Properly Reviewing a Schedule
GoalsConfirm that schedule is reasonable andattainableUnderstand Contractor’s Means & MethodsEstablish a good baseline for monitoringVerify durationsVerify logic and sequencingIdentify claims positioning issuesIdentify risks in schedule and assumptionsDocument concerns
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 3/61
Schedule Review
Baseline Schedule ReviewReview Scheduling SpecificationConfirm Submittal CompletenessGain Familiarity with ProjectImport Schedule & VerifyReview Schedule ArchitectureReview Schedule ConstructionReview Narrative
Review SequencingEvaluate Metrics & StatisticsPerform Analysis
Write Report
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 4/61
Baseline Schedule ReviewReview Scheduling Specification
Section 01320 or 01.32.16Check Related SpecificationsSections or Special ProvisionsSoftware requirementsData exchange requirementsMaster dictionaries/reports
Activity Code requirementsID Coding requirements
Preconstruction meeting
Qualifications of schedulerRequired submittal contentsOwner mandated milestonetreatment
Float ownership
CPM Network requirementsDuration definitions & restrictionsInitial schedule submissionFull detailed project schedule(baseline) submissionSchedule updatesDelays & time extensions
Notification RequirementsEarly completion schedules
Final as-built submittalCost & Resource loadingNarrative RequirementsProhibitions on manipulation
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 5/61
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 6/61
Baseline Schedule ReviewGain Familiarity with Project
Review Plans & SpecificationsReview specialty specs like DOT Bridge & Road ManualVisit job siteReview construction methodology or unusual techniques
Bring in expertise if necessary
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 7/61
Confirm Submittal CompletenessCompare to schedule specification requirementsNotify Contractor immediately if not completeDo not start review until submittal is completeTypical missing items:
Schedule NarrativeElectronic FileExplanation of Calendars, Lags, Activity Codes, Constraints,Resources, CostsMilestones and Milestone definitions
Consider two part review if costs or resources are missing
Baseline Schedule Review
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 8/61
Baseline Schedule ReviewImport Schedule & Verify
Keep original submittal file, make copy to reviewShould review in original software if possibleRecognize that there are issues with import in many softwarepackages
Develop checklist to identify potential import issuesExample - Primavera P3 to P5 import :
In P3, Lags are driven by Predecessor CalendarIn P5, Lags can be driven by choice of Calendars
Default P5 setting to drive Lags is not the Predecessor CalendarMust verify that imported schedule used to analyze is identical tooriginal submitted schedule
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 9/61
Baseline Schedule Review
Develop a checklist for reviews
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 10/61
Baseline Schedule ReviewReview Schedule Architecture
Check Schedule Rules & SettingsRecalculate ScheduleReview Organizational Tools
Review Schedule ConstructionEvaluate ActivitiesReview LogicEvaluate Critical Path
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 11/61
Baseline Schedule ReviewReview Schedule Architecture
Check Schedule Rules & SettingsRetained Logic vs. Progress Override• Won’t affect Baseline, but could cause optimistic
predictions during updates
Resource and Cost rules• Estimate to Complete setting might allow Estimate atCompletion to change
Understand all settings and how they affect EarnedValue & reportsIdentify how Critical Path is calculated
• Longest Path• Total Float value
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 12/61
Baseline Schedule ReviewReview Schedule Architecture
Recalculate Schedule, ensure no changeCheck NTP and Completion datesCheck all interim Milestone datesReview Organizational Tools
• Review Activity Code Dictionaries• Review Resource Code Dictionaries• Review Calendars• Review WBS
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 13/61
Baseline Schedule ReviewReview Schedule Construction
Evaluate ActivitiesSort by Activity Description
For good guidelines, see AACE publication No. 23R-02,Recommended Practice for Identification of ActivitiesSee if descriptions are consistent and unique
Ensure all items that could delay project are represented byactivities, such as procurement and other admin workCompare descriptions for reasonable and comparable OriginalDurationsConfirm that descriptions capture full scope of work
Sort by Original DurationCheck for specification maximum timesCheck for reasonable ODs
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 14/61
Baseline Schedule ReviewReview Schedule Construction
Review LogicSee AACE publication No. 24R-03, RecommendedPractice for Developing Activity Logic for guidelinesCheck open-ended relationships
• Should only be two; start and end• Reduces accuracy of network calculations• Watch for “dangling” activities: SS or FS with
negative Lag which leave Predecessor open-endedupon updates
Evaluate relationships• Check on all Lags• Filter by trade, check same-trade relationships• Filter by Contractor, check those relationships
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 15/61
Baseline Schedule ReviewReview Schedule Construction
Evaluate Critical PathIs it reasonable and customary?Does it start at beginning of project and run to completion?Does it have an appropriate level of detail?Are there manipulations driving the Critical Path?
