Page 1: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Purple Line Extension Construction Community Meeting March 16, 2017

1

Page 2: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Agenda

• Project Construction Updates: Western, La Brea, Fairfax and La Cienega

• La Brea Station Street Configuration Update

• Fairfax Decking: Phase I,II, III, Detours, Outreach and Communication

• La Cienega K-Rail and Pile Installation

• Safety

• Eat Shop Play Wilshire

• Business Interruption Fund

• Question & Answers

2

Page 3: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Purple Line Extension Project Alignment

3

Page 4: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Sections 1, 2 & 3 Status

4

Under Construction Forecasted Schedule

Section Section 1 Section 2 Section 3

Length 3.92 Miles 2.59 Miles 2.48 Miles

New Stations Wilshire/La Brea

Wilshire/Fairfax

Wilshire/La Cienega

Wilshire/Rodeo

Century City/

Constellation

Westwood/UCLA

Westwood/VA

Hospital

Pre-Construction

Activities

Current - 2016 2016 - 2018 2025 – 2027*

Construction 2015 - 2023 2018 – 2026* 2027 – 2035*

Operations 2024 2026* 2035*

*Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Page 5: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Purple Line Extension Section 1 Alignment

5

Page 6: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Purple Line Maintenance Facility

6

590 S Santa Fe Avenue

• Located in the Arts District, near 6th St Bridge

• Initial excavation and grading ongoing

• Sanitary sewer and storm drain relocation continues March

• Design of Building 61S continues

• Artists selected

Design Advisory Group

• Advisory group composed of Arts District leaders and artists to review and provide input on building’s exterior design

• Next Meeting: March 22, 2017

Sewer pipe line installed at Santa Fe Av / Palmetto St - complete

Page 7: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Western Station Tie-in

Western Staging Yard

• Northeast corner of Wilshire Bl and Manhattan Pl one block west of Western Av

• Soundwall construction substantially completed

• Remaining work includes adding new banners and widening of driveways

• Western Yard used intermittently for storage

Current Work

• Jet grouting began February 2017 along:

• Wilshire Bl between Bronson Av and Wilton Pl

• Wilshire Bl between Gramercy Pl and Western Av

• K-rail (concrete barriers) installed; intermittent (off peak) lane reductions and eastbound Wilshire Bl closures on weekends

• Jet grouting anticipated will require 8 to 12 weeks to complete

• Median removal and repaving completed

7

Page 8: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

8

Jet grouting set-up at Wilshire Bl/Wilton Pl

Page 9: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Crenshaw Yard Staging Site Wilshire/Crenshaw

Mitigation efforts and maintenance:

• Banners replaced with durable vinyl

• Lorraine Gate temporarily closed until further notice

• Recent maintenance included graffiti removal, debris removal and trimming of vines

• Yard used for storage of materials

9

New banners on east side of Crenshaw Yard

Page 10: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station

10

Page 11: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station

11

Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St

Page 12: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station Schedule

12

*As of March 2017, subject to change

Page 13: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station Staging Yards

Staging Yard Activities and Equipment • Sound wall is 20-24 ft high • Yard usage hours is 24/7 • Yard will be used for:

• Maintenance of equipment • Deliveries of materials • Removal of excavated soil

Mitigations • Must comply with City of Los Angeles noise requirements • Noise Control Signage • Low Impact Back up alarms • Acoustical Insulation • Metro 5 Step Noise Plan

13

Page 14: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

14

Wilshire/La Brea Station: installing ventilation ducts in south shaft, looking west

Page 15: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

15

Pulling ventilation pipes to west end of Wilshire/La Brea Station, looking east

Page 16: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station Center Opening

What • A material handling shaft in the Wilshire Bl center median between Sycamore Av and

Orange Dr, in lieu of multiple intermittent closures and panel openings

• Wilshire Bl remains two lanes in each direction between La Brea Av and Mansfield Av

• Left turns open on Wilshire Bl at La Brea Av and Detroit St in both directions

• Some parking restored on north side of Wilshire Bl and south side of Wilshire Bl

