project profile eng v1

33
December 2007 C M Wong & Associates Ltd Civil Engineering and Development Department Geotechnical Engineering Office Agreement No. CE 11/2004 (GE) 10-year Extended LPM Project, Phase 5, Package E – Tai Po Landslip Preventive Works on Government Slopes and Related Studies – Investigation, Design and Construction Landslip Preventive Works at Feature No. 3SE-B/C156 Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

Upload: others

Post on 15-Oct-2021

21 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Profile Eng v1

December 2007

C M Wong & Associates Ltd

Civil Engineering and Development Department Geotechnical Engineering Office

Agreement No. CE 11/2004 (GE)

10-year Extended LPM Project, Phase 5, Package E – Tai Po Landslip Preventive Works on Government Slopes and Related Studies – Investigation, Design and Construction

Landslip Preventive Works at Feature No. 3SE-B/C156 Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po

Project Profile

Page 2: Project Profile Eng v1

Civil Engineering and Development Department Geotechnical Engineering Office

The Government of the Hong Kong Special Administrative Region

This report has been prepared for the sole and specific use of the Government of the Hong Kong Special Administrative Region. Any other persons who use any information contained in it do so at their own risk

Landslip Preventive Works at

Feature No. 3SE-B/C156

Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po

Page 3: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

i CMWAL

Table of Contents

1. BASIC INFORMATION.................................................................................. 1

1.1. Project Title ..........................................................................................................1 1.2. Purpose and Nature of the Project ..................................................................1 1.3. Name of Project Proponent...............................................................................1 1.4. Location and Scale of Project...........................................................................1 1.5. Number and Type of Designated Project Covered by the Project Profile1 1.6. Name and Telephone Number of Contact Person(s)....................................2

2. OUTLINE OF PLANNING AND IMPLEMENTATION PROGRAMME.............. 3

2.1. Implementation and Planning of the Proposed Project...............................3 2.2. Tentative Project Timetable...............................................................................4 2.3. Interactions with Broader Programme Requirements or Other Projects.4

3. MAJOR ELEMENTS OF THE SURROUNDING ENVIRONMENT................... 6

3.1. Air Quality.............................................................................................................6 3.2. Noise ....................................................................................................................6 3.3. Water Quality........................................................................................................7 3.4. Ecology..................................................................................................................7 3.5. Cultural Heritage..................................................................................................8 3.6. Landscape and Visual Impact...........................................................................8

4. POSSIBLE IMPACT ON THE ENVIRONMENT .............................................. 9

4.1. General ..................................................................................................................9 4.2. Construction Phase ............................................................................................9 4.3. Operation Phase................................................................................................11

5. ENVIRONMENTAL PROTECTION MEASURES TO BE INCORPORATED IN THE DESIGN AND ANY FURTHER ENVIRONMENTAL IMPLICATIONS .... 12

5.1. Air Quality Impact..............................................................................................12 5.2. Noise Impact.......................................................................................................12 5.3. Water Quality Impact ........................................................................................12 5.4. Waste Management Implications ...................................................................13 5.5. Ecology................................................................................................................13 5.6. Cultural Heritage................................................................................................14 5.7. Landscape and Visual ......................................................................................14 5.8. Severity, Distribution and Duration of Environmental Effects.................15

Page 4: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

ii CMWAL

5.9. Further Implications..........................................................................................15

6. USE OF PREVIOUSLY APPROVED EIA REPORTS.................................... 16

List of Tables Table 2.1 Details of the Designated Project Table 2.2 Proposed Works for Designated Project Table 2.3 Duration of Construction Activities Table 3.1 Air Pollution Levels Recorded at EPD’s Air Quality Monitoring Station (Tai

Po) Table 3.2 Representative Air Sensitive Receivers (ASRs) Table 4.1 Estimated Waste Material Arisings Table 4.2 Area of Vegetation Removal Table 4.3 Predicted Tree Felling Table 5.1 Outline of Landscape Mitigation Proposals List of Figures Figure 1 Feature Location Plan Figure 2 Location of Sensitive Receivers for the Designated Project Figure 3 Landscape Proposal for the Designated Project Appendices Appendix A Plant Species Recorded on or Adjacent to the Designated Project Appendix B Fauna Recorded on or Adjacent to the Designated Project Appendix C Representative Photographs of the Designated Project Appendix D Plant Species of Conservation Interest Within the Proposed Works Area Appendix E Conditions for Working within Water Gathering Grounds

Page 5: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

1 CMWAL

1. BASIC INFORMATION

1.1. Project Title Landslip Preventive Works at Feature No. 3SE-B/C156 under Agreement No. CE 11/2004 (GE) : 10-year Extended Landslip Preventive Measures (LPM) Project Phase 5, Package E – Tai Po, Landslip Preventive Works on Government Slopes and Related Studies – Investigation, Design and Construction.

1.2. Purpose and Nature of the Project The acceleration of the LPM Programme was originally arranged as a 5-year Project to end in March 2000. As part of Government’s long-term strategy for upgrading slopes and retaining walls (i.e. features) in the New Catalogue of Slopes, the Geotechnical Engineering Office (GEO) has extended the Project for another 10 years beyond the year 2000. This 10-year Extended LPM Project aims to complete the upgrading works for another 2,500 substandard government features and safety-screening studies for another 3,000 private features by the year 2010.

