PROJECT MANAGEMENT PLAN
SR 109 Access Management Study
August 2014
Prepared for the Nashville Area
Metropolitan Planning Organization
SR 109 Access Management Study
iProject Management Plan
TABLE OF CONTENTS1. OVERVIEW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2. SCOPE OF SERVICES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
3. PROJECT SCHEDULE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Key Milestones . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
4. PROJECT TEAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Project Governance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
5. COMMUNICATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
External Communication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Internal Communication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
6. Data Collection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Attachment A
Attachment B
TABLESTable 3-1. Key Milestones and Deliverables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Table 5-1. Communication Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
FIGURESFigure 2-1. Project Flow Chart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
SR 109 Access Management Study
1Project Management Plan
PROJECT MANAGEMENT PLAN
1. OVERVIEWBuilding on the work completed in the Tri-County Transportation &
Land Use Study and the SR 109 Corridor Management Agreement,
the SR 109 Access Management Study represents a unique oppor-
tunity to establish corridor-wide access management standards and
practices that will simultaneously support local, regional, and state
transportation and economic development goals.
The Nashville Area Metropolitan Planning Organization (MPO) is the
lead agency and project manager, and it has retained a consulting
team, led by Nashville-based Gresham, Smith and Partners (GS&P), to
conduct the study.
The purpose of the study is to provide the MPO, state and local
community partners with a set of customized access management
strategies and a plan for coordinating access management decisions
along SR 109, stretching from SR 840 in Wilson County northward to
I-65 near the Robertson/Sumner County line. The project approach
builds on the considerable amount of planning work already
completed in the corridor and is focused on achieving the project’s
key outcome – the access management plan.
The Project Management Plan (PMP) has been developed to
guide the study process and to ensure that the project schedule is
maintained, key milestones are met, clear lines of communication are
established, and a plan for quality is addressed.
2. SCOPE OF SERVICESThe scope of services divides the SR 109 Access Management Study
into seven tasks. Collectively, the tasks describe the planning process
and technical work necessary to directly support building consensus
around the three principal elements of an access management plan,
a shared vision for the corridor, a set of access categories, and a series
of short- and medium-term improvements.
The fi rst phase of the study begins with a series of start-up tasks
describing historical, existing, and future conditions, documenting
existing access management guidelines and practices being
deployed in the study area, developing an access management
SR 109 Access Management Study2
Project Management Plan
resource kit that describes and illustrates best
management practices across a variety of
contexts, and engaging the general public
in a fi rst round of public meetings. Thus, this
phase of the study will be devoted to putting
in place the overall access management
framework, working closely with the Project
Steering Committee (PSC), stakeholders, and
the general public to defi ne the vision for the
corridor and develop an applicable set of access categories. The fi rst
of two rounds of public meetings will be used to introduce key best
practices and to gain consensus on the corridor vision and the access
categories.
The second phase of the study will focus on refi ning the resource
kit after the fi rst round of public meetings to refl ect comments on
how the best practices might be adopted specifi cally in the SR 109
corridor and more generally in the region and state. The fi nal
resource kit will be formatted for easy adaptation to a web-based
platform, and will be reviewed at the second round of public
meetings. The second round of public meetings will be used to apply
the draft access categories to the corridor and to discuss proposed
short- and medium-term improvements for areas with high crash
rates, traffi c operation concerns, or signifi cant development potential.
The third phase of the study focuses on fi nalizing and documenting
the principal elements of the access management plan – the vision,
access categories, and recommended improvements - and clearly
defi ning what was achieved and agreed upon during the planning
process. The full scope of services may be found in Attachment A.
3. PROJECT SCHEDULEThe SR 109 Access Management Study began in June 2014 and
will follow a 12-month time frame. A project schedule highlighting
individual tasks is located in Attachment B.
Key MilestonesThere are a total of 19 milestones and deliverables for this project,
beginning with the project kickoff in June 2014 and culminating
Figure 2-1. Project Flow Chart
Phase 1 – Challenges & OpportunitiesProject Management
Plan
Public Involvement
Plan
Historical, Exsiting &
Future Conditions
Existing Guidelines &
Practices
Draft Resource Kit Public Meetings:
First Round
Phase 3 – Final PlanFinal Acess
Management Plan
Final
Documentation
Phase 2 – AlternativesFinal Resource Kit Draft Access
Management Plan
Public Meetings:
Second Round
SR 109 Access Management Study
3Project Management Plan
in the fi nal technical report in May 2015. The milestones and deliv-
erables are major events or reports that will play a large part in the
success of the project and will be the focus of the work eff ort. The
milestones and deliverables are shown in Table 3-1.