• Float sequestering where everything is critical• Manipulation where Critical Path runs inappropriately through all
owner responsibilities• Critical Path is the only highly detailed string of activities in the
project• Nothing is critical due to heavy constraint use• Numerous lags, perhaps not identified, inserted in the Critical Path,
forcing it through specific activities• Is there weather planning included in Critical Path activities or will
any adverse weather cause slippage?
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 16/61
Baseline Schedule ReviewReview Schedule Construction
Evaluate Near Critical Paths
How much work is just off Critical Path?Check Longest Path and lowest Total Float paths(Recommend review of TF < ½ Reporting Period)
Sort by Total FloatCheck reasonableness of high float itemsIs there a consistent range of TF?Lots of high TF activities means underdeveloped logicAll low TF suggests inappropriate logic
Sort by Late StartThis is the worst case expectation of work flowStart at end of schedule & see if reasonableOrganize by Late Start, Order Week Ascending, see if theamount of work planned each week is possible
Check trade stacking, can they fit into spaces?
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 17/61
Baseline Schedule ReviewReview Schedule Construction
Sort by Early StartOrganize by Early Start, Order Week Ascending, againsee if the amount of work planned each week isreasonable
Are there trades stacking up?Organize by Early Start, Sort by Late Start
Summarize to Early Start, review overlaps betweenweeksSpecifically review strong overlaps (points out missingrelationships)Helps focus on small segments of project workingconcurrently
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 18/61
Baseline Schedule ReviewReview Schedule Construction
Review resourcesCheck for resource “soft” logic used to control flow ofmanpower from area to areaSchedules without reasonable soft logic will likely show
lots of high Total Float valuesOveruse of soft logic can sequester Total Float andforce Critical PathDurations should be resource-based; that is calculatedby production rate x quantity, so resource planningmust be taken into account
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 19/61
Baseline Schedule ReviewReview Written Narrative
At a minimum, Narrative should identify sequence and work
flowIdentify phasingProvide the Area Designation PlanSummary of the work
Explain plan for constructionIdentify potential problems or risksSummarize the Critical Path; does it match the schedule?Identify all Milestones
Explain schedule components:Activity ID Coding, Activity Coding, Resources, Lags, Constraints,unusual logic relationships
Adverse weather planning
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 20/61
Baseline Schedule ReviewReview Sequencing
Use Narrative as guideCheck for missing Activity Codes that may not include work insequencesChoose layout with sequencing
Compare to specification requirementsSummarize to sequences, then drill into each sequenceCheck reasonableness of logicCheck overlap of sequences
Check other layouts
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 21/61
Baseline Schedule ReviewGenerate Metrics
CountsActivities by type (procurement, construction, Ownerresponsibilities)Activities by trade (Section number, work package)
Activities on Longest PathRelationships
• Total by types• Lags
Constraints
Verify appropriate & consistent level of detail
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 22/61
Baseline Schedule ReviewData retrieval from schedule
Develop data crunching methodologiesMaster layouts with filtersExport filters to export to Excel or Lotus
Standard Pivot tablesInput/output worksheet spreadsheetsGraphical depictions for reasonableness
• Histogram distributions• Tables• Charts
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 23/61
Baseline Schedule ReviewUse Pivot Tables or other datacollecting & collating methodologies
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 24/61
Baseline Schedule ReviewGenerate Statistics
Recommend use of Pivot TablesUse statistics to identify inconsistencies
Ratio work/non-work activities
Ratio trade workRatio durations (helps spot partial overdevelopment)Ratio work in each sequence
Percentage of activities on Longest Path and NearCritical Paths
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 25/61
Baseline Schedule Review
Distribution of Activities
0
50
100
150200
250
300
H a m m
o c k s
a n d M
i l e s t o n
e s
A s p h
a l t P l a c e
m e n t
C l e a r i n g a
n d G r u b
b i n g
D e m o
l i t i o n
D e m o
b i l i z a t i o n
E l e c t r i c a l
E r o s i o n
& S e
d i m e n t
C o n t r o l
G r a d
