners from
developing and/or rehabilitating affected properties. Selection of the project area was
also based on the desire to revitalize the existing commercial uses along Foothill
Boulevard (a key commercial corridor), and to assist in rehabilitating residential sites
within the project area.
The Rancho Cucamonga Redevelopment Plan, the accompanying staff report,
and the Environmental Impact Report (EIR) originally submitted in support of the plan
adopted in 1981 and its subsequent amendments in 1987 (Plan Amendment #1), 2001
(Plan Amendment #2) and 2002 (Plan Amendment #3) identified existing blighting
influences in the project area. These blighting conditions specifically included:
1. Deteriorated and substandard structures;
2. Deterrents to development due to inadequate flood control improvements;
3. Incompatible and shifting of types of land uses;
4. Underutilized or vacancies along Foothill Boulevard, which are indicative
of economic underperformance of this area;
5. Lack of adequate or efficient circulation systems throughout the project
area;
6. Lack of adequate open/recreational space;
7. Lack of sufficient decent and safe affordable housing to meet the need of
the community's low- and moderate-income families;
8. Lack of adequate public safety facilities to service the project area.
FIVE-YEAR IMPLEMENTATION PLAN
13
Implementation Plan Goals
The Rancho Cucamonga Redevelopment Agency Implementation Plan provides a
description of programs that have been, and will be, used to alleviate blighting
conditions in the project area. Each of the Agency's activities is categorized under four
distinct areas: (1) Capital Improvements; (2) Economic Development and Enhancement
Programs; (3) Community and Cultural Facilities; and (4) Affordable/Workforce Housing.
The Agency has been very aggressive in establishing projects to further the goals
and objectives of the Redevelopment and Implementation Plans. The following
information provides an overview of blighting conditions that existed prior to adoption
of the Redevelopment Plan; an overview and description of the Agency's
accomplishments in addressing those conditions to date; and the projects or programs
that are planned over the next five-year period.
The Agency has also played a significant role in contributing to the development
of a citywide Healthy RC program. The primary emphasis of this program is the
promotion of a Healthy Mind, Body and Earth through the implementation of programs,
activities and projects that help educate the community on how to be healthier in every
aspect. The Healthy RC program is not solely for the individual, but is a philosophy for
its businesses and the City to follow as well. Visioning and leadership, fiscal stability, and
efficient use of its resources are a few prime examples of how Healthy RC is carried out
by the City. The Agency has contributed greatly to the overall health of the City by
enabling the development of capital improvements, promoting economic development
opportunities, assisting in constructing community and cultural facilities, and creating
quality workforce housing.
Capital Improvement Projects
Goal: To eliminate the physical blighting conditions of the project area and
address prevention of further blighting conditions through implementation of capital
improvement programs. These programs include, but are not limited to: the Foothill
Boulevard Implementation Plan, the Master Plan of Storm Drains, the Etiwanda/San
FIVE-YEAR IMPLEMENTATION PLAN
14
Sevaine/Day Creek drainage system, and the completion of the Master Plan of Fire
Facilities to provide adequate fire protection for the project area.
Economic Development and Enhancement Programs
Goal: The Agency’s efforts to enhance the commercial/industrial sector of the
City’s business community consist of a variety of programs designed to strengthen the
economic environment of the commercial/industrial sector of the project area through
a variety of programs geared towards existing businesses, attracting new businesses
and providing long-term employment to strengthen and compliment the economy of
the City.
Community and Cultural Facilities
Goal: The Rancho Cucamonga Redevelopment Plan identified a lack of adequate
open, recreational space, and community facilities as a blighting condition of the project
area. It is the intent of the Rancho Cucamonga’s Agency Board to promote and
encourage community and culture as one of the foundations for the City. A concerted
effort will be made to foster a sense of community. Culture inspired by the arts, theater
and libraries will also be a priority whenever possible.
Affordable/Workforce Housing Projects and Programs
Goal: The Rancho Cucamonga Redevelopment Plan identified a lack of sufficient
affordable housing to meet the needs of the community’s low- and moderate-income
families and established a goal to increase, improve and maintain the City’s supply of
affordable housing. Providing workforce housing will assist with meeting the need for
additional housing and serves as an indirect driver for the local economy. Employers
benefit from employees living in proximity to quality housing for all tiers of employment.
A sustainable community that offers a variety of employment opportunities, housing
options for workers and families and provides recreational and cultural activities within
the City limits complements one another.
FIVE-YEAR IMPLEMENTATION PLAN
15
Agency Accomplishments
Capital Improvement Projects
Goal: To eliminate the physical blighting conditions of the project area and
address prevention of further blighting conditions through implementation of capital
improvement programs. These programs include, but are not limited to: the Foothill
Boulevard Implementation Plan, the Master Plan of Storm Drains, the Etiwanda/San
Sevaine/Day Creek drainage system, and the completion of the Master Plan of Fire
Facilities to provide adequate fire protection for the project area.
Accomplishments: The Redevelopment Agency recognizes the impact that
infrastructure improvements can have on the overall enhancement and economic
viability of the project area. Consequently, the Agency’s assistance in the completion of
major infrastructure improvements has stimulated substantial investment in the
redevelopment project area by the private sector. The Redevelopment Agency’s
contributions towards offsite improvements and its investments in projects such as the
Foothill Boulevard Improvement Project have resulted in many new businesses locating
within the project area, creating additional opportunities for employment. The
following highlights some of the Agency’s prior accomplishments in implementing
capital improvement projects and programs; refer to the annual report for a more
comprehensive overview of the Agency’s accomplishments.
San Sevaine Channel/Upper Etiwanda Creek
Project - In 1982, the Redevelopment Agency
entered into an agreement with the San
Bernardino County Flood Control District for the
improvement of the Day Creek/Etiwanda Creek
Flood Control System. The Day Creek flood control
channel was completed in 1992.
In 2001, work began on improving the San
Sevaine Channel/Upper Etiwanda Creek project.
FIVE-YEAR IMPLEMENTATION PLAN
16
The System benefits the southeastern portion of the Project Area. Construction began
in 2005 and the completion of the channel occurred in mid 2009. Completion of this
important flood control project allowed many acres of underutilized and vacant
residential, commercial and industrial land along the eastern borders of the Project Area
to developed and/or improved.
Due to rising construction costs and a loss of funding from the Federal Bureau of
Reclamation, the Agency and Flood Control District amended their Agreement in June
2005 to increase the Agency's contribution from $16 Million to $20 Million. The
amended Agreement also recognizes three systems identified in the City of Rancho
Cucamonga's Master Plan Storm Drains that qualify as regional facilities, and that can be
constructed utilizing the Agency's Regional Facilities funds. The Upper Etiwanda Creek
system of the San Sevaine Channel project is nearing completion. The channel connects
the Etiwanda Creek System to the remaining phases of the channel system to the south.
Upper Cucamonga Storm Drain and Hellman Avenue Widening Improvements –
Plans and specifications were completed for this project in 2005. This project improved
the existing channel and storm drain at a point along the railroad right of way, west of
Vineyard Avenue to Base Line Road; east along Base Line Road to Roberds Street; and
north from Roberds Street to 19th Street. Phase I and Phase II of the project included
construction from Vineyard Avenue to east of Hellman Avenue. The project provides
much needed flood protection for businesses and residences which are located in the
area.
Fire Station #173/Day Creek Station - was completed in 2005 and is located just
north of Base Line Road at Day Creek
Boulevard. This Station replaced a
30-year old temporary facility and
was fully operational in November
2005. Various innovative design and
construction methods were
implemented. Most notably and in
an effort to conserve water and
FIVE-YEAR IMPLEMENTATION PLAN
17
reduce maintenance costs, artificial turf was incorporated into the landscaping with
other indigenous plant-life. This was the first city facility to utilize artificial turf.
I-15/Foothill Boulevard Interchange - Construction is complete on this important
freeway interchange, greatly improving traffic circulation of Foothill Boulevard and
serving as a catalyst to facilitate development on the east side of the project area,
including Victoria Gardens. The City is currently working with CalTrans to widen
freeway to allow cars exiting to not interfere with southbound traffic flow. $1 Million
has been budgeted for the widening project.
Foothill Boulevard/Etiwanda Avenue Improvements - In 2009 the Agency
assisted in funding the construction of a block wall and sidewalks at the intersection of
Foothill Blvd. and Etiwanda Ave. to improve the aesthetics and safety along the Foothill
Blvd. corridor in the east end of the project area.
Installation of conduit for a fiber-optic ring - Phases I and II of this project was
complete in 2007, connecting eight City facilities including the City Yard, Archibald
Library, Central Park/Senior Center/Community Center, the Victoria Gardens Cultural
Center, the Police Substation, and Fire Stations #172 and #173 with the City’s
broadband communications network. Phase III of this project was completed in 2008,
connecting the Foothill Boulevard/Rochester Avenue conduit to Victoria Gardens,
therefore completing the fiber optic redundant loop and providing additional safety to
the City’s data network. An additional goal of this project is to connect all city facilities
and become proactive in building a high-tech infrastructure that will attract high-tech
companies and jobs.