The objective of Agreement No. CE11/2004 (GE) is to upgrade up to 30 government features in Tai Po. Among them, one feature (Feature No. 3SE-B/C156) falls within the Pat Sin Leng Country Park. The scope of works at the feature comprises minor earthworks to facilitate landscaping, soil nailing, drainage improvements and landscaping works.

Upon the completion of the ecological study for the above feature, an ecological report was submitted to the Environmental Protection Department (EPD) for the determination of Designated Project. Subsequently, the landslip preventive works at the feature was considered as a Designated Project after the reviewing by EPD.

1.3. Name of Project Proponent The Project Proponent is Landslip Preventive Measures Division 1 of the Geotechnical Engineering Office, Civil Engineering and Development Department, Government of the Hong Kong Special Administrative Region (HKSAR).

1.4. Location and Scale of Project Feature No. 3SE-B/C156 is located along Bride’s Pool Road, near Chung Mei Plover Cove Reservoir, Tai Po and falls within the Pat Sin Leng Country Park.

The location of this feature is presented in Figure 1.

1.5. Number and Type of Designated Project Covered by the Project Profile In accordance with Category Q.1 of Part 1, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO), the feature No. 3SE-B/C156 along Bride’s Pool Road, Tai Po is regarded as a Designated Project and this feature falls wholly within the Pat Sin Leng Country Park, near Chung Mei Plover Cove Reservoir. Therefore, an Environmental Permit must be obtained prior to the commencement of the landslip preventive works for feature No. 3SE-B/C156 (named as “Designated Project” hereafter) under the EIAO.

Page 6: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

2 CMWAL

1.6. Name and Telephone Number of Contact Person(s) All queries regarding the project can be addressed to the project proponent (Ms. Wendy Kwan /GEO) or their consultants (Mr. Chris Lee/CMWAL) :

Ms. Wendy Kwan Engineer/Landslip Preventive Meausres Division 1

Geotechnical Engineering Office Civil Engineering and Development Department Tel : 2760 5774 Fax : 2624 4135 Email : [email protected] Mr. Chris Lee Deputy Project Manager C M Wong & Associates Ltd Tel : 2522 1068 Fax : 2526 3111 Email : [email protected]

Page 7: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

3 CMWAL

2. OUTLINE OF PLANNING AND IMPLEMENTATION PROGRAMME

2.1. Implementation and Planning of the Proposed Project The Designated Project included in Agreement No. CE 11/2004 (GE) was awarded by the Civil Engineering and Development Department to C M Wong & Associates Ltd (CMWAL) as the engineering Consultant in October 2004. CMWAL is responsible for the investigation, design and supervision of the landslip preventive works for this Designated Project. The proposed upgrading works will be undertaken in the Works Contract No. GE/2005/50.

The sequence of the proposed slope works, generally comprising 6 activities, is described below :

Activities Details

1. Minor earthworks including minor slope trimming, removal of hard surfacing and slope debris materials

- minor slope trimming of slope surface to remove loose materials on slope

- removal of hard surfacing and slope debris materials

- disposal of the excavated materials

2. Installation of soil nails - drilling holes into slope for installation of steel bars and grouting up the holes as soil nails

3. Installation of raking drains - drilling holes into slope for installation of geotextile pipes as raking drains

4. Drainage improvement works - construction of concrete surface drainage channels to control surface runoff

5. Sprayed concrete surface cover - provision of sprayed concrete surface cover on the steeper slope surface (slope angle > 55 degrees)

6. Landscaping works - provision of hydroseeding, groundcover and shrubs on the gentler slope surface (slope angle < 55 degrees)

- painting of sprayed concrete surface cover and provision of planter holes to sprayed concrete cover.

Details of the Designated Project and a summary of the above activities are presented in Tables 2.1 and 2.2 respectively.

Table 2.1 Details of the Designated Project Length along slope

toe (m) Slope angle Existing cover Feature No. Height

(m) In Soil In Rock In Soil In Rock In Soil In Rock

3SE-B/C156 24 200 - 30º-65º - 40% vegetation & 60% sprayed concrete

-

Page 8: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

4 CMWAL

Table 2.2 Proposed Works for Designated Project Feature No. Proposed Works

3SE-B/C156 • Removal of the hard surfacing and slope debris materials at the toe

• Minor trimming of the rugged slope surface

• Vegetation clearance at soil area but no tree will be felled

• Installation of soil nails and raking drains • Drainage improvement works • Provision of painted sprayed concrete

surface cover with planter holes to steeper slope surface

• Landscape works of hydroseeding with shrub mix and groundcover at gentler slope surface

2.2. Tentative Project Timetable The proposed landslip preventive works for the Designated Project shall be carried out under a LPM SoR Contract. The whole Contract, including 30 slopes, commenced in June 2006 with a duration of 24 months while the construction works for the Designated Project are scheduled for commencement in March 2008 with a duration of 7 months. The Contractor for the the construction works is China Geo-Engineering Corporation.