• More robust noise mitigation rather than series of lane closures When • Proposed dates March 2017 through December 2017 How • The work zone would be established using k-rail, fencing and sound blankets • Center opening will feature new banners highlighting adjacent businesses

16

Page 17: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station Center Opening Concept

17

Page 18: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

18

Center opening will resemble Jet grouting enclosure

Page 19: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station Center Opening Concept Area

19

Center opening work zone on Wilshire Bl between Sycamore Av and Mansfield Av, Wilshire Bl two lanes in each direction

Page 20: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station Deck Openings

What: • Deck openings are openings of the

street-deck for the purpose of delivering materials for underground construction

• Deck openings will be done at deck locations designed to open and close

• Deck openings will occur periodically, as needed

• Deck panels are 8 ft by 14 ft Decking opening will occur at all 3 station areas

20

Deck opening at Wilshire/La Brea

Page 21: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Brea Station Excavation

When • Now through the Fall of 2017

• Work hours are 7am to 11pm, and 11pm to 7am as needed

What

• Excavation will occur under the concrete deck, with intrinsically safe equipment certified by the State of California

• Work includes hanging utilities underneath Wilshire Bl, dewatering system installation, and maintenance of geotechnical instruments and dewatering wells

21

Page 22: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

22

Northwest corner of Wilshire/La Brea Station looking east

Page 23: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

23

Pulling ventilation pipes close to west end of Wilshire/La Brea Station, looking southeast

Page 24: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Jet Grouting

Overview • Jet grouting is a construction process that uses high-pressure air and grout to create

a deep soil-concrete block

• Jet grouting reinforces and strengthens the soil with concrete to support tunneling and cross-passage construction

Locations • Jet grouting will occur at 16 cross passage locations along Wilshire Bl between La

Cienega Bl and Western Av

• There will be no more than three jet-grouting operations performed at one time (this can make traffic control simpler and safer), in consultation with LADOT

• Jet grouting requires approximately 8 to 12 weeks at each location, due to traffic control and installation of geotechnical instrumentation for future tunneling

Work Hours

• Mon. thru Fri. 7am to 9pm, Sat. and Sun. 8am to 6pm

24

*Work hours subject to change

Page 25: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

25

Six “Businesses Open” signs placed along jet grouting locations

Page 26: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Jet Grouting Updates *Dates and work activities subject to change

Location Status

Wilshire Bl between Plymouth Bl and Windsor Bl Complete

Wilshire Bl between Norton Av and Wilton Pl In process

Wilshire Bl between Gramercy Pl and St. Andrews Pl In process

Crenshaw Bl Upcoming

*Construction notices will be sent and outreach will be conducted for each location

26

Page 27: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Jet Grouting Activities & Layout

27

Work Activities • Potholing, street level excavation , vertical drilling , trucking, cement silos, pumps, generators

Layout • Concrete barriers placed on the middle lanes of Wilshire Bl

• Lanes reduced to two lanes each direction at jet grouting locations

• Bus stops will be temporarily relocated as required

• Wilshire BRT lane not enforced in these areas during jet grouting

• Intermittent material deliveries during off peak hours

Page 28: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station

28

Page 29: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station

29

Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr

Page 30: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Schedule *As of March 2017, subject to change

30

Page 31: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Pile Installation Overview - COMPLETED

Pile Installation includes:

• Rig to construct 95-ft (L) deep

• Crane lifting 95-ft (L), 24-inch H-piles into holes

• 460 piles

• Drilling, pile installation and backfilled concrete completed same day

Piling Start Dates:

• Piling started in August 2016 on the north side of Wilshire Bl and switched to the south side in November 2016

Lane Reductions & Turn Restrictions:

• Wilshire Bl is reduced to two lanes in each direction with left turn restrictions in the area

31

Page 32: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Decking Overview

Decking

• Location: on Wilshire Bl, between Ogden Dr and the 99 Cents Store

• Construction of a concrete deck goes from curb to curb

• Sidewalks are maintained or pedestrian detours created

• Decking will serve as the temporary street surface

• Traffic will travel on the installed deck panels while the station is constructed underground