Economic Development and Enhancement Programs
Goal: The Agency’s efforts to enhance the commercial/industrial sector of the
City’s business community consist of a variety of programs designed to address Rancho
Cucamonga’s needs for business attraction, retention, and expansion. To strengthen
the economic environment of the commercial/industrial sector of the project area
through a variety of programs designed to address the needs of Rancho Cucamonga's
FIVE-YEAR IMPLEMENTATION PLAN
18
existing businesses, to attract new business to the City and provide long-term
employment to strengthen and compliment the economy of the City.
The following highlight some of the Agency’s prior accomplishments in
achieving its Economic Development and Enhancement Program and Projects; refer to
the annual report for a more comprehensive overview of the Agency’s
accomplishments.
Accomplishments – The Redevelopment Agency recognizes the diverse needs of
businesses and has adopted an economic development strategy to retain and attract
businesses that will strengthen Rancho Cucamonga’s economic base. In 2007 the
following distribution represents a majority of the business types in the City:
1. Retail Trade at ……………………………………………………………………20.4 %
2. Manufacturing at……………………………………………………………….6.0 %
3. Distribution at ……………………………………………………………………11.8 %
4. Employment Agency at ……………………………………………………9.2 %
5. Education at ………………………………………………………………………8.1 %
6. Construction at ………………………………………………………………….7.5 %
7. Financial, Real Estate, and Insurance at………………………….7.5 %
8. Other Services at………………………………………………………………..6.9 %
9. Balance of professions equaling ……………………………………..12.6 %
Victoria Gardens Regional Mall - In 1987, the Redevelopment Agency acquired
an approximate 99-acre site north of
Foothill Boulevard and west of the I-15
freeway for a potential regional
shopping center. An additional 55
acres were purchased in 2001. On
February 20, 2002, the Agency
approved a Disposition and
Development Agreement with the
FIVE-YEAR IMPLEMENTATION PLAN
19
partnership of Forest City Development and Lewis Development for the construction of
a 1.3 million square foot, open air regional lifestyle center.
This major project achieved many goals including the creation of a new
downtown district for the City of Rancho Cucamonga. Phase I of the project opened in
2004 with a sophisticated mix of high end retailers, fine restaurants, entertainment
venues, cafes, professional offices, housing and civic and cultural venues. The project
has made a positive economic impact on the community by providing approximately
3,500 new jobs for local residents and is serving as a catalyst for further development in
the eastern portion of the City. The Agency also supported the landowner’s request to
form a Community Facilities District to provide the necessary infrastructure for the
residential and commercial property in this area.
The Victoria Gardens Master Plan entitles the Developer to construct
approximately 1 million additional square-feet. The majority of this is expected to be
office which will significantly add to
the City’s job base.
In July of 2007, Bass Pro Shops
Outdoor World Shop, the first in the
State of California opened at Victoria
Gardens. This 180,000 square foot
sportsman’s paradise is reared as one
of the largest sporting good retailers in
the country and has brought approximately 325 jobs to the area. The store can boast
approximately 1.9 million visitors per year and has over $1,000,000 in direct sales tax
revenue.
The Agency is responsible for building additional parking or parking structure to
serve the mall. The Agency recently acquired 5.4 acres of undeveloped land that may
be used for interim parking if needed.
Economic Development Strategy - The Redevelopment Agency approved an
Economic Development Strategy in 1996 to provide a competitive assessment, target
business cluster analysis, and a strategic plan for the Agency's economic development
FIVE-YEAR IMPLEMENTATION PLAN
20
programs. Agency staff continues to implement many of the strategies suggested
under the initial economic development plan, resulting in new programs that support
business development. Due to the economic changes that have taken place since 1996,
the Agency determined that it is appropriate to update the original plan. The updated
Economic Development Strategic Plan was completed in 2003. The firm of Economic &
Politics, Inc. assisted with a comprehensive update to the Economic Development
Strategic Plan. The updated Plan provided the Agency with data, strategies and
implementation measures that facilitate positive economic growth for the community.
Areas of focus included; infrastructure development, business recruitment, business
retention, marketing and public relations, education, and housing. More recently, with
the growth in the number of hotels in the City, tourism has been added as an additional
component of economic development programs. Rancho Cucamonga launched the
“Gateway to a Southern California adventure” promotion.
Trade Shows - The Agency remains actively involved in local, regional, and
national events that provide opportunities
to further expand its business attraction
activities. Both retail-oriented (e.g.,
International Council of Shopping Centers
annual Deal Making Trade Show) and
industry-specific (e.g., manufacturing
industry) trade shows provide valuable
business contacts. The Agency also focuses
its print advertising efforts on trade journals
that target industries of interest to Rancho Cucamonga, and are distributed at national
trade shows.
Inside Rancho Web Site - In 1999, the Redevelopment Agency established an
interactive web site that provides site selection information for industrial and retail space
that is available within the City. The award-winning web site allows brokers, developers,
and retailers to conduct online GIS-based searches quickly and easily, and offers site-
specific demographic information based on 3, 5, 10 and 15-mile radii. A key economic
FIVE-YEAR IMPLEMENTATION PLAN
21
development tool, Inside Rancho has enabled the Rancho Cucamonga Redevelopment
Agency to generate interest in vacant sites that may otherwise be overlooked by
potential business investors. In addition to industrial and retail information, the Agency
recently added a new office space component. In 2006, the Agency worked with a
consultant to enhance the site to include a new feature to export custom reports in
Microsoft Word, Excel and PDF files.
National Association of Industrial and Office Properties (NAIOP) Bus Tour - The
City and Agency, for the second year, assisted in securing the NAIOP Bus Tour to begin
and end as the City’s Cultural Center. The event attracted approximately 300 people,
many of which are from outside the immediate area. Many properties (office and
industrial sites) were highlighted.
Small Business Development Center - The Redevelopment Agency and Chamber
of Commerce joined in a cooperative effort to create a Small Business Development
Center to provide consulting services for existing and start-up businesses. During this
reporting period, 560 businesses have been assisted and approximately 290 jobs have
been created.
Tourism – The Agency continued to implement its comprehensive travel and
tourism marketing
campaign that incorporates
electronic and print
advertising; radio
advertising and spotlights;
and public relations efforts.
The Agency also continued
to develop its relationship
with its neighboring
Tourism Partners to help
promote and expand
tourism in and around
Rancho Cucamonga. This multi-faceted tourism marketing effort was developed to
FIVE-YEAR IMPLEMENTATION PLAN
22
increase the community’s exposure as a travel destination and starting point for
extended travel; increase revenues through marketing travel-related businesses; and
increase the city’s transit-oriented occupancy levels. Since the onset of the campaign, the
Agency has received thousands of requests for tourism information and has experienced
increases in the city’s sales tax and transit occupancy tax revenues.
Public Relations Program – The Redevelopment Agency has supplemented its
marketing efforts with an effective public relations component that has helped to
strengthen its business attraction and tourism efforts. In addition to targeted pitches
directed at writers, editors, and media professionals, the Agency has utilized its public
relations firm for creating advertorial content associated with print and online
advertising campaigns. As a result of the Agency’s public relations activities, Rancho
Cucamonga has realized increased exposure in industry trade publications and
travel/tourism communications at the regional, state, national and international levels.
Chamber of Commerce - The Redevelopment Agency continues to maintain a
successful partnership with the Rancho Cucamonga Chamber of Commerce and
actively participates in events and activities that support local businesses and encourage
new business development.
Inland Empire Economic Partnership (IEEP) - The Agency continues to participate
with the IEEP to promote the Inland Empire region. Through its involvement with IEEP,
the Agency has participated in site searches for land and/or buildings for potential
business relocations, expansions, or start-up operations, as well as prospective film
locations by television and movie production companies.
Entrepreneur's Network - The Rancho Cucamonga Redevelopment Agency has
recently become involved with a regional economic development effort known as the
Entrepreneur's Network. In cooperation with Chaffey Community College, and other
public, non-profit, and private entities, the Agency is involved in efforts to create,
educate, and expand opportunities for entrepreneurial business activities within the
west end of San Bernardino County. Through workshops, forums, and networking
FIVE-YEAR IMPLEMENTATION PLAN
23
events, students and business members can explore new business start-up, franchising,
and business training opportunities.
Community and Economic Profile - The Community and Economic Profile
provides the Agency with important economic and demographic information that can
be utilized in carrying out ongoing economic development activities, including business
recruitment efforts and strategic planning. The Agency works with a local economist to
provide an annual in-depth analysis of the City's economic strengths and trends, and
disseminates the information to a wide variety of companies and business-related
organizations.
Graphics Standards Manual – In order to refine the promotional and information
material that is distributed by the Agency and the City, a cross-departmental group of
employees were selected to participate in a Graphics Standards project. The Project
produced graphic standards for all City related promotional or informational material
and the material has been made available on the City’s website.
Relocation/Expansion Assistance - The Redevelopment Agency provides
technical assistance to businesses that intend to expand to or relocate to, Rancho
Cucamonga. During this reporting period the Redevelopment Agency assisted 566
(SBDC) companies interested in expansion or relocation. Listed below are highlights of
the more significant projects.