The approximate periods for the various construction activities of the Designated Project are shown in Table 2.3. It should be noted that some of the construction activities (for example, installation of nails and drainage improvement works) would be carried out concurrently.

Table 2.3 Duration of Construction Activities Activities Anticipated Duration

1. Minor earthworks including slope trimming and removal of hard surfacing and slope debris materials

1-2 months

2. Installation of soil nails 2-3 months

3. Installation of raking drains 1 month

4. Drainage improvement works 1.5-2 months

5. Sprayed concrete surface cover 1-1.5 months

6. Landscaping works 1 month

2.3. Interactions with Broader Programme Requirements or Other Projects The Designated Project, namely feature No. 3SE-B/C156, is located along Bride’s Pool Road. As one of the conditions from the Assistant Commissioner for Transport,

Page 9: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

5 CMWAL

Bride’s Pool Road may be temporarily closed on Saturday, Sunday and Public Holiday. The construction works may not be carried out on these days.

According to GEO’s records, it is noted that feature Nos 3SE-D/C31 and 3SE-D/C53 located about 1000m and 1200m apart from the Designated Project are under Stage 3 Studies. Some on-going active projects, include reconstruction of footpath along Bride’s Pool Road near Chung Pui, are undertaken by the Highways Department.

The landslip preventive works for the Designated Project will not require any road closure but only closure of a section of footpath along the feature toe is required. Hence, the traffic flow along Bride’s Pool can be maintained. No interference of the landslip preventive works for the Designated Project with other on-going active projects is, therefore, expected.

Page 10: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

6 CMWAL

3. MAJOR ELEMENTS OF THE SURROUNDING ENVIRONMENT

3.1. Air Quality Vehicle emissions at Bride’s Pool Road in Tai Po would be the only major source of existing air pollution in the vicinity of the Designated Project located along Bride’s Pool Road. No other source of air pollution has been identified. The level of pollution is expected to be low due to the low traffic density as reported in “The Annual Traffic Census 2006”.

In the absence of in-situ monitoring data for the proposed works area at the Designated Project at Chung Mei area of Tai Po, the annual average concentrations of pollutants measured at EPD’s nearest monitoring station (Tai Po) would be used as a reference to provide information on the background air pollutant levels. Table 3.1 summarizes the annual average concentrations of the pollutants as reported in the “Annual Air Quality Statistic 2006” published by EPD.

Table 3.1 Air Pollutant Levels Recorded at EPD’s Air Quality Monitoring Statins (Tai Po)

Pollutants Annual Average Concentrations (ug/m3)

TSP 66

NO2 57

RSP 51

In accordance with Annex 12 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), representative air sensitive receivers (ASRs) were identified close to the site, as presented in Table 3.2 (for locations, refer to Figure 2).

Table 3.2 Representative Air Sensitive Receivers (ASRs) ASR Description Nearest distance between ASR

ans works site boundary (m)

R1 Picnic Area along Bride’s Pool Road 200

R2 Picnic Area along Bride’s Pool Road 230

3.2. Noise The Designated Project is located along Bride’s Pool Road at Chung Mei, Tai Po. The major source of existing noise would be road traffic. Traffic flow is low, however, the noise level is expected to be higher during the weekends and on the public holidays due to the influx of visitors to the Plover Cove and Pat Sin Leng Country Parks. According to Annex 13 of EIAO-TM, country parks would be regarded as noise sensitive receivers (NSRs). Visitors to the Country Park would potentially be impacted by the proposed construction works at the Designated Project. Moreover, the EIAO-TM does not specify a limit for construction noise levels received at a

Page 11: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

7 CMWAL

country park. Therefore, construction noise impact assessment at the Country Park is thus addressed qualitatively in the sections below.

According to the definitions as set out in Annex 13 of the EIAO-TM, there is no other representative NSRs identified close to the site for the purpose of quantitative noise assessment.

3.3. Water Quality Drainage culverts lie at both the northern and southern ends of the works area of the Designated Project (Figure 2).

The Designated Project is located inside the area of Water Gathering Grounds demarcated by Water Supplies Department (WSD).

3.4. Ecology Ecological surveys of the proposed works area and its adjacent areas were conducted in February 2007. The surveys consisted of the following aspects :

Habitat/Vegetation Surveys

Dominant and notable plant species (Appendix A refers), relative abundance and growth forms were recorded. Identification of species and status in Hong Kong were made with reference to Check List of Hong Kong Plants 2004 compiled by the Hong Kong Herbarium and published by AFCD.

Wildlife Surveys

Wildlife including avifauna, herpetofauna and terrestrial insects (Odonates and Lepidoptera) was surveyed by direct sighting and listening for calling animals. Active searching of potential herpetofauna/mammal habitats was undertaken. Signs of terrestrial mammals (i.e., droppings, footprints and burrows) were searched for (Appendix B refers).

Areas of Conservation Interest

The Designated Project (Appendix C refers) is located along Bride’s Pool Road, near Chung Mei and Plover Cove Reservoir that falls within the boundary of Pat Sin Leng Country Park.

