Québec–New Hampshire Interconnection INFORMATION ON THE SOLUTION SELECTED Summer 2015 The goal of this Hydro-Québec TransÉnergie project is to increase the energy interchange capacity between Québec and New England by building an interconnection to link Québec’s power grid with New Hampshire’s. Commissioning is scheduled for 2019. Connecting the grids The project involves the construction of a 320-kV direct-current transmission line, about 80 km long, in Québec. This line will be extended into the U.S.A. and will connect Des Cantons substation in Val-Joli to Franklin sub- station in southern New Hampshire. To supply the planned transmission line, equipment that converts alter- nating current to direct current will be added to Des Cantons substation. No expansion of the existing Des Cantons substation is required.

Upload: others

Post on 17-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Québec–New Hampshire Interconnection · 2015E1101-A. Printed on paper made in Québec from 100% postconsumer recycled fibre. Ce document est également publié en français. This

Québec–New Hampshire Interconnection

INFORMATION ON THE SOLUTION SELEC TED • Summer 2015

The goal of this Hydro-Québec TransÉnergie project is to increase the energy interchange capacity between Québec and New England by building an interconnection to link Québec’s power grid with New Hampshire’s. Commissioning is scheduled for 2019.

Connecting the gridsThe project involves the construction of a 320-kV direct-current transmission line, about 80 km long, in Québec. This line will be extended into the U.S.A. and will connect Des Cantons substation in Val-Joli to Franklin sub-station in southern New Hampshire. To supply the planned transmission line, equipment that converts alter-nating current to direct current will be added to Des Cantons substation. No expansion of the existing Des Cantons substation is required.

Page 2: Québec–New Hampshire Interconnection · 2015E1101-A. Printed on paper made in Québec from 100% postconsumer recycled fibre. Ce document est également publié en français. This

2

##

##

##

##

####

##

##

##

##

!!

Bury, M

Stoke, M

Newport, M

Sherbrooke, V

Coaticook, V

Compton, M

Cookshire-Eaton, V

Saint-Malo, M

Val-Joli, M

Dixville, M Saint-Herménégilde, M

Saint-Isidore-de-Clifton, M

Barnston-Ouest, M

Ascot Corner, M

Saint-Claude, M

La Patrie, M

East Hereford, M

Martinville, MWaterville, V

Sainte-Edwidge-de-Clifton, CT

Saint-Venant-de-Paquette, M

Chartierville, M

Windsor, V

Cleveland, CT

Stanstead-Est, M

SawyervilleJohnville

Birchton

COATICOOK(MRC)

LE HAUT-SAINT-FRANÇOIS(MRC)

LE VAL-SAINT-FRANÇOIS(MRC)

SHERBROOKE(TÉ)

Windsorsubstation

Coaticooksubstation

Des Cantons substation (735 kV)

Poste de Weedon

Rivière

Rivière C

oaticook

Rivière

Rivière

LacMassawippi

aux

Saumons

Massa

wippi

Moe

Rivière

LacMagog

LacWallace

Saumon

Lac Lindsay

Saint-Franço

is

NEW HAMPSHIRE

VERMONTU.S.A

SherbrookeAirport

QUÉBEC

!(A

Monts Stoke450-kV line

450-kV line

Selected route

147

206

206

251

251

251

216

253

253

212

108

214

112

10

10

108

253

143

141

Mont Hereford

71°40'

71°40'

72°0'

72°0'

45°2

0'

45°2

0'

45°0

'

45°0

'

Information for publics concerned by the project. For any other use, contact Géomatique, Hydro-Québec Équipement et services partagés.

!

!

!Boston

Québec

Montréal

U.S.A.

Ontario

NewBrunswick

NovaScotia

Québec

P.E.I.

0 200 km

0 5 10 km

MTM, zone 7, NAD837178_bu_hq_038_solution_150812a.mxd

120 kV

450 kV or 735 kV

Transmission substations and lines

Regional county municipality (MRC) orequivalent territory (TÉ)

Municipality

Boundaries

Project components

Study area

Selected route

Route and variant studied

#

#

##

##

##

##

####

##

##

##

##

!!