2014 2015
JuneProject
Steering
Committee
Meeting JuneDeliverable #1: Project Management Plan
Deliverable #2: Public, Stakeholder and Media
Outreach Plan and Program
MayDeliverable #8:Technical Memo
on Recommended
Strategies for Access
Management
Deliverable #9:Technical Memo on
Recommended Reforms
to Current Practices
Deliverable #10:SR 109 Access
Management Plan
SeptemberTechnical
Committee
Meeting
OctoberRound 1 of
Public Meetings
NovemberProject Steering
Committee Meeting
OctoberDeliverable #3:Technical Memo on the
Technical Analysis of
Historical, Existing and
Future Conditions
Deliverable #4:Technical Memo
on the Existing
Guidelines and
Practices
FebruaryRound 2 of Public Meetings
AprilDeliverable #5:Technical Memo on
the Benefi ts of Eff ective Access
Management
Deliverable #6:Technical Memo on Best Practices
for Access Management
Deliverable #7:Access Management Resource Kit
MarchProject
Steering
Committee
Meeting
MayDeliverable #11:Tri-fold Promotional Brochures Summarizing
the Study Findings and Recommendations
Deliverable #12:Final Technical Report
Deliverable #13:Electronic Copies of Documents and Data
Table 3-1. Key Milestones and Deliverables
SR 109 Access Management Study4
Project Management Plan
4. PROJECT TEAMThere are two distinct entities with direct involvement in the SR 109
Access Management Study – the Nashville Area Metropolitan
Planning Organization and the consultant team led by Gresham,
Smith and Partners. The other members of the consultant
team include Kimley-Horn and Associates, Inc. (KHA), Philip B.
Demosthenes, and Younger Associates. In addition, a Project
Steering Committee will consist of members of the SR 109 Corridor
Management Committee. Members of the PSC will designate repre-
sentatives to serve on the Technical Committee, which will review
draft deliverables on a regular basis throughout the project. This
section describes the proposed project governance structure, roles
and responsibilities, and the review and approval process.
Project GovernanceSuccessful completion of the project depends on clear and
meaningful decision making about the direction of the project,
project priorities, and project deliverables. Each team member’s roles
and responsibilities are described below.
Nashville Area Metropolitan Planning Organization (MPO)The MPO is the owner of the contract and project sponsor, and is
ultimately responsible for the project’s success. Specifi c responsi-
bilities of the MPO include:
• Creating and communicating the project vision
• Serving as the decision maker for policy-level concerns of the
stakeholder community
• Acting as the project’s advocate with other agencies and local
governments
• Ensuring that political and organizational obstacles to project
success are addressed in a timely manner
• Building commitment among stakeholder organizations
The role of the MPO Project Manager is to ensure that the project
is delivered according to established expectations. The Project
Manager carries out her role by:
• Acting as the MPO’s offi cial contact with the consultants,
providing direction, resources, and clarifi cation as needed
• Overseeing review and approval of all project deliverables in a
timely manner
• Serving as the internal clearinghouse for all project progress and
resolving project related issues
SR 109 Access Management Study
5Project Management Plan
• Attending and/or ensuring MPO participation in all coordination
meetings, committee meetings, and public meetings
The PSC will serve as the steering committee for the study and will
support the work of the project team, providing invaluable leadership
from project start-up to the fi nal study document. The responsibilities
of the PSC members are to:
• Provide overall direction to the study
• Off er policy recommendations and provide guidance to the
study
• Serve as the primary spokesperson for their respective jurisdiction
on the study
Designated by the PSC, the Project Technical Committee (PTC)
members will review the technical work at key milestones during the
project. The PTC members will be asked to:
• Receive and review technical memoranda
• Coordinate with their respective agencies
• Provide a sounding board for the project team to prepare for
public outreach activities
Gresham, Smith and PartnersGresham, Smith and Partners (GS&P) is the lead consultant for the
contract and holds responsibility for the project and all deliverables.