The Pat Sin Leng Country Park supports a variety of habitat types, with upland areas dominated by grassland and low shrub. Lowlands area and stream valleys within the Country Park supports more mature vegetation including plantation and secondary/fung shui woodland. The woodland valleys of the two streams which feed Brides Pool are known to contain many indigenous species of trees, including the protected Rhododendron simsii, and several species of orchid.

Ecological surveys were therefore undertaken at the Designated Project by China-Hong Kong Ecology Consultants Co (CECC) to extablish the ecological profile of potentially impacted areas. This report presents the results of the surveys conducted in February 2007 covering habitat/vegetation and wildlife as described in the following paragraphs :

Page 12: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

8 CMWAL

Habitat/Vegetation

This site is dominated by a steep soil cut slope approximately 200m in length and most of the slope face is covered by sprayed concrete and support little vegetation. Vegetation is limited to small patches of herb and shrub species. The southern part of the slope, as well as the crest of the slope, is covered with vegetation belonging to the woodland fringe habitat of the Pat Sin Leng Country Park and is dominated by native trees (eg. Machilus brevifora), with typical woodland understorey shrubs, climbers and herbs benneth the tree canopy.

Three plant species of conservation interest, the shrubs Pavetta hongkongensis and Antirhea chinensis and the herd Brainea insignis (Appendix D refers), were recorded within the proposed works boundary. Pavetta hongkongensis is protected under Hong Kong Legislation. Antirhea chinensis is recorded in Illustration of Rare and Endangered Plants in Guangdong Province. Brainea insignis is a wild plant under State protection (Category II) and recorded in China Plant Red Data Book.

The shrub Camellia sp. (Appendix D refers) was recorded immediate at the southern works boundary and is protected under Hong Kong Legislation.

The tree Aquilaria sinensis (Appendix D refers) was recorded behind the slope crest. A sinensis is a wild plant under State protection (Category II) and recorded in China Plant Red Data Books.

Wildlife

A total of four species of bird were recorded at the Designated Project and adjacent habitats during recent surveys (Appendix B refers). Most of the species recorded are common and widespread in Hong Kong.

No amphibian and reptile species were recorded at the Designated Project and adjacent habitats during recent surveys. No direct or indirect observations of mammals were made during the surveys.

Three species of butterfly were recorded at the Designated Project and adjacent habitats (Appendix B refers). All the recorded terrestrial insects are common and widespread in Hong Kong.

3.5. Cultural Heritage No declared monument is located wholly or partly within the works area for the Designated Project.

3.6. Landscape and Visual Impact The Designated Project is visually sensitive as it is located along Bride’s Pool Road. The slope surface of Designated Project is partly covered by sprayed concrete and is partly vegetated. Behind the slope crest, there is a natural hillside. Two slopes also along Bride’s Pool Road located at both the southern and northern side of the slope are also covered by sprayed concrete. The possible visual impacts caused by the Designated Project and the mitigation measures are mentioned in Sections 4 and 5.

Page 13: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

9 CMWAL

4. POSSIBLE IMPACT ON THE ENVIRONMENT

4.1. General The potential environmental impacts of the landslip preventive works at Tai Po are reviewed in this section.

4.2. Construction Phase Air Quality

Potential construction phase air quality impacts pertinent to the Designated Project would include dust nuisance and gaseous emissions from the construction plants and vehicles. Fugitive dust emissions arising from minor earthworks for the removal of existing slope surface material, drilling operations and wind erosion would be the main sources of air pollution.

Given that the number of plants to be used on site would be limited and the works area would be small, adverse dust impacts during construction would not be anticipated with the incorporation of mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation. Vehicle and plant exhause emissions from the site would not be considered to constitute a significant source of air pollution.

Noise

According to the construction programme of this Designated Project, the site works are scheduled for commencement in March 2008 with a duration of 7 months.

No construction activities would be anticipated to be carried out at the Designated Project during the restricted hours (between the hours of 7 p.m. and 7 a.m., or at any time on a general holiday) under the Noise Control Ordinance.

Apart from the Pat Sin Leng Country Park, there was no NSR identified within the assessment area. Visitors to the country park would potentially be impacted by the proposed construction works at the Designated Project. However, the EIAO-TM does not specify a limit for construction noise levels received at a country park. Taking into account the transient nature of visitors to the country park, insurmountable construction noise impact on this NSR would not be anticipated.

Water Quality

Water-bodies potentially affected by the proposed slope works include drainage culverts to the immediate northern and southern end of the works area of the Designated Project (Figure 2 refers). Site runoff and drainage from the works area of the Designated Project, if uncontrolled, could enter the drainage culverts.

The Designated Project is located inside the Water Gathering Ground demarcated by WSD and therefore the “Conditions for Working within Water Gathering Grounds”, issued by WSD, should be strictly followed for the slope works (see Section 5 of this report).

During the construction phase, runoff and drainage from construction site would be the main sources of potential water quality impacts to the nearby water-bodies. Site

Page 14: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

10 CMWAL

runoff and drainage may contain increased loads of suspended solids and contaminants. Potential sources of pollution from site drainage include : runoff and erosion from exposed soil surfaces and stockpiles; release of grouting and cement materials with rain wash; wash water from dust suppression sprays; and fuel and lubricants from maintenance of construction vehicles and mechanical equipment. Sewage arising from the on-site construction workforce would also have the potential to cause water pollution if it is discharged directly into adjacent waters without any appropriate treatment.