• Fairfax Decking began as of February 2017

• Additional activities under decking closures include piling and temporary civil improvements

Fairfax Station Stats

• 800-ft long

• 70-ft wide

• 60-ft deep

32

Page 33: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

33

Aerial view of decking progress from roof of the Petersen Automotive Museum

Page 34: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Decking Overview

34

Example of decking operations

Page 35: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Decking Schedule

February 2017 through Summer 2017 • Approximately 18 weekend closures, scheduled in three phases beginning east and

moving west on Wilshire Bl Phase 1: Ogden-Fairfax – 10 weekends Began Friday, February 10th Phase 2: Fairfax intersection – 4 weekends Phase 3: West of Fairfax – 4 weekends • Friday 8pm: Full closure of Wilshire Bl or Wilshire Bl/Fairfax Av intersection • Monday 6am: Streets open • LADOT approved early lane reductions to start Fridays at 10am Wilshire Bl will be

reduced to one lane in each direction from Crescent Heights Bl to Spaulding Av to allow for the loudest work (breaking of concrete) to be completed during day time hours

• Work occurs continuously throughout weekend

*Dates and work activities subject to change

35

Page 36: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Traffic Action Plan

Traffic Action Plan:

• Detour routes

• Proposed mitigations

• Signage

• Signal timing adjustment

• Traffic Control Officer locations

• Maintains local access

• Bus detours

• Approved by Board of Public Works and LADOT

36

Traffic signage examples

Page 37: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 1 Traffic Detour – 10 Weekends Wilshire Bl, Ogden Dr – Fairfax Av Closure

Westbound: Northbound La Brea Av to westbound 6th St to southbound Fairfax Av to westbound Wilshire Bl

Eastbound: Northbound Fairfax Av to Eastbound 6th St to southbound La Brea Av to Eastbound Wilshire Bl

• Local access on Wilshire Bl for business and residents will be maintained

• Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Crescent Heights Bl

• Lane reductions on Wilshire Bl going westbound will start: Wilshire Bl/Orange Dr

Essentials • Wilshire Bl reduced to one lane in each direction from Spaulding Av to Fairfax Av on Fridays

from 10am to 8pm • Full closure of Wilshire Bl, from Spaulding Av to Fairfax Av starting at 8pm on Fridays until

Mondays at 6am • Lane reductions on Fairfax Av for west end work • Anticipated duration: 10 weekends

37

Page 38: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 1 Traffic Detour – 10 Weekends Wilshire Bl, Ogden Dr – Fairfax Av Closure

38

Page 39: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 2 Traffic Detour – 4 Weekends Wilshire Bl/Fairfax Av Intersection

39

Westbound: Westbound Wilshire Bl to southbound La Brea Av to westbound Olympic Bl to northbound San Vicente Bl to westbound Wilshire Bl

Eastbound: Eastbound Wilshire Bl to southbound La Cienega Bl to eastbound Olympic Bl to northbound La Brea Av to eastbound Wilshire Bl

• Local access on Wilshire Bl for business and residents will be maintained

• Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Hamilton Dr

• Hard closure at San Vicente Bl

• Lane reductions on Wilshire Bl going westbound will start: Wilshire Bl/Orange Dr

Essentials • Early start lane reductions on Wilshire Bl and Fairfax Av starting on Fridays from 10am until 8pm • Full closure of Fairfax Av starting at 8pm on Fridays until Monday at 6am • Full closure of Wilshire Bl starting at 8pm on Fridays until Monday at 6am • Anticipated duration: 4 weekends

Page 40: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 2 Traffic Detour – 4 Weekends Wilshire Bl/Fairfax Av Intersection

40

Page 41: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 2 Fairfax Av Traffic Detour Fairfax Av/Wilshire Bl Intersection Closure

Southbound: Southbound Fairfax Av to eastbound 6th St to southbound La Brea Av to westbound Olympic Bl to southbound Fairfax Av Northbound: Northbound Fairfax Av to eastbound Olympic Bl to northbound La Brea Av to westbound 6th St to northbound Fairfax Av

