quarterly review november 15, 2000 1 gnirs quarterly review #4 november 15, 2000
TRANSCRIPT
1
Quarterly ReviewNovember 15, 2000
GNIRS Quarterly Review #4
November 15, 2000
2
Quarterly ReviewNovember 15, 2000
Outline
• Project summary
• Flexure analysis report
• Project management
• Appendix A - Images
• Appendix B - List of Released Drawings
3
Quarterly ReviewNovember 15, 2000
Project Summary
• Progress overview
• Budget and expenditures to date
• Report on last QR plans
4
Quarterly ReviewNovember 15, 2000
Progress Overview• The delivery date of the instrument has not changed
• Still scheduled for July-August, 2002
• The project is 39% complete• We are about 1.5 months behind schedule overall
• We have completed 45 of 225 total project milestones• The Systems Engineering effort is essentially complete• Software low-level code development is 56% complete• Mechanism fabrication has started• Bench fabrication is started
• OIWFS bench completes this month• Pre-Slit bench is at a vendor• Post-Slit bench releases this month
• Electronics fabrication has started
5
Quarterly ReviewNovember 15, 2000
Project Status• Progress from August ’99
• Overall project 39%
• Management & Reporting 39%
• Systems Engineering 100%
• Mechanical 30%• Benches 35%
• Mechanisms 39%
• Fixed Assemblies 7%
• Electronics 42%
• Software 27%
• Integration 0%
• Procurement 44%
6
Quarterly ReviewNovember 15, 2000
Project Costs• Baseline Estimate (Jan 99 to completion)
• Labor $3,391,232• Capital $ 836,462• Total $4,227,694
• Current Forecast (revised 9/15/00)• Labor $3,014,805• Capital $ 806,250• Total $3,821,055
• Performance ratios• BCWS = $ 1,431,064 (budgeted cost of work scheduled)• BCWP = $ 1,074,179 (budgeted cost of work performed)• ACWP = $ 928,176 (actual cost of work performed) (source: CAS)• CPI = 1.16 (BCWP/ACWP) • SPI = 0.75 (BCWP/BCWS)
7
Quarterly ReviewNovember 15, 2000
Planned Status by this Quarterly Review
• Fabrication contract awards:• all optical benches• 3 mechanisms
• Complete 3D designs of all remaining mechanisms• Complete lens delivery and acceptance testing• All optics on order or delivered• Begin 3D design of 5 of the 16 fixed assemblies• Begin electronics fabrication• Begin OIWFS components integration• Rotary and linear prototype reports• Grating master ruling test report
8
Quarterly ReviewNovember 15, 2000
Task StatusItem Status Comments
Optical benches contracted Complete - vendors selected Fabrication completes next year
Have 3 of 8 mechanisms in fabrication Complete - 3 mechanisms in fab or done: slit/decker, environmental cover and part of camera and filter wheel
Complete 3D design of remaining mechanisms
Not Complete – 3D Design of prism turret and focus mechanism complete
Will complete 3D design of grating turret, acquisition mirror and rest of camera by end of this quarter
Complete lens delivery and testing Not complete - Delivery of BaF2 late New lot ready in February, delivery in March
All optics on order or delivered Not complete - Delayed by mechanism definition
All optics should be on order by December 15th
Begin 3D design of 5 fixed assemblies Started - Thermal enclosure mount, front dewar shell, rear dewar shell, bulkhead, aft tangent bar
Will complete bulkhead assembly design by end of this year
Begin electronics fabrication Started - Thermal enclosure and cables Thermal enclosure should complete by Feb 01
Begin OIWFS integration Not complete - Components delayed Integration tentatively scheduled for January
Rotary & Linear Prototype testing Complete - Results incorporated into designs
Will carry out flexure testing on camera drive assembly to verify design
Grating master ruling report Complete - Documented in SDN
9
Quarterly ReviewNovember 15, 2000
Systems Engineering
• Flexure Analysis:• Completed 10/00
• Results show no need for active compensation• Passive compensation via collimator mount required
• Analysis will be used to guide mount design (later this year)
• All further analysis is in support of detailed design
10
Quarterly ReviewNovember 15, 2000
Flexure Analysis
• NASTRAN Model• Design presented 8/00
• Mechanisms, optics modeled as rigid bodies (reasonable assumption)
• Tilts and displacements calculated for 3 orthogonal gravity vectors
• Some subsequent modifications• Stiffened high-flexure areas identified by model
• Verified all mechanism interfaces
• Changes in flexure should be modest; expected but not required to improve
11
Quarterly ReviewNovember 15, 2000
Instrument Assembly F.E.A. ModelDeformed shape scaled by 7500x loading; gravity in the –y direction; scale in inches.
