VPVI-66:Project Planning: A Year in Review
Mickey Garcia & Jesi Cannon, BHC RHODES
![Page 2: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/2.jpg)
BHC RHODES
Engineering / Surveying
Founded 1992
115 employees
![Page 3: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/3.jpg)
Mickey Garcia
Project Accounting Supervisor / Project Management Analyst
Jesi Cannon
Bookkeeper / Vision Administrator
![Page 4: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/4.jpg)
Today’s Agenda• Why Vision Planning
• Preparation Phase
• Implementation Phase
• Using Planning Reports and Resource Utilization Screens
• Screen Design, User Defined Tab, and Help Buttons
• Main Takeaways
• Future Plans
![Page 5: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/5.jpg)
Why Vision Planning
![Page 6: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/6.jpg)
• Needed a common tool that would provide benefit to all
• Deltek already houses our project, opportunity,
client/contact, financial, and contract data
• PMs create data by planning and managing their projects
– That same data is then used by leadership to plan and manage
firm-wide resources and forecast future needs and revenue
– This single view is a win for all, making us more successful
![Page 7: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/7.jpg)
Preparation Phase
![Page 8: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/8.jpg)
• Six months of self-learning
– Deltek University courses
– Help from SilverEdge (our consultant)
– Trial and error
• Designed processes and presented to project champion
• Created training materials
• Scheduled and provided several training times
![Page 9: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/9.jpg)
Initial Training – December 2017
• One long session v. several shorter sessions
– Too much material at once; an hour or so is all they can absorb
before they’re on overload
• Created handout to go along with training
![Page 10: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/10.jpg)
Implementation Phase
![Page 11: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/11.jpg)
• Rolled out in January 2018
• Goal to have a project plan for all projects
– New plans to be created as projects were set up
– Ongoing projects to be in Planning by August
• Bi-weekly meetings with all PMs and Market Segment Leads
– Discuss status of project and plan
– Help to update plan
– One-on-one training at beginning of process
![Page 12: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/12.jpg)
• Pushback from almost everyone on almost everything
– Didn’t want to change
– Didn’t want to be “forced” to change
– Didn’t trust my knowledge or abilities
– Very little forward movement
• Accounting setup plans for existing projects to assist PMs
– Created basic shell that matched planned hours to actual hours
![Page 13: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/13.jpg)
Using Planning Reports and
Resource Utilization Screens
![Page 14: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/14.jpg)
Labor Resource Forecast
• Labor resource forecast
– Review forecasted hours, costs, and billing amounts by project
plan, employee, and labor category
– Review project assignments and determine if adjustments are
necessary
• Used for reviewing the current week’s planned hours
![Page 15: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/15.jpg)
![Page 16: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/16.jpg)
Labor Planned and Actuals
• Labor Resource Planned and actuals
– Review both planned and actual labor hours
– Determine if projects are on target, understand why or why not,
and improve performance on similar projects in the future
• Used in After Action Review meetings
![Page 17: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/17.jpg)
![Page 18: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/18.jpg)
Planned Labor for Generics
• Planned labor for generics
– Started from Labor Resource Planned/Actuals report
– Displays all projects with generic staff types
• Used to help replace generics with named staff
![Page 19: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/19.jpg)
![Page 20: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/20.jpg)
Resource Utilization
• Resource utilization
– Review employee utilization data from Project Planning and
Resource Management applications
• Used to guide staffing issues on an ongoing basis
– See which employees have capacity
– See which employees are overbooked
![Page 21: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/21.jpg)
![Page 22: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/22.jpg)
Resource Utilization Search
• Resource utilization
– Assign employees to project plans and monitor their utilization
– Search for resources based on different criteria
• Used to see an overview of a specific employee or group
of employees
– Easily reassign hours from one employee to another
![Page 23: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/23.jpg)
![Page 24: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/24.jpg)
Revenue Forecast
• Labor forecast report at billing
• Monthly by market segment
• Compare
– Budget from the revenue projections
– Planned values at billing
– Actual revenue
– Capacity based on the staffing model produced for the year
![Page 25: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/25.jpg)
Revenue Forecast
![Page 26: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/26.jpg)
Screen Design, User Defined
Tab, and Help Buttons
![Page 27: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/27.jpg)
General Tab
![Page 28: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/28.jpg)
Weekly Maintenance Tab
![Page 29: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/29.jpg)
Weekly Maintenance Tab
![Page 30: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/30.jpg)
Progress
![Page 31: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/31.jpg)
Progress
• Initial training and rollout December 2017 / January 2018
• Most current active projects have plans
• Using planning reports for staffing and forecasting
• Regular bi-weekly meetings with PMs to review plans
• Annual refresher training
• Workshops
• Only about half of project management staff using planning
![Page 32: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/32.jpg)
Main Takeaways
![Page 33: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/33.jpg)
If We Could Go Back…
• Better change management
• Thorough stakeholder analysis
• More convincing, less pushing
• Longer initial training process
• Workshops to subsidize the formal training
![Page 34: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/34.jpg)
Main Takeaways
• Change management is a big concern
• Maintain consistent communication with PMs
• Reinforces accuracy of timekeeping
• Creating culture of self-service
• More project awareness
![Page 35: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/35.jpg)
Main Takeaways
• Better risk mitigation
• Staff is starting to “get it”
• Allows improved client evaluation
• Are projects being managed better because of planning
tool?
– No backup to show yes or no, but we are definitely headed that
direction
![Page 36: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/36.jpg)
Future Plans
![Page 37: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/37.jpg)
Future Plans
• Continue to improve the forecasting by incorporating
opportunities
• Assist in creating future annual budgets
• Encourage use of Earned Value Management and the
Labor EVT Chart
![Page 38: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/38.jpg)
What does your organization do first –project or plan?
![Page 39: Project Tanis Engineering Services Presentation€¦ · •Goal to have a project plan for all projects –New plans to be created as projects were set up –Ongoing projects to be](https://reader034.vdocuments.site/reader034/viewer/2022042314/5f0243387e708231d4036388/html5/thumbnails/39.jpg)
Questions?