Gentex Corporation - An innovative technology company and a world leader in
both military and commercial markets. Redevelopment staff assisted the company in
identifying a suitable site for its new 100,000 square foot, state-of-the-art respiratory
development center. In 2007, Agency staff successfully worked with a local broker and
located an appropriate site for Gentex. The new Gentex facility has the capacity to
create an additional 100 jobs to its current workforce of technicians, engineers, and
administrative staff.
Amphastar Pharmaceuticals – A pharmaceutical company producing generic
and specialty products that is engaged in the discovery, development, manufacture and
FIVE-YEAR IMPLEMENTATION PLAN
24
marketing of generic and proprietary pharmaceuticals, innovative delivery systems and
active pharmaceutical ingredients.
Amphastar’s Management Team takes pride in the Company’s “3H” commitment
to “High Quality, High Efficiency and High Technology”. In keeping with this pledge of
excellence to the consumer, Amphastar continues to invest in state-of-the-art
equipment, research and development, facilities, and the advancement of their
employees.
Trader Joes – After negotiating for nearly two years, Trader Joes, a premier
specialty grocer opened store in Rancho Cucamonga. Agency staff provided assistance
in identifying potential sites for the store. The location opened in late 2007.
Shakey’s Pizza - Staff coordinated meetings with this company and other city
departments to facilitate the permitting process for the city’s fire, building and
development code requirements. This company is expected to occupy their new
building in 4th quarter 2009.
Torco International - Staff coordinated meetings with this company and the
Building and Safety and Planning Departments to streamline the permitting process for
occupancy requirements.
Site Acquisition & Assembly. In 2002, in an effort to mitigate blighted conditions
along Foothill Boulevard — the City's primary retail/commercial corridor — the Agency
acquired seven separate parcels located on Foothill. Due to the small size of these
individual parcels, as well as incomplete or substandard infrastructure, it was
determined that only a comprehensive assembly of parcels could ensure new
development and necessary infrastructure improvements. In 2004, the property was
sold to John Laing Homes. The proposed housing project by the developer will help
revitalize the project area, remove blight and encourage comprehensive planning for
the entire block.
FIVE-YEAR IMPLEMENTATION PLAN
25
Community and Cultural Facilities
Goal: The Rancho Cucamonga Redevelopment Plan identified a lack of adequate
open and recreational space as a blighting condition of the project area. It is the intent
of the Rancho Cucamonga’s Agency Board to promote and encourage community and
cultural opportunities. Concerted effort will continue to be made fostering community
via development/construction of infrastructure and citywide programs and events. The
following highlights many of the Agency’s accomplishments in the elimination of
blighting conditions, or the constructions of recreational facilities and ongoing
preservation of open space. Also, community facilities to serve and maintain project
area.
The following highlight some of the Agency’s prior accomplishments in
developing and constructing Community and Cultural Facilities; refer to the annual
report for a more comprehensive overview of the Agency’s accomplishments.
Accomplishments – The Redevelopment Agency continues to address the needs
of its residents in providing adequate open space and additional recreational venues
through the implementation of projects that enhance the community’s overall quality of
life. Activities included the construction of a Family Sports Center, and the completion
of the new library and cultural center complex at the Victoria Gardens Mall. Phase II on
Central Park is in the planning phase, but no immediate plans have been set for actual
construction. ERAF requirements
have affected the second phase.
Victoria Gardens Cultural Center,
Lewis Family Playhouse and Paul
Biane Library - The Agency
funded construction of this facility
which includes the 536 seat
Lewis Family Playhouse, the Paul
A. Biane Library, Celebration Hall
FIVE-YEAR IMPLEMENTATION PLAN
26
and Imagination Courtyard. All of the facilities including the programs and activities
that are offered contribute to the Healthy RC objectives of the City and Agency. This
complex is located at the north end of the Victoria Gardens Mall and serves as a cultural
node within the City. The Playhouse is the home to the Main Street Theater Company
and also serves as a learning center for local students, while the Paul Biane Library
provides over 100,000 items (books and other media) available to residents, Celebration
Hall serves as a unique rental facility for meetings, parties, and more formal gatherings
and Imagination Courtyard offers an outdoor option for events. The Cultural Center
serves as the fifth anchor to Victoria Gardens, drawing many visitors from the region
whom also patronize retailers and restaurants at the mall.
Goldy Lewis Community Center and James Brulte Senior Center at Central Park -
Phase I of this 103-acre project, located on Base Line Road and Milliken Avenue,
includes a 26,000 square foot senior center, a 25,000 square foot community center
and approximately 15 acres of developed parkland. Both community centers provides
for added services and programs
to serve our city residents.
Funding for Phase I, approximately
$13.6 Million, came from a variety
of sources, including State Park
Bond Acts 2000 and 2002, Federal
and County funding sources, and
private donations. The Agency
provided $5 million in
infrastructure funds for street improvements on Base Line Road, including storm drain,
curb/gutter and sidewalks. Completion of the Phase I occurred in winter 2005. The
Agency has funded schematic architectural plans for phase II of this park project. Due
to potential ERAF this project has been put on hold for an indefinite period of time.
The Goldy S. Lewis Community Center is home to many programs and classes
that are offered to the public; the IncredABLES/Special Needs programs, facility rentals,
Trips and Tours, Community Services Department registration and Playschool are just
FIVE-YEAR IMPLEMENTATION PLAN
27
some of these programs, which provide opportunities such as dance classes, summer
camps, martial arts classes, workshops, seminars and much, much more.
The James L. Brulte Senior Center functions with one goal in mind: improve the
quality of life for all seniors in our community. With a variety of fitness, cultural,
educational, nutrition, travel, and health and wellness opportunities, the James L. Brulte
Senior Center is a place where senior adults can spend the best years of their lives! Since
opening the doors to the James L. Brulte Senior Center in May 2005 the participation
has grown from 185,000 to an impressive 259,000 annually.
Rancho Cucamonga Epicenter/Sports Complex - The Agency constructed a 42-
acre adult sports park/stadium, which included three softball fields, two soccer fields,
one baseball diamond, an animal
control facility, and a 6,100-seat minor
league stadium - home to the Rancho
Cucamonga Quakes. The Epicenter is
home to the highest attendance
ranked Southern California team in the
Single ‘A’ Baseball League, the Quakes.
The team is a California Affiliate of the
Los Angeles Angels of Anaheim.
Quakes’ baseball is played on the Stadium field between April and September each year.
On non-game days and during the offseason, the facility is available for rent.
Animal Care and Adoption Center - The Agency assisted with implementing
necessary improvements to the city’s Animal Care and Adoption Center. These
improvements included the construction of an onsite surgical facility, an upgrade of the
Center’s heating, ventilating and air conditioning (HVAC) system, an upgrade of the
Center’s “Get Acquainted” areas and a remodel of the outer buildings for additional
storage space. This facility is located on the Sports Complex site.
Rancho Cucamonga Family Resource Center - The Agency assisted with the completion
of this facility located on Arrow Route. The Resource Center continued to be a very
effective approach for the whole community by presenting a variety of different human
FIVE-YEAR IMPLEMENTATION PLAN
28
service agencies and their services and programs. This centralized location for services
and information has been utilized by the area residents.
Affordable Housing Projects and Programs
Goal: The Rancho Cucamonga Redevelopment Plan identified a lack of sufficient
affordable housing to meet the needs of the community’s low- and moderate-income
families and established a goal to increase, improve and maintain the City’s supply of
affordable housing. Although the Agency has actively assisted with the development
and preservation of affordable housing, the ongoing need for additional housing
continues with population growth of the City and region. Additional burden has been
created by the boom then subsequent crash of the housing market.
Accomplishments – The Redevelopment Agency has partnered with several non-
profit housing corporations to provide a mixture of affordable ownership and rental
housing for income eligible households. As evidence of the Agency’s continued
commitment to promote the availability and affordability of housing to meet the needs
of the community, the Agency has assisted with the production of over 1900 affordable
units. The following paragraphs contain specific details regarding some of the more
recent projects assisted by the Agency; refer to the annual report for a more
comprehensive overview of the Agency’s accomplishments.
Sunset Heights, formerly Woodhaven Manor – In September 2005, the Agency
approved a $9 million loan to
National Community Renaissance
(CORE), formerly Southern
California Housing Development
Corporation, to assist with the
acquisition and rehabilitation of
Woodhaven Manor, an existing
117 unit family apartment project.
The project was originally
FIVE-YEAR IMPLEMENTATION PLAN
29
constructed under the California Housing Finance Authority (CalHFA) HAP Section 8
program.
The complex had a long history of public safety concerns and property
maintenance issues. The Developer, CORE, held their Grand Opening of the renovated
complex in February 2008. Improvements made to this property include new energy
efficient windows, cabinet and flooring upgrades, and the installation of heating and air
conditioning units. A new community center was also built and will provide needed
services for the residents and surrounding community, including after-school tutoring
and computer training. The project has also been enrolled in San Bernardino County’s
Multi-family Crime Free program. Through the Agency’s Regulatory Agreement, the
affordability term will be extended to not less than 99 years.
