project no. 161073sa...geotechnical investigation project no. 161073sa lift station #47 november 2,...

27

Upload: others

Post on 17-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 2: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 3: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1

1.0 INTRODUCTION This report presents the results of a subsoil investigation carried out at the site of the proposed Lift

Station #47 facility. The property is located at 4102 North 113th Avenue, in Phoenix, Arizona. The original scope of work indicated a surface mounted lift pump facility with no deep well. We now

understand that design and construction will consist of a small single story slab-on-grade office (potentially located adjacent to or over deep backfill of an existing wet well), an existing valve pit to be abandoned in place, and a new biofilter 10 feet below grade. The existing odor control system will need to be removed to make way for the proposed below grade biofilter. Structural loads are expected to be light to moderate and no special considerations regarding settlement tolerances are known at this time. We understand that no landscaping or sidewalks are planned. If the design changes and landscaping and/or sidewalks become necessary, then we should be notified so that we can provide additional recommendations.

Due to the design changes and urgency for reporting, no additional field investigation has been

conducted to address the design changes.

2.0 GENERAL SITE AND SOIL CONDITIONS

2.1 Site Conditions

The site is located within an existing lift station located north of Indian School Road and about 1.2 miles east of El Mirage Road. The site is currently a paved area inside the lift station compound. Based on record drawings the existing wet well is located near the proposed office structure and is approximately 30 feet deep. Based on discussions with the structural engineer, the existing odor control system has a bottom of slab depth of approximately 13 feet below grade. A brief review of available aerial photographs was conducted, but none coincide with the time of wet well construction. Therefore, the extent of the wet well backfill is not known. The field work was conducted after we were made aware of design changes. Therefore, the boring log does not provide information on the backfill material or condition.

2.2 Geologic Conditions

The site is located in an area that has undergone considerable subsidence due to groundwater removal. Areas of subsidence are known to produce earth fissuring, which has affected areas within 3 miles of the site. Fissure gullies form over subsurface irregularities such as bedrock highs, which cause tensional stresses and differential subsidence. Where such anomalies are not present, subsidence tends to be uniform over a wide area, this having minimal effect on surficial structures. The AZGS Earth Fissure Survey Map

Page 4: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 2

for the Luke study area dated 2008 indicated several earth fissures to the northwest of the property. These are indicated on the map. No evidence of earth fissures were observed on the site.

No cracks or crevasses were observed during our investigation. This is not a guarantee that

earth fissures will not form on the site in the future, just that what we observed did not appear to be the result of subsidence related fissures.

If any cracks or crevasses are noted during site excavation this office should be notified

immediately. Representatives from this office will then visit the site, assess the feature and make recommendations regarding restorative measures.

2.3 Seismic Design Parameters

The project area is located in a seismic zone that is considered to have low historical seismicity. Earthquakes in eastern Arizona are quite rare. The seismicity of the Phoenix area has had only two magnitude 3.0 events in over 100 years. Liquefaction is not considered a concern as groundwater generally exceeds 15 meters below ground surface.

Although borings were not advanced to 100 feet, based on the nature of the subsoils

encountered in the test locations and the geology in the area, Site Class Definition, Class D should be used for design of the structures supported at ground surface. In addition, the following seismic parameters may be used for design (based on 2008 USGS maps adopted by 2012 IBC):

Table 2.3.1 Seismic Parameters

MCE1 spectral response acceleration for 0.2 second period, SS: 0.164g MCE1 spectral response acceleration for 1.0 second period, S1: 0.055g

Site coefficient, Fa: 1.6 Site coefficient, Fv: 2.4

MCE1 spectral response acceleration adjusted for site class, SMS: 0.262g MCE1 spectral response acceleration adjusted for site class, SM1: 0.132g

5% Damped spectral response acceleration, SDS: 0.175g 5% Damped spectral response acceleration, SD1: 0.088g

NOTE 1: MCE = maximum considered earthquake

Page 5: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 3

2.4 General Subsurface Conditions

Pavement comprises 2.5 inches of asphalt concrete over 6 inches of aggregate base. Subsoil conditions at the site comprise predominantly of sandy lean clay with various amounts of gravel to the termination depths of 11 to 21.5 feet below existing grade. Weak to moderate degrees of calcareous cementation were also noted in the deeper soils. The standard penetration resistance test (SPT) values range from 20 to 35 blows per foot (bpf). No groundwater was encountered during this investigation.

