Proton Driver at Fermilab

Keith Gollwitzer

Accelerator Division

Fermilab

IDS-NF 7th Plenary Meeting Oct 17-19,2011

Page 2: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Review/Intro

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 2

Page 3: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Review/Intro

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 3

Front End (warm)H- ion source, RFQ, MEBT, Programmable Chopper System

Initially 5mA

Programmable Chopper

Capable of bunch by bunch 162.5MHz

Will suppress beam to limit beam current down stream to

1mA average

Page 4: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Review/Intro

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 4

3 GeV CW SRF LinacAverage beam current 1mA

325 and 650MHz

Page 5: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Review/Intro

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 5

Splitters

Pulsed Dipole to switch from 3GeV experiment area and Pulsed Linac

Transverse RF beam splitter synchronized with programmable chopper

Page 6: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Review/Intro

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 6

Pulsed Linac

1.3GHz SRF3-8 GeV

5% duty factor at 10Hz

Page 7: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Review/Intro

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 7

Recycler/Main Injector/Beam LinesUpgrades to handle increase beam power

Stripping H- and accumulation of protons at 8GeV

Page 8: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 8

Project X Summary

• CW Linac will support average beam current of 1 mA to 3 GeV

• Pulsed Linac (3-8 GeV) will have a ~5% duty factor

• Possible 8 GeV beam power of 320 kW

• Programmable Chopper System (part of H- source) will provide appropriate bunch structure for the linac experiments as well as fill the appropriate part of the RF buckets in the accumulating Recycler Ring

October 18, 2011

Page 9: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 9October 18, 2011

Chopping and Splitting

Average

Page 10: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 10October 18, 2011

Fine Chopping

Average

Page 11: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 11

Neutrino Factory• Upgrade Project X

– 4 MW at 8 GeV• Increase particles per linac bunch• Increase pulsed linac duty factor

• Repackage linac beam for ~60 Hz delivery– Accumulator Ring

• Collect linac beam into bunches

– Compressor Ring• Narrow bunches to <= 3 ns

– Single Bunch Transfer/Extraction

October 18, 2011

Page 12: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Neutrino Factory Layout

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 12

Accumulator Ring

Compressor Ring

4MW Target

????

??

Page 13: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 13

Task Force• Fermilab Management established a group to

identify the upgrade path from Project X and look into feasibility of providing the desired 4MW beam

• Agreed on Project X upgrade numbers– Increase to 5 mA average current– Increase pulse linac duty factor to 10%

• Outlined options/limitations– Striping– Accumulator and Compressor Rings

• Discussing instability limitation for rings

October 18, 2011

Page 14: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Upgrade Neutrino Factory

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 14

Front End (warm)H- ion source, RFQ, MEBT, Programmable Chopper System

Initially 5mARun at 10mA (Ion source is capable)

Programmable Chopper

Capable of bunch by bunch 162.5MHz

Will suppress beam to limit beam current down stream to

5mA 1mA average

Entire front end is being

designed for 10mA

Page 15: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Upgrade Neutrino Factory

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 15

3 GeV CW SRF LinacAverage beam current 1mA 5mA

325 and 650MHz

Retuning of couplers to be efficientMay set initially for higher current

Page 16: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Upgrade Neutrino Factory

October 18, 2011 Gollwitzer -- 7th IDS-NF Meeting 16

Pulsed Linac

1.3GHz SRF3-8 GeV

10% 5% duty factor at 10Hz 15HzMore RF power

Upgrade of couplersMore cryo capicity

Page 17: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 17

Rings’ Concepts• Simple numbers to start

– Trev ~ 800 ns

– frf ~ 10 MHz

– h = 8– Injection scheme

• ~50 ns beam ON followed by ~50 ns NO beam

• Evolution of design – Increase of circumference (~300m)– Space for RF and Injection/Extraction components– Concerns

• Injection: Stripping • Instabilities• Beam size in Compressor after bunch rotation

– Several designs and will settle on oneOctober 18, 2011

Page 18: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 18

Costing?• Fermilab engineering resources are busy• A little work has been done for Project X

upgrades – Project X has been doing lots of costing

exercises

• Rings (& new beam lines – inc. Final Focus)– Need to settle on lattice– Get count for components, cables, power

supplies, RF ....

October 18, 2011

Page 19: Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Gollwitzer -- 7th IDS-NF Meeting 19

Plan• Set rings and beam lines lattice• Studies of instabilities• Write Task Force report on feasibility• Move onto costing