project wide - city of golden, colorado · s sep 23 s oct 07 oct 14 oct 21 oct 28 nov 04 n nov 18 n...
TRANSCRIPT
Activity ID Activity Name OriginalDuration
ActualDuration
BL1 Start Actual Start
BL1 Finish Actual Finish
Project WideProject Wide 218 121 17-Sep-18 17-Sep-1830-Jul-19
A1000 Project Start 0 0 17-Sep-18 17-Sep-18
A1010 Mobilization 10 4 17-Sep-18 17-Sep-1828-Sep-18 21-Sep-18
A1020 Substantial Completion 0 0 16-May-19
A1030 Install Landscaping 50 0 17-May-19 30-Jul-19
A1040 Punch List 15 0 17-May-19 07-Jun-19
A1045 Demobilization 15 0 17-May-19 07-Jun-19
A1050 Project Finsih 0 0 30-Jul-19
Phase 1Phase 1 81 121 17-Sep-18 17-Sep-1815-Jan-19
Phase 1.APhase 1.A 6 5 17-Sep-18 17-Sep-1824-Sep-18 24-Sep-18
A1060 PH.1A Start 0 0 17-Sep-18 17-Sep-18
A1070 Deploy Traffic Crtl 1 0 17-Sep-18 17-Sep-1817-Sep-18 17-Sep-18
A1080 Traffic Shift 1 0 17-Sep-18 17-Sep-1817-Sep-18 17-Sep-18
A1090 Removals 1 0 18-Sep-18 18-Sep-1818-Sep-18 18-Sep-18
A1100 Uncl Ex / Subgrade 1 0 19-Sep-18 20-Sep-1819-Sep-18 20-Sep-18
A1110 24" ABC Placement 1 0 19-Sep-18 21-Sep-1819-Sep-18 21-Sep-18
A1120 8" ABC Placement (CL.6) 1 0 19-Sep-18 21-Sep-1819-Sep-18 21-Sep-18
A1130 Curb & Gutter Placement 1 0 20-Sep-18 19-Sep-1820-Sep-18 19-Sep-18
A1140 Ramps & Sidewalk Placement 1 0 21-Sep-18 19-Sep-1821-Sep-18 19-Sep-18
A1150 5" HMA Placement 1 0 24-Sep-18 24-Sep-1824-Sep-18 24-Sep-18
A1160 Ph. 1A Finish / Open to Traffic 0 0 24-Sep-18 24-Sep-18
Phase 1.BPhase 1.B 75 115 25-Sep-18 25-Sep-1815-Jan-19
A1170 Ph. 1B Start 0 0 25-Sep-18 25-Sep-18
A1180 Deploy Traffic Crtl 1 0 25-Sep-18 25-Sep-1825-Sep-18 25-Sep-18
A1190 Traffic Shift 1 0 25-Sep-18 25-Sep-1825-Sep-18 25-Sep-18
A1200 Removals 10 2 25-Sep-18 26-Sep-1808-Oct-18 28-Sep-18
A1210 Uncl Ex / Subgrade 10 31 27-Sep-18 27-Sep-1810-Oct-18 09-Nov-18
A1220 8" Waterline Relocation (Sta 107+00 & 113+50) 4 0 02-Oct-18 22-Oct-18 05-Oct-18 22-Oct-18
A1230 Install ST 8 26 08-Oct-18 04-Oct-18 17-Oct-18 09-Nov-18
A1240 Install Elec U/G 10 19 31-Oct-18 01-Nov-1813-Nov-18 30-Nov-18
A1250 24" ABC Placement 5 37 11-Oct-18 04-Oct-18 17-Oct-18 28-Nov-18
A1260 8" & 11" ABC Placement (CL.6) 5 36 22-Oct-18 05-Oct-18 26-Oct-18 28-Nov-18
A1270 Strucutre Ex 12 22 11-Oct-18 01-Oct-18 26-Oct-18 31-Oct-18
A1280 Install Retaining Wall 25 15 16-Nov-18 01-Nov-1826-Dec-18 26-Nov-18
A1285 Structural Backfill 5 3 27-Dec-18 26-Nov-1804-Jan-19 29-Nov-18
A1290 Curb & Gutter & Bike Lane Placement 6 31 29-Oct-18 18-Oct-18 05-Nov-18 04-Dec-18
A1295 Parking Lane Placement 3 0 06-Nov-18 18-Oct-18 08-Nov-18 18-Oct-18
A1300 Ramp & Sidewalk Placement 6 42 28-Nov-18 02-Nov-1805-Dec-18 09-Jan-19
A1320 5" & 5.5" HMA Placement 3 1 18-Dec-18 17-Dec-1820-Dec-18 18-Dec-18
A1330 Sign Placement 3 1 21-Dec-18 17-Dec-1827-Dec-18 18-Dec-18
A1335 Install Elec A/G 9 1 21-Dec-18 10-Jan-19 08-Jan-19 11-Jan-19
A1340 Final Striping Placement 5 1 09-Jan-19 18-Dec-1815-Jan-19 19-Dec-18
