Activity ID Activity Name Original Duration Actual Duration BL1 Start Actual Start BL1 Finish Actual Finish Project Wi Project Wide 218 121 17-Sep-18 17-Sep-1 30-Jul-19 A1000 Project Start 0 0 17-Sep-18 17-Sep A1010 Mobilization 10 4 17-Sep-18 17-Sep 28-Sep-18 21-Sep- A1020 Substantial Completion 0 0 16-May-19 A1030 Install Landscaping 50 0 17-May-19 30-Jul-19 A1040 Punch List 15 0 17-May-19 07-Jun-19 A1045 Demobilization 15 0 17-May-19 07-Jun-19 A1050 Project Finsih 0 0 30-Jul-19 Phase 1 Phase 1 81 121 17-Sep-18 17-Sep 15-Jan-19 Phase 1. Phase 1.A 6 5 17-Sep-18 17-Sep 24-Sep-18 24-Sep- A1060 PH.1A Start 0 0 17-Sep-18 17-Sep A1070 Deploy Traffic Crtl 1 0 17-Sep-18 17-Sep 17-Sep-18 17-Sep- A1080 Traffic Shift 1 0 17-Sep-18 17-Sep 17-Sep-18 17-Sep- A1090 Removals 1 0 18-Sep-18 18-Sep 18-Sep-18 18-Sep- A1100 Uncl Ex / Subgrade 1 0 19-Sep-18 20-Sep 19-Sep-18 20-Sep- A1110 24" ABC Placement 1 0 19-Sep-18 21-Sep 19-Sep-18 21-Sep- A1120 8" ABC Placement (CL.6) 1 0 19-Sep-18 21-Sep 19-Sep-18 21-Sep- A1130 Curb & Gutter Placement 1 0 20-Sep-18 19-Sep 20-Sep-18 19-Sep- A1140 Ramps & Sidewalk Placement 1 0 21-Sep-18 19-Sep 21-Sep-18 19-Sep- A1150 5" HMA Placement 1 0 24-Sep-18 24-Sep 24-Sep-18 24-Sep- A1160 Ph. 1A Finish / Open to Traffic 0 0 24-Sep-18 24-Sep- Phase 1. Phase 1.B 75 115 25-Sep-18 25-Sep 15-Jan-19 A1170 Ph. 1B Start 0 0 25-Sep-18 25-Sep A1180 Deploy Traffic Crtl 1 0 25-Sep-18 25-Sep 25-Sep-18 25-Sep- A1190 Traffic Shift 1 0 25-Sep-18 25-Sep 25-Sep-18 25-Sep- A1200 Removals 10 2 25-Sep-18 26-Sep 08-Oct-18 28-Sep- A1210 Uncl Ex / Subgrade 10 31 27-Sep-18 27-Sep 10-Oct-18 09-Nov- A1220 8" Waterline Relocation (Sta 107+00 & 4 0 02-Oct-18 22-Oct- 05-Oct-18 22-Oct-1 A1230 Install ST 8 26 08-Oct-18 04-Oct- 17-Oct-18 09-Nov- A1240 Install Elec U/G 10 19 31-Oct-18 01-Nov 13-Nov-18 30-Nov- A1250 24" ABC Placement 5 37 11-Oct-18 04-Oct- 17-Oct-18 28-Nov- A1260 8" & 11" ABC Placement (CL.6) 5 36 22-Oct-18 05-Oct- 26-Oct-18 28-Nov- A1270 Strucutre Ex 12 22 11-Oct-18 01-Oct- 26-Oct-18 31-Oct-1 A1280 Install Retaining Wall 25 15 16-Nov-18 01-Nov 26-Dec-18 26-Nov- A1285 Structural Backfill 5 3 27-Dec-18 26-Nov 04-Jan-19 29-Nov- A1290 Curb & Gutter & Bike Lane Placement 6 31 29-Oct-18 18-Oct- 05-Nov-18 04-Dec- A1295 Parking Lane Placement 3 0 06-Nov-18 18-Oct- 08-Nov-18 18-Oct-1 A1300 Ramp & Sidewalk Placement 6 42 28-Nov-18 02-Nov 05-Dec-18 09-Jan- A1320 5" & 5.5" HMA Placement 3 1 18-Dec-18 17-Dec 20-Dec-18 18-Dec- A1330 Sign Placement 3 1 21-Dec-18 17-Dec 27-Dec-18 18-Dec- A1335 Install Elec A/G 9 1 21-Dec-18 10-Jan- 08-Jan-19 11-Jan-1 A1340 Final Striping Placement 5 1 09-Jan-19 18-Dec 15-Jan-19 19-Dec- S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 D ec 23 Project Start Mobilization 24-Sep-18 A, Phase 1.A PH.1A Start Deploy Traffic Crtl Traffic Shift Removals Uncl Ex / Subgrade 24" ABC Placement 8" ABC Placement (CL.6) Curb & Gutter Placement Ramps & Sidewalk Placement 5" HMA Placement Ph. 1A Finish / Open to Traffic Ph. 1B Start Deploy Traffic Crtl Traffic Shift Removals Uncl Ex / Subgrade 8" Waterline Relocation (Sta 107+00 & 113+50) Install ST Install Elec U/G 24" ABC Placement 8" & 11" ABC Placement (CL.6) Strucutre Ex Install Retaining Wall Structural Backfill Curb & Gutter & Bike Lan Parking Lane Placement 5" & 5.5" Sign Pla Final St City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11 Actual Work Remaining Work Critical Remaining W... Milestone Page 1 of 6 TASK filter: All Activities © Oracle Corporation