Waste Management

Waste would be generated during excavation works, trimming and from the removal of existing slope surfacing materials of the Designated Project and would be taken to the Public Fill Facility at Tseng Kwan O Area 137 managed by the Civil Engineering and Development Department (CEDD). Other wastes generated from vegetation clearance and during construction activities such as timber, plastics, etc. would be taken to NENT Landfill managed by EPD. Permissions have been granted from EPD and CEDD for waste disposal to these designated facilities.

Estimated volumes of the waste materials are summarized in Table 4.1 below. Provided that these waste materials are handled, transported and disposed of using the recommended methods in Section 5 and that good site practices are adhered to, no adverse environmental impacts and nuisance would be expected.

Table 4.1 Estimated Waste Material Arisings Type of Waste Materials Estimated Volume Designated Waste Disposal

Facility

Removed Hard Surfacing 120 m3

Soil 65 m3

Rock 5 m3

Public Fill Facility at Tseng Kwan O Area 137 managed by CEDD

Other wastes generated during construction

activities

100 m3

Vegetation clearance 180 m3

NENT Landfill managed by EPD

Total 470 m3

Ecology

Removal of slope debris and minor trimming of slope surface at the Designated Project would require vegetation clearance of an estimated area of 1,200m2. No tree felling is proposed and it would be strictly avoided during the construction stage. In addition, tree rings are proposed for existing trees on the proposed sprayed concrete surface cover. The impact of vegetation clearance is considered relatively minor, as the affected habitats (grassland/shrubland and plantation) are of low ecological value. Four plant species of conservation interest recorded on the works area (Pavetta hongkongensis, Brainea insignis, Antirhea chinensis and Camellia sp.)

Page 15: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

11 CMWAL

would potentially be affected by the proposed slope works. No direct impacts are anticipated to the protected Aquilaria sinensis, which was recorded adjacent to the proposed works area.

Other potential indirect impacts to the works area and adjacent habitats/wildlife would result from construction phase activities and increased human activity during the construction phase, such as trampling of habitats/vegetation, littering, human waste discharge and fires. Such impacts would be temporary in nature and only affect low value ecological habitats. Provided the mitigation measures presented in Section 5 are implemented, indirect ecological impacts are expected to be minimal.

Table 4.2 Area of Vegetation Removal Approximate Total Slope Works Area at

the Designated Project (m2) Approximate Area of Vegetation to be

Removed (m2)

4,000 1,200

(Exisiting trees would be retained and tree rings are proposed for existing trees on the

slope surface with sprayed concrete)

Cultural Heritage

No declared monument would be affected by the proposed landslip preventive works.

Landscape and Visual Impact

During the construction works, temporary scaffolding and working platforms would be erected on the slope face to install soil nails and carry out landscaping works. No tree felling would be required.

Table 4.3 Predicted Tree Felling Approximate Number of Trees

within Slope Works Area of the Designated Project

Number of Trees to be Felled

Number of Trees to be Transplanted

110 0 0

4.3. Operation Phase No adverse impact would be expected during the operation phase of the proposed landslip preventive works with regard to the environmental issues of noise, air quality, water quality, waste management, ecology and cultural heritage.

It is expected that the proposed landslip preventive works with proposed whip planting and the other landscaping works would result in positive impacts in terms of landscape character in the long term.

Page 16: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

12 CMWAL

5. ENVIRONMENTAL PROTECTION MEASURES TO BE INCORPORATED IN THE DESIGN AND ANY FURTHER ENVIRONMENTAL IMPLICATIONS

5.1. Air Quality Impact Dust mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation should be implemented to minimize fugitive dust emissions from the works area during the construction phase. Relevant control measures are listed below :

Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved road, with complete coverage, particularly during dry weather;

Use of frequent watering for particularly dusty static construction areas;

Tarpaulin covering of all dusty vehicle loads transported to and from site; and

Water construction vehicles’ wheel and body before exiting the construction site.

5.2. Noise Impact The following good site practices are recommended and have been incorporated into the Contract Specification :

Good Site Practice and Management

Good site practices and noise management would considerably reduce the impact of construction activities on nearby areas. The following package of measures should be followed during each phase of construction :

Only well-maintained plant should be operated on-site and plant should be serviced regularly diring the construction program;

Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction program;

Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum; and

Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

5.3. Water Quality Impact The Contractor shall comply with the Water Pollution Control Ordinance (WPCO) and its subsidiary regulations. In addition, the Contractor shall comply with the “Conditions for Working within Water Gathering Grounds” issued by WSD for the proposed landslip preventive works at the Designated Project (refer to Appendix E).

The Contractor should ensure that all runoff arising from the work sites are properly treated, e.g. by the use of sedimentation tank or silt trap, and that the discharge standards as stipulated in WPCO are met. Any trade effluent or foul or contaminated or cooling or hot water should not be discharged into any public sewer, stormwater drain, channel, stream course or the sea. If toilet facilities are erected,

Page 17: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

13 CMWAL

foul water effluent should be directed to a foul sewer or to a sewage treatment and disposal facility.