10m
Note: Much of the Offner deflection is due to rigid body motion of the assembly with respect to its support bulkhead, and will not contribute image decenter.
12
Quarterly ReviewNovember 15, 2000
Instrument Assembly F.E.A. ModelDeformed shape scaled by 7500x loading; gravity in the –x direction; scale in inches.
14m
13
Quarterly ReviewNovember 15, 2000
Instrument Assembly F.E.A. ModelDeformed shape scaled by 7500x loading; gravity in the –z direction; scale in inches.
5m
14
Quarterly ReviewNovember 15, 2000
Flexure Analysis
• Optical Model• Calculations done independently with 2 programs by E. Pearson and M.
Liang: good agreement
• Optics laid out in absolute coordinates
• Tested with rigid-body rotation of spectrograph (should have no net effect)
• Apply NASTRAN tilts/displacements to optical elements
15
Quarterly ReviewNovember 15, 2000
Optical Ray Trace
Red ray: Spectrograph
Blue ray: On-Instrument Wave Front Sensor
16
Quarterly ReviewNovember 15, 2000
Flexure Analysis
• Results - WFS to Slit• Differential flexure of WFS relative to slit should keep star centered on
slit to <10 m during 1 hour• Calculated shifts in microns for 1 gravity:
• Worst case for 1 hour ~5 m shift• Meets specification comfortably
Gravity x y -y -14.4 -9.0 x -1.7 -5.3 z -10.7 -0.4
17
Quarterly ReviewNovember 15, 2000
Flexure Analysis
• Results - Slit to Detector to Slit• Differential motion between slit/star and detector should keep image
centered to 2.7 m (0.1 pixel) during 1 hour• Motion of slit image in dispersion direction (z)
• Motion of star image along slit (y) (motion of slit image similar)
• Calculated shifts in microns for 1 gravity:
Gravity z y -y -13.1 -14.6 x 1.3 3.5 z -24.2 3.5
18
Quarterly ReviewNovember 15, 2000
Flexure Analysis
• Results - Slit to Detector to Slit (2)• Worst case 1 hour in z = 7.2 m; worst case in y = 4.0 m
• Design collimator mount to provide passive compensation for 2 largest components
• Worst case in y now 1.8 m in 1 hour (meets spec)
• Worst case in z now 3.7 m in 1 hour (factor of 1.4)
• Analyze final bench design to guide collimator mount design
19
Quarterly ReviewNovember 15, 2000
Project Management
• Project Status• Problems and Concerns• Schedule & Planning• Milestones• Budget and Expenditures• Labor and Capital Projections• Project Organization• Plans for Next Review
20
Quarterly ReviewNovember 15, 2000
Mechanical Status #1• Bench design and analysis
• Bench flexure analysis is complete• Large plate has been cut
• Distributed to vendors with drawing packages
• All benches in fabrication as of 11/20 • OIWFS bench released 9/20; fabrication completes 11/23• Pre-Slit bench released on 9/20; 10% complete• Post-slit bench drawings will be released 11/20
• Mechanism designs in process• Camera turret assembly• Acquisition mirror assembly• Focus mechanism assembly• Grating turret assembly• Prism turret assembly
21
Quarterly ReviewNovember 15, 2000
Mechanical Status #2
• Mechanism components currently in fabrication• Camera hub spindle and drive assembly
• Camera barrels
• Slit/Decker
• Filter wheel assembly
• Mechanism common components• Motor drive assembly
• Cryo heads/lines• Will be ordered in March 2001
22
Quarterly ReviewNovember 15, 2000
Electronics Status• Design activities
• Component controller thermal enclosure design completed• Hard-stop circuit required for the mechanisms and the Phytron drivers
has been designed and the schematics finished• A scale model GNIRS for harnessing design has been completed• Dewar, mechanisms and OIWFS cabling