Laboratory testing indicates in-situ dry densities of the upper soils on the order of 115 pcf and

water contents on the order of 13 percent at the time of investigation. Liquid limits were on the order of 36 with plasticity indices on the order of 21 percent. The upper clayey soils exhibit volume increase (swell) due to wetting of approximately 3.5 percent when compacted to moisture and density levels normally expected during construction. Undisturbed samples displayed small additional compression (1%) due to inundation under a maximum confining load of 3,200 psf. Laboratory testing of the corrosive properties of the soils indicate a pH of 7.8, a laboratory minimum resistivity of 660 ohm-cm, sulfate content of 15 ppm and a chloride content of 173 ppm.

3.0 ANALYSIS AND RECOMMENDATIONS

3.1 Analysis

Analysis of the field and laboratory data indicates that subsoils at the site are generally favorable for the support of the proposed office structure on shallow foundations and for slab-on-grade construction, subject to remedial earthworks and depending on proximity to the existing wet well. Deep foundation alternatives are recommended if loose backfill conditions are encountered during construction. The proposed biofilter will require demolition of the existing odor control containment area. Construction of the biofilter (approximately 10 feet below grade) near existing infrastructure and/or CMU walls will require shoring during construction. We understand that the valve box will be abandoned in place and backfilled with aggregate base.

The upper soils at the boring location are medium to dense consistency, but are capable of

post-construction settlement when subjected to wetting under load. This could cause settlement resulting in cracking problems. Recommendations are to over-excavate or deepen footings to reduce (not eliminate) the potential for collapse. This does not remove the potential for deeper seated settlement of potentially loose backfill soils (if encountered). Accordingly, it will be critical to provide proper drainage to limit the potential for water infiltration of deeper soils.

Page 6: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 4

As an alternate to shallow spread footings bearing on dense native soil, a mat or structural slab can be used for design. This type of foundation system may be applicable for smaller surface (at grade) structures such as equipment pads. Over-excavation of native soils is not required. However, the exposed subgrade soils should be moisture conditioned and compacted.

The swell potential of the fine portion of the upper clayey soils is a concern. The potential is

usually strong enough to cause differential movements of slabs-on-grade such as floors and landings and lightly loaded foundation but not enough to cause damage to heavier structures. Accordingly, it is paramount to provide proper drainage to limit the potential for water infiltrating under slabs. A minimum slope of at least 5 percent for a distance of 10 feet is recommended for unpaved landscaped areas.

Typical recommendations to reduce the swell potential (not eliminate) include reducing the

compaction requirements, requiring higher moisture contents during pad preparation. It is also recommended to provide a 12 inch pad cap of non-expansive material to be placed directly beneath the building slabs and equipment pads.

For standard foundations to perform as expected, attention must be paid to provide proper

drainage to limit the potential for water infiltration of deeper soils. The slope may be reduced to 2 percent provide extra care is taken to ensure landings and other hardscape features do not create a “dam” that prevents positive drainage away from the buildings that creates a "pond" adjacent to the building. Roof drainage should also be directed away from the building in paved scuppers. Pre-cast loose splash blocks should not be used as they can be dislodged and/or eroded. Roof drains should not be allowed to discharge adjacent to the structure. It is preferred that they be directed to discharge to pavement (per photo example), retention basins or discharge points located at least 10 feet away from the building.

It is reiterated that shallow spread footings are recommended for

the exterior walls and other light interior columns since this is the most economical system available. However, this shallow system relies on the dry strength of the unsaturated native soils. A limited depth of re-compaction is optionally recommended to increase density of the near surface soils that are more likely to encounter seasonal moisture changes. The deeper native soils are moisture sensitive and could experience differential settlement if subjected to significant surface water infiltration. Recognizing the need to minimize significant water penetration adjacent to the building perimeter that could detrimentally impact the building foundation, the following additional recommendations are made to protect foundations:

Page 7: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 5

1. Take extra precaution to backfill and compact native soil fill to 95 percent in all exterior wall locations.

2. Avoid utility trenches passing through retention basins leading to structures. If unavoidable, backfill the trench with MAG Section 728 ½-sack CLSM to cut off preferred drainage paths.

3. Create and maintain positive drainage away from the exterior wall for a minimum of 10 feet. 4. Avoid sidewalks, curbs or other elements that create a dam that could cause water to pond within 5

feet of the perimeter wall. Excavation operations should be relatively straightforward using conventional equipment,

although loose backfill soils may be encountered requiring special excavation techniques. Depending on proximity of excavations to existing infrastructure, shoring may be required. Groundwater is not expected to be a factor in the design or construction of foundations and underground utilities.