Rancho Verde East – In July 2005, the Agency began working with National
Community Renaissance (CORE), formerly Southern California Housing Development
Corporation to assist with the expansion of the existing Rancho Verde Village
Development. The Agency approved a $6.5 million loan for the acquisition of land and
the expansion of the existing complex. The expansion project included 40 additional
three-bedroom affordable units, available to large families earning 35%, 45%, 60%, and
80% of the area median income for a term of not less than 99 years. The project also
added a 5,500 square foot Community Center, Tot-Lot, and new energy star appliances.
The construction of additional units began in 2008 and a Grand Opening/Dedication
Ceremony was held on October 2009.
Olen Jones Senior Apartments - The Redevelopment Agency entered into a
Disposition and Development Agreement with the Northtown Housing Development
Corporation (NHDC) to provide funding for the development of a 96-unit senior
housing project. In addition to the Agency's participation, NHDC received 4% tax
credits, and a County of San Bernardino Home loan. The project was completed in May
2004.
Other Housing Programs and Activities - The Redevelopment Agency participates
in the California Cities Home Ownership Authority (CCHOA), which provides lease-to-
own opportunities for Rancho Cucamonga residents. The City is currently taking action
FIVE-YEAR IMPLEMENTATION PLAN
30
to formally dissolve the joint power authority of CCHOA. These programs utilize bond
revenues rather than Redevelopment Agency Housing Set-Aside funds. Currently, there
are no bond funds available for this program.
FIVE-YEAR IMPLEMENTATION PLAN
31
Ongoing and Potential Projects for 2009-2014
Ongoing and Potential Capital Improvement Projects
A substantial portion of the Redevelopment Agency’s annual tax increment must
pay for debt service for the established projects, as well as pass-through agreements to
school districts and other public entities. The remaining revenue is allocated to potential
projects that benefit the Project Area. If the SERAF take by the State of $32.1 million in
FY2009-2010 and $6.9 million in FY2010-2011 occurs, then the Agency will be severely
limited in its ability to complete many of the highlighted capital projects.
The potential projects identified in the tables below are representative of those
opportunities known to the Agency to exist as this time in the project area and are not
intended to represent every potential project that may be needed. The Agency must be
able to respond to opportunities to alleviate blight in the project area; therefore, new
programs and/or opportunities may arise with new or updated information. These
potential projects are also impacted by regional economic climate, the ability of private
or other public sector involvement and the Redevelopment Agency’s ability to maintain
or increase tax revenue. The Agency also recognizes that with the passage of time,
existing infrastructure deterioration and blighting conditions identified in the
Redevelopment Plan may become prevalent. Should unforeseen needs arise, the
Agency may elect to respond to those conditions as a priority.
Foothill Boulevard Improvements - Phase I and
Phase II of the Foothill Boulevard Improvement
Project was completed in 2000 and 2001,
respectively. Both Phases of this project included
substantial median work, as well as general
construction and landscaping enhancements to
Foothill Blvd. The project has significantly improved
traffic circulation and reduced traffic accidents
FIVE-YEAR IMPLEMENTATION PLAN
32
along the city's primary retail/commercial corridor, and has helped revitalize portions of
the boulevard.
Currently, the Agency is working on Phase III and IV of the project along Foothill
Blvd. between Grove and Vineyard, and between I-15 and East Avenue, respectively.
The westerly phase III includes additional median improvements, street widening,
sidewalks, landscaping, a pedestrian bridge, a street archway and a point-of-interest
park that will celebrate Historic Route 66 and connect the route to the Pacific Electric
Trail to the north. Construction of the project is expected to begin in the first quarter of
2010 with completion scheduled for the end of the year. The easterly Phase IV includes
similar types of street work and street graphics, including a street archway.
Haven Avenue Railroad Overpass - The Haven Avenue Grade Separation project
is a major infrastructure project that will improve vehicle travel and enhance safety for
all travelers by separating train traffic
from vehicle traffic. Currently, each day,
approximately 38,000 vehicles travel on
Haven Avenue and up to 40 trains cross
Haven Avenue.
When completed, the project will
provide six traffic lanes (three in each
direction) on Haven Avenue, two
bicycle lanes, pedestrian sidewalks
under a new railroad two-track bridge and full landscaping of the side slopes and
replacement of the landscaped median islands that were removed as a result of the
project. The project is expected to be complete by March 2010.
Etiwanda Avenue Railroad Overpass - The final overpass to be built that will
separate rail traffic from vehicle is at Etiwanda Avenue and the Railroad. The
expectation is it will be similar in design to recently completed Haven overpass. The
overpass is immediately adjacent to eastern Project Area boundary. The overpass
FIVE-YEAR IMPLEMENTATION PLAN
33
project will benefit traffic safety and efficiently allow for the movement of goods and
services.
Hellman Avenue (Lower Reach) Storm Drain - This project will improve and
provide much needed flood control service in the south west corner of the Project Area
and help implement the City’s general Storm Drain Master Plan. This project includes
the installation of a storm drain mainline, a catch basin, manholes and widening the
railroad track. Currently, the storm drain alignment and Hydrology report is being
prepared. We expect
construction to begin by spring
2010 with construction taking
approximately 18 months.
Hellman Avenue (Upper Reach)
Storm Drain - This project runs
northeast from Cucamonga Creek
along the Pacific Electric Trail (old
SPRR easement) crossing Hellman and Base Line, then north along Amethyst to 19th
Street, then easterly along 19th for approximately 300 feet.
Phases I and II from Cucamonga Creek to east of Hellman was completed in
2008. Phase III from east of Hellman to 19th Street is designed and waiting for the
availability of funds. Phase III is estimated to cost approximately $3.5 million.
I-15/Arrow Route Interchange - Right-of-way acquisition for the proposed
interchange began in 2005. This project will add an on and off ramp in our industrial
area, improving access to the freeway and reducing traffic congestion on adjacent
streets. In August 2006, the City Council approved a Professional Services Agreement to
prepare a project report, environmental documents and design for the on/off ramp.
The project report and environmental documents are expected to be complete by the
end of 2010. The City has acquired some of the right-of-way needed for the project but
additional land for the project is still needed. This project has been put on hold for an
indefinite period of time due to the SERAF takes of Agency funds approved by the State.
FIVE-YEAR IMPLEMENTATION PLAN
34
I-15/Base Line Boulevard Interchange - This project is currently in the Project
Report/Environmental Document and Design Stage phase. Both project reports and
design are being worked on concurrently and are expected to be complete by early
summer 2010, with the design completed by the end of 2010. Construction of this
project is expected to begin first quarter of 2011.
The project will expand the existing on and off ramps at I-15 Freeway at Base
Line Road. This is a much needed improvement as result of the housing growth that
has occurred over the last 10-years.
Fire Administration Building - The Redevelopment Agency, through a negotiated
sale, purchased an approximate one-acre parcel at the corner of Utica Avenue and Civic
Center Drive and took title to the property on March 27, 2002. The parcel was selected
due to its availability and proximity to Rancho Cucamonga City Hall and other regional
civic uses. The Redevelopment Agency will continue working with the Rancho
Cucamonga Fire protection District through the design and entitlement phases of this
project, which will consolidate Fire District Administrative operations.
Fire Station #172 /San Bernardino Road Relocation - On January 26, 2009,
through a trustee sale, the Redevelopment Agency purchased an approximate .55-acre
parcel located at 9561 San
Bernardino Road and became
the recorded owner of that
property on February 10,
2009. Subsequently, the
Agency, through a negotiated
sale, purchased an adjacent
property (approximately .82
acres) located at 9547 San
Bernardino Road and took title
of that property on May 12, 2009. In 2010, the Redevelopment Agency will work with
the Rancho Cucamonga Fire Protection District to demolish the existing structures
located on the two properties and prepare them for the future construction of San
FIVE-YEAR IMPLEMENTATION PLAN
35
Bernardino Road Fire Station #172, which will provide a better level of service for the
southwest portion of the City.
Fire Station #174 /Jersey Station – the Master Plan for this station calls for the
additional construction of a specialized fire fighting train tower and storage warehouse.
When funds are secured the Fire District plans to complete these needed projects.
Fire Station #175/Banyan Station Expansion – The Rancho Cucamonga Fire
District plans to add/attach a large garage
(called an apparatus bay) to the northeast
corner of the existing Fire Station layout.
The new bay will be two-wide and two
deep (approximately 70’x35’). The addition
will allow fire personnel to park all of the
Station equipment appropriately indoors
and out of the elements. This will not only protect expensive specialized fire suppression
equipment, but will also make the equipment more easily accessible when calls-for-
service are received.
Fire Station #177/Demens Basin Project - Agency staff is working with staff from
the City Manager’s Office, the Fire District, and engineering staff on the future
development of Fire Station #177. City Council approved a Purchase and Sale
Agreement with San Bernardino County for the land needed to build the fire station.
Related agreements were also approved which include preparing the property for
construction. Staff participated in several neighborhood meetings during the first
quarter of 2009 and received feedback from the residents surrounding the project site.
Construction of the Fire Station will be done in two phases. The first phase of the
project was completed, which included filling in the Demens Basin Property with 90,000
cubic yards of dirt and preparing a developable pad. The second phase includes the
construction of the fire station. The construction will be done by the Fire District.
Fire Station #178/Central Park – In 2008, the Agency began the preliminary
design phase for this fire station, the proposed station is to be located adjacent to the
FIVE-YEAR IMPLEMENTATION PLAN
36
western portion of the City’s
Central Park facility. Its ease of
access to and from Base Line
Road, a primary artery, makes
this an ideal location to serve
this area of the Project Area.