The Contractor should be responsible for the design, construction, operation and maintenance of all the mitigation measures and practices specified in the Professional Persons Environmental Consultative Committee Practice Note (ProPECC PN) 1/94 “Construction Site Drainage” issued by the Director of Environmental Protection.

5.4. Waste Management Implications The Contractor should comply with the Waste Disposal (Chemical Waste) (General) Regulation, the Waste Disposal Ordinance and its subsidiary regulations.

The Contractor should not permit any sewage, waste water or effluent containing sand, cement, silt or any other suspended or dissolved material to flow from site onto any adjoining land or allow any waste matter which is not part of the final product from waste processing plants to be deposited anywhere within any site or onto any adjoining land.

The construction waste generated by the Contractor on-site would be transported to the designated disposal facilities managed by EPD or CEDD. Monitoring of the Contractor’s compliance with the requirements of the trip ticket system would be carried out to ensure that the waste actually reaches the intended disposal facility and the correct procedures are being followed at all times.

5.5. Ecology Overall, ecological impacts resulting from the proposed works are expected to be relatively minor. The works would be small in scale, and direct impacts would be limited to common habitat types of low ecological value. Landscape planting would provide compensation for disturbance to existing vegetation on the Designated Project. The compensatory planting will be detailed in Section 5.7 below.

The most notable potential impact would be to plant species of conservation interest recorded on the Designated Project. The location of these plants have been taken into consideration during the detailed design of slope works, and the plants would be retained in-situ. The exact locations of plant species of conservation interest would be identified on site prior to the commencement of the proposed works and the plants would be surrounded with barricades to avoid any damage during construction phase by the Contractor. Moreover, protective rings, similar to tree rings, for the plants within the proposed sprayed concrete surface area would be provided.

No tree felling would be required for the Designated Project. Temporary protective hessian armouring around the tree trucks would be provided by the Contractor to protect the existing trees prior to the commencement of site clearance, demolition, construction of the soil nails and other temporary works. Moreover, tree rings would be provided to the existing trees within the proposed sprayed concrete surface area.

Standard good site practice would be implemented to ensure disturbance to the

Page 18: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

14 CMWAL

surrounding habitats is avoided or minimized. Such measures would include :

Placement of equipment or stockpile in the works area and access routes would be selected at existing disturbed land where possible to minimise disturbance to vegetation, or at the locations most convenient to gain access to the slope area. If existing vegetation is affected for the latter case, tree felling would be avoided and appropriate mitigation measures (for example, hydroseeding with shrub mix) would be proposed for the affected area. The choice of temporary stockpiling area and access routes would be far away from the identified plant species of conservation interest.

Construction activities would be restricted to works area that should be clearly demarcated.

Temporary works area would be reinstated immediately after completion of the construction work.

To protect nearby watercourses, water quality mitigation measures stipulated in Section 5.3 would be implemented.

Open fires would be strictly prohibited on the works site.

Waste generated from the site would be disposed of in a timely and proper manner.

The Resident Site Staff would monitor the proper implementation of the above mitigation measures.

5.6. Cultural Heritage The impact assessment showed that no sites of cultural heritage would be affected by the proposed slope works and therefore no mitigation measures would be required.

5.7. Landscape and Visual Temporary hoarding would be erected along the toe of the works site to screen the proposed landslip preventive works. Part of the current vegetation cover on the slope surface of the Designated Project would be removed and replaced by sprayed concrete with colour paints and planter holes to reduce visual impacts.

In addition, hydroseeding with shrub mix and planting of whip at the slope crest and the southern slope portion are proposed to compensate the vegetation clearance there. Approximate area for compensatory planting is 1200 m2. No tree felling would be required and no removal of the plant species of conservation interest would also be required. The protective measures for the existing trees and the plants are mentioned in Section 5.5 above.

The visual impact of the maintenance staircases would be minimized by providing colour paints to blend with the surrounding environments. An outline of the landscape mitigation proposal is presented in Figure 3 and Table 5.1 below.

Page 19: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

15 CMWAL

Table 5.1 Outline of Landscape Mitigation Proposals Landscape Mitigation proposal for the Designated Project

Planting of climbers (Parthenocissus himalaya and Ficus pumila) in planter holes across the proposed sprayed concrete surface cover

Colour painting to the entire proposed sprayed concrete surface cover

Hydroseeding with groundcover (Nephrolepis auticulata) and shrub mix (Rhaphiolepis indica, Ligustrum sinensis and Psychotria asiatica) and planting of whip (Celtis sinensis and Gordonia axillaris) at the slope crest and the southern slope portion

5.8. Severity, Distribution and Duration of Environmental Effects No adverse residual environmental impacts are anticipated with the implementation of the recommended mitigation measures.

5.9. Further Implications No further environmental implications are anticipated with the implementation of the recommended mitigation measures.