For exterior slabs on grade, frequent jointing is recommended to control cracking and reduce

tripping hazards should differential movement occur. It is also recommended to pin the landing slab to the building floor/stem wall. This will reduce the potential for the exterior slab lifting and blocking the operation of outswinging doors. Pinning typically consists of 24-inch long No. 4 reinforcing steel dowels placed at 12-inch centers.

3.2 Site Preparation

The entire area to be occupied by the proposed construction should be stripped of all vegetation, debris, rubble and obviously loose surface soils. Existing concrete structures should be removed along with soil disturbed by their removal. The upper 18 inches of the proposed office pad should be over-excavated to aid in location of buried hazards and to facilitate the placement of 12 inches of non-expansive pad fill below the office slab. Conventional footings may bear on dense native soils. Loose soils (if encountered at bearing depth should be over-excavated 2 feet (minimum) and replaced with engineered fill or slurry backfill (CLSM per MAG specification section 728).

For the proposed biofilter, we recommend utilizing the existing below grade walls (where

feasible) to minimize the amount of shoring required for excavation. It may be possible to use soil nails to stabilize the existing walls if working space permits and they do not encroach on existing buried infrastructure or adjacent property. Permission will be required from adjacent property owners if soil nails encroach their property. Some pavement may need to be removed to make way for the proposed improvements.

We understand that the valve pit will be abandoned in place and backfilled with aggregate

base. Moisture conditioning and backfill placement should be done in accordance with the requirements of

Page 8: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 6

the section ‘Fill and Backfill’. In addition, we recommend that the bottom slab be perforated to facilitate drainage and mitigate the potential accumulation of infiltration water in the backfill.

A representative of the geotechnical engineer should examine the subgrade once sub-

excavation is complete and prior to backfilling to ensure removal of deleterious materials. Fill placement and quality should be as defined in the "Fill and Backfill" section of this report.

Prior to placing structural fill below footing bottom elevation, the exposed grade should be

scarified to a depth of 8 inches, moisture conditioned to optimum (±2 percent) and compacted to at least 95 percent of maximum dry density as determined by ASTM D-698. Pavement areas should be scarified, moisture- conditioned and compacted in a similar manner.

All cut areas and areas above footing bottom elevation that are to receive floor slab only fill

should be scarified 8 inches, moisture conditioned to at least optimum to 3 percent above optimum and compacted to at least 95 percent of maximum dry density as determined by ASTM D-698.

3.3 Excavation and Temporary Cut Slopes

Care should be taken during excavation not to endanger nearby existing structures, CMU walls, roadways, utilities, etc. Depending on proximity, existing structures (including utilities) may require shoring, bracing or underpinning to provide structural stability and protect personnel working in the excavation.

All excavations must comply with current governmental regulations including the current OSHA Excavation and Trench Safety Standards. Preliminary indications are that the upper fine-grained soils would be classified as Type C. Side slopes for open-cut excavation should be cut back at 1½:1 (horizontal to vertical). The slopes should be protected from erosion due to run-off or long term surcharge at the slope crest. Construction equipment, building materials, excavated soil and vehicular traffic should not be allowed within 10 feet or one-third the slope height, whichever is greater, from the top of slope. All cut slopes should be observed by the Soils Engineer or contractors qualified person during excavation. Adjustments to the recommended slopes may be necessary due to wet zones, loose strata and other conditions not observed in the borings. Localized shoring may also be required. Shotcrete or soil stabilizer on the slope face may be useful in preventing erosion due to run-off and/or drying of the slope. Shotcrete protection is recommended for slopes that will remain open for extended periods of time (more than a week). Provision should be made for drainage (such as weep holes) to mitigate potential build-up of hydrostatic pressure below the shotcrete. If seepage from the slopes is encountered during construction, Speedie should be notified so that these recommendations can be reviewed.

Page 9: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 7

3.4 Shoring

Portions of cuts may encroach on adjacent pavement and/or structures. In areas where open-cut excavation is not feasible, consideration must be given to a shoring system. A standard system made up of steel soldier piles, lagging and tiebacks (or interior bracing), depending on depth and loading, is one option. This system typically requires pre-drilling and installing heavy steel shoulder beams spaced on 8 to 10 foot centers and backfilled with lean grout. As the excavation progresses, wood lagging can be installed and tieback anchors installed and tensioned. Cantilever systems may not be possible in the deeper cut areas. For the relatively short periods of time required to install lagging and tiebacks, excavations should stand at vertical. Sloughing soils may be encountered and require special procedures. For preliminary design of braced temporary shoring systems, we recommend the following conservative pressure diagram.

