project management plan for global project management conference (gpm)

39
E-Sis Company Project Management Plan for Global Project Management Conference (GPM)

Upload: lucia-denis

Post on 23-Jan-2018

1.696 views

Category:

Leadership & Management


1 download

TRANSCRIPT

Page 1: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Project

Management Plan

for Global Project Management Conference (GPM)

Page 2: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Project Management Plan

(1) Scope

(2) Schedule

(3) Cost

(4)Quality

(5)Communications

(6)Human

Resources

(7)Risks

(8)Stakeholders

Page 3: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

1) Scope

Page 4: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Project Scope Statement

• Project Scope

• Provide necessary resources and capabilities of Project

Management as a tool to take decisions on critical

businesses in order to conduct Global Project

Management conference.

Page 5: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Project Scope Statement

• Main Objective

• To conduct Global Project Management Conference in

order to emphasize that Project Management is crucial for

mitigating and avoiding risks of critical businesses

including nuclear threats due to natural disasters.

• Deliverables

1) Master Project Plan

2) Global Project Management Conference

3) Summary bulletin

Page 6: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Project Scope Statement

• Constraints• Budget Constraint

• Government budget is limited. The financial plan has to mention the project costs,

revenues, the conference fee and other financial elements in detail.

• Cost & Profit

• Conference entry fee must be less than 200 US$. Profit ratio should be in the range of 5%

to 10%.

• Time Constraint

• 20th. November, 2014 – 29th May, 2015

• Assumptions• Participants

• 4000 individuals and two participants from each 60 companies will be participated.

• All participants will be actively participated in avoiding and mitigating nuclear threats

associated with natural disasters.

• Analogue cost estimate method will be succeeded

Page 7: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Proj: Scope StatementTime Description

Nov. 20 RFP submitting

Nov. 21 – Dec. 5 Master project plan development

Nov. 27 Internal Review

Dec. 4 Internal Review

Dec. 11 Master project plan presentation

Dec. 12 - 19 Primary contractor selection

Dec. 24 Project kickoff

Dec. 25. – Jan. 16 Detail project plan development

Jan. 21 Final project plan review

Feb. 2 –Apr. 27 Fortnightly progress review

May 1 Final progress Review

May 13 -15 Conference

May. 29 Closing reviewMil

esto

nes

Page 8: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Conference Venue Layout

Main Auditorium Hall

Exhibition Hall

Conference Room(1)

Conference Room(2)

Conference Room(3)

Conference Room(4)

Page 9: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Conference Schedule

Time Day 1 Day 2 Day 3

General Session Seminar 2 for G1,G2,G3,G4 -

At R1,R2,R3,R4

Introduction on ExhibitionExhibition Part 2 for

G5,G6,G7,G8

12.00 - 1.00 p.m Break Break Break

Seminar 1 for

G1,G2,G3,G4 -At

R1,R2,R3,R4

Seminar 2 for G5,G6,G7,G8-

At R1,R2,R3,R4

Exhibition Part 1 for

G5,G6,G7,G8

Exhibition Part 2 for

G1,G2,G3,G4

4.00 - 4.30 p.m. Tea Break Tea Break Tea party & Close

Seminar 1 for

G5,G6,G7,G8 - At

R1,R2,R3,R4

Exhibition Part 1 for

G1,G2,G3,G4

Conference Schedule

9.00 a.m - 12.00

1.00 - 4.00 p.m

4.30 - 7.30 p.m.

