PROJECT REPORTING

in MSCA under H2020

NCP Academy Training

Prague, 26/9/2017

Marcela Groholova

Research Executive Agency

Brussels

Page 2: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Table of content

• Monitoring Project Implementation

• Reporting obligations

• Continuous Reporting

• Periodic Reporting

• Amendments

• FAQs from projects

Page 3: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Monitoring Project Implementation

Art. 22 of the GA:

• The Agency will — during the implementation of the action or

afterwards — check the proper implementation of the action and

compliance with the obligations under the Agreement, including

assessing deliverables and reports.

• For this purpose the Agency may be assisted by external persons or

bodies.

Project Officers monitor projects. External experts may assist.

Page 4: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Participant Portal (PP): "The entry point for submission"

• Project Reports

• Researchers' Declarations for all researchers

• Other documents (e.g. Notification of Starting date, Amendment)

• "My Area" – "My projects" tab

Page 5: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Principles of submission in H2020:

• Forms and templates provided in the electronic system (PP)

• Two-step submission process:

1 - Beneficiary Coordinator

2 - Coordinator REA

• No paper signed document, only electronic submission

• Single submission

• Process more automated

Page 6: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Type of reporting:

Continuous reporting (at any moment):

• Monitoring of project implementation – e.g. deliverables

• Some statistical data

Periodic reporting (at the time of payment):

• After each reporting period

Project Start date

Project End date

End period 1

End period 2, 3

Periodic Periodic

Continuous Reporting Module

Periodic + Final

Page 7: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

1. Continuous reporting (during whole project life cycle) • Researchers' Declarations (art. 19 of the GA)

• Deliverables

• Milestones

• Publications

• Dissemination and communication activities

• Progress Report (ITN and RISE)

• Patents

• Info on gender balance

• Training activities

• Questionnaires for researchers • etc.

2. Periodic reporting (for each reporting period) • Reports from art. 20 of the GA

• Predefined templates in the system

Page 8: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

1 – Continuous Reporting

Page 9: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

9

Log on to the Participant Portal. "My Area"

Page 10: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

10

Go to “My Projects” section. Then click on MP icon so to reach Participant Portal Grant Management Services

Page 11: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

11

Continuous Reporting Module

Page 12: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Researcher's Declaration (RD): • Art. 19 of the GA (ITN, RISE, COFUND)

• No RD for MSCA-IF

• To be submitted by each beneficiary for all researchers

Content of RD:

• Personal data (name, date of birth, nationality, gender, family

charges, email of researcher, etc.)

• Data linked to the project allowances: start date and end date of

recruitment/secondment, hosting institution, etc.

Page 13: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Researcher's Declaration – step 1:

Project researcher library:

• Each beneficiary can add researcher and fill in all personal data

• It is saved in the project database

• Once RD needs to be created, researcher's data are taken automatically

Advantages:

• Consistent data

• Time saving

Page 14: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 15: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Researcher's Declaration – step 2:

Create RD:

According to GA – to be submitted within

20 days after the recruitment (ITN)

20 days after the secondment (RISE): in case of split stays within 20 days

after the start of the first stay

20 days after the start of the research training activities (COFUND)

- For researchers that already exist in the project library, all personal data are

automatically prefilled.

- Who: - ITN and COFUND - recruiting beneficiary;

- RISE – seconding beneficiary (in case of Partner org . – the coordinator will submit)

Page 16: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 17: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Researcher's Declaration – important!

• RD is the main input document for calculating the duration of

recruitment/secondment.

• Ensure that data encoded in the RD are 100% correct (mainly start

date, end date, organization).

• RD feeds the financial statement.

• If the number of units in the financial statement is not correct, RD

must be corrected and financial statement must be resubmitted.

Page 18: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

RISE - How to report a split stay ?

• Create and submit only one RD per secondment.

• In case of split stay, no new RD to be created

• "Add period" in the "Secondment period tab" for RD already

created for the secondment.

Page 19: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Deliverables: • To be uploaded directly on the PP by the Coordinator

• Scientific deliverables and other deliverables as defined in the GA

Annex 1

Progress report (ITN and RISE) = deliverable :

• ITN - Within 30 days after year 1

• RISE - Within 30 days after year 1 and 3

• NO financial reports required

• Template defined on the Participant Portal

• Attachments possible

• Via PP MP

Page 20: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Deliverable's status (draft, pending (overdue),

submitted, approved, rejected (comments possible)):

Page 21: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

• The status of the deliverable is 'Pending' when a deliverable hasn't been uploaded

yet.

• When the status is displayed with a red background ( ) this means that the

estimated delivery date has passed.

• If the deliverable’s estimated delivery date falls in a given reporting period and the

deliverable is not submitted here on time, before the periodic report is "Locked for

review", participants will be asked to justify the delay (in the Periodic Reporting

module).

Deliverables

21

Continuous Reporting

Current view

Page 22: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

• Before submission a comment can be added and user is asked for confirmation whether s/he

wants to submit.