H=Depth of Excavation γ=Unit Wet Soil Weight=100 pcf

If shoring is required, it may be incorporated into the below-grade wall system

whether the wall is cast-in-place or constructed of gunite in top down construction.

Locally, excavations have been braced using the Soil Nail technology. Several firms have experience in the immediate area. This system generally consists of excavating the cut face in increments on the order of 5 feet, installing passive tie back soil nails (anchors) and constructing a reinforced concrete (Shotcrete) face. Consideration may be given to using this system due to the local success, speed of installation and apparent economical cost. Due to the granular nature of the soil in some locations, this technology may not be efficient. Specialized contractors should make their own evaluations. Tiebacks installations are expected to encroach on other private/public property. The owner and/or contractor will have to obtain permission as required prior to tieback installation. In addition there is a potential for the installations to encroach on existing plant utilities, therefore it is recommended if Soil Nails are used that a preconstruction survey be conducted (potholing) to accurately locate any utilities in the area.

3.5 Foundation Design

If site preparation is carried out as set forth herein, the following bearing capacities can be utilized for design.

Page 10: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 8

Table 3.5.1 Foundation Bearing Capacities

Structure Foundation

Type Foundation

Depth (1) Bearing Medium

Bearing Capacity

Comments

Screen Walls & Equipment Pads

Spread 1.5ft. Compacted Subgrade

1,500 psf 2 Mat 0.5 ft. k=100 pci 3

Office Structure at Grade

Spread 2.0 ft. Dense native soil or 2 feet of engineered fill

2,500 psf 4

Helical Piers See notes Dense native soils See notes 5

Below Grade Structures

Spread 10.0 ft. Dense Native

4,000 psf 6 Mat 10.0 ft. k=200 pci 7

Comments: 1. Foundation depth refers to the minimum depth to bottom of foundation. 2. For minor structures such as screen walls, planter walls, equipment pads, etc. not connected to any

main structure. To minimize potential settlement, the bottom of footing excavation should be compacted to 95 percent of standard proctor.

3. For a structural mat foundations a subgrade modulus k=100 pci can be used for design bearing on compacted subgrade or engineered fill (depending on grading plans). To minimize potential settlement, the bottom of mat excavation should be compacted to 95 percent of standard proctor.

4. Shallow spread footings bearing on undisturbed native soils. If loose soils are encountered at depth, they must be removed and replaced with engineered fill or slurry fill (2-sack). Alternatively, if deep loose backfill soils are encountered helical piers may be required (see below)

5. Foundation Support Works™ round bar or Chance® square bar system or approved equal advanced down to contact dense native soil. Depending on device used, these will support 20 to 40 kips allowable load capacity per device. These can be incorporated into a structural mat or grade beam to provide lateral support using passive pressure. The contractors can select the optimum system to meet project needs.

6. Spread footings bearing on undisturbed native soils. If loose soils are encountered at depth, they must be removed and replaced with slurry fill (2-sack). Placement of fill for inadvertent over-excavation of below-grade foundations is not allowed. Slurry backfill must be used.

7. For below grade mat or structural slabs a subgrade modulus of 200 pci can be used for design. If loose soils are encountered at depth, they must be removed and replaced with slurry fill (2-sack). Placement of fill for inadvertent over-excavation of below-grade foundations is not allowed. Slurry backfill must be used.

Page 11: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 9

These bearing capacities refer to the total of all loads, dead and live, and are net pressures. They may be increased one-third for wind, seismic or other loads of short duration. These values may be increased by one-third as the allowable toe pressure for retaining walls. All footing excavations should be level and cleaned of all loose or disturbed materials. Positive drainage away from the proposed buildings must be maintained at all times.

Continuous wall footings and isolated rectangular footings should be designed with minimum

widths of 16 and 24 inches respectively, regardless of the resultant bearing pressure. Lightly loaded interior partitions (less than 800 plf) may be supported on reinforced thickened slab sections (minimum 12 inches of bearing width).

Estimated settlements under design loads are on the order of 0.5 to 1-inches, virtually all of

which will occur during construction. Post-construction differential settlements will be on the order of one-half total settlement, under existing and compacted moisture contents. Additional localized settlements or heave, of the same magnitude (or greater if water is allowed to saturate soils at depth) could occur if native supporting soils were to experience a significant increase in moisture content. Positive drainage away from structures, and controlled routing of roof runoff should be provided to prevent ponding adjacent to perimeter walls. Care should be taken in design and construction to insure that domestic and interior storm drain water is contained to prevent seepage.

