![Page 1: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/1.jpg)
1
Kigali on 06/02/2017
Ref: N° 11.07.023/2829/17/MD-EDCL/EK/uc
REQUEST FOR EXPRESSIONS OF INTEREST “INDIVIDUAL CONSULTANT”
( Re- advertised)
Project Name: ‘‘Improving Access to Reliable On-grid Electricity Service for Households and Priority
Public institutions –Belgian contribution to EARP’’; Project No: RWA1509411
Title of Tender: Supervision consulting services for installation and commissioning of
93MVA 220/110kV transformer at SHANGO Substation
REFERENCE NO003/S/2016/REOI/BEEARP
The Government of Rwanda has received financing from the Belgian Kingdom toward the cost
of the ‘‘Improving Access to Reliable On-grid Electricity Service for Households and
Priority Public Institutions –Belgian contribution to EARP”(BE2 EARP) and intends to
apply part of the proceeds for consulting services.
The Energy Development Corporation Limited (EDCL)/BE2 EARP invite eligible individual
consultant to express their interest in providing the Services. Interested Consultants should
provide information demonstrating that they have the required qualifications and relevant
experience to perform the Services.
The Scope of consultancy service and qualification criteria are specified in the terms of
references (TOR) below.
The consultant will be selected in accordance with the Rwanda Law N° 05/2013 of
13/02/2013 modifying and completing the law N° 12/2007 of 27/03/2007 on Public
Procurement.
The procuring entity will select the consultant as follow:
First stage: At least three consultant will be shortlisted on the basis of their
detailed CVs; qualifications for the assignment and at least two similar project
executed (academic background and relevant specific experience).
![Page 2: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/2.jpg)
2
Individuals consultant considered for comparison of qualifications shall meet the minimum
relevant qualifications.
Second stage the first ranked three consultants will be invited for presentation or
interviews.
The Procuring Entity shall negotiate a contract with the first ranked individual consultant,
after reaching agreement on satisfactory terms and conditions of the contract. Only experts
that submitted EOIs shall be shortlisted.
Time: The contract duration will be 12 months.
Further information can be obtained at the address below during office hours from 08:00am to
17:00pm:
Energy Development Corporation Limited (EDCL)
Electricity Access Roll-out Program (EARP)
Attn: Head of Procurement of EDCL,
E-mail: [email protected] and copy to [email protected], Tel. No.:
+250788466130;
3. Application and Submission
Interested and suitably qualified candidates should submit their Expression of Interest
including the following documents:
Letter of expression of interest to the Assignment signed by himself
Detailed Curriculum vitae ( CV) signed
Copy of degrees and certificates
Certificate of good performance of similar assignments (at least two assignment
executed in the last 5 years)
All applications should be submitted by Email to the above email addresses or hard copy in a
written form to the address below on 02/ March /2017
Energy Development Corporation Limited ( EDCL)
KN2 ST, Nyarugenge District, Kigali City, PO Box 3855 Kigali, Rwanda, KCT: 10th floor.
Done at Kigali, on 06/ February/2017
RUHIGULA Jackson GAFULEKA Emmanuel KAMANZI
Head of Procurement Managing Director
![Page 3: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/3.jpg)
3
Terms of References of Supervision consulting services for installation and commissioning
of 93MVA 220/110kV transformer at SHANGO Substation
(Individual consultant).
![Page 4: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/4.jpg)
4
TABLE OF CONTENTS
Page
1.0 INTRODUCTION .............................................................................................................................. 5
2.0 PROJECT CONCEPT AND AREA .................................................................................................. 5
3.0 PROJECT OBJECTIVE .................................................................................................................... 5
4.0 PROJECT DESCRIPTION ............................................................................................................... 5
5.0 PROJECT FINANCING .................................................................................................................... 5
6.0 PROCUREMENT OF GOODS ......................................................................................................... 5
7.0 STATUS OF THE PROJECT ............................................................................................................ 6
8.0 OBJECTIVE OF THE CONSULTANCY SERVICES ..................................................................... 6
9 SCOPE OF THE CONSULTANCY SERVICES .................................................................................. 6
9.0 GENERAL ............................................................................................................................................... 6
9.1 PAYMENT CERTIFICATION ......................................................................................................... 7
9.2 SITE MEETINGS .............................................................................................................................. 7
9.3 KNOWLEDGE TRANSFER AND TRAINING OF THE EMPLOYER’S STAFF ......................... 8
9.4 ASSISTANCE DURING THE DEFECT LIABILITY PERIOD ...................................................... 8
10 REPORTS .............................................................................................................................................. 8
10.1 GENERAL ............................................................................................................................................. 8
10.2 PROGRESS REPORTS ........................................................................................................................ 8
10.3 PROJECT COMPLETION REPORT (PCR) ....................................................................................... 9
11 CONSULTANT, QUALIFICATION REQUIREMENTS AND MAN-MONTHS ALLOCATION ..... 9
11.1 Qualification and Experience ....................................................................................................... 9
11.2 Shortlisting criteria .................................................................................................................... 10
12 DATA, LOCAL SERVICES AND FACILITIES TO BE PROVIDED ............................................... 10
13. TERMS OF PAYMENT OF FEES( LUMPSUM CONTRACT) ........................................................... 11
14. IMPLEMENTATION SCHEDULE FOR SERVICES AND INDICATIVE CALENDAR ............ 11
![Page 5: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/5.jpg)
- 5 -
Terms of References of Supervision consulting services for installation and commissioning
of 93MVA 220/110kV transformer at SHANGO SUBSTATION( Individual consultant).