This project has been put on
hold for an indefinite period of time due to the SERAF takes of Agency funds approved
by the State.
Corporate/City Yard Expansion – The Agency has negotiated an agreement with
a local Architectural firm to create a master plan exhibit and design of phase I for the
Corporate Yard Expansion project. The site is approximately 14 acres with 7 of those
acres already developed. Along with a new Public Works facility, the relocation of the
City’s existing Household Hazardous Waste facility and a Fire Helicopter Rescue/Medical
Assistance Helipad may be relocated to this site. These improvements will allow the
Public Works Department an opportunity to better serve the City’s residents and the
Project Area.
Pacific Electric (PE) Trail Phase – Currently the Agency is working on Phase IV,
which will include the construction of a trail, trail lighting, traffic signals, and
landscaping. This phase of the project will connect the
section of trail with completed segments in the neighboring
cities and within the City’s Project Area. This project will
address SANBAG’s Trail Master Plan and provide residents
with alternative forms of transportation as well as
encourage a healthy living style through exercise. This
phase of the project is currently under construction and is
expected to be complete by the end of 2010. This phase will
complete the seven mile trail through the City, of which a
significant portion is within the Project Area. The Agency may pursue trail
enhancements in the future.
FIVE-YEAR IMPLEMENTATION PLAN
37
9th and Madrone Park Land - In 2005 the Agency acquired 3.4 acres of land as
part of an affordable housing project. The land was zoned open space for the purpose
of developing a much needed neighborhood park in the southwest area of the City.
The property remains undeveloped and Agency staff is currently working with
Community Services staff on a grant submittal application for the development of the
park. Part of the grant requirements are that the City host five neighborhood meeting
to solicit feedback from residents on how the park will be developed. Park amenities
will be limited because of the size of the land. However, the Agency will continue to
explore future opportunities to acquire additional land to expand the park size.
Etiwanda Storm Drains (Drainage Facilities) – Line 8: will extend from an existing
basin north of Base Line Road to Foothill Boulevard. It will also include a tie in-to the
East Avenue drain from the existing Base Line storm drain west of East Avenue.
Approximately 522 acres are tributary to the Line 8 drain ($8 M). Line 10: alignment will
follow the unimproved Lower Etiwanda Channel. The drain will extend from Arrow
Route to 4th Street, then east on 4th Street to the improved Etiwanda/San Sevaine
Regional Channel. Approximately 375 acres are tributary to the Line 10 drain ($25 M).
Line 11: will be contained within the street right-of-way for Etiwanda Avenue. It will
convey flows primarily from west of Etiwanda Avenue and south of Foothill Boulevard,
approximately 225 acres. The drain extends from Arrow Route to 4th Street.($6.2 M).
The Etiwanda drain system is the Agency’s near term focus. The Agency will
pursue any other remaining unbuilt master plan storm drains that benefit the Project
Area.
Public Safety Substation – The Agency and City are in negotiations with the
County of San Bernardino to lease a property (approximately 15,000 square/feet) north
of the I-210 Freeway for the development of a Public Safety Substation that will improve
service to the city and the project area. The facility will house both County and City
sheriff services. The design and environmental review phases of this project are
currently underway, with construction anticipated to begin in FY 2010-2011. The
completion of this project will provide increased public safety for this area of the Project
Area.
FIVE-YEAR IMPLEMENTATION PLAN
38
Metrolink Station Improvements – This station has the distinction of being the
most used on the San Bernardino Line, which connects the Inland Empire with the Los
Angeles County and Orange County areas. The Agency will assist with necessary
improvements as demand and usage increases.
Table II. Ongoing and Potential Capital Improvement Projects
Project Description
Impact on Blight Elimination
Total Estimated 2009-2014
Foothill Boulevard Improvements
Elimination of under-utilized parcels, substandard structures, improved circulation system.
$14,500,000
Haven Avenue Railroad Overpass and 8th Street Realignment
Improved traffic circulation system. $18,000,000
Etiwanda Avenue Railroad Overpass Improved traffic circulation system. $25,000,000
Hellman Avenue (Lower Reach) Storm Drain
Improved traffic circulation system; provision of adequate flood control. $15,000,000
Hellman Avenue (Upper Reach) Storm Drain
Improved traffic circulation system; provision of adequate flood control. $3,500,000
I-15/Arrow Route Interchange Improved traffic circulation system. $30,000,000
I-15/Base Line Boulevard Interchange
Improved traffic circulation system; provision of adequate flood control. $35,630,000
Fire Admin. Building (Fire Master Plan)
Provision of Fire Facilities to protect project area. $8,000,000
FIVE-YEAR IMPLEMENTATION PLAN
39
Fire Station #172/San Bernardino Road Station
Provision of Fire Facilities to protect project area. $3,958,000
Fire Station #174/ Jersey Station
Provision of Fire Facilities to protect project area. TBD
Fire Station #175/Banyan Station Expansion
Provision of Fire Facilities to protect project area. TBD
Fire Station #177/Demens Basin Project
The Fire District will be completing the project. $580,000
Fire Station #178/Central Park Fire Station
Provision of Fire Facilities to protect project area. $4,411,000
Corporate/City Yard Expansion Removal of blighting conditions $8,000,000
Fire Training Facility/Tower
Provision of Fire Facilities to protect project area. $1,500,000
Pacific Electric Trail Phase IV Removal of blighting conditions. $1,679,312
9th and Madrone Park Land Removal of blighting conditions. TBD
Etiwanda Storm Drains Provision of adequate flood control. Line 8 = $8M
Line 10 = $25M Line 11 = $6.2M
Public Safety Substation Provision of Public Safety Facilities to protect project area. $2,000,000
Route 66 Trail Head at Foothill Blvd. Removal of blighting conditions. $2,000,000
FIVE-YEAR IMPLEMENTATION PLAN
40
Foothill Median Light Retrofit Removal of blighting conditions. $355,000
Ongoing and Potential Economic Development and
Enhancement Programs
The Redevelopment Agency’s efforts to expand its economic development
activities through the enhancement of new and ongoing programs, has helped ensure
a strong economic environment and has increased the number of employment
opportunities for local residents. The Agency will continue to take a proactive approach
to mitigating economic deterioration by assisting in the establishment of new
businesses and the creation of new jobs through the support of economic strategies
that help eliminate economic blight in the community. Again, if the SERAF take by the
State of $32.1 million in FY2009-2010 and $6.9 million in FY2010-2011 occurs, then the
Agency will be severely limited in its ability to fund many of the highlighted economic
development programs.
Banner Promotion Program - The Rancho Cucamonga Redevelopment Agency
implemented the banner program in 1997 to encourage community pride and to
attract customers to primary retail-commercial corridors within the city. In 2002, a
sponsorship component was added to the program, which provides an opportunity for
local businesses to enhance their efforts in attracting customers that are necessary to
sustain positive economic growth. The Banner Promotion Program, which provides
Rancho Cucamonga businesses with the opportunity to sponsor a banner along the
highly traveled Foothill Boulevard retail corridor, has received positive feedback from
local merchants. The Agency will continue to support and enhance this activity in the
future.
Third Party Electrical Certification Program - To date, 41 companies have been
assisted through the Agency's Electrical Certification Program. This program was
developed to assist local manufacturers in complying with the National Electrical Code
FIVE-YEAR IMPLEMENTATION PLAN
41
requirement for safety certifications for all manufacturing equipment. The program is
designed to assist companies by providing low-cost inspection services and certification,
thereby extending their ability to reduce costs and remain competitive.
Broker Networking - The Agency continues to network with area brokers to
market Rancho Cucamonga properties. Agency staff members have provided
presentations to the brokerage community and participate in regional broker tours. The
purpose of this program is to develop positive relationships with the brokers and leasing
professionals, and to ensure that brokers who market properties in Rancho Cucamonga
are aware of the business support services available to existing and potential tenants.
Marketing, Advertising and Public Relations - In 2009, the Agency continued to
maintain ongoing advertisements focusing on the recruitment of office users in several
local, regional and national industry publications. The Agency recently completed an
advertising campaign with the Inland Empire radio station, 590 KTIE, to spotlight local
businesses and promote tourism. Other tourism related advertisements were published
in the summer issues of travel publications, Sunset Magazine and the California and
Inland Empire Visitors Guides. To correspond with the west coast ICSC convention, the
Agency advertised in several publications during the months of May and September to
expand on the attraction of retail
organizations in the City.
E-Mail Marketing - The Rancho
Cucamonga Redevelopment Agency
launched its new e-mail marketing program
in 2002 and has developed various
marketing elements that help to promote
business activities and development
opportunities within the city. FastTrack, the
Agency's interactive "e-newsletter," is
distributed six times a year via e-mail to local businesses, brokers, developers, retailers
and the media. The newsletter provides the Agency with a valuable communication
tool for informing its target audience of changes in the business environment. Another
FIVE-YEAR IMPLEMENTATION PLAN
42
e-mail marketing element launched in 2002 is the Agency’s property update and site
selection “e-bulletin” Opportunities. This publication is distributed periodically to brokers,
developers, and retailers alerting them to selected property listings and retail availability.
