RENÉE MARTÍNEZ (CHIEF INFORMATION OFFICER)
GREG RIDGLEY (DEPUTY GENERAL COUNSEL)
RICK DESIMONE (WATER RIGHTS ABSTRACTING BUREAU CHIEF)
Office of the State Engineer-Interstate Stream Commission
WATER RIGHTS DATA QUERY, ANALYSIS & EXCHANGE SYSTEM
- Implementation Phase --Project Certification Committee
Presentation -
Appropriations Background
Fiscal Year FY2009
Amount $200,000 GF
Funding Source(s) 48th Legislature - State Of New Mexico - Second Session, 2008 HAFC Substitute for House Bills 2, 3, 4, 5, 6 and 10 (24) STATE ENGINEER - To complete development and implementation of
the data extract, transform and load tools and processes to allow data exchange between the water rights adjudication tracking system and the waters administration technical engineering resource system
The appropriation may be expended in fiscal years 2008, 2009 and 2010. Any unexpended balances remaining at the end of fiscal year 2010 shall revert to the general fund
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
2
Agency Background
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
3
The adjudication of water rights by the Litigation and Adjudication Program (LAP) and the administration of water rights by the Water Resources Allocation Program (WRAP) are two distinct yet complementary activities performed by the Office of the State Engineer
WRATS - The Water Rights Adjudication Tracking System is used to generate legal pleadings and manage its data and attorney work product as water rights are adjudicated by the court system
WATERS – The Water Administration Technical Engineering System is used to manage a variety of historical and current data and work products to facilitate the processing of water rights applications and to administer water rights
Project Purpose
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
4
The purpose of this project is to design, build and implement a data query, analysis and exchange system that allows users to:
Query, extract and associate data within the primary adjudication (WRATS) and water rights administration (WATERS) databases and other data stores
Notify appropriate parties when certain events occur in one system or the other
Automate the process of exchanging data between databases
The new system is needed to support the current and future business activities of the Agency
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
5
Program Alignment
The program activities to be supported by the new system are:
Start of Adjudication – Users need a snapshot of the water rights history of a geographic area at the outset of an adjudication
Ongoing Adjudication – Users need periodic updates of water rights transactions (declarations, permits, licenses, ownership changes) that take place during the course of the adjudication
Ongoing Water Rights Administration – Users need to research the current water uses that are identified by hydrographic surveys and to be able to determine when water rights transactions may interact with an ongoing legal action
Completion of Adjudication - Users need to pull offers of judgment resulting from the adjudication into WATERS
System Diagram
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
6
WATERS WRATS
Water Rights Adjudication Tracking System Water Administration Technical Engineering System
Query, Analysis & Exchange
System
Query, Analysis & Exchange
System
Users
Users
Users
Users
• Owners• Claimants• Legal Pleadings• Judicial Determinations• Consent Orders
• Owners• Applications• Permits• Transfers• Wells• Documents
Microsoft SQLInformix
Map ViewMap View Table ViewTable View
Project Planning & Status
Planning & Initiation Phase – Project Deliverables Project Business Case Project Charter Project Management Plan
Requirements-Analysis Phase – Project Deliverables “As-Is” Environment Discovery Report “To-Be” Environment Discovery Report System Design Alternatives Assessment Report System Prototype Scope of Work
Design Phase – Project Deliverables WE ARE HERE
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
7
Project Schedule & Key Deliverables
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
8
Phase Deliverable Due Date & Cost
Requirements & Analysis System RequirementsSystem Design Alternatives
October ‘08 ($35.0)*
Design System PrototypeSystem Design SpecificationSystem Implementation Plan
January ‘09 ($25.0)*
Build & Test Development EnvironmentIterative BuildsTestingTraining Materials
July ‘09 ($90.0)
Acceptance Testing & Training
User Acceptance Test Results Training ScheduleProduction Environment
September 09 ($80.0)
Deploy Post-Implementation Assessment October ‘09 ($20.0)
Total (*$50.k funded using operating budget) $250.0
Project Governance
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
9
• Agency-IT Strategy Integration• Agency IT Investment Decisions• Agency IT Project Portfolio Management
• Project Task Execution• Project Issue & Risk Management
• Program-IT Strategy Integration• Project Investment Decisions• Project Scope Management
OSE-ISC IT Governance Committee MeetingCo-chairs: State Engineer, CIO
Project Steering CommitteeCo-chairs: LAP Manager, WRAP Manager
Project TeamProject Manager, IT Staff, Program Staff, Contractor
DoIT Infrastructure Impact
11/19/2008OSE/ISC Water Rights Query, Analysis & Exchange System
10
Data Center Will use Agency VMWare platform housed at SIMMS or Bataan
depending on capacity and cost-benefit
Telecommunications (Network Bandwidth) Low transaction volume (less than 50 per day). Internal users only.
Enterprise Applications Potential use of State Email System for event notifications
Business Continuity & Disaster Recovery Data will have a back-up schedule
Security User and data access privileges will be specific to user and role
Questions
OSE/ISC Water Rights Query, Analysis & Exchange System 11/19/2008