Continuous footings and stem walls should be reinforced to distribute stresses arising from

small differential movements, and long walls should be provided with control joints to accommodate these movements. Reinforcement and control joints are suggested to allow slight movement and prevent minor floor slab cracking.

3.6 Lateral Pressures

The following equivalent fluid lateral pressure values may be utilized for the proposed construction:

Active Pressures Unrestrained Walls 35 pcf Restrained Walls 60 pcf Passive Pressures

Continuous Footings 300 pcf Spread Footings or Drilled Piers 350 pcf Coefficient of Friction (w/ passive pressure) 0.35 Coefficient of Friction (w/out passive pressure) 0.45

Page 12: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 10

All backfill must be compacted to not less than 95 percent (ASTM D-698) to mobilize these passive values at low strain. Expansive soils should not be used as retaining wall backfill, except as a surface seal to limit infiltration of storm/irrigation water. The expansive pressures could greatly increase active pressures.

3.7 Fill and Backfill

Native soils are considered suitable for use in general grading and engineered structural fill below foundations but should not be used in the top 12-inches of conventional building slab pad fill, contiguous sidewalks, or as retaining wall backfill. The top 12-inches of pad fill should be completed with an approved low or non-expansive soil, either approved imported common borrow or select granular soil. If select granular soil (AB) is used, the 4 inches of under-slab aggregate base may be included as part of the top 12-inches. Otherwise, 12-inches of approved common borrow should be used in addition to the normal 4 inches of aggregate base.

Successful backfill of below-grade walls can be difficult to achieve given the sometimes tight

access. That is why well-graded granular import should be specified for backfill of below grade walls. Placement and compaction must be carefully controlled in order to minimize the potential for post construction settlement should the backfill zone be subjected to water infiltration. Even the most well controlled fills could experience additional settlement on the order of 1 inch (1-inch per 10 feet of fill) if subjected to significant moisture increases. Using the native soils may increase settlement potential. This will impact anything supported on this fill. Accordingly, it is recommended to design and construct a structural slab over the backfill zone in the most critical areas such as interior slabs, pipe header supports or reinforce and pin the landing/entry slabs to the building stem wall to span over the backfill zone. This will reduce the potential for the exterior slab dropping and creating a tripping hazard. Critical areas can be considered to include not only concrete walkways and slabs, but also concrete and asphaltic concrete paving. Paving over wall backfill zones should be detailed to minimize the effects of backfill settlement. Utility lines (especially gravity sewer lines), except for building service connections, should be avoided in this zone.

If imported common fill for use in site grading is required, it should be examined by a Soils

Engineer to ensure that it is of low swell potential and free of organic or otherwise deleterious material. In general, the low or non-expansive fill should have 100 percent passing the 3-inch sieve and no more than 60 percent passing the 200 sieve. For the fine fraction (passing the 40 sieve), the liquid limit and plasticity index should not exceed 30 percent and 10 percent, respectively. It should exhibit less than 1.5 percent swell potential when compacted to 95 percent of maximum dry density (ASTM D-698) at a moisture content of 2 percent below optimum, confined under a 100 psf surcharge, and inundated. Select granular soil should have

Page 13: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 11

100 percent passing the 3-inch sieve, no more than 15 percent passing the 200 sieve and the plasticity index should not exceed 5 percent.

Fill should be placed on subgrade which has been properly prepared and approved by a Soils

Engineer. Fill must be wetted and thoroughly mixed to achieve optimum moisture content, ±2 percent (optimum to 3 percent above optimum for under slab fill). Fill should be placed in horizontal lifts of 8-inch thickness (or as dictated by compaction equipment) and compacted to the percent of maximum dry density per ASTM D-698 set forth as follows:

A. Building Areas 1. Below footing level (at grade structures) 95 2. Below slabs-on-grade (non-expansive soils) 95 3. Below slabs-on-grade (expansive soils) 90-95 (max) (Not recommended in top 12 inches of pad) B. Pavement Subgrade or Fill 95 C. Utility Trench Backfill (onsite) 95 D. Valve Pit ABC backfill 97 E. Aggregate Base Course

1. Below floor slabs 95 2. Below asphalt paving 100

F. Landscape Areas 90

3.8 Utilities Installation Trench excavations for utilities can be accomplished by conventional trenching equipment.

Trench walls should stand near-vertical for the short periods of time required to install shallow utilities although some sloughing may occur in looser and/or sandier soils requiring laying back of side slopes and/or temporary shoring. Adequate precautions must be taken to protect workmen in accordance with all current governmental regulations.