Page 20: Project Profile Eng v1

Landslip Preventive Works at Feature No. 3SE-B/C156, Along Bride’s Pool Road, Near Chung Mei Plover Cove Reservoir, Tai Po Project Profile

16 CMWAL

6. USE OF PREVIOUSLY APPROVED EIA REPORTS Relevant project profiles submitted for application for permission to apply directly for an Environmental Permit (EP) are listed below :

Agreement No. CE 75/2001 (GE) 10-Year Extended LPM Project Phase 3, Package C – Kowloon and Northern New Territories, Landslip Preventive Works on Government Slopes and Related Studies – Investigation, Design and Construction (Submitted in June 2004 and EP was granted in September 2002 with EP no. EP-196/2004)

Agreement No. CE 76/2001 (GE) 10-Year Extended LPM Project Phase 3, Package D – Outlying Islands, Landslip Preventive Works on Government Slopes and Related Studies – Investigation, Design and Construction (Submitted in September 2004 and EP was granted in December 2004 with EP no. EP-205/2004)

Page 21: Project Profile Eng v1

List of Figures Figure 1 Feature Location Plan Figure 2 Location of Sensitive Receivers for the Designated

Project Figure 3 Landscape Proposal for the Designated Project

Page 22: Project Profile Eng v1
Page 23: Project Profile Eng v1
Page 24: Project Profile Eng v1
Page 25: Project Profile Eng v1

Appendices Appendix A Plant Species Recorded on or Adjacent to the

Designated Project Appendix B Fauna Recorded on or Adjacent to the Designated

Project Appendix C Representative Photographs of the Designated

Project Appendix D Plant Species of Conservation Interest Within the

Proposed Works Area Appendix E Conditions for Working within Water Gathering

Grounds

Page 26: Project Profile Eng v1

Appendix A: Plant Species Recorded on or Adjacent to the Designated Project Note: # - S = shrub; H=herb; C=climber; G=grass; T=tree; N=native plant Abundance: * - +, occurred at site; ++, common at site; +++, abundant at site

Family 科名 Species Affected area*

Adjacent area*

Plant Form # Status #

Actinidiaceae Saurauia tristyla + S N Adiantaceae Adiantum capillus-veneris + H N Anacardiaceae Rhus succedanea + S/T N Annonaceae Uvaria macrophylla + C N Annonaceae Desmos chinensis + C N Aquifoliaceae Ilex pubescens + S N Araliaceae Schefflera heptaphylla + T N Asteraceae Blumea megacephala + H N Blechnaceae Blechnum orientale + + S N Blechnaceae Brainea insignis + H N Caprifoliaceae Viburnum odoratissimum + T N Clusiaceae Garcinia oblongifolia + T N Connaraceae Rourea microphylla + C N Dilleniaceae Tetracera asiatica + C N Elaeocarpaceae Elaeocarpus sylvestris + T N Euphorbiaceae Aporusa dioica + + T N Euphorbiaceae Breynia fruticosa + + S N Euphorbiaceae Mallotus paniculatus + T N Euphorbiaceae Phyllanthus urinaria + S N Euphorbiaceae Bridelia tomentosa + T N Euphorbiaceae Sapium discolor + T N Euphorbiaceae Glochidion eriocarpum + S N Fabaceae Dalbergia hancei + C N Fabaceae Millettia reticulata + C N Fabaceae Dalbergia benthamii + C N Flacourtiaceae Homalium cochinchinensis + S N Gleicheniaceae Dicranopteris pedata + + S N Gnetaceae Gnetum lofuense + + C N Gramineae Arundinella nepalensis + G N Gramineae Lophatherum gracile + G N Guttiferae Cratoxylum cochinchinense + + S N Hamamelidaceae Liquidambar formosana + T N Lauraceae Machilus breviflora +++ ++ T N Lauraceae Cinnamomum parthenoxylon + T N Lauraceae Litsea rotundifolia + + S N Lauraceae Cassytha filiformis + C N

Page 27: Project Profile Eng v1

Family 科名 Species Affected area*

Adjacent area*

Plant Form # Status #

Liliaceae Liriope spicata + H N Liliaceae Dianella ensifolia + G N Lygodiaceae Lygodium japonicum + C N Melastomataceae Melastoma sanguineum + S N Moraceae Ficus variegata + T N Moraceae Ficus hispida + T N Moraceae Ficus variolosa + S N Moraceae Ficus simplicissima + S N Myrsinaceae Maesa perlarius + S N Myrsinaceae Myrsine seguinii + S N Myrsinaceae Ardisia quinquegona + S N Myrsinaceae Ardisia crenata + S N Myrtaceae Syzygium hancei + + T N Myrtaceae Rhodomyrtus tomentosa + S N Pandanaceae Pandanus furcatus + S N Pinaceae Pinus massoniana + T N Rosaceae Rubus reflexus + C N Rosaceae Rosa laevigata + C N Rubiaceae Antirhea chinensis + + S N Rubiaceae Pavetta hongkongensis + S N Rubiaceae Mussaenda pubescens + C N Rubiaceae Psychotria asiatica + + S N Rubiaceae Canthium dicoccum + T N Rubiaceae Diplospora dubia + S N Rutaceae Zanthoxylum nitidum + C N Rutaceae Acronychia pedunculata + T N Rutaceae Zanthoxylum avicennae + S N Rutaceae Melicope pteleifolia + S N Smilacaceae Smilax china + C N Smilacaceae smilax glabra + C N Sterculiaceae Sterculia lanceolata + T N Theaceae Schima superba + + T N Theaceae Eurya chinensis + S N Theaceae Gordonia axillaris + T N Theaceae Eurya groffii + T N Thymelaeaceae Aquilaria sinensis + T N Tiliaceae Microcos paniculata + T N Theaceae Camellia sp. + S N

