public disclosure authorized national urban transport ......stakeholder dynamics o baseline...
TRANSCRIPT
1
CONSULTANCY SERVICES FOR REVIEWING AND UPDATING OF THE
ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) FOR THE
PROPOSED KISUMU NORTHERN BYPASS
1.0 Introduction
The Government of the Republic of Kenya (GoK) has received a credit from the
International Development Association (IDA) in towards the cost of the National Urban
Transport Improvement Project (NUTRIP), and intends to apply a portion of proceeds
from this credit for Construction of Kisumu Northern Bypass.
The Kisumu Northern By-Pass starts at Mamboleo Junction of Kisumu-Kakamega (A1)
Highway. After Mambo Leo Junction, the Kisumu Northern Bypass goes through quarry
field, then after first curve, heads towards piedmont of Kanyakwar Hills at Riat Tor
(Hill). Then it curves around the Kogony Hill, passes infront of Jans Senior Academy and
runs for about 1 km. After curving out westward after Tor 9, it crosses Riat-Paradise
Murram road 100 m to the south of Abuson Shop, and the bypass then runs southwards
in a straight line. It crosses Kisumu – Butere rail line before joining the adjoining Kisumu
Airport-Kisian Junction (B1) Road at a point about 400 m to the east of Kotetni Primary
School fence. The restructured project will be expanded to include the adjoining Kisumu
Airport-Kisian junction.
The restructured Kisumu Northern Bypass project will comprise of the following: (i) 8.0
km road section commencing Kisumu -Kakamega (A1/C34) to Otonglo; and (ii) the
expansion of the 7.4 km adjoining Kisumu International Airport-Kisian Junction
(B1/C27).
Kisumu Northern Bypass project will be 8.0 km road section long commencing Kisumu -
Kakamega (A1/C34) to Otonglo. It will consist construction of a new road over rail
bridge at Otonglo, construction of an Interchange at Otonglo and construction of main
carriageway pavement layers. This will be a new road alignment and involves land
acquisition. The process of land acquisition has started and the consultant will review the
RAP which was prepared in 2012 and disclosed.
The entrance to Kisumu International Airport to Kisian Junction (B1/C27) will include
the construction of the 2 Lane (7.0m wide) Second Carriageway from the entrance of the
NATIONAL URBAN TRANSPORT IMPROVEMENT PROJECT
(NUTRIP)
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
Kisumu International Airport up to the Kisian junction B1/C27. It will also include the
construction/Rehabilitation of the Kisian River Bridge and construction of an Intersection
at Kisian junction. This will be capacity enhancement of the existing road by adding a
second carriageway on the existing road reserve.
3
Figure Error! No text of specified style in document.-1: Location Traversed by the Proposed 8km long Mamboleo to Otonglo Kisumu Northern
By-Pass Road and Airport Kisian Junction
4
2.0 ESIA Reviewing and Updating Justification
Kenya National Highways Authority (KeNHA) undertook the preparation of
Environmental and Social Impact Assessment (ESIA) for the proposed Kisumu Northern
Bypass approximately 8km in the year 2011 and the ESIA report was disclosed in
country and in the World Bank InfoShop, and the project was issued with National
Environment Management Authority (NEMA) license for the project as per national
requirements. However, studies by GoK have necessitated the expansion of the adjoining
7.4 km Kisumu International Airport -Kisian junction to accommodate the increase of
traffic in the area, and hence the inclusion of this section into the proposed Kisumu
Northern Bypass project. Also, the original project was assigned Environmental Category
‘B’, however, based on ongoing restructuring of the NUTRIP project, the project
environmental category has been reclassified as Category ‘A’ , since the project is likely
to have significant adverse environmental and social impacts that are sensitive, diverse or
unprecedented. Thus, the change in project scope and reclassification of the Environment
Category to ‘A’ has necessitated the review and updating of the initial ESIA by an
independent consultants, in accordance with the requirements of World Bank Safeguards
Policies, OP/BP Environment Assessment, for Category A projects and to include the
adjoining section (about 7.4 km) which was initially not part of the project.
This Terms of Reference (ToR) cover the independent review and updating of
Environmental and Social Impact Assessments (ESIA) prepared in 2011, for the proposed
Kisumu Northern Bypass and the adjoining Kisumu International Airport to Kisian
Junction (B1/C27). This ESIA shall be reviewed and updated in a manner consistent
with World Bank Safeguards Policies and Procedures, World Bank Group (WBG)
General Environmental Health and Safety Guidelines and WBG Industry Sector
Guidelines for Construction Materials Extraction, relevant laws and regulations of the
Government of Kenya (GoK), and KeNHA Environmental policy requirements.