The interactive features of the e-bulletin also allow recipients to connect to the Agency's
site selection web site, "Inside Rancho," and view additional properties. In December of
2006, the Agency launched the third component to its e-mail marketing program to
promote tourism. Electronic publications were sent to over 3,000 Fast-Track subscribers
providing business and tourism information to brokers and the public.
Special Marketing - Periodically, the Agency is involved in the development of
events that help market the community to potential business investors, visitors, and
tourists. Additionally, the Agency may also participate in projects that assist in the
branding and general promotion of the community. In 2007, the Agency completed a
Quality of Life Video, “Living the Dream”. The Video is the first major production project
in more than 10 years and received positive comments from viewers and awards.
Business Appreciation Week - Each year during the month of May the
Redevelopment Agency, in partnership with the Rancho Cucamonga Chamber of
Commerce, designates one week as Business Appreciation Week. This program was
created to recognize the valuable
contributions of the business community
and exemplify the City’s appreciation to all
Rancho Cucamonga businesses. This year
the Chamber of Commerce kicked off the
week long celebration by hosting its annual
Spring Swing Golf Tournament at the Sierra
Lakes Golf Course. The Agency wrapped up
the celebration with its annual Business
Appreciation Night event at the Epicenter, which hosted over 300 business owners and
their employees to a BBQ picnic and a fun-filled night of Quakes baseball, followed by a
post-game firework spectacular.
FIVE-YEAR IMPLEMENTATION PLAN
43
Wayfinding Directional Guide Sign Project - The Wayfinding Sign Taskforce has
been working together since 2008 to establish a guide sign program that will provide
vehicular directional assistance to places of interest throughout the community. The
taskforce is currently working on final selection of locations for the signs, the venues to
be listed on the signs, and has selected a company to fabricate the signs. Construction
on this project will begin later in 2009 and is expected to be completed in 2010.
Job Fairs - The Agency has participated in and will continue to co-host job fairs to
benefit local residents and others seeking employment, and local companies looking for
employees within the region. Partnerships with neighboring Cities, elected officials,
County, and other employment agencies/organizations will be encouraged to best
utilize limited resources and consolidate efforts.
Table III. Ongoing and Potential Economic Development Programs
Project Description
Impact on Economic Development
Total Estimated 2009-2014
Continuation of Existing Economic Development Programs including: Banner Promotion, Third Party, Broker Networking, Business Appreciation, Marketing, E-Mail Marketing, and Wayfinding Project
Prevent economic deterioration through establishment of new businesses and job creation.
TBD
Job Fairs Catalysts for Economic Growth TBD
Other Economic Development Opportunities
Prevent economic deterioration through establishment of new businesses and job creation.
TBD
FIVE-YEAR IMPLEMENTATION PLAN
44
Ongoing and Potential Community/Cultural Facilities
To extend the Agency's efforts in creating recreational and cultural opportunities,
and increasing open space, the Agency continues to facilitate activities within the
project area that support these objectives. Again, if the SERAF take by the State of $32.1
million in FY2009-2010 and $6.9 million in FY2010-2011 occurs, then the Agency will be
severely limited in its ability to complete many of the highlighted community and
cultural projects.
Central Park Phase II – This project has been put on hold due to previous ERAF
takes by the State. Approximately 60 acres remain to
be developed when funding can be secured. Phase II
of Central Park includes the Family Aquatics Center, 24
acres of park improvement and open space and the
fire station mentioned earlier. The concept, design
and philosophy behind Phase II run parallel with the
City’s Healthy RC program.
Property Acquisition (Vitoria Gardens) – In 2009, the Agency purchased a 5.4
acre parcel of property located on the southeast corner of Church and Arbor Lane. This
property is uniquely positioned for a mix of potential uses and is the last undeveloped
land adjacent to the Victoria Gardens Mall. The Agency intends for the site to be used
to complement Victoria Gardens and the City’s Cultural Center. Open space, Cultural or
Community facilities, and other uses are under consideration.
Etiwanda Train Depot – SANBAG and the City of Rancho Cucamonga reached
an agreement for the sale of the Etiwanda Train Depot structure and approximately ½
acre of the depot site. Purchase agreements for the sale of the structure and ½ acre as
well as lease agreements for the remainder of the site and trail are being drafted by
SANBAG and the City of Rancho Cucamonga. It is anticipated that the sale will be
complete by early spring of 2010.
The City’s goal is the adaptive re-use of the Pacific Electric Railroad Depot as an
interactive museum and trailhead. The Depot would benefit the community by
FIVE-YEAR IMPLEMENTATION PLAN
45
providing a link to the City’s history with opportunities for field trips, rest stop and picnic
area. The depot is adjacent to our newly completed Rails to Trails project. The museum
would highlight the importance of the Pacific Electric rail system in the development of
Southern California and the City of Rancho Cucamonga.
Historic Preservation – The Redevelopment Project Area encompasses a
significant portion of the City including many historic areas that pre-date cityhood. In
an effort to preserve its rich agricultural and cultural history, the Agency supports,
whenever possible, historic preservation projects and programs. In addition to creating
cultural value for its residents, these preservation activities also support the Agency’s
economic development objectives and tourism efforts.
Table IV. Community/Cultural Enhancement Projects
Project Description
Impact on Blight Elimination
Total Estimated 2009-2014
Central Park Phase II Provide cultural and recreational opportunities within the project area for remaining acreage/future phases.
TBD
Property Acquisition Provide cultural and recreational opportunities within the project area for remaining acreage/future phases.
TBD
Etiwanda Train Depot Preservation of Historic Site TBD
Ongoing and Potential Affordable Housing Projects and
Programs
The following summarizes the Agency’s efforts with regard to the use of its 20
percent housing set-aside funds. These projects and programs have been implemented
to meet the affordable housing needs of low- and moderate-income families and
FIVE-YEAR IMPLEMENTATION PLAN
46
seniors. Again, if the SERAF take by the State of $32.1 million in FY2009-2010 and $6.9
million in FY2010-2011 occurs, then the Agency will be severely limited in its ability to
complete many of the highlighted affordable housing projects.
San Sevaine Villas – In August of 2005, the Redevelopment Agency approved a
loan agreement with Northtown Housing Development Corporation for land
acquisition and construction of 225 affordable family units. Under the Redevelopment
Agency’s regulatory agreement for this project, the units will remain affordable at least
55 years. Of the $40.7 million loan commitment, an initial disbursement of $8.3 million
was made to acquire the 14-acre parcel and provide reimbursement of pre-development
expenses to the developer.
The subsequent disbursements were contingent upon the Agency’s approval of
the project through various stages, tax credit financing, entitlement process, grading,
and construction. The groundbreaking event for the project was held on July 13, 2009.
The project site is currently in the grading phase and will soon have pads certified and
ready for the construction of 225 units of workforce housing. The project is scheduled
to take approximately 18 months to complete and will be ready for lease up and should
be fully occupied in mid 2011. There are already interested families calling to be place
on the interest list for this project.
Villaggio On Route 66 - In 2008 the Redevelopment Agency executed a
Disposition and Development
Agreement with Workforce Home
Builder, LP for the construction of a
166-unit mixed-income workforce
housing project in the Agency’s
Redevelopment Project Area. The
project broke ground on September
2008 and currently is in its final
stages of construction. Nearly 50%
of the project is occupied with
almost two thirds of the units having been preleased. The project is expected to be fully
FIVE-YEAR IMPLEMENTATION PLAN
47
completed and occupied by December 2009. This will be the Agency’s first new
construction family complex since the Agency’s inception in 1981. The project will
provide much needed quality affordable housing in the City and conveniently located in
the heart of the City’s commercial corridor. The project not only achieves the Agency’s
goal of providing workforce housing, but it also achieves the goals of the Foothill
Specific Plan by providing more housing along Foothill Boulevard.
First Time Home Buyer Program - Since the program's inception in FY 1995/96,
the Agency has assisted 109 low- and moderate-income, first time home buyers with
silent second mortgages under this program.
The program is administered through the
Agency's agreement with Neighborhood
Housing Services of the Inland Empire (NHSIE),
a local non-profit organization specializing in
mortgage assistance programs for lower income
families. NHSIE also provides credit counseling
and home buyer workshops for income-
qualified applicants. Additionally, monies received from participants through a equity
share provision are returned to the Program to assist more families in purchasing their
first home. In February 2004, the Agency Board approved an increase to the program
for a maximum silent second loan of $80,000 in response to the significant increase in
housing costs in the City. In 2007, to address the foreclosure crisis, NHSIE initiated a
foreclosure hotline to assist homeowners in danger of losing their homes.
In 2008 the City received funding from the federal Neighborhood Stabilization
Program (NSP) and chose to direct a majority of the awarded funds into the First Time
Home Buyer Program, which the Agency is managing. The additional funds will allow
the Agency to offer financial assistance to families earning up to a 120% area median
income for the purchase of a home. To assist all applicants in their efforts to purchase
and maintain a home, the Agency also began funding HUD approved financial
management and property ownership classes.