1.0 INTRODUCTION
SHANGO substation is a substation under construction and it is located at around 25 km from
the main round about in the Northern part of Kigali City, in the Republic of Rwanda.
2.0 PROJECT CONCEPT AND AREA
Shango substation is a transmission substation where 2x220kV lines from Uganda, 2x220kV
lines from the Eastern part of Democratic Republic of Congo (DRC) and 2x220kV from
Regional Rusumo Hydropower plant meet. A 2x110kV line from the substation will supply
Kigali City Distribution. A 220/110kV 93MVA transformer for Kigali City Distribution and a
220/30kV 30MVA for local use are already installed. However, there is a need of the second
220/110kV 93MVA transformer.
3.0 PROJECT OBJECTIVE
Project objectives are to:
(i) Increase the distribution capacity of the substation and
(ii) The reliability of the network.
4.0 PROJECT DESCRIPTION
The Project is managed by Energy Development Corporation Ltd (EDCL), a subsidiary of
Rwanda Energy Group Limited (REG).
The Project has only one component: Construction of 220/110kV 93MVA transformer. This
component includes supply, installation and commissioning of the transformer including its
accessories (transformers bays, etc).
A consultant will be hired for engineering and Installation supervision for 220/110kV
93MVA transformer.
5.0 PROJECT FINANCING
The republic of Rwanda has received a Grant from the Kingdom of Belgium. The
Government of Rwanda intends to use part of these funds to recruit a Contractor for supply,
installation and commissioning of a 93MVA transformer at SHANGO substation.
6.0 PROCUREMENT OF GOODS
The procurement of goods will be done using the Procurement Law of the Republic of
Rwanda. The tender will be one Lot.
![Page 6: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/6.jpg)
- 6 -
7.0 STATUS OF THE PROJECT
Currently, SHANGO substation is under construction and the works are advanced at 75%.
8.0 OBJECTIVE OF THE CONSULTANCY SERVICES
The general objective of the consultancy services is to ensure that EDCL obtains an economic
solution of high technical standards and that the project is implemented in a timely and
efficient manner.
9 SCOPE OF THE CONSULTANCY SERVICES
9.0 GENERAL
In general, the scope of consultancy services shall include, but not limited to:
(a) Assist EDCL with technical expertise during the procurement process for the
transformer, analyze and prepare the responses to the inquires from the bidders in
consultation with EDCL;
(b) Supervision of the implementation of the contract for the Project and establishment of
a Project Site Organization for the contract as specified below:
i) Examination and approval of the Contractor detailed design documents
and drawings for compliance with the specifications in accordance with sound
engineering practice;
ii) Supervision of all transformer installation activities and ensure that the
works are done in compliance with the contract plans and specifications with
regards to both quality and timing,
iii) Inspecting and witnessing with EDCL representatives the factory
acceptance tests (FAT) during the manufacture of major items of equipment
and at the manufacturers’ premises;
iv) Verify in collaboration with EDCL, if the material and equipment
delivered at field sites correspond to the technical specifications.
v) Supervise and approve the testing and commissioning of transformer
installation works.
vi) Check and approval of complete set of “As-Built” drawings, and
documentation; and hand over formalities to EDCL
vii) Approval of the Contractor’s human resources and occupational health and
safety policy.