Upload: others

Post on 26-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Wide - City of Golden, Colorado · S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 DDec 23 Project Start Mobilization 24-Sep-18 A, Phase 1.A PH.1A Start

Activity ID Activity Name OriginalDuration

ActualDuration

BL1 Start Actual Start

BL1 Finish Actual Finish

Project WideProject Wide 218 121 17-Sep-18 17-Sep-1830-Jul-19

A1000 Project Start 0 0 17-Sep-18 17-Sep-18

A1010 Mobilization 10 4 17-Sep-18 17-Sep-1828-Sep-18 21-Sep-18

A1020 Substantial Completion 0 0 16-May-19

A1030 Install Landscaping 50 0 17-May-19 30-Jul-19

A1040 Punch List 15 0 17-May-19 07-Jun-19

A1045 Demobilization 15 0 17-May-19 07-Jun-19

A1050 Project Finsih 0 0 30-Jul-19

Phase 1Phase 1 81 121 17-Sep-18 17-Sep-1815-Jan-19

Phase 1.APhase 1.A 6 5 17-Sep-18 17-Sep-1824-Sep-18 24-Sep-18

A1060 PH.1A Start 0 0 17-Sep-18 17-Sep-18

A1070 Deploy Traffic Crtl 1 0 17-Sep-18 17-Sep-1817-Sep-18 17-Sep-18

A1080 Traffic Shift 1 0 17-Sep-18 17-Sep-1817-Sep-18 17-Sep-18

A1090 Removals 1 0 18-Sep-18 18-Sep-1818-Sep-18 18-Sep-18

A1100 Uncl Ex / Subgrade 1 0 19-Sep-18 20-Sep-1819-Sep-18 20-Sep-18

A1110 24" ABC Placement 1 0 19-Sep-18 21-Sep-1819-Sep-18 21-Sep-18

A1120 8" ABC Placement (CL.6) 1 0 19-Sep-18 21-Sep-1819-Sep-18 21-Sep-18

A1130 Curb & Gutter Placement 1 0 20-Sep-18 19-Sep-1820-Sep-18 19-Sep-18

A1140 Ramps & Sidewalk Placement 1 0 21-Sep-18 19-Sep-1821-Sep-18 19-Sep-18

A1150 5" HMA Placement 1 0 24-Sep-18 24-Sep-1824-Sep-18 24-Sep-18

A1160 Ph. 1A Finish / Open to Traffic 0 0 24-Sep-18 24-Sep-18

Phase 1.BPhase 1.B 75 115 25-Sep-18 25-Sep-1815-Jan-19

A1170 Ph. 1B Start 0 0 25-Sep-18 25-Sep-18

A1180 Deploy Traffic Crtl 1 0 25-Sep-18 25-Sep-1825-Sep-18 25-Sep-18

A1190 Traffic Shift 1 0 25-Sep-18 25-Sep-1825-Sep-18 25-Sep-18

A1200 Removals 10 2 25-Sep-18 26-Sep-1808-Oct-18 28-Sep-18

A1210 Uncl Ex / Subgrade 10 31 27-Sep-18 27-Sep-1810-Oct-18 09-Nov-18

A1220 8" Waterline Relocation (Sta 107+00 & 113+50) 4 0 02-Oct-18 22-Oct-18 05-Oct-18 22-Oct-18

A1230 Install ST 8 26 08-Oct-18 04-Oct-18 17-Oct-18 09-Nov-18

A1240 Install Elec U/G 10 19 31-Oct-18 01-Nov-1813-Nov-18 30-Nov-18