3.0 Objective of the Assignment
The objectives of the assignment are: (i) review and update the existing ESIA report,
identify any gaps vis-à-vis WB safeguards policy requirements of OP/BP 4.01
(Environment Assessment) for Category A projects and the national requirements for
ESIA; (ii) identify and fill in those gaps by updating the ESIA, including collection of
additional baseline information, and in depth analysis of environmental and social
impacts that are not currently covered in the existing report; (iii) updating the ESMP to
include both generic construction measures and site-specific measures (iv) carry out
environmental and social assessment for the expansion of the adjoining Kisumu
International Airport to Kisian Junction (B1/C27) which was not part of the original
5
project and update the existing ESIA done in 2011 and (iv) Carry out two public
consultations as per the Category A, project requirements.
The specific objectives of the assignment are:
To review and update the existing ESIA report to conform with World Bank
Environmental and Social Safeguards Policies and Procedures for Environment
Assessment (OP/BP 4.01), for project assigned Category A, WBG General EHS
Guidelines and applicable WBG Industry Sector Guidelines and laws and
regulations of the Government of Kenya,
To review and identify gaps in the existing ESIA report prepared for this
subproject and address them by evaluating the established social and
environmental context, reviewing the identified potential risks and impacts,
benefits and opportunities.
To review and identify all the potential significant positive and adverse
environmental and social impacts, including direct, indirect and cumulative
impacts associated with the proposed project
To review proposed measures to avoid, reduce, mitigate, manage and/or
compensate for such impacts, including the institutional arrangements and
required capacity building to implement all such measures and monitor their
effectiveness
To review and update the Environmental and Social Management Plan (ESMP)
Ensure that the stakeholder analysis and consultation are conducted as part of the
ESIA review, and identify who among the affected population is particularly
vulnerable to potential adverse impacts. The project should adopt differentiated
measures so that potential adverse impacts do not fall disproportionately on the
disadvantaged or vulnerable
To carry out site investigations to collect primary data and review available
relevant secondary data to establish a comprehensive environmental and social
baseline, indicators, and data collection methodology
To conduct public consultations and meaningful stakeholder engagement with
project-affected persons, lead agencies and Non-Governmental Organizations
(NGOs) about the project's environmental and social impacts, as well as offer
opportunity to receive their opinions and feedback so as to take their views into
account and reflect the issues raised into the final design for the project.
To come with appropriate budget for environmental, social and, health and safety
mitigation measures for the project.
To document all the above mitigation and development interventions in
acceptable format to be further discussed and agreed with KeNHA and in
compliance with the World Bank Safeguards Policies, WBG EHS guidelines and
EHS guidelines for Toll Roads
6
4.0 Environmental and Social Assessment Requirements
Scope of Work
The Consultant shall undertake through review of the existing ESIA report in terms of: (i)
consistency and compliance with World Bank Operational Policy Environment
Assessment (OP/BP 4.01), Category A project requirements and the GoK laws and
regulations in order to identify existing gaps and update the ESIA; (ii) consistency with
respect to the project’s feasibility study and /or detailed engineering designs, RAP and /or
other similar project documents. The review and updating of the ESIA will build on and
be guided by the ESIA report prepared and disclosed in 2012.
The review and update for the subproject will be according to the following table of
content (Adapted from the World Bank OP 4.01, Annex B, Content of an Environmental
Assessment Report for a Category A Project):
The consultant shall review and update the existing ESIA to ensure it covers but not
limited to the following:
Task 1. Non-Technical Executive Summary:
The Non -Technical Summary should include:
Description of the proposed road subproject,
Rationale for the proposed subproject,
Geographical area that the project will influence
Any significant environmental and social impacts
Any Significant issues and opportunities
Summary of key findings of the environmental and social management plan,
KeNHA systematic approach to manage the environmental and social aspects
of the subproject including monitoring procedures
Task 2: Background:
This section should discuss:
explain the purpose of the ESIA and the timeline of its preparation
summarize available literature on the subproject and its potential impacts;
KeNHA will provide available literature to the Consultant, which will serve
as a starting point
make reference the Resettlement Action Plan (RAP) that has been prepared
for this subproject
7
Task 3: Detailed Description of the Proposed Project:
The Consultant will concisely describe:
the proposed project (construction, operations and decommissioning),
including the technology to be used and construction timeline
project ancillary facilities and potentially linked activities that may be
required (access roads, quarries, worker camps, and raw material or product
storage facilities)
geographic location and areas of traverse (provided by KeNHA)
Task 4: Policy, Legal, Regulatory and Institutional Framework
This section shall review and discuss the policy, legal, and administrative frameworks
within which the ESIA and ESMP will be carried out. Most particularly, the Consultant
will:
(i) Review Government of Kenya requirements and procedures for the
management of environmental and social issues, including labour, occupational,
health and safety requirements.