(c) General assistance for administration of the Project including: -
i) Acting for EDCL for all contract notices, instructions, orders, certificates,
approvals and all communications under the contract (generally referred to as
contract administration) for the contract and liaison with the contractor
ii) advise on any dispute or differences that may arise between EDCL and the
Contractor
![Page 7: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/7.jpg)
- 7 -
iii) Any change (variation) orders, completion time extension and/or financial
claims arising from the contractor, requires the approval of EDCL after a deep
assessment and recommendations to EDCL based on the day-to-day records and
applicable conditions of contract.
iv) Establishment of contract billing procedures, verification and certification
of all contractor billing before submission to EDCL for issue of authorization of
payment,
v) In consultation with EDCL, issue completion certificates and final
acceptance certificates to contractor as per the terms and conditions of the
contract,
vi) Preparation of monthly and quarterly project progress reports as required
by EDCL
(d) Provide on-the-job training and technology transfer to the staffs of EDCL in
contractor’s design approval, project management and supervision of installation
works;
(e) Monitor compliance by the Contractor during installation and commissioning for
applicable legal requirements of Rwanda.
(f) Prepare and submit the Project Completion Report that outlines, inter-alia,
achievements in meeting the objectives and target set out for EDCL under BTC
requirements.
9.1 PAYMENT CERTIFICATION
Check the quantities of work carried out and equipment/materials supplied and certify
contractor’s invoices. The contractor shall submit to the consultant, statement showing costs
of the work executed upto the end of the month. The form of the statement shall be in
accordance with standard format agreed by each EDCL and the contractor. All relevant
measurement sheets and quality schedules shall be submitted together with the statement. The
consultant shall compare the statement with his own records and solve issues of differences
with the contractor's representative. The updated master copies of progress charts shall be
submitted to EDCL along with the monthly statement, the time table progress charts (with
planned and actual progress), the works diary, the monthly site financial statement, etc.
9.2 SITE MEETINGS
Consultant shall hold site meetings regularly as required with the contractors' site
representatives and EDCL.
Chair site meetings and draw up minutes of meetings,
The meeting shall deal with (i) approval or rejection of executed work elements;
contractor's work schedule, contractor's work method, temporary works and additional
works (if any), etc.
Minutes of the meeting shall be prepared and signed by the participating parties. Copies of the
minutes shall be given to the participants.
![Page 8: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/8.jpg)
- 8 -
9.3 KNOWLEDGE TRANSFER AND TRAINING OF THE EMPLOYER’S STAFF
EDCL consider this consultant services contract as an opportunity for knowledge transfer to a
number of its staff through on the job training working with the consultant and contractors.
Such training and knowledge transfer shall be conducted during both the stages of approval of
the contractor’s detailed design, as well as during the construction stages of the Project.
9.4 ASSISTANCE DURING THE DEFECT LIABILITY PERIOD
The consultant shall:
Ensure that all defects and remarks are properly cleared/removed by the
contractors,
Ensure that all operation and maintenance manuals and all type of as-built
drawings are submitted and handed over to EDCL as per the requirement and
quantity specified in the contracts.
At the end of the liability period, the consultant shall perform a one-week
assignment to EDCL to prepare final acceptance certificate and prepare a final
report on this basis.
10 REPORTS
10.1 GENERAL
All documents and reports must be done in English.
All reports shall be submitted in 3 copies to EDCL. Content of technical reports must be
discussed and agreed upon with EDCL.
10.2 PROGRESS REPORTS
The consultant shall prepare and submit a coordinated monthly and quarterly progress report
to EDCL. The quarterly progress reports shall be prepared in accordance with the BTC's
guidelines. The reports by contracts shall at least include.
i. Written description of:
Progress of the works and expenditure to-date;
Progress of the works during the month;
Future planned works and expenditure;
Summary of the prevailing weather conditions at site during the reporting
period.
Technical problems, if any;
Delays of any kind, if any
List of consultant's and contractor’s personnel
![Page 9: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/9.jpg)
- 9 -
List of machinery and equipment scheduled and made available of the works
by the contractors; and
Any other issues, which could facilitate or affect the progress of the work.
ii. Tabulated summary of work progress
iii. Graphical presentation of:
Physical progress planned/actual;
Cash flow planned/actual
Expected future progress and expenditure; and
Labor force size.