• Each time a deliverable has been submitted, the EU Officers will be notified.

• Each time the EU Officers reject the deliverable, the Coordinator Contacts and the

Participant Contacts are notified through the Participant Portal Notification System.

22

Deliverables Continuous Reporting

Page 23: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 24: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Milestones

• Milestones as defined in the GA Annex 1

• Tick box to confirm that it is achieved

Page 25: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 26: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Publications

• The main data to be specified (Title, author, journal, etc.)

Page 27: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 28: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Patents (if applicable)

Page 29: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 30: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Gender information

• Gender dimension in research

• R&D participants involved in the project

Page 31: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 32: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Dissemination and Communication

activities

• No of Dissemination/Communication activities

• Funding amount of the activities

• No of people reached by the activities

Page 33: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 34: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

SME impact

To measure impact on growth and job creation:

• Turnover and No of employees – only for SMEs

Page 35: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 36: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Training activities

• Organizer

• Module title

• Skills acquired

• Duration

• No of project researchers attending the event

• No of external participants

Page 37: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 38: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Questionnaires (will be available soon):

• Evaluation questionnaire - at the end of the

recruitment/secondment

• Follow-up questionnaire - two years after recruitment/secondment

• Each recruited/seconded researcher

Page 39: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

2 – Periodic Reporting

Page 40: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Periodic reporting obligations

• Periodic Report (within 60 days following the end of each reporting

period) Periodic technical report

Periodic financial report

• Final Report (in addition to the periodic report for the last reporting

period) Final technical report – summary for publication

Final financial report (final summary financial statement created

automatically by the electronic exchange system, consolidating the individual

financial statements for all reporting periods)

NB: For MSCA IF with 1 reporting period - "Report "+ "Final Report" covering

a single reporting period

Article 20 of the GA

Page 42: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Periodic report - technical report

Part A

• Publishable summary

• Data from Continuous reporting

Part B – narrative part

• Explanation of the work carried out by the beneficiaries and overview of

progress

• Update of the plan for exploitation and dissemination of results

• Explanations on deviations from DoA

Information entered in the IT tool through the Continuous Reporting module.

Submitted in a PDF through the Periodic Reporting module.

Page 43: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Periodic report - financial statement

1. Individual financial statements (Annex 4 to the GA)

• Financial statements for MSCA: only No if units to report, costs are

calculated automatically

• No of units coming from

• RD (ITN, RISE, COFUND)

• Duration of fellowships (IF)

2. Periodic summary financial statement including the request

for payment

Report generated automatically by the IT tool based on the information entered through the Periodic Reporting module.

Page 44: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Periodic reporting module (Activated after the end of each reporting period)

• Beneficiaries complete on-line the financial statements.

• Coordinator uploads the Part B of the periodic technical report (narrative

part).

44

.

At the time the coordinator submits the periodic report, the IT tool will capture the information from the continuous reporting module in order to generate automatically the Part A of the Periodic report

Make sure the information in the continuous reporting module is complete and up-to-date before the periodic report is 'locked for review'

Automatic activation except if an amendment with financial implications is on-going or a previous periodic report is still open

Page 45: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

45

Periodic Reporting Module

Periodic Reporting

Page 46: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Final report (Art 20 of GA)

• Within 60 days following the end of the last reporting period

• Report covers whole project period

• Final technical report

• Final financial report (final summary financial statement created

automatically by the electronic system, consolidating the individual

financial statements for all reporting periods)

• To be submitted together with Periodic report for the last RP

• Via PP MP

Page 47: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

1. Notification: All beneficiaries receive a notification.

2. Beneficiaries complete PR and e-sign FS: All beneficiaries complete their own

Financial Statement and their contribution to the Technical Part of the Periodic

Report. Beneficiaries e-sign and submit their Financial Statements to the

Coordinator.

3. The Coordinator approves & submits the elements of the Periodic Report.

Coordinator submits all reports in one package – Single Submission.

4. The EU Services review the submitted Periodic Report and accept or reject it.

5. Interim or Final Payment

NB: In case of need the Coordinator may decide to submit package without some

Form Cs (beneficiaries didn't submit Form C on time and blocking payment for

whole consortium), those beneficiaries will not have any opportunity to submit

their Form C within the same reporting period, only in the next reporting period!

Periodic reporting module – summary of steps

47

Periodic Reporting

Page 48: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Notifications

• LEAR directly via PP

• To notify about changes in the organization legal data - address,

name, universal transfer of rights, etc.

• PO is informed

• Via PPMy AreaMy Organization

Page 50: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

After the grant agreement is signed by the Coordinator and by the REA

Page 51: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 52: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication
Page 53: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

It is highly recommended to involve the PO during the amendment request preparation

Page 54: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

The Amendment Request can only be:

• Rejected (the whole) (with comments) • Accepted (the whole) - 45 days • Withdrawn by the initiating party No other option; no 'negotiation'

Page 55: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Coordinator

Progress report

Periodic report

Final report

Amendments

•Each beneficiary incl. Coordinator

Financial Statement – FORM C

Researchers' Declarations

Notifications

•Each researcher

Questionnaires

Page 56: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Frequently asked questions:

Page 57: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

How to report long-term sick leave in MSCA project:

IF:

Periods in which a researcher was absent for more than 30 days (for reasons

other than normal annual leave) can NOT be charged to the action (and must be

removed from the financial statement, by requesting an amendment to suspend

the action; see Article 49.1.1.2).