i n g
L a n d
s c a p i n g
M a t e r
i a l D e
l i v e r y
M o b i l i z a
t i o n
M a i n t e
n a n c e
o f T r a f f i c
S t o r m
D r a i n /
S t o r m
S e w e r
S o u n
d w a l l
S t r i p i n g /
P a i n t i n g
S u b m
i t t a l /
A p p r o
v a l
S i d e w a
l k / M e
d i a n
U n d e
r g r o u n d
U t i l i t i e s
Feature of Work
N o . A
c t i v i t i e s
Histogram of Activity Work Scope (showing out of proportion detail in trade activities)
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 26/61
Baseline Schedule ReviewPerform Analysis
Review types of constraints
Remove constraints, one by oneLook at results with each removal and identify effectsEvaluate total number of constraints
Date constraints; should be minimum and only thosedictated by OwnerDon’t allow mandatory constraints which sequester floatLogic constraints; watch for float removal constraints likeZero Total or Free FloatNetwork should be logic driven, not constraint driven
Constraints can cause multiple Critical PathsRequires analysis of each path in baseline and updates
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 27/61
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 28/61
Baseline Schedule ReviewReview shape of Earned Value S-Curve (BCWS)
Might point out front-end loading or unreasonable planMay show too aggressive expectations for billing
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 29/61
Baseline Schedule ReviewWrite Report
Organize checklist to match reportProvide Executive SummaryProvide recommendations for Best Practicesimprovement in schedule
Provide Deficiency ListRequire response to Deficiency ListDo not dictate means and methodsKeep report professional without addressing assumedmotivation for schedule features
Don’t say, “Use of so many constraints is clearly a deviousattempt to pervert Critical Path”
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 30/61
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 31/61
Update Schedule ReviewUpdate Schedule Review
Same steps as Baseline ReviewReview Scheduling SpecificationReview Plans & SpecificationsConfirm Submittal CompletenessImport Schedule & Verify
Data Validation – must be done with each updateSame steps as Baseline Review
Review Schedule Architecture
Review Schedule ConstructionReview Narrative
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 32/61
Update Schedule ReviewData Validation
Field information – should have been kept on a dailybasis
Verify Actual Start DatesVerify Actual Finish Dates
Verify Predicted Finish for any activity started but notfinishedVerify Percent Complete if schedule is cost loadedPrefer Remaining Duration, not Percent Complete, for time
reporting• Superintendents generally cannot provide accurate
Percent Complete
Data validation is very important
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 33/61
Update Schedule ReviewData Validation
Office informationWatch status of buyout process; purchase orders &subcontracts – what is not bought outVerify Submittal & Approval status
Verify status of administrative tasks• Utility paperwork status• Permits – site, building, right-of-way, Health Department• Environmental releases, etc.
Verify status of materials fabrication and order time - “LeadTime” – this is an area where schedule manipulation canoccur
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 34/61
Update Schedule ReviewData Validation
Owner informationIndependently verify status of Owner controlled activities
• Owner utility applications & progress- Electricity- Gas service- Water & sewer- Telephone- Cable or data- Security system
• Delivery dates for Owner furnished equipment• Other Owner contractual work• Verify coordination with Owner work
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 35/61
Update Schedule ReviewCalculate Schedule
Ensure software setting is Retained LogicVerify Data Date is correct date
Calculate scheduleCheck for Out-of-Sequence Work
Change setting temporarily to Progress Override
If the completion date changes significantly, then thereis a lot of out-of-sequence work needing correctingIf minimal change, no significant out-of-sequence work
Change the setting back to Retained Logic (default)
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 36/61
Update Schedule ReviewPrepare for Schedule Analysis
Use standard Layout with comparison to lastupdateCheck for slippage in Substantial Completion
date or MilestonesIf no slippage, project predicts on time completion
• Perform standard analysis, use standard reports andpublish
If slippage, will need additional analysis of slippedschedule
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 37/61
Update Schedule ReviewStandard Schedule Analysis (On-TimeCompletion)