• These cabling issues are being addressed thru the scale model GNIRS • cable routing and possible intermediary connectors• how to route cables around the Bench and thru the Radiation Shields
• A complete GNIRS thermal enclosure parts list has been prepared
• Fabrication in progress• Thermal enclosure wiring and assembly• Dewar and shield interface PCB’s• Connectors and boards on order
23
Quarterly ReviewNovember 15, 2000
Software Status
• Component Controller code 56% complete
• High level (EPICS) code 7% complete• Waiting for completion of the electronics
thermal enclosure• The next phase is actual testing of component
controller code• Motor drive and mechanism status/position
sensing
24
Quarterly ReviewNovember 15, 2000
Optics Status• Lenses and Windows
• Large lenses & windows in fabrication with RMI; 11 of 18 accepted• Only BaF2 lenses for short red and blue cameras remain
• Two lots of BaF2 material have failed so far; a third lot is in process
• Pupil viewer lenses ordered and received
• Mirrors• Flat mirrors to be ordered as individual mechanism design proceeds; 2
aluminum substrates & 7 glass substrates
• Gratings• Master rulings complete and tested• Grating replicas to be ordered by 12/15/00
• Filters• 7 filters ordered through UH consortium; 2 failed spec and vendor is
expected to replace
• Prisms• Prisms to be ordered by 12/15/00
25
Quarterly ReviewNovember 15, 2000
Phytron Motor Status
• Motor qualification initiated• Tested 4 motors, 3 out of 4 failed
• Phytron is replacing all 12 motors• Delivery of first 4 replacements expected 11/15/00
• Qualification will proceed after delivery
• 2 Gemini spare motors available on loan; these will support mechanism cold testing until motors pass muster
26
Quarterly ReviewNovember 15, 2000
Problems and Concerns• OIWFS component late delivery
• Will cause resources to be diverted from other activities to work on OIWFS integration and test
• Filter wheel will arrive untested
• Focus assembly now in NIRI has been promised to us for January 2001
• Completing bench fabrication without major rework • Contingency time to re-fabricate a bench component is marginal
• Camera drive assembly flexure testing still pending• Design modifications may affect turret drive designs on three mechanisms
• Completion of the RMI camera optics order• BaF2 material lot failures have caused a significant delay in completing the order
• Over 130 days required to grow a new lot
• We are working to assist RMI in procuring material
• Firm quotes and schedules on prisms still pending
27
Quarterly ReviewNovember 15, 2000
Three Phases of the Project
| Aug 99 – Feb 00 | Mar 00 – Jun 01 | Jul 01 – Jul 02 |
Analysis & Prototyping
Pre-Fab Review
Design/Fab/Test
Mid-Fab Review
Integration & Test
28
Quarterly ReviewNovember 15, 2000
Summary PlanJ F M A M J J A S O N D J F M A M J J A S O N D
CY-2001 CY-2002
Fixed Assemblies Design/Fab
Integration/Alignment
WFS Integration/Alignment
Mechanism Design/Fab/Assy/Test
IFU Modules
Software Development/Code/Test
SW Plan/Low-Level/High-Level Code
Electronics Design/Fab/Test
Manuals
ATP
Ship
Training
GNIRS SUMMARY PLAN11/00
MFR
N D J F M A M J J A S O N DCY-2000
Risk Reduction Prototypes
PFR
Structural Analysis
Bench Design/Fab/Assy
OIWFS/Post-Slit/Pre-Slit
Mechanism Design/Fab/Assy/Test
9 Mechanisms
Electronics Design/Fab/Test
Optics Procurement
OIWFS Hardware
29
Quarterly ReviewNovember 15, 2000
Project Plan – Sheet 1
30
Quarterly ReviewNovember 15, 2000
Project Plan – Sheet 2
31
Quarterly ReviewNovember 15, 2000
Project Milestones by Quarter
Calendar Year Quarter
Number of Milestones
DueRunning
Total
Number of Milestones
CompRunning