The GS&P Principal-in-Charge is ultimately responsible for the
consultant’s performance on the project. Responsibilities of the GS&P
Principal-in-Charge include:
• Establishing project goals relative to the scope of work for the
consultant team
• Defi ning team members’ roles and responsibilities
• Assisting with facilitation of public meetings and supporting
client and elected offi cials/stakeholder group meetings
• Addressing client’s policy-level concerns
• Approving study development and review
The role of the GS&P Project Manager is to ensure that the project
is delivered according to established expectations. The Project
Manager carries out its role by:
• Acting as the consultant’s offi cial contact with the MPO
• Monitoring production and quality assurance/quality control of
all project deliverables
• Managing and communicating with all subconsultants and
vendors
• Managing the review and approval process of consultant work
products
• Developing and distributing project status reports
SR 109 Access Management Study6
Project Management Plan
Technical Teams have been identifi ed for the project. Their role is to
produce the team’s interim and fi nal work products. Technical team
responsibilities include:
• Working closely with client project management to ensure
project expectations are completely understood
• Developing interim and fi nal work products while meeting the
project’s schedule, budget, and quality goals
• Ensuring deliverables have followed project review and approval
process
• Coordinating with client, technical teams, and committee
members as necessary
• Maintaining a repository of the technical team’s information and
documentation
• Identifying issues and risks and taking action, in conjunction with
GS&P Project Manager, to resolve or avoid them.
Review and Approval ProcessThe review and approval process identifi es the types of approvals to
be made, the individuals and organizations responsible, and expected
approval timing. The process consists of four review levels:
Figure 4-1. Team Organization Chart
TASK 2Public Outreach, Stakeholder, and Media Outreach
Task Leader
Lindsay Puckett, AICPGS&P
Kevin Tilbury, AICPCynthia Frear
GS&P
Stephen Stansbery, AICPKHA
Sharon Younger, PhD
Younger Associates
TASK 3Technical Review and
Analysis of historic, Existing and Future
ConditionsTask Leader
Kevin Tilbury, AICPGS&P
Patrick Leap, PEAndrew Gaskins
GS&P
Allison Fluitt, PE, AICPKHA
TASK 4&5Existing Guidelines
and Practices & Access Management Resource
KitTask Leader
John Houghton, AICPGS&P
Phil DemosthenesPD
Patrick Leap, PELindsay Puckett, AICP
GS&P
David Coode, AICPChristopher Rhodes, PE
KHA
TASK 6Corridor Specifi c Access
Management PlanTask Leader
Kevin Tilbury, AICPGS&P
Jay Bockisch, PE, PTOEPatrick Leap, PE
GS&P
Phil DemosthenesPD
Christopher Rhodes, PEStephen Stansbery, AICPTimothy White, PE, PTOE
KHA
TASK 7Final Documentation
Task Leader
Lindsay Puckett, AICPGS&P
Patrick Leap, PEAndrew Gaskins
GS&P
Phil DemosthenesPD
Allison Fluitt, PE, AICPStephen Stansbery, AICP
KHA
Nashville Area MPOAnna Emerson
Project Manager
Principal-in-ChargeMarshall Elizer, PE, PTOE
GS&P
Project ManagerJohn Houghton, AICP
GS&P
Project Coordination CommitteeTDOTTDEC
Nashville MPOSumner County
Wilson CountyCity of GallatinCity of LebanonCity of Portland
Nashville Area MPOMichael Skipper
Executive Director
SR 109 Access Management Study
7Project Management Plan
1. Technical Team Review: Work product is submitted to GS&P
Project Manager after review and approval by the Technical Team
members.
2. GS&P QA/QC Review: GS&P Project Manager and one off -team,
senior GS&P professional review work product and request
revisions or approve. GS&P Project manager submits work
product to MPO Project Manager.
3. MPO Project Manager Review: MPO Project Manager reviews
work product and requests revisions or approves submission to
the PTC. Work deliverables require only MPO Project Manager
approval. Target: Complete review within fi ve working days.
4. Project Technical Committee Review: PTC members review work
deliverables and submit comments. The MPO Project Manager
will coordinate with the PTC members. Target: Complete review
within ten working days.