S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 D Dec 23
Project Start
Mobilization
24-Sep-18 A, Phase 1.A
PH.1A Start
Deploy Traffic Crtl
Traffic Shift
Removals
Uncl Ex / Subgrade
24" ABC Placement
8" ABC Placement (CL.6)
Curb & Gutter Placement
Ramps & Sidewalk Placement
5" HMA Placement
Ph. 1A Finish / Open to Traffic
Ph. 1B Start
Deploy Traffic Crtl
Traffic Shift
Removals
Uncl Ex / Subgrade
8" Waterline Relocation (Sta 107+00 & 113+50)
Install ST
Install Elec U/G
24" ABC Placement
8" & 11" ABC Placement (CL.6)
Strucutre Ex
Install Retaining Wall
Structural Backfill
Curb & Gutter & Bike Lane Placement
Parking Lane Placement
5" & 5.5" HMA Placement
Sign Placement
Final Striping Placement
City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 1 of 6 TASK filter: All Activities
© Oracle Corporation
Dec 23 D Jan 06 Jan 13 Jan 20 Jan 27 Feb 03 Feb 10 Feb 17 Feb 24 Mar 03 Mar 10 Mar 17 Mar 24 Mar 31 Apr 07 Apr 14 Apr 21 Apr 28 M M M M Jun 02 Jun 09 Jun 16 Jun 23 Jun 30 Jul 07 Jul 14 Jul 21 Jul 28
30-Jul-19, Project Wide
Substantial Completion
Install Landscaping
Punch List
Demobilization
Project Finsih
03-Apr-19, Phase 1
03-Apr-19, Phase 1.B
Curb & Gutter & Bike Lane Placement
Ramp & Sidewalk Placement
5" & 5.5" HMA Placement
Sign Placement
Install Elec A/G
Final Striping Placement
City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 2 of 6 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
ActualDuration
BL1 Start Actual Start
BL1 Finish Actual Finish
A1345 Install Irrigation 16 84 18-Dec-18 07-Nov-1814-Jan-19
A1350 Ph. 1B Finish / Open to Traffic 0 0 15-Jan-19 20-Dec-18
Phase 2Phase 2 94 95 29-Oct-18 22-Oct-18 15-Mar-19
A1360 Phase 2 Start 0 0 29-Oct-18 22-Oct-18
A1370 Deploy Traffic Crtl 1 0 29-Oct-18 22-Oct-18 29-Oct-18 22-Oct-18
A1380 Traffic Shift 1 0 29-Oct-18 22-Oct-18 29-Oct-18 22-Oct-18
A1390 Removals 5 0 29-Oct-18 22-Oct-18 02-Nov-18 22-Oct-18
A1400 Uncl Ex / Subgrade 5 9 05-Nov-18 26-Nov-1809-Nov-18 07-Dec-18
A1410 Install SS 3 4 05-Nov-18 29-Oct-18 07-Nov-18 02-Nov-18
A1420 Install ST 3 4 31-Oct-18 05-Nov-1802-Nov-18 09-Nov-18
A1430 6" FH Install, FH & WM Resets 2 2 30-Nov-18 05-Dec-1803-Dec-18 07-Dec-18
A1440 Install Elec U/G 5 4 07-Dec-18 03-Dec-1813-Dec-18 07-Dec-18
A1450 11" ABC (CL.6) Placement 5 12 07-Dec-18 05-Dec-1813-Dec-18 21-Dec-18
A1460 Curb & Gutter & Bike lane Placement 3 4 14-Dec-18 10-Dec-1818-Dec-18 14-Dec-18
A1470 Driveway Placement 5 2 19-Dec-18 12-Dec-1827-Dec-18 14-Dec-18
A1480 Ramp & Sidewalk Placement 5 4 28-Dec-18 10-Dec-1807-Jan-19 14-Dec-18
A1490 5.5" HMA Placement 2 0 08-Jan-19 19-Dec-1809-Jan-19 19-Dec-18
A1500 Reset Landscape Walls 3 0 10-Jan-19 12-Mar-19 14-Jan-19 12-Mar-19
A1510 Install Fence 3 0 13-Mar-19 15-Mar-19
A1520 Install Irrigation 1 0 13-Mar-19 13-Mar-19
A1530 Install Elec A/G 3 0 13-Mar-19 15-Mar-19