10.3 PROJECT COMPLETION REPORT (PCR)
Upon completion of the project construction activities, the consultant shall prepare a Project
Completion Report (PCR) for EDCL in accordance with BTC's PCR requirements. The PCR
will form a comprehensive record of the design, construction and erection works
accomplished including: -
i) A description of changes or modifications to the design;
ii) Problems encountered and solutions adopted; and
iii) Overall construction volume, quantities and costs
iv) Lesson learnt on Project design and implementation,
11 CONSULTANT, QUALIFICATION REQUIREMENTS AND MAN-MONTHS
ALLOCATION
11.1 Qualification and Experience
The consultant must be highly qualified for the design and supervision of installation of high
voltage power transformers. The consultant must demonstrate previous experience in the
supervision of installation of high voltage power transformer. More particularly, the
consultant must have, in the last 5 years:
2 similar experiences in the design and supervision of installation of high voltage
power transformer process.
Must be an engineer holder at least a bachelors degree in electrical or
electromechanical from a recognized university;
Having a minimum experience of:
Ten (8) years in the field of substations projects and should have an extensive
experience in management of power transmission project
![Page 10: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/10.jpg)
- 10 -
11.2 Shortlisting criteria
In accordance with Rwandan Public Procurement rules and regulations on selection of
Individual Consultants;
For the first stage at least three consultant will be shortlisted on the basis of
their detailed CVs; qualifications for the assignment and similar project executed (at
least two).
Individuals consultant considered for comparison of qualifications shall meet the minimum
relevant qualifications. The selection shall be carried out through the comparison of the
relevant overall capacity. Shortlisted candidates are ranked by their experiences and
qualifications. All shortlisted candidates must meet the eligibility criteria.
Only experts that submitted EOIs shall be shortlisted.
For the second stage the first three consultants ranked on the first stage will be
invited for presentation and interviews.
The EDCL will request the first ranked candidate for the second stage to confirm availability
and to provide financial proposal and other information that may be required for clarification.
The Procuring Entity shall negotiate a contract with the first ranked consultant after
presentation and interview, after reaching agreement on satisfactory terms and conditions of
the contract.
The interested consultant should present the following documents:
Letter of expression of interest to the Assignment signed by himself
Detailed Current Curriculum vitae signed
Copy of degrees and certificates
At least two Certificate of good performance of similar assignments
12 DATA, LOCAL SERVICES AND FACILITIES TO BE PROVIDED
The consultant shall supply all necessary equipment for a high quality performance of its
mandate.
All communication related costs made by the consultant (telephone, fax, courier, internet,
etc.) shall be covered by the consultant.
The consultant shall open an office in Kigali and all related costs shall be covered by the
consultancy fees.
EDCL will provide the following facilities to the consultant:
a) Access to the project area covered by this consultancy,
b) Access to relevant design documentation of existing transformer to the extent of
their availability;
c) Liaise with the government and facilitate all requirements/supports needed for the
![Page 11: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/11.jpg)
- 11 -
consultant duties.
13. Terms of payment of fees( Lumpsum contract)
The Consultant’s fees and the schedule of payment will follow the conditions and terms
contained in the contract signed between EDCL and the Consultant. Payment will be done in
euros and should be the same currency used by the consultant in his proposal.
Payment conditions Percentage of total
amount.
Review of the existing information/data and preparation of
the tender document, preparation of clarifications ,
evaluation, up to the signature of contract
10%
Approval of detailed design documents of the Contractor. 10%
Factory acceptance test, verify and approve if the material
and equipment delivered at field sites correspond to the
technical specifications.
10%
Completion of civil works by the Contractor 10%
Complete the installation works by the Contractor and
approve the testing and commissioning of transformer
installation works.
30%
Check and approval of complete set of “As-Built”
drawings, and documentation; and hand over formalities
to EDCL.
20%
EDCL Approval of the final report prepared by the
consultant.
10%
14. Implementation schedule for services and indicative calendar
The estimated duration of the project is 12 months.
Activities Period
Signing contract by consultant March
2017
Review of the tender document and preparation of clarifications requested by
bidder
March-
May 2017
Approval of detailed design documents of the contractor. August
2017
Verify and approve if the material and equipment delivered at field sites
correspond to the technical specifications.
January
2018
![Page 12: Project Name: ‘‘Improving Access to Reliable On-grid ... · PDF fileSHANGO substation is a substation under construction and it is located at around 25 km from the main round about](https://reader033.vdocuments.site/reader033/viewer/2022051719/5a7327f97f8b9aa2538e685d/html5/thumbnails/12.jpg)
- 12 -
Supervise and approve the testing and commissioning of transformer installation
works.
January –
March 2018
Check and approval of complete set of “As-Built” drawings, and documentation;
and hand over formalities to EDCL. April 2018