5. COMMUNICATIONHaving a clear plan for communication is important to the success
of any project. The following sections outline GS&P’s strategy for
communication on the SR 109 Access Management Study.
External CommunicationThe MPO has primary responsibility for external communication.
External communication may include contact with agencies, the
press, or the general public. GS&P will provide support to and
undertake external communications at the direction of the MPO.
If the MPO directs GS&P to undertake external communications, GS&P
will use the following protocol. In situations where sensitive or offi cial
project information is being disseminated, GS&P will seek review and
approval from the MPO in advance. In situations of basic commu-
nication where no critical information is disseminated, prior review
and approval from the MPO is not necessary; however, GS&P will
coordinate with the MPO on such communication where feasible and
appropriate. Specifi c conditions involving prior review and approval
are delineated in Table 5-1.
Internal CommunicationIn an eff ort to streamline communication and eliminate confusion for
the MPO, GS&P has implemented a single point of contact approach
to internal communication. The MPO may use the point of contact
for all matters related to the study, whether they be technical or
administrative/procedural. Additionally, the MPO may refer outside
individuals to the point of contact.
SR 109 Access Management Study8
Project Management Plan
• Primary point of contact – The GS&P Project Manager will serve
as the single point of contact for GS&P.
• Alternate point of contact – The GS&P Project Professional or
task leader will serve as the alternate point of contact in the event
that the primary point of contact is unavailable or for regular task
communications.
Unless directed otherwise, GS&P will use the MPO’s Project Manager
for the study as the MPO’s point of contact. All internal communi-
cation from the consulting team will fl ow through this individual.
6. DATA COLLECTION
Gresham, Smith and Partners will coordinate public data collection
through the MPO. GS&P will initiate and manage data collection
according to the following procedures:
• Identify data requirements – including data requirements for all
subconsultants
• Develop data needs table – including data needs by subject
matter, type of data (GIS, plan, other), intended use of data, and
any specifi c issues
• Coordinate with MPO – including data requests and data sharing
agreements; obtain data only from sources agreed upon
• Manage and maintain project data – including data fi les
associated with specifi c tasks and major deliverables
The following will be a target of the data collection eff ort:
• Inventory of existing plans and policies
• Inventory of existing capital budget and programs
• Land use/parcel information
• Transportation system and networks
Table 5-1. Communication Plan
Basic Communication – Review and Approval from the MPO is not necessary.
• Data requests
• Status updates
• General coordination
• Meeting notifi cation
Dissemination of Information – Review and approval from the MPO is necessary.
• Press releases
• Press interviews
• Project deliverables
• Interim project materials
• Meeting materials
• Web page content
• Communication with public offi cials and general public
SR 109 Access Management Study
9Project Management Plan
• Information about other public infrastructure systems
• Natural resources and environmental features
• Socio-cultural assets and resources
• Population and employment estimates and forecasts
Other data not listed above may be required as part of the study.
SR 109 Access Management Study Page 1
SR 109 ACCESS MANAGEMENT STUDY NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION This scope of services describes the work necessary to provide the Nashville Area Metropolitan Planning Organization (MPO) and state and local community partners with a with a set of customized access management strategies and a plan for coordinating access management decisions along State Route 109 stretching from I‐40 in Wilson County northward to I‐65 near the Robertson/Sumner County line. Our team’s project approach builds on the considerable amount of planning work already completed in the corridor and is focused on achieving the project’s key outcome – the access management plan. TASK 1. PROJECT MANAGEMENT/COORDINATION 1.1 Project Management Plan Gresham, Smith and Partners (“CONSULTANT" hereafter) will be responsible for internal project organization and coordination with the MPO Project Manager. The CONSULTANT will prepare a project management plan that will outline coordination, roles, and study schedule. The plan will include:
• An organizational chart of the project team and a description of roles and responsibilities for consultant and subcontractor team members;
• A final scope of work with a detailed description of major tasks and deliverables; • A schedule and budget for each major task and requested deliverable; • A description of the project management protocol for quality control procedures and client
progress reports; • A list of project participants and the expected level of participation (e.g., MPO staff, project
committee members, agency partners, etc.); • An assessment of local data and information needed to carry out the scope of services, and a