Feedback, Review Session

Network Meeting - All

Group at Main Auditorium

Panel Discussion- All

Groups at main Auditorium

Page 10: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Work Breakdown Structure

Global Project Management Conference (GPM)

(D1)Master Project Plan

Develop Master Plan

Submit Proposal

Finale Project Review

Presentation to IUJ

(D2)Conference

General Session

Logistic

Seminars

Logistic

Network meetings

Logistics

Panel discussions

Logistics

Exhibitions

Logistics

Feedback

Session

(D3)Summary Bulletins

Reviewing

Documentation

Submit Bulletin

Page 11: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Work Breakdown Structure

Logistics

Venue

Enquires

Select & Book

Speakers

Invitations

Confirmations

Delegation/ Participants

Invitation Confirmation Public Announce

Press Conference

Press Release

Advertising

Food & Accommodation

Enquires

Select & Book

Transportation

Enquires

Bus Timetable

Handouts

Collect Handouts

Printing

Page 12: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

2) Schedule

Page 13: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Tim

elin

e

Task Name Duration Start FinishPredecessors

Global Conference Project 97 days Wed 12/24/14 Thu 5/7/15

Gloobal Conference Project 97 days Wed 12/24/14 Thu 5/7/15

Project governance 3 days Wed 12/24/14 Fri 12/26/14

kickoff meeting 1 day Wed 12/24/14 Wed 12/24/14

Final Project Plan Review 2 days Thu 12/25/14 Fri 12/26/14

D1) Develop project management plan 94 days Mon 12/29/14 Thu 5/7/15

Define scope & Schedule 9 days Mon 12/29/14 Thu 1/8/15

Review project charter 1 day Mon 12/29/14 Mon 12/29/14

Analyze requirements 4 days Tue 12/30/14 Fri 1/2/158

Document scope statement 2 days Mon 1/5/15 Tue 1/6/159

Crete WBS 1 day Wed 1/7/15 Wed 1/7/1510

Define Schedule 1 day Thu 1/8/15 Thu 1/8/1511

Estimate cost 2 days Fri 1/9/15 Mon 1/12/15

Estimate activity cost 1 day Fri 1/9/15 Fri 1/9/15

Budgeting cost 1 day Mon 1/12/15 Mon 1/12/1514

Communication 1 day Tue 1/13/15 Tue 1/13/15

Define Channels 1 day Tue 1/13/15 Tue 1/13/15

Resource Management Plan 1 day Tue 1/20/15 Tue 1/20/15

Organization Chart & Resource Plan 1 day Tue 1/20/15 Tue 1/20/15

Develop risk management plan 1 day Wed 1/21/15 Wed 1/21/15

Identify risks 1 day Wed 1/21/15 Wed 1/21/15

Plan risk response 1 day Wed 1/21/15 Wed 1/21/1521FF

Submitting & Approving 77 days Wed 1/21/15 Thu 5/7/15

Submit plan 1 day Wed 1/21/15 Wed 1/21/15

Final Project Review 71 days Thu 1/22/15 Thu 4/30/15

Presentation to IUJ 5 days Fri 5/1/15 Thu 5/7/1525

Page 14: Project management plan for Global Project Management Conference (GPM)

E-Sis

CompanyTask Name Duration Start Finish

Predecessors

D2) Conference Plan 66 days Fri 1/2/15 Fri 4/3/15

General Sessions 22 days Fri 1/2/15 Mon 2/2/15

Venue 18 days Mon 1/5/15 Wed 1/28/15

Enquires 13 days Mon 1/5/15 Wed 1/21/15

Select & Book 3 days Mon 1/26/15 Wed 1/28/1531

Speakers 13 days Fri 1/2/15 Tue 1/20/15

Invitations 10 days Fri 1/2/15 Thu 1/15/15

Confirmation 3 days Fri 1/16/15 Tue 1/20/1534

Participants 20 days Mon 1/5/15 Fri 1/30/15

Invitations 8 days Mon 1/5/15 Wed 1/14/15

Confirmation 5 days Thu 1/15/15 Wed 1/21/1537

Public Announcement 7 days Thu 1/22/15 Fri 1/30/15

Press Conference 3 days Thu 1/22/15 Mon 1/26/15

Press Release 2 days Mon 1/26/15 Tue 1/27/1540

Advertising 3 days Wed 1/28/15 Fri 1/30/15

Food & Accomodations 15 days Mon 1/5/15 Fri 1/23/15

Enquires 10 days Mon 1/5/15 Fri 1/16/1531SS

Select & Book 5 days Mon 1/19/15 Fri 1/23/1544

Transportation 13 days Mon 1/5/15 Wed 1/21/15

Enquires 10 days Mon 1/5/15 Fri 1/16/1531SS

Bus Timetable 3 days Mon 1/19/15 Wed 1/21/1547

Handouts 8 days Thu 1/22/15 Mon 2/2/15

Collect Handouts 5 days Thu 1/22/15 Wed 1/28/1538

Prinint 3 days Thu 1/29/15 Mon 2/2/1550

Tim

elin

e

Page 15: Project management plan for Global Project Management Conference (GPM)