Total1999 4th 1 1 1 12000 1st 15 16 15 162000 2nd 13 29 13 292000 3rd 12 41 8 372000 4th 42 83 7 442001 1st 64 147 1 452001 2nd 47 194 0 452001 3rd 14 208 0 452001 4th 8 216 0 452002 1st 1 217 0 452002 2nd 3 220 0 452002 3rd 5 225 0 45
TOTAL 225 45
As of 11/3/00
32
Quarterly ReviewNovember 15, 2000
Milestones since PFR (5/00)WBS TASK Baseline Plan Est. Plan Act. Finish5.3.1.1.3 Complete Final Revision Mechanism Test Plan 6/6/00 6/6/00 6/7/005.3.1.7.1.6 Filter Wheel Assembly Design Complete 3/8/00 7/17/00 7/17/005.5.2.2.2 Motor Control Component Complete NA 8/4/00 8/4/005.3.3.1.2.4 Entrance Window Assembly Drafting Complete 5/21/01 8/4/00 8/4/005.3.3.8.1.4 Environmental Cover Filter Design Complete 5/22/01 8/7/005.3.3.8.2.4 Environmental Cover Filter Drafting Complete 5/31/01 8/15/005.3.3.8.3.2 Environmental Cover Filter Fabrication Complete 6/7/01 8/22/005.3.3.8.4.3 Environmental Cover Filter Assembly Complete 6/8/01 8/23/005.3.2.4.2.1.5 Offner Assembly Design Complete 3/23/00 9/8/00 9/8/005.3.1.103.2 Motor Drive Assembly Fabrication Complete 7/26/00 9/14/00 9/14/005.3.2.4.1.1.5 Pick-Off/Fold Mirror Assembly Complete 3/9/00 9/21/00 9/21/005.3.2.2.4.1.3 OIWFS Assembly Design Complete NA 9/22/00 9/22/005.3.1.6.1.1.6 Slit/Decker Housing Assembly Design Complete 8/1/00 9/29/00 9/29/005.3.2.4.2.2.6 Offner Assembly Drafting Complete 6/14/00 10/4/005.3.2.2.1.2.6 OIWFS Assembly Drafting Complete 8/11/00 10/5/00 10/5/005.3.1.2.6.2.6 Camera Hub Drafting Complete 8/8/00 10/6/00 10/6/005.3.1.6.1.2.6 Slit/Decker Assembly Drafting Complete 11/27/00 10/6/00 10/6/005.3.2.4.1.2.6 Pick-Off/Fold Mirror Assembly Drafting Complete 6/30/00 10/13/005.3.2.2.3.1 Receive and Inspect IFA WFS electronics 9/5/00 10/16/005.3.2.1.7.1.5 Top Camera Cover Design Complete 6/12/00 10/20/00 10/20/005.3.2.1.6.1.5 LCFMH Design Complete 6/14/00 10/20/00 10/20/005.3.3.2.1.6 Detector Mount Assembly Design Complete 7/17/00 10/25/005.3.1.4.3.6 Environmental Cover Assembly Fabrication Complete 8/3/00 10/31/005.3.3.1.3.5 Entrance Window Assembly Fabrication Complete 6/8/01 10/31/005.3.1.4.4.2 Environmental Cover Assembly Testing Complete 8/7/00 11/1/005.3.2.2.2.2 Wavefront Sensor Hardware Received 9/8/00 11/1/005.2.8.3 Validate Structural Analysis 7/11/00 11/1/00 11/1/005.3.3.7.1.4 Optical Bench Mount Assembly Design Complete 7/25/00 11/2/005.3.1.104.5 Motor Drive Assembly Complete 8/2/00 11/2/005.3.1.9.1.6 Prism Turret Design Complete 5/10/00 11/3/00 11/3/005.3.1.7.2.6 Filter Wheel Assembly Drafting Complete 6/21/00 11/8/005.3.2.1.8.1.5 Bottom Camera Cover Design Complete 6/12/00 11/13/005.3.2.1.6.2.6 LCFMH Drafting Complete 6/30/00 11/14/005.3.1.6.3.3.5 Decker Slit Slide Fabrication Complete 12/5/00 11/15/00
33
Quarterly ReviewNovember 15, 2000
Planned vs Actual Expenditures
Item Labor Capital Total
Project Management $1,144,627 $5,000 $1,149,627Systems Engineering $216,372 $16,610 $232,982Mechanical $1,164,055 $592,010 $1,756,065Electronics $138,966 $7,400 $146,366Software $108,802 $0 $108,802Alignment & Integration $200,260 $1,700 $201,960Deliverables $37,164 $0 $37,164Procurement $4,560 $183,530 $188,090
Total Project $3,014,805 $806,250 $3,821,055
Total Budget
Labor Capital Total Labor Capital Total
$426,427 $0 $426,427 $392,093 $4,045 $396,138$203,608 $16,610 $220,218 $216,221 $47,029 $263,250$389,711 $133,302 $523,013 $249,388 $69,144 $318,532$38,190 $5,450 $43,640 $30,930 $5,027 $35,957$16,243 $0 $16,243 $32,339 $0 $32,339
$0 $0 $0 $0 $0 $0$0 $0 $0 $0 $0 $0$0 $164,152 $164,152 $7,204 $288,028 $295,232
$1,074,179 $319,515 $1,393,694 $928,175 $413,273 $1,341,448
Actual Expenditure to Date Planned Expenditure to Date
Planned
Project Management