• Lane reductions on Fairfax Av going northbound will start: Wilshire Bl/Whitworth Dr

• Lane reductions on Wilshire Bl going southbound will start: Wilshire Bl/Maryland Dr

• Local access on Fairfax Av for business and residents will be maintained

Essentials • Early start lane reductions on Wilshire Bl and Fairfax Av starting on Fridays from 10am until 8pm • Full closure of Fairfax Av starting at 8pm on Fridays until Monday at 6am • Full closure of Wilshire Bl starting at 8pm on Fridays until Monday at 6am • Anticipated duration: 4 weekends

41

Page 42: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 2 Fairfax Av Traffic Detour Fairfax Av/Wilshire Bl Intersection Closure

42

Page 43: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 3 Traffic Detour – 4 Weekends Wilshire Bl, West of Fairfax Av

Westbound: Southbound Fairfax Av to westbound San Vicente Bl to westbound Wilshire Bl

Eastbound: Eastbound Wilshire Bl to southbound La Cienega Bl to eastbound Olympic Bl to northbound La

Brea Av to eastbound Wilshire Bl

• Local access on Wilshire Bl for business and residents will be maintained

• Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Hamilton Dr

• Hard closure at San Vicente Bl

• Lane reductions on Wilshire Bl going westbound will start: Wilshire Bl/Orange Dr

Essentials • Wilshire Bl from Fairfax Av to Crescent Heights Bl reduced to one lane in each direction on Fridays from

10am until 8pm • Full closure of Wilshire Bl from 8pm on Fridays until 6am on Mondays • Working with City of Los Angeles to address access to buildings between Crescent Heights Bl and Fairfax Av

(zone shown in yellow), work zone shown in purple • Lane reductions on Fairfax Av to support work on the east end of the closure • Anticipated Duration: 4 weekends

43

Page 44: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Phase 3 Traffic Detour – 4 Weekends Wilshire Bl, West of Fairfax Av

44

Page 45: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire Bus Detours Phase 1: Fairfax Decking

720/20 Wilshire bus stops have been relocated • In effect: 8pm Friday, February 10, 2017, until 6am Monday February 13, 2017

and continuing every weekend until further notice Eastbound Detour • Regular route to Wilshire Bl and McCarthy Vista then continue via Wilshire Bl

to Fairfax Av to 3rd St to La Brea Av to Wilshire Bl and regular route Westbound Detour • Regular route to Wilshire Bl and La Brea Av then La Brea Av to 3rd St and

Fairfax Av to Wilshire Bl and regular route *Passenger stops available at all intersection where it is safe, while on detour route.

45

Page 46: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Decking Community Outreach

Robust Marketing Campaign • Social media: Facebook, Twitter, and Nextdoor • Advertising: print, radio, and online • Media coverage: press releases

• Business and residential outreach

• Meetings with local groups, leaders

• Elected Official Briefings

• Safety Presentations

• School Presentations

• Community Partnerships

46

Page 47: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Decking Community Outreach

47

Chrysalis, non-profit, helps with door to door outreach

Page 48: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/Fairfax Station Deck Openings

What: • Deck openings are openings of the

street-deck for the purpose of delivering materials for underground construction

• Deck openings will be done at deck locations designed to open and close

• Deck openings will occur periodically, as needed

• Deck panels are 8 ft by 14 ft Decking opening will occur at all 3 station areas

48

Typical deck opening

Page 49: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station

49

Page 50: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station

50

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

Page 51: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station *As of March 2017, subject to change

51

Page 52: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station La Cienega Staging Yards

52

Photos of preparation work for soundwalls at the La Cienega staging

Page 53: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station Gale Staging Yard

53

Completed soundwall at Gale Staging Yard

Page 54: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station Upcoming Work

54

March thru May, 2017

• Instrumentation installation on Wilshire Bl, La Cienega Bl and adjacent streets to began in January and continues thru May.