A1250 24" ABC Placement 5 37 11-Oct-18 04-Oct-18 17-Oct-18 28-Nov-18

A1260 8" & 11" ABC Placement (CL.6) 5 36 22-Oct-18 05-Oct-18 26-Oct-18 28-Nov-18

A1270 Strucutre Ex 12 22 11-Oct-18 01-Oct-18 26-Oct-18 31-Oct-18

A1280 Install Retaining Wall 25 15 16-Nov-18 01-Nov-1826-Dec-18 26-Nov-18

A1285 Structural Backfill 5 3 27-Dec-18 26-Nov-1804-Jan-19 29-Nov-18

A1290 Curb & Gutter & Bike Lane Placement 6 31 29-Oct-18 18-Oct-18 05-Nov-18 04-Dec-18

A1295 Parking Lane Placement 3 0 06-Nov-18 18-Oct-18 08-Nov-18 18-Oct-18

A1300 Ramp & Sidewalk Placement 6 42 28-Nov-18 02-Nov-1805-Dec-18 09-Jan-19

A1320 5" & 5.5" HMA Placement 3 1 18-Dec-18 17-Dec-1820-Dec-18 18-Dec-18

A1330 Sign Placement 3 1 21-Dec-18 17-Dec-1827-Dec-18 18-Dec-18

A1335 Install Elec A/G 9 1 21-Dec-18 10-Jan-19 08-Jan-19 11-Jan-19

A1340 Final Striping Placement 5 1 09-Jan-19 18-Dec-1815-Jan-19 19-Dec-18

S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 D Dec 23

Project Start

Mobilization

24-Sep-18 A, Phase 1.A

PH.1A Start

Deploy Traffic Crtl

Traffic Shift

Removals

Uncl Ex / Subgrade

24" ABC Placement

8" ABC Placement (CL.6)

Curb & Gutter Placement

Ramps & Sidewalk Placement

5" HMA Placement

Ph. 1A Finish / Open to Traffic

Ph. 1B Start

Deploy Traffic Crtl

Traffic Shift

Removals

Uncl Ex / Subgrade

8" Waterline Relocation (Sta 107+00 & 113+50)

Install ST

Install Elec U/G

24" ABC Placement

8" & 11" ABC Placement (CL.6)

Strucutre Ex

Install Retaining Wall

Structural Backfill

Curb & Gutter & Bike Lane Placement

Parking Lane Placement

5" & 5.5" HMA Placement

Sign Placement

Final Striping Placement

City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 1 of 6 TASK filter: All Activities

© Oracle Corporation

Page 2: Project Wide - City of Golden, Colorado · S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 DDec 23 Project Start Mobilization 24-Sep-18 A, Phase 1.A PH.1A Start

Dec 23 D Jan 06 Jan 13 Jan 20 Jan 27 Feb 03 Feb 10 Feb 17 Feb 24 Mar 03 Mar 10 Mar 17 Mar 24 Mar 31 Apr 07 Apr 14 Apr 21 Apr 28 M M M M Jun 02 Jun 09 Jun 16 Jun 23 Jun 30 Jul 07 Jul 14 Jul 21 Jul 28