33%
Systems Engineering
10%
Procurement11%
Mechanical39%
Deliverables0%
Alignment & Integration
0%
Electronics4%
Softw are3%
Actual
Project Management
31%
Systems Engineering
20%
Procurement17%
Mechanical27%
Deliverables0%
Electronics2%
Alignment & Integration
0%
Softw are3%
34
Quarterly ReviewNovember 15, 2000
Capital and Labor Comments
• The capital reported is as of 11/3/00• Some capital expenditures have been charged to
procurement instead of the respective WBS number
• The labor histogram shows the result of shared resources, utilizing fewer instrument makers and subcontracting work vs. doing it in-house
• Capital expenditures are expected to increase substantially in the next two quarters
35
Quarterly ReviewNovember 15, 2000
Planned vs Actual Expenditures WBS Title Total Planned Actual
Plan to date to date
5.0 GNIRS Total $3,821,055 $1,393,694 $1,341,448 5.1 Management $1,149,627 $ 426,427 $ 396,138 5.2 Systems Eng $ 232,982 $ 220,218 $ 263,250 5.3.1 Mechanisms $ 951,854 $ 380,589 $ 255,816 5.3.2 Bench Assemblies $ 303,037 $ 119,142 $ 59,418 5.3.3 Fixed Assemblies $ 501,174 $ 23,227 $ 14,895 5.4 Electronics $ 146,366 $ 43,640 $ 35,957
5.5 Software $ 108,802 $ 16,243 $ 32,3395.6 Integration $ 201,960 $ 0 $ 0
5.7 Deliverables $ 37,164 $ 0 $ 05.8 Procurement $ 188,090 $ 164,152 $ 295,232
36
Quarterly ReviewNovember 15, 2000
GNIRS Staffing FTE by Month
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
Month
FT
E
Plan FTE Actual FTE
37
Quarterly ReviewNovember 15, 2000
GNIRS Cumulative Work
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
Month
Ho
urs
Actual Baseline Nov'00 Plan
79,835h
79,725Baseline
Jan 99
38
Quarterly ReviewNovember 15, 2000
$806,250
$759,192
GNIRS Capital Spend Plan
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
Month
Dol
lars
Actual Baseline Nov'00 PlanJan 99
39
Quarterly ReviewNovember 15, 2000
GNIRS Project Organization
Gemini ProjectsProject Manager
N. Gaughan
Director, NOAOS. Wolff
Project AssistantD. Eklund (.5)
Administrative AssistantM. Bowersock
Project Scientist,Systems
EngineeringJ. Elias
Mechanical Engineers E. Hileman G. Muller
Electrical Engineer
J. Penegor
Optical EngineerM. Liang
Procurement & Vendor Liaison
A. Davis
SoftwareR. Wolff
Support Scientists
D. Joyce (.5)[B. Gregory]
Mechanical DesignersJ. AndrewD. Rosin
E. DowneyR. RoblesD. Circle
Electrical TechniciansR. George
Staff Added: R. George/ D. CircleStaff Transferred: No changes
Updated 11/1/00
General TechnicianJ. Pina (.5)
ProgrammerP. Ruckle
Instrument MakerJ. Stein
40
Quarterly ReviewNovember 15, 2000
Plans for Next Review• The Next Quarterly Review will be held in the February-March timeframe• The project expects to make significant progress in fabrication
• All benches complete• All remaining mechanisms will be in fabrication
• All optics on order• Flats/Prisms/Grating replicas
• Design effort will concentrate on fixed assemblies• Bulkhead assemblies• Dewar components• Mounting trusses• Cryo hardware
• Electronics TE fabrication should be completed• Software testing should be in process• OIWFS components integration/test should be underway
41
Quarterly ReviewNovember 15, 2000
Appendix A - Images
42
Quarterly ReviewNovember 15, 2000
Wave Front Sensor Bench Rendering
43
Quarterly ReviewNovember 15, 2000
Wave Front Sensor Bench in Fab
44
Quarterly ReviewNovember 15, 2000
Wave Front Sensor Bench Rendering
45
Quarterly ReviewNovember 15, 2000
Wave Front Sensor Bench in Fab
46
Quarterly ReviewNovember 15, 2000
Wave Front Sensor Bench Cover
47
Quarterly ReviewNovember 15, 2000
Camera Turret Hub Assembly
48
Quarterly ReviewNovember 15, 2000