Backfill of trenches may be carried out with native excavated material. This material should

be moisture-conditioned, placed in 8-inch lifts and mechanically compacted. Water settling is not recommended. Compaction requirements are summarized in the "Fill and Backfill" section of this report.

Page 14: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 12

3.9 Slabs-on-Grade To facilitate fine grading operations and aid in concrete curing, a 4-inch thick layer of

granular material conforming to the gradation for aggregate base (A.B.) as per M.A.G. Specification Section 702 should be utilized beneath the slab. Dried subgrade soils must be re-moistened prior to placing the aggregate base if allowed to dry out, especially if fine-grained soils are used in the top 12-inches of the pad.

The native soils are capable of storing a significant amount of moisture, which could increase

the natural vapor drive through the slab. Accordingly, if moisture sensitive flooring and/or adhesive are planned, the use of a vapor barrier or low permeability concrete should be considered. Vapor barriers should be a minimum 15-mil thick polyolefin (or equivalent), which meets ASTM E 1745 Class A specifications. Vapor barriers do increase the potential for slab curling and water entrapment under the slab. Accordingly, if a vapor barrier is used, additional precautions such as low slump concrete, frequent jointing and proper curing will be required to reduce curling potential and detailed to prevent the entrapment of outside water sources.

3.10 Asphalt Pavement If earthwork in paved areas is carried out to finish subgrade elevation as set forth herein, the

subgrade will provide adequate support for pavements. The location designation is for reference only. The designer/owner should choose the appropriate sections to meet the anticipated traffic volume and life expectancy. The section capacity is reported as daily ESALs, Equivalent 18 kip Single Axle Loads. Typical heavy trucks impart 1.0 to 2.5 ESALs per truck depending on load. It takes approximately 1,200 passenger cars to impart 1 ESAL.

Table 3.10.1 Pavement Sections

Area of Placement Daily 18-kip ESALs Flexible Rigid

AC PCCP AC (0.39) ABC (0.12) PCCP

Auto Parking/Drives 2 7 2.0” 6.0” 5.0”

Truck Parking/Drives 8 12 3.0” 6.0” 5.5” 16 18 3.0” 8.0” 6.0”

Notes: 1. Designs are based on AASHTO design equations and ADOT correlated R-values. 2. The PCCP thickness is increased to provide better load transfer, and reduce potential for joint and

edge failures. Design PCCP per ACI 330R-87. 3. Full depth asphalt or increased asphalt thickness can be increased by adding 1.0 inch of asphalt for

each 3 inches of base course replaced.

Page 15: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 13

Pavement Design Parameters: Assume: One 18 kip Equivalent Single Axle Load (ESAL)/Truck Life: 20 years Subgrade Soil Profile:

% Passing #200 sieve: 65% Plasticity Index: 21 k: 100 pci (assumed) R value: 18 (per ADOT tables) MR: 11,000 (per AASHTO design)

These designs assume that all subgrades are prepared in accordance with the

recommendations contained in the "Site Preparation" and "Fill and Backfill" sections of this report, and paving operations carried out in a proper manner. If pavement subgrade preparation is not carried out immediately prior to paving, the entire area should be proof-rolled at that time with a heavy pneumatic-tired roller to identify locally unstable areas for repair.

Pavement base course material should be aggregate base per M.A.G. Section 702

Specifications. Asphalt concrete materials and mix design should conform to M.A.G. 710 using the Marshall Mix design criteria for high volume traffic. It is recommended that a ½-inch or ¾-inch mix designation be used for the pavements. While a ¾-inch mix may have a somewhat rougher texture, it offers more stability and resistance to scuffing, particularly in turning areas. Pavement installation should be carried out under applicable portions of M.A.G. Section 321 and municipality standards. The asphalt supplier should be informed of the pavement use and be required to provide a mix that will provide stability and be aesthetically acceptable. Some of the newer M.A.G. mixes are very coarse and could cause placing and finish problems. A mix design should be submitted for review to determine if it will be acceptable for the intended use.

For landings not subjective to vehicular traffic a 4-inch section of concrete will be sufficient.