A1540 Sign Placement 1 2 10-Jan-19 17-Dec-1810-Jan-19 19-Dec-18
A1545 Final Striping Placement 3 1 10-Jan-19 20-Dec-1814-Jan-19 21-Dec-18
A1550 Phase 2 Finish / Open to Traffic 0 0 14-Jan-19 22-Dec-18
Phase 3Phase 3 66 53 22-Jan-19 22-Dec-1823-Apr-19
Phase 3.APhase 3.A 51 53 22-Jan-19 22-Dec-1802-Apr-19
A1555 Weather Days 5 22 18-Mar-19 11-Feb-19 22-Mar-19 13-Mar-19
A1557 Winter Break 6 6 22-Jan-19 22-Dec-1829-Jan-19 06-Jan-19
A1560 Phase 3.A Start 0 0 30-Jan-19 07-Jan-19
A1570 Deploy Traffic Ctrl 1 0 30-Jan-19 07-Jan-19 30-Jan-19 07-Jan-19
A1580 Traffic Shift 1 0 30-Jan-19 07-Jan-19 30-Jan-19 07-Jan-19
A1590 Removals 5 5 30-Jan-19 07-Jan-19 05-Feb-19 12-Jan-19
A1600 Uncl Ex / Subgrade 5 4 06-Feb-19 16-Jan-19 12-Feb-19 22-Jan-19
A1610 Install SS 7 3 07-Feb-19 09-Jan-19 15-Feb-19 12-Jan-19
A1620 Install ST 2 2 18-Feb-19 07-Jan-19 19-Feb-19 09-Jan-19
A1630 Reset FH & WM 3 2 20-Feb-19 15-Jan-19 22-Feb-19 17-Jan-19
A1640 Install Elec U/G 10 2 13-Feb-19 11-Mar-19 26-Feb-19
A1650 11" ABC (CL.6) Placement 5 38 13-Feb-19 16-Jan-19 19-Feb-19 11-Mar-19
A1660 Curb & Gutter & Bike Lane Placement 5 3 20-Feb-19 21-Jan-19 26-Feb-19 24-Jan-19
A1670 Parking Lane / Driveway Placement 5 9 27-Feb-19 21-Jan-19 05-Mar-19 01-Feb-19
A1680 Ramp & Sidewalk Placement 6 23 06-Mar-19 07-Feb-19 13-Mar-19 12-Mar-19
A1690 5.5" HMA Placement 2 0 13-Mar-19 14-Mar-19
S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 D Dec 23
Ph. 1B Finish / Open to Traffic
Phase 2 Start
Deploy Traffic Crtl
Traffic Shift
Removals
Uncl Ex / Subgrade
Install SS
Install ST
6" FH Install, FH & WM Resets
Install Elec U/G
11" ABC (CL.6) Placement
Curb & Gutter & Bike lane Placement
Driveway Placement
Ramp & Sidewalk Placement
5.5" HMA Placement
Sign Placement
Final Striping Placement
Phase 2 Finish / Open to Traffic
City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 3 of 6 TASK filter: All Activities
© Oracle Corporation
Dec 23 D Jan 06 Jan 13 Jan 20 Jan 27 Feb 03 Feb 10 Feb 17 Feb 24 Mar 03 Mar 10 Mar 17 Mar 24 Mar 31 Apr 07 Apr 14 Apr 21 Apr 28 M M M M Jun 02 Jun 09 Jun 16 Jun 23 Jun 30 Jul 07 Jul 14 Jul 21 Jul 28
Install Irrigation
Ph. 1B Finish / Open to Traffic
15-Mar-19, Phase 2
6" FH Install, FH & WM Resets
11" ABC (CL.6) Placement
Curb & Gutter & Bike lane Placement
Driveway Placement
Ramp & Sidewalk Placement
5.5" HMA Placement
Reset Landscape Walls
Install Fence
Install Irrigation
Install Elec A/G
Sign Placement
Final Striping Placement
Phase 2 Finish / Open to Traffic
23-Apr-19, Phase 3
02-Apr-19, Phase 3.A
Weather Days
Winter Break
Phase 3.A Start
Deploy Traffic Ctrl
Traffic Shift
Removals
Uncl Ex / Subgrade
Install SS
Install ST
Reset FH & WM
Install Elec U/G
11" ABC (CL.6) Placement
Curb & Gutter & Bike Lane Placement
Parking Lane / Driveway Placement
Ramp & Sidewalk Placement
5.5" HMA Placement
City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 4 of 6 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