E-Sis

CompanyTask Name Duration Start Finish

Predecessors

Seminars 24 days Mon 2/2/15 Thu 3/5/15

Venue 18 days Thu 2/5/15 Mon 3/2/15

Enquires 13 days Thu 2/5/15 Mon 2/23/15

Select & Book 3 days Thu 2/26/15 Mon 3/2/1554

Speakers 13 days Mon 2/2/15 Wed 2/18/15

Invitations 10 days Mon 2/2/15 Fri 2/13/15

Confirmation 3 days Mon 2/16/15 Wed 2/18/1557

Participants 19 days Thu 2/5/15 Tue 3/3/15

Invitations 8 days Thu 2/5/15 Mon 2/16/15

Confirmation 5 days Tue 2/17/15 Mon 2/23/1560

Public Announcement 7 days Sun 2/22/15 Tue 3/3/15

Press Conference 3 days Sun 2/22/15 Tue 2/24/15

Press Release 2 days Thu 2/26/15 Fri 2/27/1563

Advertising 3 days Sat 2/28/15 Tue 3/3/15

Food & Accomodations 15 days Thu 2/5/15 Wed 2/25/15

Enquires 10 days Thu 2/5/15 Wed 2/18/1554SS

Select & Book 5 days Thu 2/19/15 Wed 2/25/1567

Transportation 13 days Thu 2/5/15 Mon 2/23/15

Enquires 10 days Thu 2/5/15 Wed 2/18/1554SS

Bus Timetable 3 days Thu 2/19/15 Mon 2/23/1570

Handouts 8 days Tue 2/24/15 Thu 3/5/15

Collect Handouts 5 days Tue 2/24/15 Mon 3/2/1561

Prinint 3 days Tue 3/3/15 Thu 3/5/1573

Tim

elin

e

Page 16: Project management plan for Global Project Management Conference (GPM)

E-Sis

CompanyTask Name Duration Start Finish

Predecessors

Network Meeting & Panel Discussion 21 days Fri 3/6/15 Fri 4/3/15

Venue 16 days Fri 3/6/15 Fri 3/27/15

Enquires 13 days Fri 3/6/15 Tue 3/24/1574

Select & Book 3 days Wed 3/25/15 Fri 3/27/1577

Speakers 13 days Fri 3/6/15 Tue 3/24/15

Invitations 10 days Fri 3/6/15 Thu 3/19/1574

Confirmation 3 days Fri 3/20/15 Tue 3/24/1580

Participants 18 days Fri 3/6/15 Tue 3/31/15

Invitations 8 days Fri 3/6/15 Tue 3/17/1574

Confirmation 5 days Wed 3/18/15 Tue 3/24/1583

Public Announcement 5 days Wed 3/25/15 Tue 3/31/15

Press Conference 3 days Wed 3/25/15 Fri 3/27/1584

Press Release 2 days Mon 3/30/15 Tue 3/31/1586

Advertising 3 days Sat 3/28/15 Tue 3/31/15

Food & Accomodations 15 days Fri 3/6/15 Thu 3/26/15

Enquires 10 days Fri 3/6/15 Thu 3/19/1577SS

Select & Book 5 days Fri 3/20/15 Thu 3/26/1590

Transportation 13 days Fri 3/6/15 Tue 3/24/15

Enquires 10 days Fri 3/6/15 Thu 3/19/1577SS

Bus Timetable 3 days Fri 3/20/15 Tue 3/24/1593

Handouts 8 days Wed 3/25/15 Fri 4/3/15

Collect Handouts 5 days Wed 3/25/15 Tue 3/31/1584

Prinint 3 days Wed 4/1/15 Fri 4/3/1596

Tim

elin

e

Page 17: Project management plan for Global Project Management Conference (GPM)