• Pre-pile activities and instrumentation will be ongoing behind k-rail and throughout the station area

• Piling on the south side of Wilshire Bl to start mid-March

• Jet grouting at east and west ends of the station

Details for all work will be communicated in construction notices and through outreach to affected businesses, residents and stakeholders

Page 55: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station Work zone, south side of Wilshire

55

Approximate location of south side pile work zones at Wilshire Bl/La Cienega Bl

Page 56: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station

56

Pile installation, south side of Wilshire between La Cienega Av and Tower Dr

• Approximately 470 piles total to be installed – approximately 166 piles on the south side

• Work zone delineated by k-rail and fencing

• Piling is projected to start mid-March 2017

• Work hours: 7am-8pm; drilling and setting of piles; 8pm-10pm; breakdown, cleanup, non-drill activities.

Wilshire/La Cienega Stats:

• 990 ft long

• 70 ft wide

• 60 ft deep

Page 57: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station Piling Mailer

57

Page 58: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station Upcoming Work – Pending Approval

58

Cross-section showing work zone and drill rig for pile installation

Page 59: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Wilshire/La Cienega Station Upcoming Work

59

Jet Grouting at Wilshire/La Cienega

• Jet grouting is soil reinforcement using a drill rig to support station excavation and tunneling. Additional equipment include generators, pumps and a grout silo

• Jet grouting will occur within the south side k-rail work zone

• Additional jet grouting will happen under lane reductions outside of work zone

• Anticipated to start in March of 2017

Work hours:

• 7am-8pm; drilling

• 8pm-10pm; breakdown, cleanup, non-drill activities (Lane closures will follow permitted hours)

• Pending City of Beverly Hills approval

Page 60: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Staying Safe Near Construction Sites

60

• Stop, Look, & Listen

• Be alert and aware of your surrounding

• Avoid distractions

• See and be seen

• Obey construction signage

• Use designated sidewalk or walkways

Page 61: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Help Us Keep You Safe

61

Purple Line Extension 24/7 Project Hotline - 213.922.6934 On Metro Transit See Something, Say Something 888-950-SAFE (7233) Construction Safety Awareness Program Glyssa Alcazar, Community Relations Officer Email: [email protected] Phone: 323.900.2192

Page 62: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Win 7-Day Metro TAP Card

62

Page 63: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Recap: Lunch Meet-Up with Book My-Lot Food Trucks

63

Page 64: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Next Lunch Meet-Up at Bru's Wiffle Beverly Hills

Tuesday, April 4, 2017 - 11:30am to 1:30pm

64

8635 Wilshire Blvd., Beverly Hills, CA 90211

Page 65: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation
Page 66: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

BIF Grant Award Update

> Purple Line Extension, Phase 1 (as of 3/10/17)

> BIF Applications Submitted: 99

> BIF Applications Awarded: 77

> BIF Grant Amount Awarded: $1,627,060.14

*13 applications pending completion

*9 applicants have been deemed ineligible

> Noteworthy Updates:

> 41 businesses have received one or more BIF grants

> Average amount per grant: $21,130.65

Page 67: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Metro Business Interruption Fund

• Financial assistance to small “mom & pop” businesses impacted by Metro transit rail construction along three project areas:

• Purple Line Extension, Phase 1

• Crenshaw/LAX Transit Project

• Regional Connector, Little Tokyo area & 2nd/Broadway segment

• Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements

• Grant amount determined by demonstrated loss of business revenue directly related to the period of construction disruption

• Maximum annual grant amount per business is $50,000

BIF Business Advisor for PLE

• Brian Lazo, PCR at 213-739-2999, ext. 240

67

Page 68: Purple Line Extension · 2017. 3. 21. · Purple Line Maintenance Facility . 6 . 590 S Santa Fe Avenue • Located in the Arts District, near 6. th. St Bridge • Initial excavation

Next Meeting

Section 1: Construction Community Meeting

Thursday, May 18, 2017

6pm – 7:30pm

SAG/AFTRA

5757 Wilshire Bl Los Angeles, CA 90036

68