30-Jul-19, Project Wide

Substantial Completion

Install Landscaping

Punch List

Demobilization

Project Finsih

03-Apr-19, Phase 1

03-Apr-19, Phase 1.B

Curb & Gutter & Bike Lane Placement

Ramp & Sidewalk Placement

5" & 5.5" HMA Placement

Sign Placement

Install Elec A/G

Final Striping Placement

City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 2 of 6 TASK filter: All Activities

© Oracle Corporation

Page 3: Project Wide - City of Golden, Colorado · S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 DDec 23 Project Start Mobilization 24-Sep-18 A, Phase 1.A PH.1A Start

Activity ID Activity Name OriginalDuration

ActualDuration

BL1 Start Actual Start

BL1 Finish Actual Finish

A1345 Install Irrigation 16 84 18-Dec-18 07-Nov-1814-Jan-19

A1350 Ph. 1B Finish / Open to Traffic 0 0 15-Jan-19 20-Dec-18

Phase 2Phase 2 94 95 29-Oct-18 22-Oct-18 15-Mar-19

A1360 Phase 2 Start 0 0 29-Oct-18 22-Oct-18

A1370 Deploy Traffic Crtl 1 0 29-Oct-18 22-Oct-18 29-Oct-18 22-Oct-18

A1380 Traffic Shift 1 0 29-Oct-18 22-Oct-18 29-Oct-18 22-Oct-18

A1390 Removals 5 0 29-Oct-18 22-Oct-18 02-Nov-18 22-Oct-18

A1400 Uncl Ex / Subgrade 5 9 05-Nov-18 26-Nov-1809-Nov-18 07-Dec-18

A1410 Install SS 3 4 05-Nov-18 29-Oct-18 07-Nov-18 02-Nov-18

A1420 Install ST 3 4 31-Oct-18 05-Nov-1802-Nov-18 09-Nov-18

A1430 6" FH Install, FH & WM Resets 2 2 30-Nov-18 05-Dec-1803-Dec-18 07-Dec-18

A1440 Install Elec U/G 5 4 07-Dec-18 03-Dec-1813-Dec-18 07-Dec-18

A1450 11" ABC (CL.6) Placement 5 12 07-Dec-18 05-Dec-1813-Dec-18 21-Dec-18

A1460 Curb & Gutter & Bike lane Placement 3 4 14-Dec-18 10-Dec-1818-Dec-18 14-Dec-18