ActualDuration
BL1 Start Actual Start
BL1 Finish Actual Finish
A1730 Install Elec A/G 5 0 27-Mar-19 02-Apr-19
A1740 Phase 3.A Finish / Open to Traffic 0 0 14-Mar-19
Phase 3.BPhase 3.B 28 0 15-Mar-19 23-Apr-19
A1750 Phase 3.B Start 0 0 15-Mar-19
A1760 Deploy Traffic Crtl 1 0 15-Mar-19 15-Mar-19
A1770 Traffic Shift 1 0 15-Mar-19 15-Mar-19
A1780 Removals 5 0 15-Mar-19 21-Mar-19
A1790 Uncl Ex / Subgrade 5 0 22-Mar-19 28-Mar-19
A1800 Install SS 3 0 22-Mar-19 26-Mar-19
A1810 Install ST 4 0 25-Mar-19 28-Mar-19
A1820 Install Elec U/G 6 0 29-Mar-19 05-Apr-19
A1830 11" ABC (CL.6) Placement 5 0 25-Mar-19 29-Mar-19
A1840 Curb & Gutter & Bike Lane Placement 5 0 01-Apr-19 05-Apr-19
A1850 Parking Lane / Driveway Placement 5 0 04-Apr-19 10-Apr-19
A1860 Ramp & Sidewalk Placement 6 0 10-Apr-19 17-Apr-19
A1870 5.5" HMA Placement 2 0 18-Apr-19 19-Apr-19
A1880 Install Elec A/G 2 0 08-Apr-19 09-Apr-19
A1890 Sign Placement 2 0 22-Apr-19 23-Apr-19
A1900 Final Striping Placement 2 0 22-Apr-19 23-Apr-19
A1910 Phase 3.B Finish / Open to Traffic 0 0 23-Apr-19
Phase 4Phase 4 17 0 24-Apr-19 16-May-19
A1920 Phase 4 Start 0 0 24-Apr-19
A1930 Deploy Traffic Ctrl 1 0 24-Apr-19 24-Apr-19
A1940 Removals / Uncl Ex / Subgrade 4 0 24-Apr-19 29-Apr-19
A1950 ABC Placement 2 0 30-Apr-19 01-May-19
A1960 Curb & Gutter & Pan Placement 2 0 02-May-19 03-May-19
A1970 Ramp & Sidewalk Placement 2 0 06-May-19 07-May-19
A1980 Install Guardrail 5 0 08-May-19 14-May-19
A1990 Sign Placement 5 0 08-May-19 14-May-19
A2000 Final Striping Placement 2 0 15-May-19 16-May-19
A2010 Phase 4 Finish 0 0 16-May-19
S Sep 23 S Oct 07 Oct 14 Oct 21 Oct 28 Nov 04 N Nov 18 N D Dec 09 D Dec 23
City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 5 of 6 TASK filter: All Activities
© Oracle Corporation
Dec 23 D Jan 06 Jan 13 Jan 20 Jan 27 Feb 03 Feb 10 Feb 17 Feb 24 Mar 03 Mar 10 Mar 17 Mar 24 Mar 31 Apr 07 Apr 14 Apr 21 Apr 28 M M M M Jun 02 Jun 09 Jun 16 Jun 23 Jun 30 Jul 07 Jul 14 Jul 21 Jul 28
Install Elec A/G
Phase 3.A Finish / Open to Traffic
23-Apr-19, Phase 3.B
Phase 3.B Start
Deploy Traffic Crtl
Traffic Shift
Removals
Uncl Ex / Subgrade
Install SS
Install ST
Install Elec U/G
11" ABC (CL.6) Placement
Curb & Gutter & Bike Lane Placement
Parking Lane / Driveway Placement
Ramp & Sidewalk Placement
5.5" HMA Placement
Install Elec A/G
Sign Placement
Final Striping Placement
Phase 3.B Finish / Open to Traffic
16-May-19, Phase 4
Phase 4 Start
Deploy Traffic Ctrl
Removals / Uncl Ex / Subgrade
ABC Placement
Curb & Gutter & Pan Placement
Ramp & Sidewalk Placement
Install Guardrail
Sign Placement
Final Striping Placement
Phase 4 Finish
City of Golden - Washington Ave Complete St (SH93 to SH58) Classic Schedule Layout 13-Mar-19 14:11
Actual Work
Remaining Work
Critical Remaining W...
Milestone
Page 6 of 6 TASK filter: All Activities
© Oracle Corporation