For trash and dumpster enclosures a thicker section of 6 inches of concrete is recommended. Portland Cement Concrete Pavement must have a minimum 28-day flexural strength 550 psi

(compressive strength of approximately 3,700 psi). While it may be cast directly on the prepared subgrade with proper compaction (reduced) and the elevated moisture content as recommended in the report, it is recommended to provide a nominal 4-inch AB sub-base to aid in fine grading. Attention must be paid to using low slump concrete and proper curing, especially on the thinner sections. No reinforcing is necessary. Joint design and spacing should be in accordance with ACI recommendations. Construction joints should

Page 16: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 14

contain dowels or be tongue-and-grooved to provide load transfer. Tie bars are recommended on the joints adjacent to unsupported edges. Maximum joint spacing in feet should not exceed 2 to 3 times the thickness in inches. Joint sealing with a quality silicone sealer is recommended to prevent water from entering the subgrade allowing pumping and loss of support.

Proper subgrade preparation and joint sealing will reduce (but not eliminate) the potential for

slab movements (thus cracking) on the expansive native soils. Frequent jointing will reduce uncontrolled cracking and increase the efficiency of aggregate interlock joint transfer.

3.11 Corrosion

Laboratory testing of the native soil concluded a pH of 7.8 and a laboratory minimum resistivity of 660 ohm-cm. Chloride concentrations were on the order of 173 ppm. These results indicate a severe degree of corrosivity to direct buried metal. Accordingly, suitable pipe wall thickness and corrosion protection should be selected per the lifetime requirements of the project. Soluble sulfate concentrations were recorded to be 15 ppm. This indicates a negligible to mild degree of sulfate attack. Subsurface concrete should use Type I or II cement, which is readily available and used in the area.

4.0 GENERAL The scope of this investigation and report includes only regional published considerations for seismic

activity and ground fissures resulting from subsidence due to groundwater withdrawal, not any site specific studies. The scope does not include any considerations of hazardous releases or toxic contamination of any type.

Our analysis of data and the recommendations presented herein are based on the assumption that soil

conditions do not vary significantly from those found at specific sample locations. Our work has been performed in accordance with generally accepted engineering principles and practice; this warranty is in lieu of all other warranties expressed or implied.

Page 17: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 18: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 19: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

FIELD AND LABORATORY INVESTIGATION

On June 22, 2016 soil test borings were drilled at the approximate locations shown on the attached Soil Boring Location Plan. All exploration work was carried out under the full-time supervision of our staff engineer, who recorded subsurface conditions and obtained samples for laboratory testing. The soil borings were advanced with a truck-mounted CME-75 drill rig utilizing 7-inch diameter hollow stem flight augers. Detailed information regarding the borings and samples obtained can be found on an individual Log of Test Boring prepared for each drilling location.

Laboratory testing consisted of moisture content, dry density, grain-size distribution and plasticity

(Atterberg Limits) tests for classification and pavement design parameters. Remolded swell tests were performed on samples compacted to densities and moisture contents expected during construction. Compression tests were performed on a selected ring sample in order to estimate settlements and determine effects of inundation. All field and laboratory data is presented in this appendix.

Page 20: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 21: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation

SW

PEAT, HUMUS, SWAMP SOILS WITHHIGH ORGANIC CONTENTS

GRAVELS WITHFINES

(LITTLE OR NO FINES)

CLEANGRAVELS

HIGHLY ORGANIC SOILS

SILTSAND

CLAYS

SILTSAND

CLAYS

MORE THAN 50% OFCOARSE FRACTIONPASSING ON NO. 4SIEVE

SANDAND

SANDYSOILS

MORE THAN 50% OFCOARSE FRACTIONRETAINED ON NO. 4SIEVE

GRAVELAND

GRAVELLYSOILS

MORE THAN 50% OFMATERIAL ISSMALLER THAN NO.200 SIEVE SIZE

FINEGRAINED

SOILS

MAJOR DIVISIONS

LIQUID LIMITGREATER THAN 50

LIQUID LIMITLESS THAN 50

(APPRECIABLE AMOUNTOF FINES)

SANDS WITHFINES

MH

OL

CL

ML

SC

SM

SP

WELL-GRADED GRAVELS, GRAVEL -SAND MIXTURES, LITTLE OR NO FINES

TYPICALLETTERGRAPH

SYMBOLS

ORGANIC CLAYS OF MEDIUM TO HIGHPLASTICITY, ORGANIC SILTS

INORGANIC CLAYS OF HIGHPLASTICITY

(LITTLE OR NO FINES)