Three basic components to monitorCritical Path progress
• Slippage will directly delay workNear Critical progress
• Slippage could easily overtake Critical Path and delayworkNon-Critical (“mass volume”) work
• Lack of progress will cause trade stacking and over-
crowding of work space at a later date• Could easily allow too much work for areas available• Good place to use Earned Value for monitoring• Can use Float Dissipation to monitor• Can use other methods to monitor
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 38/61
Update Schedule ReviewStandard Schedule Analysis (On-TimeCompletion)
Two types of paths to watchCritical Path to end of project (Substantial Completion)Critical Path to Interim Milestones
Critical Path to end of projectIdeally use Longest PathMonitor minimum Total Float value Critical Path as well
Critical Paths to Interim MilestonesOne path per each Milestone to watchThis can be time consuming, but necessarySlippage in interim Milestones and achieving final Milestonecan be basis for acceleration claims
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 39/61
Update Schedule ReviewStandard Schedule Analysis (On-TimeCompletion)
Identify current period Critical Path (Longest Path)Identify current period Near-Critical activitiesIdentify Milestones to review
Owner mandated onlyWatch particularly for Milestones with Liquidated Damages
Identify historical trends and statistics (mass volume)Graphics are powerful in the report
Identify resource problems or concernsIdentify risks, either continuing or new
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 40/61
Update Schedule ReviewHistorical Comparisons & Statistics
Run Tipper (TPR) reports
Run Total Float dissipation (Erosion of Float) reportsRun Free Float dissipation reports (monitorsdisruption)
Review Out-of-Sequence work by tradeWhich trade is causing most out-of-sequence work?Are they working out-of-sequence due to other tradefailures to complete?
Or working in open areas without regard for planning?Run Resource reports
Are appropriate resources working?
Check against Tipper reports
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 41/61
U d t S h d l R i
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 42/61
Update Schedule ReviewReview (TPR) Time Performance Ratio trending byMilestone by Responsible Contractor (AD/OD)
U d t S h d l R i
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 43/61
Update Schedule ReviewReview (TPR) Time Performance Ratio per trade(AD/OD)
Time Performance Ratio
0.0
2.04.0
6.0
8.0
10.012.0
A d m i n
S i t e w
o r k
C o n c r
e t e
M a s o
n r y M e
t a l s
C a r p e n
t r y
R o o f
i n g
D o o r s / W i
n d o w s
F i n i s h e s
E q u i p m
e n t
F u r n i s h i n g s
E l e v a t
o r s
M e c h a n i
c a l
E l e c t r i c a l
Type of Work
T P R
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 44/61
Update Schedule ReviewReview (TPR) Time Performance Ratio trending by
trade (AD/OD)
Time Performance Ratio (Concrete)
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
3 0 - S e p - 0 6
3 1 - O c t - 0 6
3 0 - N o v - 0 6
3 1 - D e c - 0 6 3 1 -
J a n - 0 7 2 8 -
F e b - 0 7 T o t a l
Period Ending
T P R
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 45/61
Update Schedule ReviewTrade Monitoring by Crew – no resource loading
available, load single crew resources into activities
AMP Terminals Yard Project
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 46/61
U d t S h d l R i
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 47/61
Update Schedule ReviewEarned Value Management Reporting
• Earned Value and Actual Costs• Compared against Planned Value
Ciudad Juarez Earned Value
$0.00
$10,000,000.00
$20,000,000.00
$30,000,000.00
$40,000,000.00
$50,000,000.00
$60,000,000.00
$70,000,000.00
S e p - 0
5 O c
t - 0 5
N o v - 0
5
D e c - 0
5 J a
n - 0 6
F e b - 0
6 M a
r - 0 6
A p r - 0
6
M a y - 0
6 J u
n - 0 6 J u l - 0
6
A u g - 0 6
S e p - 0
6 O c
t - 0 6
N o v - 0
6
D e c - 0
6 J a
n - 0 7
F e b - 0
7 M a
r - 0 7 A p
r - 0 7
M a y - 0
7 J u
n - 0 7 J u l - 0
7
A u g - 0 7
S e p - 0
7 O c
t - 0 7 N o
v - 0 7
D e c - 0
7 J a
n - 0 8
F e b - 0
8 M a
r - 0 8
Period Ending
B i l l i n g
V a l u e
Early Curve
Late Curve
Actual Curve
Project Update Earned Value
U d S h d l R i
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 48/61
Update Schedule ReviewEarned Value Management Reporting
• SPI and CPI metrics• Watch trending
Schedule Performance Index
0.00
0.20
0.40
0.60
0.80
1.00
1.20
S e p - 0
5 O c
t - 0 5
N o v - 0
5
D e c - 0
5 J a n
- 0 6 F e
b - 0 6
M a r - 0
6 A p
r - 0 6
M a y - 0
6 J u n
- 0 6 J u l - 0 6
A u g - 0 6
S e p - 0
6 O c
t - 0 6
N o v - 0
6
D e c - 0
6 J a n
- 0 7 F e