Camera Turret - Fabricated
49
Quarterly ReviewNovember 15, 2000
Pre-Slit Bench Assembly
50
Quarterly ReviewNovember 15, 2000
Pickoff/Fold Mirror Assembly
51
Quarterly ReviewNovember 15, 2000
Prism Turret Assembly
52
Quarterly ReviewNovember 15, 2000
Prism Turret Hub Assembly
53
Quarterly ReviewNovember 15, 2000
Appendix B – List of Released Drawings
54
Quarterly ReviewNovember 15, 2000
List of Released DrawingsPART NUMBER TITLE REV REL DATE STATUS COMMENTS
89-NOAO-4200-1279-1 ACME SCREW (FLOATING) OD 29-Aug-00 In fab inhouse
89-NOAO-4203-0043 MANUAL DRIVE ADAPTER ASSEMBLY OD 29-Aug-00 On Hold
89-NOAO-4200-1300 SPUR GEAR MODIFICATION, 48 PITCH 48 TOOTH A 29-Aug-00 READY FOR FAB
89-NOAO-4200-1163 BEVEL GEAR MODIFICATION, SMALL OD 29-Aug-00 In fab inhouse
89-NOAO-4203-1107 ADAPTER BLOCK OD 29-Aug-00 READY FOR FAB
89-NOAO-4200-1162 BEVEL GEAR MODIFICATION, LARGE OD 29-Aug-00 In fab inhouse
89-NOAO-4200-1161 SPUR GEAR MODIFICATION OD 29-Aug-00 In fab inhouse
89-NOAO-4200-1273 SLIT DRIVE HOUSING OD 29-Aug-00 In fab inhouse
89-NOAO-4200-1274 END PLATE OD 29-Aug-00 In fab inhouse
89-NOAO-4200-1217 STEP PIN A 29-Aug-00 In fab inhouse
89-NOAO-4200-1278 SCREW SHAFT OD 29-Aug-00 In fab inhouse
89-NOAO-4200-1280 COLLAR MODIFICATION OD 29-Aug-00 In fab inhouse
89-NOAO-4200-1281 SPUR SHAFT OD 29-Aug-00 In fab inhouse
89-NOAO-4200-0097 SLIT SLIDE ANTI-BACKLASH DRIVE ASSEMBLY OD 29-Aug-00 IN SHOP FOR FAB
89-NOAO-4200-1279-2 ACME SCREW (STATIC) OD 29-Aug-00 In fab inhouse
89-NOAO-4203-1109 SPACER OD 29-Aug-00 READY FOR FAB
89-NOAO-4203-1108 DRIVE BALL OD 29-Aug-00 READY FOR FAB
89-NOAO-4200-1329 SWITCH WASHER PLATE OD 31-Aug-00 FAB COMPLETE
89-NOAO-4200-1065 SPACER BLOCK OD 31-Aug-00 FAB COMPLETE
89-NOAO-4200-0052-2 GENERIC HOME SWITCH ASSY (LEFT HAND CONFIGURATION) OD 31-Aug-00 At Merit Due 10/31/00
89-NOAO-4200-1062 REAR FLEXURE OD 31-Aug-00 FAB COMPLETE
89-NOAO-4200-1059 BEARING MOUNT OD 31-Aug-00 FAB COMPLETE
89-NOAO-4200-1307-2 RACK GEAR OD 31-Aug-00 FAB COMPLETE
89-NOAO-4200-1063 FRONT FLEXURE OD 31-Aug-00 FAB COMPLETE
55
Quarterly ReviewNovember 15, 2000
List of Released Drawings89-NOAO-4200-1061 BACKING PLATE OD 31-Aug-00 FAB COMPLETE
89-NOAO-4200-1307-1 RACK GEAR OD 31-Aug-00 FAB COMPLETE
89-NOAO-4200-0108 DECKER SLIDE ASSEMBLY OD 31-Aug-00 at Merit for fab
89-NOAO-4200-1158 DECKER PLATE C 31-Aug-00 FAB COMPLETE
89-NOAO-4200-1060 SWITCH MOUNT A 31-Aug-00 FAB COMPLETE
89-NOAO-4200-0052-1 GENERIC HOME SWITCH ASSY (RIGHT HAND CONFIGURATION) OD 31-Aug-00 At Merit Due 10/31/00
89-NOAO-4200-1064 SETSCREW MOUNT PLATE A 31-Aug-00 FAB COMPLETE
89-NOAO-4200-1082 CAMERA TURRET FRONT HUB OD 8-Sep-00 FAB COMPLETE
89-NOAO-4200-0121 TURRET HUB MACHINING ASSEMBLY OD 8-Sep-00 FAB COMPLETE 10/23/2000
89-NOAO-4200-1083 CAMERA TURRET REAR HUB OD 8-Sep-00 FAB COMPLETE
89-NOAO-4200-1084 CAMERA TURRET HUB SPACER OD 8-Sep-00 FAB COMPLETE
89-NOAO-4200-0101 SLIT IDLER ASSEMBLY OD 11-Sep-00 Out for Fab
89-NOAO-4200-1286 SLIT SLIDE COUNTERWEIGHT OD 11-Sep-00 Assy Dw g not released
89-NOAO-4200-1114 PARALLEL SPRING FLEXURE MOUNT RAIL OD 20-Sep-00 At Vendor for Fab
89-NOAO-4200-1258 UPPER SLIT SLIDE RAIL OD 20-Sep-00 At Vendor for Fab
89-NOAO-4200-1159 PARALLEL SPRING FLEXURE OD 20-Sep-00 At Vendor for Fab
89-NOAO-4200-1167 OIWFS BENCH HOGOUT OD 22-Sep-00 IN SHOP FOR FAB
89-NOAO-4200-1306 OIWFS COVER OD 22-Sep-00 In fab 40% done 10/10/00
89-NOAO-4200-1055 PINION GEAR MODIFICATION OD 25-Sep-00 In Shop for Fab
89-NOAO-4200-1301 SLIT MOTOR MOUNT BLOCK OD 25-Sep-00 In Shop for Fab
89-NOAO-4200-1053 MOTOR DRIVE INTERFACE GEAR OD 25-Sep-00 In Shop for Fa
89-NOAO-4200-0098 SLIT MOTOR MOUNT ASSEMBLY OD 25-Sep-00 IN SHOP FOR FAB