A1470 Driveway Placement 5 2 19-Dec-18 12-Dec-1827-Dec-18 14-Dec-18

A1480 Ramp & Sidewalk Placement 5 4 28-Dec-18 10-Dec-1807-Jan-19 14-Dec-18

A1490 5.5" HMA Placement 2 0 08-Jan-19 19-Dec-1809-Jan-19 19-Dec-18

A1500 Reset Landscape Walls 3 0 10-Jan-19 12-Mar-19 14-Jan-19 12-Mar-19

A1510 Install Fence 3 0 13-Mar-19 15-Mar-19

A1520 Install Irrigation 1 0 13-Mar-19 13-Mar-19

A1530 Install Elec A/G 3 0 13-Mar-19 15-Mar-19

A1540 Sign Placement 1 2 10-Jan-19 17-Dec-1810-Jan-19 19-Dec-18

A1545 Final Striping Placement 3 1 10-Jan-19 20-Dec-1814-Jan-19 21-Dec-18

A1550 Phase 2 Finish / Open to Traffic 0 0 14-Jan-19 22-Dec-18

Phase 3Phase 3 66 53 22-Jan-19 22-Dec-1823-Apr-19

Phase 3.APhase 3.A 51 53 22-Jan-19 22-Dec-1802-Apr-19

A1555 Weather Days 5 22 18-Mar-19 11-Feb-19 22-Mar-19 13-Mar-19

A1557 Winter Break 6 6 22-Jan-19 22-Dec-1829-Jan-19 06-Jan-19

A1560 Phase 3.A Start 0 0 30-Jan-19 07-Jan-19

A1570 Deploy Traffic Ctrl 1 0 30-Jan-19 07-Jan-19 30-Jan-19 07-Jan-19

A1580 Traffic Shift 1 0 30-Jan-19 07-Jan-19 30-Jan-19 07-Jan-19

A1590 Removals 5 5 30-Jan-19 07-Jan-19 05-Feb-19 12-Jan-19

A1600 Uncl Ex / Subgrade 5 4 06-Feb-19 16-Jan-19 12-Feb-19 22-Jan-19

A1610 Install SS 7 3 07-Feb-19 09-Jan-19 15-Feb-19 12-Jan-19

A1620 Install ST 2 2 18-Feb-19 07-Jan-19 19-Feb-19 09-Jan-19

A1630 Reset FH & WM 3 2 20-Feb-19 15-Jan-19 22-Feb-19 17-Jan-19

A1640 Install Elec U/G 10 2 13-Feb-19 11-Mar-19 26-Feb-19

A1650 11" ABC (CL.6) Placement 5 38 13-Feb-19 16-Jan-19 19-Feb-19 11-Mar-19

A1660 Curb & Gutter & Bike Lane Placement 5 3 20-Feb-19 21-Jan-19 26-Feb-19 24-Jan-19

A1670 Parking Lane / Driveway Placement 5 9 27-Feb-19 21-Jan-19 05-Mar-19 01-Feb-19

A1680 Ramp & Sidewalk Placement 6 23 06-Mar-19 07-Feb-19 13-Mar-19 12-Mar-19

A1690 5.5" HMA Placement 2 0 13-Mar-19 14-Mar-19

S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 D Dec 23

Ph. 1B Finish / Open to Traffic

Phase 2 Start

Deploy Traffic Crtl

Traffic Shift

Removals

Uncl Ex / Subgrade

Install SS

Install ST

6" FH Install, FH & WM Resets

Install Elec U/G

11" ABC (CL.6) Placement

Curb & Gutter & Bike lane Placement

Driveway Placement

Ramp & Sidewalk Placement

5.5" HMA Placement

Sign Placement

Final Striping Placement

Phase 2 Finish / Open to Traffic

City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 3 of 6 TASK filter: All Activities

© Oracle Corporation

Page 4: Project Wide - City of Golden, Colorado · S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 DDec 23 Project Start Mobilization 24-Sep-18 A, Phase 1.A PH.1A Start

Dec 23 D Jan 06 Jan 13 Jan 20 Jan 27 Feb 03 Feb 10 Feb 17 Feb 24 Mar 03 Mar 10 Mar 17 Mar 24 Mar 31 Apr 07 Apr 14 Apr 21 Apr 28 M M M M Jun 02 Jun 09 Jun 16 Jun 23 Jun 30 Jul 07 Jul 14 Jul 21 Jul 28

Install Irrigation

Ph. 1B Finish / Open to Traffic

15-Mar-19, Phase 2

6" FH Install, FH & WM Resets

11" ABC (CL.6) Placement

Curb & Gutter & Bike lane Placement

Driveway Placement

Ramp & Sidewalk Placement

5.5" HMA Placement

Reset Landscape Walls

Install Fence

Install Irrigation

Install Elec A/G

Sign Placement

Final Striping Placement

Phase 2 Finish / Open to Traffic

23-Apr-19, Phase 3

02-Apr-19, Phase 3.A

Weather Days

Winter Break

Phase 3.A Start

Deploy Traffic Ctrl

Traffic Shift

Removals

Uncl Ex / Subgrade

Install SS

Install ST

Reset FH & WM

Install Elec U/G

11" ABC (CL.6) Placement

Curb & Gutter & Bike Lane Placement

Parking Lane / Driveway Placement

Ramp & Sidewalk Placement

5.5" HMA Placement

City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 4 of 6 TASK filter: All Activities

© Oracle Corporation

Page 5: Project Wide - City of Golden, Colorado · S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 DDec 23 Project Start Mobilization 24-Sep-18 A, Phase 1.A PH.1A Start