Page 28: Project Profile Eng v1

Appendix B: Fauna Recorded on or Adjacent to the Designated Project

Bird species recorded in Study area

Common name Species Local Abundant Status in Hong Kong

Common Tailorbird Orthotomus sutorius + common

Japanese White Eye Zosterops japonica (simplex) + common

Chinese Bulbul Pycnonotus sinensis + common Crested bulbul Pycnonotus jocosus + common

Butterfly species recorded in Study area

Common name Species Local Abundant Status in Hong Kong

Red-base Jezebel Delias pasithoe + common Great Mormon Papilio memnon + common Glassy Tiger Parantica aglea + common

Note: “+” represent 1 – 5 individuals recorded within study area

“++” represent 5 – 10 individuals recorded within study area “+++” represent more than 10 individuals recorded within study area

Page 29: Project Profile Eng v1

Appendix C: Representative Photographs of the Designated Project

General View of feature No. 3SE-B/C156, looking south

General view of feature No. 3SE-B/C156, looking north

Page 30: Project Profile Eng v1

Appendix D: Plant Species of Conservation Interest Within the Proposed Works Area

Species Protection status Photo No. Aquilaria sinensis Wild plant under State Protection (Category II) in China

and recorded as vulnerable in China Plant Red Data Book. Photo 1

Pavetta hongkongensis

The Forestry Regulation (Cap.96) Photo 2

Camellia sp. The Forestry Regulation (Cap.96) Photo 3 Brainea insignis 1) Wild plant under State Protection (Category II) in China

and recorded as vulnerable in China Plant Red Data Book.

2) Listed as Restricted species (Xing, 2000)1

Photo 4

Antirhea chinensis Recorded in Illustration of Rare and Endangered Plants in Guangdong Province.

Photo 5

Photos

Photo 1. Aquilaria sinensis Photo 2. Pavetta hongkongensis

1 Xing Fu Wu., Ng Sai Chit and Lawrence K.C. Chau (2000). Gymnosperms and Angiosperms of Hong Kong. Memoirs of The Hong Kong Natural History Society. No. 23: 21-136

Page 31: Project Profile Eng v1

Photo 3. Camellia sp. Photo 4. Brainea insignis

Photo 5 Antirhea chinensis

Page 32: Project Profile Eng v1

Appendix E: Conditions for Working within Water Gathering Grounds

(a) Adequate measures shall be taken to ensure that no pollution or siltation occurs to the gathering grounds.

(b) No earth, building materials, fuel, oil or toxic materials and other materials which may cause contamination to the gathering grounds are allowed to be stockpiled or stored on site.

(c) All surplus spoil shall be removed from gathering grounds as soon as possible.

(d) Temporary drains with silt traps shall be constructed at the boundary of the site prior to the commencement of any earthworks.

(e) Regular cleaning of the silt traps shall be carried out to ensure that they function properly at all time.

(f) All excavated or filled surfaces which have the risk of erosion shall be protected from erosion at all time.

(g) Facilities for washing the wheels of vehicles before leaving the site shall be provided.

(h) Any construction plant which causes pollution to the gathering grounds due to leakage of oil or fuel shall be removed off site immediately.

(i) Any soil contamination with fuel leaked from plant shall be removed off site and the void arising from removal of contaminated soil shall be replaced by suitable material to the approval of the Director of Water Supplies.

(j) Provision of temporary toilet facilities is to be subject to the approval of the Director of Water Supplies.

(k) All waterworks access roads must be maintained unobstructed at all time.

(l) Site formation plans shall be submitted to W.S.D. for approval prior to commencement of work.

(m) No structure or temporary works shall be erected in the catchwaters without prior approval of W.S.D.

(n) The Contractor shall be responsible for cleaning frequently any waterworks roads and associated drainage works of mud and debris.

(o) The Contractor shall limit the gross weight of the vehicles imposed on the waterworks access to 5 tonnes and the axle load to 3 tonnes. He shall apply to W.S.D with details of his vehicles for using the access.

(p) The approval for using the access may be withdrawn on written notice to the Contractor by W.S.D. at their absolute discretion.

(q) The Contractor shall recover immediately his vehicle which fell into the catchwater or stream bed or pay to Government on demand the cost of recovery that may be necessary through the occurrence of any incident caused by the Contractor.

(r) The Contractor shall carry out repair or reinstatement works to the satisfaction of W.S.D. or pay to Government on demand the cost of repair and reinstatement to any waterworks installations that shall or may be necessary at any time as a result of damaged caused by the Contractor or others under his charge.

Page 33: Project Profile Eng v1

(s) The Contractor shall enter and remain on and use the access at his own risk and he shall indemnify the Government of Hong Kong from all claims, costs, damages and expense arising from the use of the access.

(t) No excavation with depth more than 2m shall be permitted within 120m from the centerline of WSD water tunnels without the prior approval of WSD.