89-NOAO-4200-1076 EXIT FOLD MIRROR HOUSING OD 29-Sep-00 DRAWING RELEASED
89-NOAO-4200-1256 PRE SLIT BENCH FORWARD HOUSING OD 29-Sep-00 AT VENDOR FOR FAB
89-NOAO-4200-1075 PICKOFF MIRROR HOUSING OD 29-Sep-00 DRAWING RELEASED
56
Quarterly ReviewNovember 15, 2000
List of Released Drawings89-NOAO-4200-1257 PRE SLIT BENCH AFT HOUSING OD 1-Oct-00 At Landmark in Fab
89-NOAO-4200-1284 IDLER BUSHING OD 5-Oct-00 At Vendor for Fab
89-NOAO-4200-1285 IDLER SHAFT A 5-Oct-00 At Vendor for Fab
89-NOAO-4200-0112 SLIT SLIDE PARALLEL SPRING FLEXURE ASSY OD 5-Oct-00 Out for Fab
89-NOAO-4200-1160 IDLER GEAR OD 5-Oct-00 At Vendor for Fab
89-NOAO-4200-1308 SLIT SLIDE LIMIT SWITCH DOVETAIL OD 6-Oct-00 In Shop for Fab
89-NOAO-4200-1066 SLIT FRAME OD 6-Oct-00 At Vendor for Fab
89-NOAO-4200-1010 PUPIL VIEWER LENS RETAINER OD 6-Oct-00 At Vendor for Fab
89-NOAO-4200-1315 SWITCH COVER PLATE A 6-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1067 CLAMP PLATE OD 6-Oct-00 At Vendor for Fab
89-NOAO-4200-1068 SLIT MASK PLATE OD 6-Oct-00 At Vendor for Fab
89-NOAO-4200-0053 SLIT MODULE ASSEMBLY OD 6-Oct-00 Out for fab
89-NOAO-4200-1282 CAPTIVE SCREW, M4 X 18 LG OD 6-Oct-00 At Vendor for Fab
89-NOAO-4200-0115 SLIT SLIDE HOME SWITCH ASSEMBLY OD 6-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-0119 SLIT SLIDE LIMIT SWITCH ASSEMBLY OD 6-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1320 SWITCH HOUSING OD 6-Oct-00 DWG RELEASED, READY FOR FAB
89-NOAO-4200-1317 SLIT SLIDE LIMIT SWITCH MOUNT OD 6-Oct-00 In Shop for Fab
89-NOAO-4200-1316-2 LIMIT/HOME SWITCH DOVETAIL SLIDE A 6-Oct-00 DWG RELEASED, READY FOR FAB
89-NOAO-4200-0042 SHORT RED CAMERA ASSEMBLY OD 10-Oct-00
89-NOAO-4200-1296-2 CAMERA TURRET CLAMP BLOCK OD 13-Oct-00 Ready for Fab out for bid
89-NOAO-4200-1328-1 PRELOAD SCREW PLUG OD 13-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1085 CAMERA TURRET SPUR GEAR OD 13-Oct-00 Ready for Fab out for bid
89-NOAO-4200-1324-1 CAMERA TURRET MOUNT BLOCK OD 13-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1326 COLLET OD 13-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1325 COLLAR OD 13-Oct-00 IN SHOP FOR FAB
57
Quarterly ReviewNovember 15, 2000
List of Released Drawings89-NOAO-4200-1328-2 PRELOAD SCREW PLUG OD 13-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1324-2 CAMERA TURRET MOUNT BLOCK OD 13-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1296-1 CAMERA TURRET CLAMP BLOCK OD 13-Oct-00 Ready for Fab out for bid
89-NOAO-4200-1293 CAMERA TURRET PRELOAD RING OD 16-Oct-00 Ready for Fab out for bid
89-NOAO-4200-1116 SHORT RED CAM FORWARD CELL OD 16-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1117 SHORT RED CAM REAR CELL OD 16-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1120 SHORT RED CAM SPACER OD 16-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1295-1 PRELOAD SCREW OD 16-Oct-00 Ready for Fab out for bid
89-NOAO-4200-1086-1 TURRET AXLE OD 16-Oct-00 In Fab complete in 6 w eeks from 11/8/00
89-NOAO-4200-1327 CAMERA TURRET PRELOAD PIN OD 16-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1343 M8 X 25 LG. CAPTIVE SHCS MODIFICATION OD 16-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1086-3 TURRET AXLE OD 16-Oct-00 RELEASED, READY FOR FAB
89-NOAO-4200-0046 CAMERA TURRET HUB ASSY OD 16-Oct-00 READY FOR FAB
89-NOAO-4200-1295-2 PRELOAD SCREW OD 16-Oct-00 RELEASED, READY FOR FAB
89-NOAO-4200-1086-2 TURRET AXLE OD 16-Oct-00 RELEASED, READY FOR FAB
89-NOAO-4200-1342 SPRING CONNECTOR BLOCK OD 16-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1253 SUPPORT TUBE AT OIWFS BENCH OD 17-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1077 PICKOFF MIRROR MOUNT PLATE OD 20-Oct-00 IN SHOP FOR FAB