FIVE-YEAR IMPLEMENTATION PLAN
48
Extended Affordability Terms on 498 units/60 new units - In August 2007, the
Agency entered into an Agreement with National Community Renaissance for $42.5
million to increase the affordability restrictions for 25 existing low-income units. In
addition, the Agreement added 60 units additional low-income units, which will be
phased in over a five-year period and will be completed by December 2012.
Land-banked Properties - The Redevelopment Agency acquired several
properties in the city for future affordable housing projects. These properties were "land
banked" as part of the Affordable Housing Strategy until such time as public-private
partnership opportunities allow for development. One of the properties was deemed
unsuitable for development by the Redevelopment Agency was sold in August 2002 to
a private developer. The proceeds were deposited in the Housing Set-Aside Fund. The
Agency also acquired a property in 1993 (Regina Winery) that was to be used for a
potential housing project. Funds for this purchase were originally taken from the
housing fund. However, after the property was deemed to be unsuitable as an
affordable housing site and ownership of the property was transferred to the City of
Rancho Cucamonga. As a result of this action, the housing fund was reimbursed.
Foreclosure and Prevention Workshops – Over the past year, in response to the
increases in foreclosures within the City and the Inland Empire, the Agency partnered
with local elected officials, neighboring cities, and national lenders to facilitate loan
modification and adjustments for those in need. A total of three workshops have been
hosted, and approximately 300, 600, and 250 southern Californian homeowners
attended each of the workshops.
Mobile Home Rental Assistance Program – In June 2008, the Agency approved
the implementation of a Mobile Home Rental Assistance Program that provides up to
$50 per month towards the rent of a mobile home space for families that are at or
below 60% of the county median income and paying 30% or more of their income on
housing. In 2009, staff recommended that the benefit amount be increased to $100 per
month to better serve the participants. Staff continues to administer and market the
program.
FIVE-YEAR IMPLEMENTATION PLAN
49
Mobile Home Accord – In 2008, the Agency took over the administration of the
City’s Mobile Home Accord, which was previously managed by the City Manager’s
Office. The Mobile Home Accord serves as a rent stabilization agreement between the
City and the eight mobile home park owners, which limit how much park owners can
raise rents based on the Consumer Price Index (CPI).
Table V. Ongoing and Potential Affordable Housing Projects
Project Description
Provision of Affordable Housing
Total Estimated 2009-2014
San Sevaine Villas Provide quality affordable housing for low- and moderate-income households. $39,000,000
Villaggio on Route 66 Provide quality affordable housing for low- and moderate-income households. $27,565,000
First Time Home Buyer Program
Provide quality affordable housing for low- and moderate-income households. $5,000,000
Extended Affordability Provide quality affordable housing for low- and moderate-income households. $42,500,000
Foreclosure and Prevention Workshops
Preserve quality affordable housing for low- and moderate- income households. $10,000
Mobile Home Rental Assistance
Preserve quality affordable housing for low- and moderate- income households. $500,000
The specific programs and projects identified above include descriptions of how
the alleviation of blight will be addressed as a result of the project. The cumulative
effects of all the projects will have a greater impact in alleviating blight in the
Redevelopment Project Area by the following actions:
Increasing employment opportunities through job creation; Increasing residential and business stability through improved flood
control and traffic circulation; Encouraging private investment in the project area; Enriching historical significance through preservation of historical
structures; Providing cultural and recreational opportunities in the project area; Creating housing opportunities affordable to all income levels'
FIVE-YEAR IMPLEMENTATION PLAN
50
Encouraging and fostering economic development in the project area; Providing a safe environment for residents and business owners through
adequate police and fire services. Providing facilities that serve and maintain the project area.
FIVE-YEAR IMPLEMENTATION PLAN
51
Housing Requirements
It should be noted that while the Redevelopment Agency has provided
assistance for over 2,000 units, the Agency is only receiving credit for a little over 1,000
units. This is due to the fact that some of the units are located outside the project area,
triggering the 2-for-1 rule, thus resulting in the Agency receiving credit for only half of
these units.
Table VI. Affordable Housing Unit Summary
Project Tenure
35% Median Income
45% Median Income
60% Median Income
90% Median Income
Unit Total
% RDA Assist Units
# RDA Assist Units
Other Tax
Credit Assist
Total % Afford-able
Villa del Norte R 32 15 41 0 88 49% 43 51% 100%
Las Casitas R 0 7 7 0 14 49% 7 100%
Rancho Verde* R 20 32 20 32 248 42% 104 (52) 42%
Rancho Verde East* R 6 13 13 8 40 100% 40 (20) 100%
Mountainside R 48 48 48 44 384 49% 188 49%
Monterey Village R 28 28 28 26 220 50% 110 50%
Sycamore Springs* R 30 30 30 6 240 40% 96 (48) 40%
Pepperwood R 10 10 16 10 230 20% 46 20%
Villa Pacifica* R 0 0 158 0 158 49% 77 (39) 51% 100%
Habitat for Humanity O 0 1 0 0 1 100% 1 100%
Heritage Pointe* R 12 12 24 0 48 49% 24 (12) 51% 100%
Olen Jones* R 15 28 53 0 96 49% 47 (24) 51% 100%
NHDC In-Fill O 0 0 0 40 40 100% 40 100%
Sunset Heights * (Woodhaven) R 20 40 57 0 117 100% 117 (58) 100%
Villaggio On Route 66 R 22 44 65 0 166 88% 131 17% 88%
First-Time Homebuyers O 0 1 20 88 109 100% 109 (74) 100%
San Sevaine Villas** R 36 73 55 59 225 100% 223
(112) TC 100%
Total 279 382 635 313 2424 46% (35%)
1403 (1005) 74%
* Units outside project area (2-for-1 rule applies). ** This project is currently under construction. R=rental and O=owner
FIVE-YEAR IMPLEMENTATION PLAN
52
Table VII contains the City’s RHNA requirements for the period of 2006-2014 and
the requirements for each income category listed; very low, low, moderate and above
moderate. The Planning Department is drafting updated Housing Elements and
Housing Production Plan to comply with RHNA requirements.
Table VII. 2006-2014 RHNA Requirements
In addition to requiring reporting of specific goals and objectives of the
Redevelopment Agency, the Implementation Plan must comply with Health and Safety
Code Section 33334.4. The Affordable Housing Unit Summary table below contains the
data for units produced by income category as required by the code.
Table VIII. Affordable Housing Unit Summary - 2009
Income Group 2006-2014 RHNA Requirements
Percent of Units
Very Low Income 317 25%
Low Income 216 17%
Moderate Income 245 19%
Above Moderate Income 504 40%
Total Units 1282 100%
Income Group Number of Units Percent of Units
Very Low Income 259 18%
Low Income 907 64%
Moderate Income 253 18%
Total Units 1419 100%
FIVE-YEAR IMPLEMENTATION PLAN
53
Section 33334.4 of the Health and Safety Code also requires the number of units
available to both families and people over the age of 65 be in at least the same
proportion as the total population of the community reported in the most recent census
data by the United States Census Bureau. Figure II below illustrates the percentages for
individuals under and over 65 years of age in the City of Rancho Cucamonga, according
to the 2000 Census.
Figure II – Percent of Community that are under/over 65 years of age.
The previous Plan acknowledged the requirement of Health & Safety Code
Section 33334.4 and the need to provide family and senior housing in the proportion to
the City population. Over the next five years the Agency will continue to expend and
provide units in the same proportion to the City population as required by the Health &
Safety Code. During the period of 2004-2009, the Agency assisted with development of
family and workforce housing, but during the period of 1999-2004, the Agency focused
more on senior housing projects.
The following table and data provide additional information regarding the
expenditures of the Housing Fund for each group during the period of FY 2004-2005 to
FY 2008-2009. Each table also identifies programs that the Agency is currently
undertaking or intends to undertake to ensure that expenditures from the Housing
Fund are in proportion with the requirements of Section 33334.4.
Rancho Cucamonga Population – 2000 Census
Under age 65 Over age 65
FIVE-YEAR IMPLEMENTATION PLAN
54
Table IX. Housing Fund Expenditures
FY 2004 - 2005
Revenue Project Expenditure Units
Assisted Housing Type
Family Seniors
VL&L M VL&L M
First-Time Homebuyers $756,200 10 0/4 6
Wells Fargo Bank Debt $371,674
CHFA Reserve on behalf of So. Cal. Housing
$337,600
Bank of New York- Northtown pledge $1,400,000
Admin (1) $178,889
Total $3,044,363 10
(1) Includes administrative/legal/property maintenance.
Total Expenditures
Total Family Expenditures
Total Senior Expenditures
Percent Family Expenditures
Percent Senior Expenditures
$12,692,244 $3,044,636 $0 100% 0%
FIVE-YEAR IMPLEMENTATION PLAN
55
Table X. Housing Fund Expenditures
FY 2005 - 2006
Revenue Project Expenditure Units
Assisted Housing Type
Family Seniors
VL&L M VL&L
M
First-Time Homebuyers $80,000 1 0/1
San Sevaine $5,894,976 (1) 221 (2) 110/55 56
Villagio on Route 66 $8,177,674 (1) 131 (2) 66/65
Woodhaven $6,906,286 (1) 116 (2) 60/56
Pepperwood $7,203,242 (1) 46 (2) 24/13 9
Villa Pacifica $5,974 (1) 157 (2)
63/0 94
Wells Fargo Bank Debt $371,674
CHFA Reserve on behalf of So. Cal. Housing $337,600
Bank of New York- Northtown pledge $1,400,000
Admin (3) $239,370
Total $30,617,096 672
(1) Partial Funding. (2) Total units for completed project. (3) Includes administrative/legal/property maintenance.