Activity ID Activity Name OriginalDuration

ActualDuration

BL1 Start Actual Start

BL1 Finish Actual Finish

A1730 Install Elec A/G 5 0 27-Mar-19 02-Apr-19

A1740 Phase 3.A Finish / Open to Traffic 0 0 14-Mar-19

Phase 3.BPhase 3.B 28 0 15-Mar-19 23-Apr-19

A1750 Phase 3.B Start 0 0 15-Mar-19

A1760 Deploy Traffic Crtl 1 0 15-Mar-19 15-Mar-19

A1770 Traffic Shift 1 0 15-Mar-19 15-Mar-19

A1780 Removals 5 0 15-Mar-19 21-Mar-19

A1790 Uncl Ex / Subgrade 5 0 22-Mar-19 28-Mar-19

A1800 Install SS 3 0 22-Mar-19 26-Mar-19

A1810 Install ST 4 0 25-Mar-19 28-Mar-19

A1820 Install Elec U/G 6 0 29-Mar-19 05-Apr-19

A1830 11" ABC (CL.6) Placement 5 0 25-Mar-19 29-Mar-19

A1840 Curb & Gutter & Bike Lane Placement 5 0 01-Apr-19 05-Apr-19

A1850 Parking Lane / Driveway Placement 5 0 04-Apr-19 10-Apr-19

A1860 Ramp & Sidewalk Placement 6 0 10-Apr-19 17-Apr-19

A1870 5.5" HMA Placement 2 0 18-Apr-19 19-Apr-19

A1880 Install Elec A/G 2 0 08-Apr-19 09-Apr-19

A1890 Sign Placement 2 0 22-Apr-19 23-Apr-19

A1900 Final Striping Placement 2 0 22-Apr-19 23-Apr-19

A1910 Phase 3.B Finish / Open to Traffic 0 0 23-Apr-19

Phase 4Phase 4 17 0 24-Apr-19 16-May-19

A1920 Phase 4 Start 0 0 24-Apr-19

A1930 Deploy Traffic Ctrl 1 0 24-Apr-19 24-Apr-19

A1940 Removals / Uncl Ex / Subgrade 4 0 24-Apr-19 29-Apr-19

A1950 ABC Placement 2 0 30-Apr-19 01-May-19

A1960 Curb & Gutter & Pan Placement 2 0 02-May-19 03-May-19

A1970 Ramp & Sidewalk Placement 2 0 06-May-19 07-May-19

A1980 Install Guardrail 5 0 08-May-19 14-May-19

A1990 Sign Placement 5 0 08-May-19 14-May-19

A2000 Final Striping Placement 2 0 15-May-19 16-May-19

A2010 Phase 4 Finish 0 0 16-May-19

S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 D Dec 23

City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11

Actual Work

Remaining Work

Critical Remaining W...

Milestone

Page 5 of 6 TASK filter: All Activities

© Oracle Corporation

Page 6: Project Wide - City of Golden, Colorado · S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 DDec 23 Project Start Mobilization 24-Sep-18 A, Phase 1.A PH.1A Start

Dec 23 D Jan 06 Jan 13 Jan 20 Jan 27 Feb 03 Feb 10 Feb 17 Feb 24 Mar 03 Mar 10 Mar 17 Mar 24 Mar 31 Apr 07 Apr 14 Apr 21 Apr 28 M M M M Jun 02 Jun 09 Jun 16 Jun 23 Jun 30 Jul 07 Jul 14 Jul 21 Jul 28

Install Elec A/G

Phase 3.A Finish / Open to Traffic

23-Apr-19, Phase 3.B

Phase 3.B Start

Deploy Traffic Crtl

Traffic Shift

Removals

Uncl Ex / Subgrade

Install SS

Install ST

Install Elec U/G

11" ABC (CL.6) Placement

Curb & Gutter & Bike Lane Placement

Parking Lane / Driveway Placement

Ramp & Sidewalk Placement

5.5" HMA Placement

Install Elec A/G

Sign Placement

Final Striping Placement

Phase 3.B Finish / Open to Traffic

16-May-19, Phase 4

Phase 4 Start

Deploy Traffic Ctrl

Removals / Uncl Ex / Subgrade

ABC Placement

Curb & Gutter & Pan Placement

Ramp & Sidewalk Placement

Install Guardrail

Sign Placement

Final Striping Placement

Phase 4 Finish

City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11

Actual Work

Remaining Work

Critical Remaining W...

Milestone