Bury, M

Stoke, M

Newport, M

Sherbrooke, V

Coaticook, V

Compton, M

Cookshire-Eaton, V

Saint-Malo, M

Val-Joli, M

Dixville, M Saint-Herménégilde, M

Saint-Isidore-de-Clifton, M

Barnston-Ouest, M

Ascot Corner, M

Saint-Claude, M

La Patrie, M

East Hereford, M

Martinville, MWaterville, V

Sainte-Edwidge-de-Clifton, CT

Saint-Venant-de-Paquette, M

Chartierville, M

Windsor, V

Cleveland, CT

Stanstead-Est, M

SawyervilleJohnville

Birchton

COATICOOK(MRC)

LE HAUT-SAINT-FRANÇOIS(MRC)

LE VAL-SAINT-FRANÇOIS(MRC)

SHERBROOKE(TÉ)

Windsorsubstation

Coaticooksubstation

Des Cantons substation (735 kV)

Poste de Weedon

Rivière

Rivière C

oaticook

Rivière

Rivière

LacMassawippi

aux

Saumons

Massa

wippi

Moe

Rivière

LacMagog

LacWallace

Saumon

Lac Lindsay

Saint-Franço

is

NEW HAMPSHIRE

VERMONTU.S.A

SherbrookeAirport

QUÉBEC

!(A

Monts Stoke450-kV line

450-kV line

Selected route

147

206

206

251

251

251

216

253

253

212

108

214

112

10

10

108

253

143

141

Mont Hereford

71°40'

71°40'

72°0'

72°0'

45°2

0'

45°2

0'

45°0

'

45°0

'

Information for publics concerned by the project. For any other use, contact Géomatique, Hydro-Québec Équipement et services partagés.

!

!

!Boston

Québec

Montréal

U.S.A.

Ontario

NewBrunswick

NovaScotia

Québec

P.E.I.

0 200 km

0 5 10 km

MTM, zone 7, NAD837178_bu_hq_038_solution_150812a.mxd

120 kV

450 kV or 735 kV

Transmission substations and lines

Regional county municipality (MRC) orequivalent territory (TÉ)

Municipality

Boundaries

Project components

Study area

Selected route

Route and variant studied

#

#

Environmental studies From the start of the draft-design study, Hydro-Québec delineated a vast study area to expand its knowledge of the territory. Hydro-Québec confirmed that the route with the least impact consists in running the new 320-kV line near the existing 450-kV line over the longest possible distance.

The study area (571 km2) covers parts of three regional county municipalities (MRCs): Val-Saint-François, Haut-Saint-François and Coaticook. Within these MRCs, it crosses through the following municipalities: Val-Joli, Stoke, Ascot Corner, Cookshire-Eaton, Saint-Isidore-de-Clifton, Martinville, Sainte-Edwidge- de-Clifton, Saint-Malo, Saint-Venant-de-Paquette, East Hereford and Saint-Herménégilde.

Work completed in recent monthsEnvironmental field surveys were carried out in spring and summer 2015.

Field crews recorded numerous com-ponents of the biophysical environment (rare plants, snakes, etc.) in the section of the new line route that runs parallel to the existing 450-kV line and along the path of the variants studied.

Each variant was evaluated based on its impacts on the region’s landscape, as well as on the human and natural environments (noise, archeology, etc.).

Key role of host community’s commentsIn recent months, Hydro-Québec has been working with local authorities to obtain information on the host community and gather their opinion on the route under study (i.e., the section that runs parallel to the 450-kV line and the four variants in the other section). In addition, last June, we held meetings with the host community to present the project and gather comments. The community’s input had a decisive influence on the solution selected.

Location criteria for the lineIn developing the line route, the following main criteria were taken into account: • Run the line along the existing 450-kV line wherever

possible.

• Avoid siting near homes as much as possible.

• As much as possible, avoid sensitive elements such as farmland, sugar bush operations, exceptional forest ecosystems, habitats of special-status plant and animal species, wetlands and recreational or tourist sites.

• Avoid the highlands of the Mont Hereford massif.

• Avoid open spaces and sites offering panoramic views.

• Optimize line design with a view to harmonious integration into the environment.