(ii) Describe the reporting requirements of the National Environmental
Management Authority (NEMA)
(iii) Review the requirements of the World Bank Safeguards Policies triggered under
NUTRIP , including the World Bank Group General Environmental, Health and
Safety (EHS) Guidelines and the Industry Specific EHS Guidelines for
Construction Materials Extraction. Toll Roads
(iv) Review the environmental, social and safety procedures of KeNHA
(v) Review and Analyse the gaps between the triggered World Bank Safeguards
Policies and Kenyans laws and regulations
(vi) State the compliance requirements that the Project must meet
(vii) Identify relevant international environmental agreements, conventions and
treaties to which Kenya is a party.
Task 5: Description of the Environmental and Socioeconomic Baseline
If required based on the review and gap analysis, the Consultant will collect, collate and
present additional baseline information on the existing environmental and socioeconomic
characteristics of, within and around the subproject sites/area of influence. The baseline
will:
(i) Present data directly relevant to decisions about subproject location, design,
8
operation, or mitigation measures, including:
o Physical environment (such as topography, landforms, geology, soils,
climate, air quality, and hydrology)
o Biological environment (including biodiversity, fauna, flora, animal
migration, endangered species, critical natural habitats, forests,
protected and sensitive areas)
o Socioeconomic and cultural environment (such as demography,
settlements, community structures, vulnerable and marginal groups,
sources and distribution of income, employment and labour markets,
land use, and cultural heritage).
o Stakeholder mapping including analysis of stakeholder influence and
stakeholder dynamics
o Baseline assessment of the community conflict dynamics, youth and
gender dynamics in the area.
(ii) Identify any changes anticipated before the project commences.
(iii) Take into account current and proposed development activities within the
subproject area but not directly connected to the subproject.
(iv) Collate available data from existing sources, and if necessary collect original
data. Include data directly provided and confirmed by relevant data sources,
such a Kenya National Household Survey (KNHS), county integrated
development plans, National Environment and Management Authority (NEMA)
and the County authorities.
(v) Identify and estimate the extent, quality, accuracy and reliability of available
data, key data gaps, and uncertainties associated with predictions, and specifies
topics that do not require further attention.
Task 6: Identify Potential Environmental and Social Impacts that could result
from the Project:
The Consultant shall review, analyze and describe all significant deviations from the
environmental and socioeconomic baseline that might be caused by the subproject,
including environmental and social impacts, both positive and negative.
During the analysis, the consultant shall consider both biophysical and socioeconomic
factors, such as (list is not exhaustive):
o Population change and migration
o Forms of social organization (ethnicity, clan/tribal structures and
minority groups,)
o Income sources and expenditure
o Household sources of income
9
o Gender-based violence
o Gender issues
o Population influx
o Labour issues and working conditions
o Community health and safety
o Conflict and social tensions
o Physical and social infrastructure
o Changes in economic activities
o Relocation and resettlement (make sure that information in the ESIA
are consistent with the RAP)
o Removal of structure/sites
o Development resources
o Improved access
o Water resources
o Accident rates
o Visual/aesthetic changes
o Vegetation clearance
o Mechanical disturbance
o Effects on flora and fauna, air quality, water quality and quantity.
o Occupational health and safety
o Sensitive receptors along the road corridor, ancillary facilities and
potentially linked activities
More specifically, the consultant will:
i. Predict and assess the subproject's potential positive and negative
environmental and social impacts (clearly articulated in respective sub-
sections for environmental and social impacts) that might change the baseline
conditions, in quantitative terms to the extent possible, during the
construction, operation and decommissioning phases.
ii. Differentiate between short, medium and long-term impacts, estimate the
magnitude of impacts, and identify generic both generic environmental and
social impacts and site-specific impacts.
iii. Identify mitigation measures and any residual negative impacts that cannot be
mitigated.
iv. Explore opportunities for environmental enhancement.