b - 0 7
Period Ending
S P I ( E V / P V )
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 49/61
Update Schedule ReviewSchedule Analysis – Sequencing Review
Set up a Layout for SequenceGroup by Phase or Location
• Look for out-of-sequence work by tradeSummarize to Phase
Neck for non-work periodsReview the sequence shown by the summary bars
Set up a Layout for ResponsibilityGroup by ResponsibilitySummarize to ResponsibilityNeck for non-work periodsReview trade workload
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 50/61
Update Schedule ReviewSchedule Analysis – Constructability
Set up a Layout for weekly workGroup by Early StartOrder by WeekSort by ES, EF , TF
Zoom in to weekly weekSet Major Vertical Sight Lines to one weekExpose column for Responsibility and LocationReview work to be done weekly over the next few monthsfor reasonableness
Update Schedule Review
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 51/61
Update Schedule ReviewSchedule Analysis (Slipped Completion)
If slippage is due to the Owner, then a time extensionis owed to the ContractorIf slippage is due to the Contractor or hisSubcontractors, then the Contractor owes the Owner aRecovery Schedule
If the Owner causes a delay and the Sub or GC causesa concurrent delay, then a time extension is owed tothe Contractor with no costs; and no recovery schedulerequiredUnderstand excusable/inexcusable andcompensable/non-compensable timeClean up all Owner caused delays each period
U d S h d l R i
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 52/61
Update Schedule Review
Schedule Analysis (Slipped Completion)Identify previous period Critical Path (Longest Path)
Use layout to compare against current scheduleIdentify current Critical Path & changes from previousIdentify which activities slipped and drove progress
Causal Activities drive progressIdentify Start Gain or LossIdentify Production Gain or Loss
Identify specific Causal Activity or Activities for delayDevelop process for dealing with slipped completionbefore needed
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 53/61
Update Schedule Review
Schedule Analysis (Slipped Completion)Quantify start and production changes for each causalactivity by working from the beginning of the period, usinga standard layout with current baseline as schedule targetVerify the totals
Research the issues that caused the changes to thecausal activitiesInterview Owner project admin teamReview project documents; issue files, minutes,RFI/submittal logs, field reports, photographsThis research is usually a discussion about reasonablycurrent problems – quick, painless, and easy
U d S h d l R i
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 54/61
Update Schedule Review
Schedule Analysis (Slipped Completion)Identify the Driving Issues that Affect the Causal ActivitiesAssess Responsibility for Driving IssuesReview Concurrency of Driving Issues– Can Be Delay and/orAcceleration/MitigationWork Through Concurrent Driving Issues from the Beginning ofthe Period, Identifying first driving issue, establishing anyconcurrency with next driving issuePerform a Careful Concurrent Delay Analysis, Record in ClearGraphical FormatAssign Responsibilities for All Driving Concurrent Delays
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 55/61
Update Schedule Review
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 56/61
Update Schedule ReviewReport should include general status summaries:
Update Schedule Review
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 57/61
Update Schedule ReviewInclude Earned Value metrics in report
Update Schedule Review
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 58/61
Update Schedule ReviewCustomized reports – Enterprise - myPrimavera
Update Schedule Review
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 59/61
Update Schedule ReviewReview - Standard Reporting Format
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 60/61
Schedule Review CommentsReview provides claims avoidance opportunitiesReview identifies risksAlways request recovery schedule when Contractor hasslipped completion of any milestoneAlways resolve Owner caused delays to limit exposure toconstructive acceleration delays
Be reasonable, goal is to get a good schedule in placeand update regularlyDo not be confrontational or judgmental in reportWatch trending of work slippageOwner should support report recommendationsProvide a clear Discrepancy List necessary forContractor to correct
8/6/2019 Properly Reviewing a Schedule
http://slidepdf.com/reader/full/properly-reviewing-a-schedule 61/61
Questions?
Properly Reviewing a ScheduleMarch 20, 2008
Chris Carson, PSPProject Controls Manager
Alpha [email protected]