corresponding data collection plan. 1.2 Project Kickoff Meetings The CONSULTANT will meet with appropriate MPO staff to discuss the task‐specific schedule, establish ground rules and project expectations within the confines of the scope and fee, exchange relevant information and documents, initiate requests for other necessary data, and to explain administration of the contract. An in‐house kick‐off for the CONSULTANT team members is also included. 1.3 Monthly Progress Reports and Meetings The CONSULTANT will submit to the MPO brief monthly progress reports outlining the work completed to date and an updated schedule of the tasks remaining for timely completion of the project. The CONSULTANT will also attend regular progress meetings with MPO personnel to discuss project status and project issues. 1.4 Project Coordination This task includes overall project management, liaison with the MPO and team members, and written documentation as appropriate for all meetings that are not specifically addressed elsewhere in this
SR 109 Access Management Study Page 2
Scope. Communications and coordination with other federal, state, and local agencies will be closely coordinated with the MPO and documented. The CONSULTANT’s Project Manager will be responsible for project coordination and communication of issues under this task. Deliverable #1: Project Management Plan Figure 1. Project Flow Chart
TASK 2: PUBLIC, STAKEHOLDER, AND MEDIA OUTREACH PLAN 2.1 Public, Stakeholder, and Media Outreach Plan The CONSULTANT will prepare an outreach plan in cooperation with the MPO. The plan is intended to provide opportunities for the public, stakeholders, and the media to participate in the formation of the study’s recommendations. The plan will address:
• Outreach Coordination—The CONSULTANT will facilitate all meetings, prepare all meeting materials, and document public and stakeholder comments throughout the process, including synthesizing findings from public involvement conducted by local agencies during recent and ongoing comprehensive planning activities throughout the study area based on readily available data and information produced by others.
Phase Three - Final Plan
Final Access Management Plan Final Documentation
Phase Two - Alternatives
Final Resource Kit Draft Access Management Plan Public Meetings: Second Round
Phase One - Challenges & Opportunities
Project Management Plan
Public Involvement Plan
Historical, Existing & Future
Conditions
Existing Guidelines & Practices Draft Resource Kit Public Meetings:
First Round
SR 109 Access Management Study Page 3
• Meetings—The plan will list potential meeting materials and present recommended meeting formats, potential time of day, and locations. In addition, the plan will specify lead roles at the meetings and that each meeting will be documented and made available on the project website. Project Coordination Committee Meetings (5 meetings). The project coordination
committee will consist of members of the SR 109 Corridor Management Committee. Public Meetings (4 meetings). Two rounds of two meetings. The first round will focus
on the corridor vision and discuss how access management can help achieve that vision through improved operational performance and safety. The second round of public meetings will present the draft access categories for the corridor and also identify potential short‐ and medium‐term improvements that address access management “hotspots”.
Elected Officials & Stakeholder Group Meetings – The CONSULATANT will make up to seven (7) presentations to elected officials after the second round of public meetings or prior to finalizing the study. We will also conduct up to six (6) meetings with stakeholder groups. These may be presentations and/or working sessions with property owners, residents, and businesses along the corridor or with larger groups such as chambers of commerce, neighborhood associations, or non‐profit organizations representing a variety of interests, especially traditionally underserved populations.
• Outreach and Engagement Strategies—Strategies include:
The CONSULTANT will work with the MPO and the project coordination committee to develop a database of stakeholders and interested parties that will be supplemented throughout the life of the project. This database will be used primarily for meeting notices.
Use of the MPO website and social media: The CONSULTANT will work with the MPO by providing periodic updates for posting on the MPO project study webpage and social media at key project milestones, such as in advance of and following public meetings and when study deliverables are available.
Press releases and newspaper advertisements: The CONSULTANT will develop drafts for the MPO to coordinate with press and publications.
Environmental Justice populations: The CONSULTANT will work to ensure that minority and low income populations receive meeting notifications and that meeting locations are readily accessible.
Deliverable #2: Public, Stakeholder, and Media Outreach Plan and Program TASK 3: TECHNICAL ANALYSIS OF HISTORICAL, EXISTING, AND FUTURE CONDITIONS 3.1 Data Collection The CONSULTANT will compile historic, base year, and forecast year data to describe the conditions and trends for the study area. We will then work with the MPO to identify a set of transportation and land use performance measures and performance targets that the steering committee finds acceptable within the framework of the goals and objectives identified in local, regional, and statewide plans.