Page 3: Québec–New Hampshire Interconnection · 2015E1101-A. Printed on paper made in Québec from 100% postconsumer recycled fibre. Ce document est également publié en français. This

3

"

"

"

Coaticook, V

Compton, M

Saint-Malo, M

Dixville, M

Saint-Herménégilde, M

Saint-Isidore-de-Clifton, M

East Hereford, M

Sainte-Edwidge-de-Clifton, CT

Saint-Venant-de-Paquette, M

NEW HAMPSHIRE

VERMONT

253251

251

206

206

253

147

147

141

141

Rivière

Rivière

Saumons

Moe

Rivière

aux

Lac Lindsay

Lac Wallace

Coaticook

Riviè

re

Hall

COATICOOK(MRC)

COATICOOK(MRC)

QUÉBEC

U.S.A.

Ch. de Coaticook

9e Rang

Ch. des Côtes

Ch. du 9e-Rang

West Stewartstown

Stewartstown

Pittsburg

Happy CornerMont Hereford

450-kV line

¬\

Selected route

71°30'

71°30'

71°45'

71°45'

45°0

'

45°0

'

Information for publics concerned by the project. For any other use, contact Géomatique, Hydro-Québec Équipement et services partagés.

!(A

0 2 4 km

MTM, zone 7, NAD837178_bu_hq_039_solution_sect_sud_150812a.mxd

Project components

Study area

Selected route

Proposed crossing point¬\

International border

Regional county municipality (MRC) orequivalent territory (TÉ) boundary

Municipal boundary

450-kV transmission line

"

"

"

Coaticook, V

Compton, M

Saint-Malo, M

Dixville, M

Saint-Herménégilde, M

Saint-Isidore-de-Clifton, M

East Hereford, M

Sainte-Edwidge-de-Clifton, CT

Saint-Venant-de-Paquette, M

NEW HAMPSHIRE

VERMONT

253251

251

206

206

253

147

147

141

141

Rivière

Rivière

Saumons

Moe

Rivière

aux

Lac Lindsay

Lac Wallace

Coaticook

Riviè

re

Hall

COATICOOK(MRC)

COATICOOK(MRC)

QUÉBEC

U.S.A.

Ch. de Coaticook

9e Rang

Ch. des Côtes

Ch. du 9e-Rang

West Stewartstown

Stewartstown

Pittsburg

Happy CornerMont Hereford

450-kV line

¬\

Selected route

71°30'

71°30'

71°45'

71°45'

45°0

'

45°0

'

Information for publics concerned by the project. For any other use, contact Géomatique, Hydro-Québec Équipement et services partagés.

!(A

0 2 4 km

MTM, zone 7, NAD837178_bu_hq_039_solution_sect_sud_150812a.mxd

Project components

Study area

Selected route

Proposed crossing point¬\

International border

Regional county municipality (MRC) orequivalent territory (TÉ) boundary

Municipal boundary

450-kV transmission line

Selected line routeBased on the results of its studies and the comments from community representatives and the public, Hydro-Québec has opted for the route described below.

For 80% of its length, from Des Cantons substation to the municipality of Saint-Malo, the planned line will run along the east side of the 450-kV line.

In the southern section, Hydro-Québec studied four variants that took into account technical and environmental criteria and the community’s suggestions and concerns. To reach the crossing point, the line will run west of the mountain, mainly because this side allows for a better integration into the landscape. By selecting this route, Hydro-Québec aims to bypass Mont Hereford and not interfere with outdoor activities, which are practiced more widely east of the mountain.

In addition, Hydro-Québec is currently working on optimizing the selected route by taking into account comments from residents and local authorities.

Tangible support for community developmentHydro-Québec sees its projects as an opportunity to participate in the development of host communities. With this in mind, it grants eligible organizations funding equivalent to 1% of the initially authorized value of the facilities covered by the Integrated Enhancement Program, to be used for local enhancement initiatives that improve the community.

Improved mitigation measuresStarting at the project design phase, Hydro-Québec implements a number of mitigation measures, including selecting the most suitable types of towers and careful tower siting. In this project, towers will be erected side by side when possible when the two lines are parallel, especially in open areas.