E-Sis

CompanyTask Name Duration Start Finish

Predecessors

Exhibation 24 days Fri 3/27/15 Wed 4/29/15

Venue 16 days Mon 4/6/15 Mon 4/27/15

Enquires 13 days Wed 4/1/15 Fri 4/17/1596

Select & Book 3 days Mon 4/20/15 Wed 4/22/15101

Speakers 13 days Wed 4/1/15 Fri 4/17/15

Invitations 10 days Wed 4/1/15 Tue 4/14/1596

Confirmation 3 days Wed 4/15/15 Fri 4/17/15104

Participants 13 days Wed 4/1/15 Fri 4/17/15

Invitations 8 days Wed 4/1/15 Fri 4/10/1596

Confirmation 5 days Mon 4/13/15 Fri 4/17/15107

Public Announcement 21 days Fri 3/27/15 Fri 4/24/15

Press Conference 3 days Mon 4/20/15 Wed 4/22/15108

Press Release 2 days Thu 4/23/15 Fri 4/24/15110

Advertising 3 days Fri 3/27/15 Tue 3/31/15

Food & Accomodations 15 days Wed 4/1/15 Tue 4/21/1596

Enquires 10 days Wed 4/1/15 Tue 4/14/15101SS

Select & Book 5 days Wed 4/15/15 Tue 4/21/15114

Transportation 13 days Wed 4/1/15 Fri 4/17/15

Enquires 10 days Wed 4/1/15 Tue 4/14/15101SS

Bus Timetable 3 days Wed 4/15/15 Fri 4/17/15117

Handouts 8 days Mon 4/20/15 Wed 4/29/15

Collect Handouts 5 days Mon 4/20/15 Fri 4/24/15108

Prinint 3 days Mon 4/27/15 Wed 4/29/15120

Feedback Session 5 days Thu 4/30/15 Wed 5/6/15121

Tim

elin

e

Page 18: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Task Name Duration Start FinishPredecessors

HELD CONFERENCE 3 days Wed 5/13/15 Fri 5/15/15

General Sessions 1 day Wed 5/13/15 Wed 5/13/15

Seminars 2 days Wed 5/13/15 Thu 5/14/15

Exhibations 2 days Wed 5/13/15 Thu 5/14/15

Pannel Discussions 1 day Thu 5/14/15 Thu 5/14/15

Network Meeting 1 day Fri 5/15/15 Fri 5/15/15

Feedback & seminar review 1 day Fri 5/15/15 Fri 5/15/15

D3) Summary Bulletin 10 days Mon 5/18/15 Fri 5/29/15

Reviewing 3 days Mon 5/18/15 Wed 5/20/15

Documentation 5 days Thu 5/21/15 Wed 5/27/15

Summit Bulletin 1 day Thu 5/28/15 Thu 5/28/15

Closing Project 1 day Fri 5/29/15 Fri 5/29/15

Timeline

Page 19: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

3) Cost

Cost estimate based on Analogue Estimating

* Used our previous Experiences of similar projects

Page 20: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Conference Activity Plan

Page 21: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Conference Activity Plan

Total Budget for venue is = $ 2000

Page 22: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Cost Estimate

Expected Revenue

No. of Participants

Individuals 4,000

Company 60* 2 persons 120

Total Participants 4,120

Expected Project Revenue = No. of Expected Participants * fee

per one participant

=4120*US$200

= US$ 824,000

Page 23: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Estimate cost

US$

Total Bugeted Staff Cost 72,975 Annex 1

Deliverable-1

Fees for Hire Expertise of Project Dev Plan -

Deliverable-2

Advertising Fees 1,500

Fees for Venue (May 12 ~15) 500 Per Day 4 Days 2,000

Mailing Fees to invite delegates 1 Per Mail 4120 Perticipants 4,120

Public Announcement 500

Food & Beverages 4 Days 15 Per Day 4120 Perticipants 247,200

Accomodations 4 Days 15 Per Day 4120 Perticipants 247,200 Printing Handouts 7 booklets 2 Per Booklet 4120 Perticipants 57,680