SR 109 Access Management Study Page 4
Those performance measures and targets shall be used to evaluate the various access management strategies that will be developed for the customized plan as part of Task 6. The following will be included in the analyses:
• Economic and market conditions; • Land use and development patterns; • Travel demand and transportation system performance; • Environmental features and conflicts; • Local planning practices; • Natural resource conservation efforts
The CONSULTANT will also compile data and plans from a variety of sources. The following will be a target of the data collection effort:
• Inventory of existing policies and plans; • Inventory of existing capital budget and programs; • Land use/parcel information; • Transportation system and networks; • Information about other public infrastructure systems; • Natural resources and environmental features; • Socio‐cultural assets and resources; • Population and employment estimates and forecasts.
The CONSULTANT will be responsible for obtaining, organizing, and analyzing this information, however, cooperation will be provided by the MPO and other public agencies, as needed. Other data not listed above may be required as part of the analysis. Special attention will be given to reviewing consistency between the Tri‐County’s Preferred Vision for Growth & Development, local plans, and planned transportation investments along the corridor. The CONSULTANT will augment the information from those plans with information gathered from research that may provide insight into pending real estate development or economic activity within the study area that could affect the corridor’s future trajectory. Deliverable #3: Technical Memo on the Technical Analysis of Historical, Existing, and Future Conditions TASK 4: DOCUMENT & ASSESS EXISTING ACCESS MANAGEMENT GUIDELINES AND PRACTICES The CONSULTANT will investigate, document, and evaluate current access management strategies being deployed in the area. The investigation will cover, at a minimum, the following:
• TDOT’s preliminary engineering and final design plans for roadway or intersection improvements not yet implemented along the corridor;
• TDOT’s process to grant or deny access permits along state routes including the application process, the evaluation process, and the degree to which local communities or stakeholders are involved in the permitting process;
• State or local traffic control measures or ITS deployed to manage traffic along the corridor;
SR 109 Access Management Study Page 5
• State or local safety measures deployed to reduce vehicular or pedestrian crashes; • County or municipal policies that set parameters for land uses along the corridor; and • County or municipal regulations that affect the design and placement of development.
The CONSULTANT will review plans and documents as well as actual access permitting or land use cases along this corridor or similar corridors in the area. Through field visits, we will capture where access management is working and not working with photographs and measurements. For the purposes of reviewing TDOT’s permitting process, the analysis will not be limited to the SR 109 corridor. We will conduct personal interviews with staff associated with each of these processes as needed. Deliverable #4: Technical Memo on the Existing Guidelines and Practices TASK 5: DEVELOP ACCESS MANAGEMENT RESOURCE KIT The CONSULTANT will prepare an access management resource kit that describes and illustrates best practices across a variety of contexts. We will begin documenting best practices for the study immediately – including evidence of benefits, lessons learned, and typical treatments, policies, regulations, and standards – with an eye toward introducing key best practices at the first round of public meetings. The resource kit will include, at a minimum:
• Evidence of the benefits of access management for mobility, accessibility, safety, economy, environment, and other relevant community objectives;
• A discussion of major pitfalls or traps to avoid in the pursuit of access management; • Illustrations and discussion of common access management treatments; • Examples of land use guidelines that aid in managing travel demand or undesirable traffic
patterns; • Examples of multi‐agency coordination practices; • Model codes and ordinances that affect urban form and function; • Recommendations for identifying problems and measuring success; • A illustrated glossary of key terms and acronyms; • References to additional resources.