Page 4: Québec–New Hampshire Interconnection · 2015E1101-A. Printed on paper made in Québec from 100% postconsumer recycled fibre. Ce document est également publié en français. This

2015E1101-APrinted on paper made in Québec from 100% postconsumer recycled fibre.

Ce document est également publié en français. This is a translation of the original French text.

26.5 m 10 m60 m

53 m

30 m

26.5 m 10 m60 m

53 m

30 m

Pylône et emprise types lorsque la ligne projetée est juxtaposée à la ligne existante

7178

_bu_

hq_0

41_p

yl_1

5080

4a.F

H10

Guyed towers

Self-supporting towers

Aver

age

heig

ht: 3

5 m

Des Cantons–New England 450 kV DC

Planned line

Québec–New Hampshire320 kV DC

Aver

age

heig

ht: 4

0 m

Existing right-of-way

Existing right-of-wayPlanned right-of-way

average

Aver

age

heig

ht: 3

5 m

Des Cantons–New England 450 kV DC

Planned line

Québec–New Hampshire320 kV DC

Aver

age

heig

ht: 4

0 m

Existing right-of-way

Existing right-of-wayPlanned right-of-way

average

Information for publics concerned by the project. For any other use, contact Géomatique, Hydro-Québec Équipement et services partagés.

East

East West

West

26.5 m 10 m60 m

53 m

30 m

26.5 m 10 m60 m

53 m

30 m

Pylône et emprise types lorsque la ligne projetée est juxtaposée à la ligne existante

7178

_bu_

hq_0

41_p

yl_1

5080

4a.F

H10

Guyed towers

Self-supporting towers

Aver

age

heig

ht: 3

5 m

Des Cantons–New England 450 kV DC

Planned line

Québec–New Hampshire320 kV DC

Aver

age

heig

ht: 4

0 m

Existing right-of-way

Existing right-of-wayPlanned right-of-way

average

Aver

age

heig

ht: 3

5 m

Des Cantons–New England 450 kV DC

Planned line

Québec–New Hampshire320 kV DC

Aver

age

heig

ht: 4

0 m

Existing right-of-way

Existing right-of-wayPlanned right-of-way

average

Information for publics concerned by the project. For any other use, contact Géomatique, Hydro-Québec Équipement et services partagés.

East

East West

West

Typical towers and right-of-way when planned line is parallel to existing line

26.5 m10 m

60 m53 m

30 m

26.5 m10 m

60 m53 m

30 m

Pylô

ne et em

prise typ

es lorsq

ue la lig

ne

pro

jetée est juxtap

osée à la lig

ne existan

te

7178_bu_hq_041_pyl_150804a.FH10

Gu

yed to

wers

Self-su

pp

ortin

g to

wers

Average height: 35 m

Des C

antons–New

England 450 kV D

C

Planned line

Québec–N

ew H

ampshire

320 kV DC

Average height: 40 m

Existing right-of-way

Existing right-of-way

Planned right-of-way

average

Average height: 35 m

Des C

antons–New

England 450 kV D

C

Planned line

Québec–N

ew H

ampshire

320 kV DC

Average height: 40 m

Existing right-of-way

Existing right-of-way

Planned right-of-way

average

Information for publics concerned by the project. F

or any other use, contact Géom

atique, Hydro-Q

uébec Équipem

ent et services partagés.

East

EastW

est

West

Tower types and right-of-wayThis will be the first 320-kV DC line built by Hydro-Québec, so a new type of steel tower will be used.

These towers will be similar to the ones for the existing 450-kV line, but will be smaller. They will be installed near existing towers wherever possible.

ScheduleDRAFT DESIGN

General information Winter 2014-2015

Public consultation on line routes Spring 2015

Information on the route selected Summer 2015

PROJECT

Permitting Fall 2015 to spring 2017

Construction 2017–2019

Commissioning 2019

For more information

Info-project line 1 8 7 7 6 5 3-1 1 3 9

Ginette CantinAdvisor – Community Relations – Richelieu Direction – Affaires régionales et collectivités 705, boul. Clairevue Ouest, 1er étage Saint-Bruno-de-Montarville (Québec) J3V 6B6E-mail: [email protected]

www.hydroquebec.com/quebec-new-hampshire www.hydroforthefuture.com