ITN, COFUND:

Periods in which a researcher was absent for more than 30 days (for reasons

other than normal annual leave) can NOT be charged to the action (and must be

removed from the financial statement, by changing the researcher declaration).

Page 58: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Can we make changes in the secondment plan? If so, how flexible are you?

It depends. Normally changes should be limited to the minimum necessary and

should be duly justified. However contact your PO to discuss the details.

Is it possible to replace a partner/beneficiary during GAP?

Normally not. H2020 proposals must be mature and ready to be implemented (no

negotiation). Changes during GAP are limited to the absolute minimum (e.g.

participant becomes bankrupt).

I cannot submit my amendment request, why?

The amendment request can be prepared by anyone having access to the

participant portal (with Coordinator Contact rights) but the submission and

withdrawal buttons can only be clicked by the PLSIGN.

Page 59: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Would a request for exceptional funding (TC) be accepted during GAP or

project implementation?

Very unlikely, this must be part of the evaluation (see General Annex of the WP "List

of countries eligible for funding").

How is the EU contribution in RISE calculated for split stays?

For partial months (split stays), a pro-rata unit cost of 1/30 will be reimbursed for

each day (for ease of implementation, each month is considered to have 30 days).

Details are available in AGA.

When does the consortium receive the EU contribution and how should it be

distributed?

Pre-financing payment within 30 days, either from the entry into force of the

Agreement or from 10 days before the starting date, whichever is the latest. Interim

payment and Payment of balance within 90 days from receiving the complete

Interim/Final report. Distribution according to GA and detailed in Consortium

agreement.

Page 60: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

RISE: Are ESRs without employment contract with the sending University

eligible? Are there any special arrangements possible?

Employment contract is not an obligation for RISE, staff members must be actively

engaged in or linked to research and/or innovation activities for at least one month

(full-time equivalent) at the sending institution, before the first period of

secondment. More details are in AGA.

Where to find the template for periodic report?

Participant Portal:

http://ec.europa.eu/research/participants/data/ref/h2020/gm/reporting/h2020-tmpl-

periodic-rep_en.pdf.

Can 'Publishable summary '' in the Continuous reporting be filled in at any

time during project implementation or only at the end of the project?

Yes, it can be filled in at any moment during the project duration, but at the latest

before submission of the Periodic report (Final report for IF).

Page 61: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

What is the procedure for Early termination?

It is a Notification, not an Amendment, "Launch new interaction" in the PP. The

Termination Date and the Fellowship End Date (for IF) should be specified. It

cannot be retroactive date, if this is the case, the date of Notification is taken by

the system.

IF: My project already finished and I realized that my Start date,

communicated to the REA, is wrong in the system: can I change it?

No, it is not possible to change anything after the project end date.

How to submit the Final Report?

The Final report must be submitted together with the Periodic report for the last

reporting period, Normally it is triggered by the system after the end day of the

project.

Who can submit the Financial statement (access rights):

Only the FSIGN can submit the financial statement.

Page 62: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Where to upload the scientific deliverables:

IF – no scientific deliverables needed, only Ethics requirements and the Data

Management Plan (if art. 29.3 activated);

ITN, RISE, COFUND – deliverables are contractual obligation, submit under

Continuous reporting.

Which information provided in the Reporting are considered confidential?

Is Publishable summary confidential?

'Publishable summary' is public information, ensure that no confidential information

is included. All Deliverables marked as "confidential" are not public. All information

included in the Part B (Technical report) of the proposal are also confidential.

Do I need to involve PO before I submit my amendment request?

It is not an obligation, but it is highly recommended. Please consult your PO before

you formally submit your amendment in order to avoid delays in the process.

Page 63: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Do we need a web site and can we submit without one or whether we should

put the one that is linked to the institution?

Whatever fits better to your project needs. But ensure that your PO can access it.

When do we need to submit the Data Management Plan and what it should

contain?

A DMP should be submitted during the project implementation, it is part of the

deliverables. It is obligatory for all projects which do not "opt-out" of the Open

Research Data Pilot.

It describes the data management life cycle for the data to be collected, processed

or generated by a research project. It must cover how to make data findable,

accessible, interoperable and reusable (FAIR). More information on PP

http://ec.europa.eu/research/participants/docs/h2020-funding-guide/cross-cutting-

issues/open-access-dissemination_en.htm

Page 65: PROJECT REPORTING in MSCA under H2020 · NCP Academy Training Prague, 26/9/2017 Marcela Groholova Research Executive Agency Brussels . ... Final technical report – summary for publication

Thank you

for your attention