The identification of impacts for the subproject will be closely coordinated with the
updating of the Resettlement Action Plan to ensure coherence and comprehensiveness.
10
Task 7: Analysis of Alternatives to the Proposed Project
The consultant will:
(i) Systematically compare feasible alternatives to the proposed road alignment
and associated ancillary facilities, such as alignment, technology, design, and
operation - including the "without project" situation -in terms of their potential
environmental and social impacts; the feasibility of mitigating these impacts;
their capital and recurrent costs; their suitability under local conditions; and
their institutional, training, and monitoring requirements.
(ii) For each of the alternatives, quantify the environmental and social impacts to the
extent possible, and attaches economic values where feasible.
(iii) State the basis for selecting the subproject design proposed.
Task 8: Public Consultation and Disclosures
The Consultant will carry out two rounds of public consultations (in line with the
Worldbank category A project requirements) for the subproject, to collect the concerns,
expectations, and opinions of affected, concerned and interested stakeholders for the
subproject.
A robust stakeholder mapping and analysis will be undertaken, that will guide the
preparation of the Stakeholder Engagement Plan (SEP) for the ESIA. Stakeholders to be
consulted must include Kenya Railways, Kenya Airports Authority, Kenya Prison
Service and NEMA, respective Kisumu County Government, NGOs/CSOs, and
local/impacted communities among others.
Disclosure of the ESIA report will be in a manner, form, and language that are
understandable, and will be accessible, to enable full public participation.
The Consultant will carry out public participation and consultations on the positive and
negative impacts of the proposed subproject
The Consultant shall:
i. Take into account the concerns, expectations and opinions of consulted
stakeholders in the final ESIA report.
ii. The consultant will document the public consultations, including consultation
dates, venues, list and signatures of attendees, photos of consultation sessions, a
summary of both the positive and negative concerns of the stakeholders, and how
these concerns, expectations and opinions are incorporated into the final design of
the subproject.
iii. The Consultant will be responsible for public disclosure of the ESIA once the
documents have been approved.
11
Task 9: Development of the Environmental and Social Management Plan
(ESMP)
The Consultant shall review the Environmental and Social Management Plan (ESMP)
prepared for the ESIA, and update the ESMP to address any inconsistencies and gaps
with generic construction measures and site-specific measures.
The ESMP will provide time frames and implementation mechanisms, reporting
responsibilities, description and technical details of monitoring measures, assessment of
the institutional needs, staffing requirements and cost outlay for implementation. The
plan will show how management and mitigation methods are phased with subproject
implementation. The plan will also include measures to prevent health hazards and to
ensure safety in the working environment for the employees and the communities
adjacent to the subproject sites and subproject affected people.
The ESMP will propose:
Individual mitigation and monitoring measures during both construction,
operation, and decommissioning, assign institutional responsibilities, and
estimate the resources required for its implementation.
Measures for preventing, minimizing, mitigating or compensating for the
adverse environmental and social impacts and enhancing beneficial impacts,
including costs of the measures and monitoring requirements.
ESMP will be prepared according to the format (adapted from World Bank OP 4.01,
Annex C, Environmental management plan (EMP) as necessary.
a. Mitigation Plan
The Consultant will identify feasible and cost-effective measures to avoid the potentially
significant adverse environmental and social impacts identified in the subproject ESIA, or
otherwise reduce them to acceptable levels. The Consultant will propose compensatory
measures for residual impacts if mitigation measures are not technically feasible, cost-
effective, or sufficient, and will explore opportunities for environmental enhancement.
The plan distinguishes between the construction and operations phases.
The mitigation plan will:
i. Identify and summarize all anticipated significant adverse environmental and
social impacts (including those of involuntary resettlement) and define both
generic and site specific environmental and social mitigation measures during
construction and operation.
ii. Provide technical details for each mitigation measure, including the type of
impact to which it relates and the conditions under which it is required (e.g.,
continuously or in the event of contingencies), together with designs, equipment
12
descriptions, and operating procedures, as appropriate.
iii. Include emergency/disaster preparedness plans.
iv. Describe with details other plans that will be required during the construction and
operation phases (e.g. Contractor ESMP, Occupational Health and Safety plans
Waste management plan and labour influx plan).
v. Estimate any potential environmental and social impacts of these measures.
vi. Provide linkage with any other mitigation plans (e.g., for involuntary resettlement
and cultural property) required for the subproject.
vii. Include additional data collection to fill identified data gaps.
b. Contractor clauses
The section will cover worksite health and safety, the environmental and social
management of construction sites; labour camps/out of area workers, HIV/AIDS and
other Sexually Transmitted Diseases (STDs), stakeholder engagement plans, grievance
redress mechanism, child protection, gender equity and sexual harassment, labour rights
and the employment of community members.