CLEAN SANDS

(APPRECIABLE AMOUNTOF FINES)

MORE THAN 50% OFMATERIAL ISLARGER THAN NO.200 SIEVE SIZE

COARSEGRAINED

SOILS

INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS FINE SAND OR SILTYSOILS

ORGANIC SILTS AND ORGANIC SILTYCLAYS OF LOW PLASTICITY

INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS,LEAN CLAYS

INORGANIC SILTS AND VERY FINESANDS, ROCK FLOUR, SILTY ORCLAYEY FINE SANDS OR CLAYEYSILTS WITH SLIGHT PLASTICITY

CLAYEY SANDS, SAND - CLAYMIXTURES

SILTY SANDS, SAND - SILT MIXTURES

POORLY-GRADED SANDS, GRAVELLYSAND, LITTLE OR NO FINES

WELL-GRADED SANDS, GRAVELLYSANDS, LITTLE OR NO FINES

CLAYEY GRAVELS, GRAVEL - SAND -CLAY MIXTURES

SILTY GRAVELS, GRAVEL - SAND -SILT MIXTURES

POORLY-GRADED GRAVELS, GRAVEL- SAND MIXTURES, LITTLE OR NOFINES

PT

OH

CH

GC

GM

GP

GW

DESCRIPTIONS

NOTE: DUAL OR MODIFIED SYMBOLS MAY BE USED TO INDICATE BORDERLINE SOILCLASSIFICATIONS OR TO PROVIDE A BETTER GRAPHICAL PRESENTATION OF THE SOIL

Very SoftSoftFirmStiff

Very StiffHard

0 - 22 - 45 - 8

9 - 1516 - 30

> 30

0 - 0.250.25 - 0.50.5 - 1.0

1 - 22 - 4> 4

Very LooseLoose

Medium DenseDense

Very Dense

0 - 45 - 10

11 - 3031 - 50

> 50

Clays & Silts Blows/Foot Strength (tons/sq ft) Sands & Gravels Blows/Foot

CONSISTENCY RELATIVE DENSITY

0.0750.4202.000

4.7519

75

300

0.422.004.75

1975

300

900

#200#40#10

#40.75"

#40#10#4

0.75"3"

3"

12"

12"

36"

mmmmLower Limit Upper Limit

PARTICLE SIZEMATERIAL

SIZE

SANDSFine

MediumCoarse

GRAVELSFine

Coarse

COBBLES

BOULDERS

Sieve Size Sieve Size

U.S. Standard Clear Square Openings

50

60

00

10

80 100Liquid Limit

30

40

CL-ML

CL

20

20 40 60

CH

B-Line

A-Line

ML & OL

MH & OH

Plasticity Index

A grab sample taken directly from auger flights.

A grab sample taken from auger spoils or from bucket of backhoe.

Standard Penetration Test (ASTM D-1586) Driving a 2.0 inch outside diameter splitspoon sampler into undisturbed soil for three successive 6-inch increments bymeans of a 140 lb. weight free falling through a distance of 30 inches. Thecumulative number of blows for the final 12 inches of penetration is the StandardPenetration Resistance.

Driving a 3.0 inch outside diameter spoon equipped with a series of 2.42-inch insidediameter, 1-inch long brass rings, into undisturbed soil for one 12-inch increment bythe same means of the Spoon Sample. The blows required for the 12 inches ofpenetration are recorded.

Standard Penetration Test driving a 2.0-inch outside diameter split spoon equippedwith two 3-inch long, 3/8-inch inside diameter brass liners, separated by a 1-inchlong spacer, into undisturbed soil by the same means of the Spoon Sample.

A 3.0-inch outside diameter thin-walled tube continuously pushed into theundisturbed soil by a rapid motion, without impact or twisting (ASTM D-1587).

Driving a 2.0-inch outside diameter "Bullnose Penetrometer" continuously intoundisturbed soil by the same means of the spoon sample. The blows for eachsuccessive 12-inch increment are recorded.

DESCRIPTION

Auger SampleAS

BS Large Bulk Sample

S Spoon Sample

RS Ring Sample

LS Liner Sample

ST Shelby Tube

ContinuousPenetrationResistance

--

DESIGNATIONSAMPLE

SOIL LEGEND

Page 22: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 23: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 24: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 25: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 26: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation
Page 27: Project No. 161073SA...Geotechnical Investigation Project No. 161073SA Lift Station #47 November 2, 2016 – Page 1 1.0 INTRODUCTION This report presents the results of a subsoil investigation