89-NOAO-4200-1316-1 LIMIT/HOME SWITCH DOVETAIL SLIDE A 23-Oct-00 READY FOR CHECK
89-NOAO-4200-0074 CAMERA TURRET DRIVE ASSEMBLY OD 23-Oct-00 DRAWING RE-RELEASED
89-NOAO-4200-1058 SWITCH MOUNT BASE OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1069 PINION GEAR MODIFICATION OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1007-1 FILTER SPECIFICATION OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1191 FILTER BLANK OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1150 PRELOAD SPACER OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
58
Quarterly ReviewNovember 15, 2000
List of Released Drawings89-NOAO-4200-1148 RETAINER, LENS OD 7-Nov-00
89-NOAO-4200-1149 SPRING CUP OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0039 FILTER WHEEL ASSEMBLY OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1151 HEAT SINK OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1146-4 DELRIN FILTER SEAT OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1146-3 DELRIN FILTER SEAT OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0073 PUPIL VIEWER CELL ASSEMBLY OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1007-3 FILTER SPECIFICATION OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1146-2 DELRIN FILTER SEAT OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1287 WASHER MODIFICATION OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1141-2 FILTER WHEEL OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1288 COVER,FILTER WHEEL OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1289 CAPTIVE SCREW, M6 X 25 LG OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1290 DELRIN LIGHT SEAL OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1291 LIGHT SEAL MOUNT OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1292 G-10 WIRE CLIP OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1007-2 FILTER SPECIFICATION OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0071 FILTER WHEEL AXLE ASSEMBLY OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1137 PLATE,GUIDE RAIL OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1138 PLATE, SIDE OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1139 BRACKET,SHAFT CLAMP OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1140 BRACKET,SHAFT STABILIZER OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0067 FILTER WHEEL NO. 1 ASSY OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0068 FILTER WHEEL NO. 2 ASSY OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1147 CELL, PUPIL VIEWER OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
59
Quarterly ReviewNovember 15, 2000
List of Released Drawings
89-NOAO-4200-0070 FILTER WHEEL HOME SWITCH ASSEMBLY NO.2 OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1135 SHAFT,FILTER WHEEL OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1141-1 FILTER WHEEL OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0111 FILTER WHEEL DRIVE ASSEMBLY OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1142 PLATE, HALF MASK OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0072 FILTER COVER ASSEMBLY OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1144 COVER, FILTER OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1145 SPRING STRIP OD 7-Nov-00
89-NOAO-4200-1146-1 DELRIN FILTER SEAT OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-0069 FILTER WHEEL HOME SWITCH ASSEMBLY NO. 1 OD 7-Nov-00 DWG RELEASED, READY FOR MAKE/BUY
89-NOAO-4200-1136 FILTER WHEEL HOUSING OD 8-Nov-00 DWG RELEASED, READY FOR MAKE/BUY