We will refine the resource kit after the first round of public meetings to reflect comments on how the best practices might be adopted specifically in the SR 109 corridor and more generally in the region and state. We will then review the resource kit in conjunction with draft access categories and recommended improvement at the second round of public meetings. The final resource kit will be formatted for easy adaptation to a web‐based platform, which will we will also provide. Deliverable #5: Technical Memo on the Benefits of Effective Access Management Deliverable #6: Technical Memo on Best Practices for Access Management Deliverable #7: Access Management Resource Kit – bound hard copies and original electronic files; an interactive web version also is desirable
SR 109 Access Management Study Page 6
TASK 6: DEVELOP CORRIDOR SPECIFIC ACCESS MANAGEMENT PLAN The final corridor access management plan will be the logical outcome of the step‐by‐step and iterative study process. In effect, the principal elements of the final plan – the vision, access categories, and recommended improvements – will have been identified and publicly reviewed by the end of the second round of public meetings. With consensus on the key elements, we will use this task to finalize the recommendations and develop an action plan for all of the participating agencies. Final Recommendations Following the three‐part framework established at the outset of the study, the final plan will clearly define what was achieved and agreed upon during the planning process. It will lay out:
• A Shared Vision for the Corridor – The shared vision will confirm the long‐term land use, transportation, and growth plan for SR 109. Relying on local plans and the regional vision captured in the Tri‐County study, the illustrated corridor vision will depict how the corridor’s land uses, general character, and transportation system change over the length of SR 109. The vision will set the stage for the access management plan’s goals, objectives, performance measures, and access categories.
• Access Categories – Putting into practice the vision for the corridor, the access categories will establish the overall access management framework for the corridor based on the development and transportation context. On a corridor map, color‐coded categories will visually identify corridor segments of different performance and provide a way to easily view their length and frequency. The categories will address the following basic standards and guidelines:
Roadway design and capacity – alignment and optimal cross‐sections Levels of access ‐ full or partially controlled or conventional access Access points – intersecting street and driveway location, spacing, and design Medians – median type (full opening, directional, left‐in only, restrictive) and median
opening spacing
• Recommended Improvements – While the access categories reinforce the corridor vision by establishing the long‐term access management framework, the recommended improvements will focus on short‐ and medium‐term improvements. We will identify priority issues and areas for access management improvements prior to the second round of public meetings, and reviewing possible solutions during those meetings. The recommended improvements will span a full array of issues and “hotspots” along the corridor, including: Roadway design enhancements and treatments – for example, consolidated driveways,
medians, intersection geometry, turn lanes, and pedestrian and bicycle facilities Traffic management and operations – traffic signal timing and coordination, integrated
Intelligent Transportation Systems (ITS), and Traffic Impact Study (TIS) requirements Land development planning – land use plans, zoning ordinances, and subdivision
regulations
SR 109 Access Management Study Page 7
Governance – access permit process including appeal process, interagency coordination, performance monitoring, and funding
Deliverable #8: Technical Memo on Recommended Strategies for Access Management Deliverable #9: Technical Memo on Recommended Reforms to Current Practices Deliverable #10: SR 109 Access Management Plan – 25 bound hard copies and original electronic files TASK 7: PREPARE FINAL DOCUMENTATION & ELECTRONIC FILES The CONSULTANT will develop a promotional brochure and a final technical report on the study’s findings and recommendations. The final technical report will incorporate information from the technical memorandums and include supporting documentation from analyses and modeling. In addition, we will present findings and recommendations to the SR 109 Corridor Management Committee, the MPO Technical Advisory Committee, and Executive Board, and to the local planning commissions and/or legislative bodies representing the jurisdictions participating in the study (at the discretion of the local planning director and budget availability). All documents will be provided in PDF and the native editable version (Word, Illustrator, Publisher, InDesign, etc.). Data will be provided in an agreed upon format to ensure that the MPO and its partners are able to access the information after the completion of the CONSULTANT’S effort. All GIS data will be provided to the MPO in a format compatible with ESRI software. Deliverable #11: 250 full‐size tri‐fold promotional brochures summarizing the study findings and recommendations Deliverable #12: 25 hard copies of the final technical report Deliverable #13: Electronic copies of documents and data
SR 109 Access Management Study
Project Schedule
Task 1: Project Management Plan
Task 2: Public, Stakeholder, and Media
Outreach Plan
Task 3: Technical Review & Analysis of
Historic, Existing and Future Conditions
Task 4: Document & Assess Existing Access
Management Guidelines and Practices
Task 5: Develop Access Management
Resource Kit
Task 6: Develop Corridor Specific Access
Management Plan
Task 7: Prepare Final Documentation &
Electronic Files
Steering Committee/Corridor Management Commitee Meetings Public Meetings
Technical Committee Meetings Major Deliverables
TaskAprilJune SeptAugJuly MarchNov DecOct Jan Feb
2014 2015
May
0 0
0