The Consultant will:
Define standardized environmental and social clauses that KeNHA will include in
supply and installation bidding documents and contracts for the construction and
supervision consultants, to ensure satisfactory environmental, social, health and
safety performance of contractors. The clauses will cover possibly six issues
i. Environment, Health and Safety (EHS)
ii. Environmental and social monitoring by contractor
iii. Environmental and social liabilities
iv. Grievance mechanism for workers
v. Stakeholder engagement plans
vi. Child protection strategy
c. Monitoring Plan
i. Defines monitoring objectives and indicators, and specifies the type of
monitoring, with linkages to the impacts assessed in the ESIA report and
the mitigation measures described in the ESMP.
ii. Provides: (a) a specific description, and technical details, of monitoring
measures, including responsibilities (KeNHA, Supervision
Engineer/Consultant and Contractor ), the parameters to be measured,
methods to be used, sampling locations, frequency of measurements,
detection limits (where appropriate), and a definition of thresholds that
will signal the need for corrective actions; and (b) monitoring and
reporting procedures to ensure early detection of conditions that
necessitate particular mitigation measures, and to furnish information on
the progress and results of mitigation.
13
iii. Includes compliance monitoring of the socioeconomic impact related to
the concerns raised by individuals and communities affected by the
subproject.
d. Institutional Arrangements
i. Review the institutional arrangements, responsibilities, and procedures
within KeNHA, Supervision Engineer/Consultant and its contractor to
carry out each of the mitigatory and monitoring measures (e.g., for
operation, supervision, enforcement, monitoring of implementation,
remedial action, financing, reporting, and staff training).
ii. Describes the role of NEMA in monitoring the implementation of the
ESMP and in certifying compliance.
iii. Includes training of contractors and Supervision Engineer/Consultant
regarding the environmental and social clauses that apply to them.
iv. Estimates the resources required by KeNHA to implement and monitor the
ESMP, such as level of effort (LOE), and equipment.
v. As necessary, proposes capacity building, additional technical support or
organizational changes, to ensure the timely and effective implementation
of the ESMP.
e. Grievance Redress Mechanism
i. Review the proposed GRM procedures for receiving, handling and resolving
complaints from affected individuals and communities (this should be
discussed and consulted upon during the public consultation process).
f. Implementation Schedule and Cost Estimates
i. Implementation schedule for mitigation measures that must be carried out as
part of the subproject, showing phasing and coordination with overall
subproject implementation plans.
ii. The capital and recurrent cost estimates and sources of funds for
implementing the ESMP.
g. Chance Find Procedures
Describe briefly the ‘Chance Find’ procedures to ensure preventive and mitigation
measures are formulated and implemented in the event physical cultural resources
are encountered during subproject implementation. However, the fully ‘Chance
Find’ procedures shall be included as an annex to the ESIA report.
Appendices
List of ESIA report preparers-individuals and organizations.
(ii) References-written materials both published and unpublished, used in study
preparation.
14
Record of interagency and consultation meetings, including consultations for
obtaining the informed views of the affected people and local nongovernmental
organizations (NGOs). The record specifies any means other than consultations
(e.g., surveys) that were used to obtain the views of affected groups and local
NGOs.
List of associated reports (e.g., Resettlement Action Plan and Design Reports
e.tc.)
5.0 Facilities to be provided by the KeNHA
The Client will provide the following subject to availability:
I. Latest/updated project feasibility and engineering design documents
II. ESIA Report
III. RAP report
IV. Access to other relevant information to the extent of its availability
V. Access to the project site and other sites belonging to the Client as the
Consultant may request
The consultant shall be assisted by the Client in any needed consultation/coordination
with the project engineering and design teams and the RAP team.