Total Expenditures
Total Family Expenditures
Total Senior Expenditures
Percent Family Expenditures
Percent Senior Expenditures
$30,617,096 $30,611,122 $5,974 99% 1%
FIVE-YEAR IMPLEMENTATION PLAN
56
Table XI. Housing Fund Expenditures
FY 2006 - 2007
Revenue Project Expenditure Units
Assisted Housing Type
Family Seniors
VL&L M VL&L
M
First-Time Homebuyers $642,400 8 0/2 6
San Sevaine $612,439 (1) 221 (2)
110/55 56
Villagio on Route 66 $46,855 (1) 131 (2) 66/65
Woodhaven $1,514,864 (1) 116 (2) 60/56 Pepperwood
$8,171,012 (1) 46 (2) 24/13 9
Rancho Verde East $641,462 (1) 39(2) 19/20
Wells Fargo Bank Debt $371,674
CHFA Reserve on behalf of So. Cal. Housing $337,600
Bank of New York- Northtown pledge $1,400,000
Admin (3) $251,335
Total $12,252,041 561
(1) Partial Funding. (2) Total units for completed project. (3) Includes administrative/legal/property maintenance.
Total Expenditures
Total Family Expenditures
Total Senior Expenditures
Percent Family Expenditures
Percent Senior
Expenditures
$12,252,041 $12,252,041 $0 100% 0%
FIVE-YEAR IMPLEMENTATION PLAN
57
Table XII. Housing Fund Expenditures
FY 2007 - 2008
Revenue Project Expenditure Units
Assisted Housing Type
Family Seniors
VL&L M VL&L
M
First-Time Homebuyers $793,393 10 0/3 7
San Sevaine $933,677 (1) 221 (2) 110/55 56
Pepperwood $4,154,542 (1) 46 (2) 24/13 9 Rancho Verde East
$2,107,255 (1) 39(2) 19/20
Wells Fargo Bank Debt $371,674
CHFA Reserve on behalf of So. Cal. Housing $337,600
Bank of New York- Northtown pledge $1,400,000
Admin (3) $476,204
Total $10,574,345 316
(1) Partial Funding. (2) Total units for completed project. (3) Includes administrative/legal/property maintenance.
Total Expenditures
Total Family Expenditures
Total Senior Expenditures
Percent Family Expenditures
Percent Senior Expenditures
$10,574,345 $10,574,345 $0 100% 0%
FIVE-YEAR IMPLEMENTATION PLAN
58
Table XIII. Housing Fund Expenditures
FY 2008 - 2009
Revenue Project Expenditure Units
Assisted Housing Type Family Seniors
VL&L M VL&L M
First-Time Homebuyers $1,538,842 20 0 (2) 18 44
Mobile Home Rental Assistance $5,700 59 15
San Sevaine Villas $1,328,753 (1) 221 (2)
110 (55) 56
Villago on Route 66 $7,756,399 131 (2) 66
(65)
CHFA Reserve on behalf of So. Cal. Housing $337,600
Bank of NY Northtown pledge $1,400,00
Administration $208,170
Total $12,692,244 431
(1) Partial Funding. (2) Total units for completed project. (3) Includes administrative/legal/property maintenance.
Total Expenditures
Total Family Expenditures
Total Senior Expenditures
Percent Family Expenditures
Percent Senior
Expenditures
$12,692,244 $12,687,969 $4,275 99% 1%
FIVE-YEAR IMPLEMENTATION PLAN
59
Housing Compliance
State Law requires that Redevelopment Agencies in the State of California set
aside twenty percent (20%) of the tax increment received into a low and moderate
income housing fund. Agencies must use this fund only for the purpose of increasing,
improving, and preserving affordable housing in the community. An existing
agreement between the Rancho Cucamonga Redevelopment Agency and Western
Center for Law and Poverty stipulates that any units assisted by the Redevelopment
Agency remain affordable for the longest period allowed by law. Current law stipulates
a minimum of at least forty-five (45) years for ownership housing and fifty-five (55) years
for rental housing.
In 1990, the Redevelopment Agency approved an Affordable Housing Strategy
as recommended by the Affordable Housing Task Force. The goal of this plan was to
promote new construction and rehabilitation of existing units affordable for low and
moderate-income residents. As a further stipulation in the agreement with Western
Center for Law and Poverty, assistance utilizing the Housing Set-Aside Fund is limited to
the following four income levels:
Level I Families earning less than 35% of the area median income, adjusted for
family size
Level II Families earning less than 36% and 45% of the area median income,
adjusted for family size
Level III Families earning less than 46% and 60% of the area median income,
adjusted for family size
Level IV Families earning less than 61% and 90% of the area median income,
adjusted for family size
The Agreement further requires that not less than 50% of the units assisted by
the Agency must be available for very low income households, of which one-third must
be available to Level I families.
FIVE-YEAR IMPLEMENTATION PLAN
60
Housing Replacement Activity
The Rancho Cucamonga Redevelopment Agency does not anticipate that any
low or moderate income housing units will be removed as a result of projects or
programs proposed in the Implementation Plan. If, however, some unforeseen activity
does require removal of units, the Redevelopment Agency will comply with Section
33413.5 of the Health and Safety Code, which requires that the Agency adopt a
replacement housing plan thirty (30) days prior to entering into any agreement which
results in the destruction of units affordable to low and moderate income families.
Additionally, there are no prior replacement housing obligations that the
Redevelopment Agency is required to address as part of past Agency projects.
Five-Year Proposed Housing Programs and Projects
The Agency will aggressively continue to provide, improve, and maintain the
City's supply of affordable/workforce housing by leveraging opportunities with local
non-profits, county, state and federal agencies. The Agency will continue to explore
opportunities for development of land-banked parcels. The Agency will also continue
contacts with apartment complex owners, both current partners and potential future
ones, to purchase additional affordability covenants or extend the term of affordability
for existing family units.
With the shortage of available land for residential development remaining in the
City due to the housing boom that occurred in 2000 to 2005, the Agency will also
explore other options to provide affordable family projects, including the purchase and
rehabilitation of existing homes or purchase of single vacant lots for in-fill development,
to be sold or rented upon completion to qualifying families.
The table below provides additional information regarding the estimated
expenditures of the Housing Fund for the period of FY 2009-2010 to FY 2013-2014.
FIVE-YEAR IMPLEMENTATION PLAN
61
Table XIV. Housing Estimated Revenues and Expenditures
Estimated Revenues 2009-10 2010-11 2011-12 2012-13 2013-14
2007 Bond Proceeds $31,272,859 $0 $0 $0 $0
Estimated Tax Increment $18,647,965 $19,020,925 $19,401,343 $19,789,370 $20,000,000
Total Revenue $49,920,824 $19,020,925 $19,401,343 $19,789,370 $20,000,000Estimated Units to be Assisted 221 238 155 155 155
Estimated Expenditures $49,920,824 $17,000,000 $17,340,000 $17,686,800 $18,040,536
FIVE-YEAR IMPLEMENTATION PLAN
62
Conclusion
The Agency's Five-Year Implementation Plan identifies potential projects,
programs and expenditures during the next five years in conformance with the Rancho
Redevelopment Plan and California Community Redevelopment Law. The City of
Rancho Cucamonga has realized the need to target economic development activities
toward job growth, business expansions and to create a job-to-housing balance. To
further this goal, the Agency has implemented an aggressive program to revitalize
many commercial and industrial areas while providing affordable/workforce housing to
support the local labor pool.
The Redevelopment Agency's assistance in the completion of major infrastructure
improvements has significantly stimulated private investment in the project area. This is
evidenced by the following:
Creation of approximately 14,811 new jobs between 2003 to 2007 The addition of over 5.3 million square feet of industrial space from 2000
to 2003. The addition of over 1,234,052 square feet of new office space built
between 2004-2008. At least 160 firms averaging 81 workers to expand into Rancho
Cucamonga from 1994 to 2008. Local payroll in excess of $2.5 billion in 2007. Taxable sales in excess of $2.4 billion in 2008.
Furthermore, through partnerships with nonprofit agencies, over 800 families
have been provided safe, decent affordable housing, and the numbers will continue to
increase.
Although substantial progress has been made, significant blighting conditions
remain in the Project Area. Through the Implementation Plan, and plans of the future,
the Redevelopment Agency strives to alleviate blight and improve economic conditions
for the residents and business owners of the City of Rancho Cucamonga.
FIVE-YEAR IMPLEMENTATION PLAN
63
Comments
Comments and questions regarding the Rancho Cucamonga Redevelopment Agency's
2010-2014 Implementation Plan may be forwarded to:
Rancho Cucamonga Redevelopment Agency 10500 Civic Center Drive Rancho Cucamonga, CA 91730 P. (909) 477-2700 F. (909) 477-2848 email: [email protected]