6.0 Consultant’s Minimum Qualification and Team Composition
The Consultant will ensure that there will be a sociologist working with him/her on this
review and updating of the ESIA.
a. Environmental Specialist/Team Leader
At least a Master’s Degree in Environmental Management or Environmental
related training from a recognized University
NEMA Registered Lead Expert
Minimum overall experience of 15 years, with at least 5 years’ experience on
similar projects in sub-Saharan Africa
Participation in an ESIA for large infrastructure project that met the
requirements of an International Financial Institution, such as the World Bank,
IFC , JICA, KfW, AfDB, or EIB
Registration and/or membership of professional field and valid annual
operating license will be an added advantage
15
b. Social Specialist
At least a Master’s Degree in Social Sciences or related training from a
recognized University
Minimum overall experience of 10 years, with at least 5 years’ practical
experience on similar projects in sub-Saharan Africa
Participation in ESIA for large infrastructure project that met the
requirements of an International Financial Institution, such as the World
Bank, IFC , JICA, KfW, AfDB, or EIB
He/she should should be conversant with the World Bank safeguard policies.
7.0: Reports and Time Schedules
Commencement
The Consultant shall commence the ESIA review and updating within seven (7) calendar
days of the effective date of signing of the contract with the Client.
Reports
The Consultant shall prepare and submit the following reports to the Client. All reports
shall be in English and prepared on A4 metric size.
I. Inception Reports: This reports shall summarize the initial findings and give
defined proposals covering the methodologies to be employed for different tasks
for the ESIA, and a detailed work program of all major activities of the
assignment (3 No. Hard copy and 2No. Soft copy to Client for each report).
II. Draft Final Reviewed and Updated ESIA Reports: This reports shall
summarize the findings, analyses, results and recommendations of the study, and
shall contain all supporting materials - (3 No. Hard copies and 2 No. Soft copies
to Client for each reports).
III. Final Reviewed and Updated ESIA Reports: This reports shall incorporate all
revisions deemed necessary arising from comments received from the Client and
the Financier following discussions and agreement from the client and the
Consultant – (6 No. Hard copies and 3No. Soft copies to Client for each
reports).
IV. Stand-alone non-technical Executive Summary for the Environment and Social
16
Impact Assessment Report
Format of the Reports
The reports shall be provided in CD-ROM in Microsoft Word for text, Microsoft Excel
for tables/graphs and spread sheets and AutoCAD for drawings.
Submission of Reports
The above reports shall be submitted to:
Director (Development)
Kenya National Highways Authority
Blue Shield Towers
P.O Box 49712-00100
NAIROBI
Implementation Time Schedule
The expected schedule of the assignment is as follows:
a) The Consultant shall commence the ESIA review and updating within seven
(7) calendar days of the effective date of the contract. The effective date shall
be the date on which the Consultancy agreement shall be signed by the Client.
b) The review and updating Consultancy will take a total of Eight (8) weeks
c) The following tentative time schedule shall be observed in carrying out the
studies:
Activity Month
Responsibility
(i) Effective Date of Contract M+0 KeNHA
(ii) Commencement of Services M+0.25 Consultant
(Reviewed and Updated ESIA Report)
(iii) Inception Report M+0.5 Consultant
(iv) Draft Final Report M+1.5 Consultant
(v) Reviews of Draft Final Report M+2.5 KeNHA &WB
(vi) Final Report M+3 Consultant
17
The consultant is expected to indicate clearly assignment critical milestones, with timing
for each activity; taking into account the duration of the entire project implementation
period.
In addition to the above, the Consultant would, however, outline the scheduling of
activities for the ESIA update.
18
References
The World Bank has designated 10 Operational Policies as environmental and social
Safeguard Policies. NUTRIP triggers the safeguard policies on Environmental
Assessment (OP/BP 4.01, Physical Cultural Resources (OP/BP4.11), and Involuntary
Resettlement (OP/BP 4.12).
The World Bank Group Environment, Health and Safety (EHS) guidelines are referenced
in footnote 1 of OP 4.01. They are technical reference documents with general and
industry-specific examples of Good International Industry Practice (GIIP). They define
acceptable pollution prevention and abatement measures and emission levels in World
Bank financed projects. The General Environment Health and Safety (EHS) Guidelines
and the Guidelines for Toll Roads are applicable to NUTRIP.
The relevant Kenyan environmental legislation and regulations include EMCA Act, 1999
as amended in 2015 and the Constitution of Kenya, 2010.
Environmental & Social Impact Assessment study report for the proposed construction of
Kisumu Northern Bypass, 2011
Resettlement Action Plan(RAP) report for the proposed for the proposed construction of
Kisumu Northern Bypass, 2011