Resource Person 2 hrs 100 Per Hr 7 Resource Person 1,400

Printing & Submitting Bulletins 7 booklets 2 Per Booklet 4120 Perticipants 57,680

Deliverable-3

Printing Bulletins 1 booklet 3 4120 Perticipants 12,360

Contigency Amout (5% of Budget) 37,007

741,622

Estimate Cost

Page 24: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Total Budgeted Staff Cost

Budget for Project Staffs USD

Appointment

Date

End Date of the

Contact

Work

Duration in

Months

Salary Per

MonthBudget

Project Staff

Project Manager 01.11.2014 30.05.2014 7 1,000 7,000

Project Director 01.11.2014 30.05.2014 7 950 6,650

Project Execurive 15.11.2014 30.05.2014 6.5 900 5,850

Project Staff 1 15.11.2014 30.05.2014 6.5 700 4,550

Project Staff 2 15.11.2014 30.05.2014 6.5 700 4,550

Accountant 15.11.2014 30.05.2014 6.5 900 5,850

Supporting Staff 1 15.11.2014 30.05.2014 6.5 750 4,875

Supporting Staff 2 15.11.2014 30.05.2014 6.5 750 4,875

Project Marketing Executive 01.12.2014 30.05.2014 6 900 5,400

Supoting Staff 1 01.12.2014 30.05.2014 6 700 4,200

Project HR Executive 15.11.2014 30.05.2014 6.5 800 5,200

Suporting Staff 1 15.11.2014 30.05.2014 6.5 700 4,550

Logistic Officer 15.11.2014 30.05.2014 6.5 750 4,875

Suprting Staff 1 15.11.2014 30.05.2014 6.5 700 4,550

Total Bugeted Staff Cost 72,975

Page 25: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

4) Quality

Page 26: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Quality

Project Quality Plan

USD

Conference entry fee 4120 200 824,000

Estimated Total project cost 746,497

Estimated Project Profit 77,503

Cost Benefit Ratio = Estimated Project Profit = 10.38223

Estimated Total project cost

Estimated Profit as a percentge of entry fee = Estimated Project Profit = 9.405704

Conference entry fee

Cost per person = Estimated Project cost = 746,497

No of Participates 4120

= 181

Page 27: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

5) Communication

Page 28: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Stakeholders

• International University of Japan (IUJ)

• Project contractor

• Executive Director(Yuichi Naito)

• Projective Executive (Jey Rajasekera)

• Niigata Prefectural office

• Ministry of Economy, Trade and Industry(METI)

• Japan International Cooperation Agency (JICA)

• Project Management Association of Japan (PMAJ)

• Public Companies

• General Participants

Page 29: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

No of Channels = N(N-1)/2

• Stakeholders = 9

• Required potential communication

cannels = 36

Page 30: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Project Team

Communication Plan

Audience Information Method Frequency Who is

Responsible

Owner and

Cosponsor

Project

announcement

E-Mai l,

Fax

Weekly Team Leads

Project teams Team Meeting Meeting Daily Team Leads

Project Teams

Owner and

Cosponsor

Team Meeting ,

Meeting Minute

E mail, Fax Weekly Team leads

Participants Meeting Agenda Email , Fax 2 Weeks

before

Conference

Project

manager

Page 31: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Project Team Communication

Plan (cont. )

Audience Information Method Frequency Who is

Responsible

Owner and

Cosponsor

Project

Implementation

Network

Meeting, Video

Conferencing

One Month Project

Manager

Project

Manager

Feedback from

Stakeholder

E mail, Fax,

Video

conferencing,

cell phone

One Month Owner,

Cosponsor

Page 32: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Output from Com: Plan

• Outputs

• Document Update

• Meeting Minutes

• Change Request

Page 33: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

6) Human Resource

Page 34: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Human Resource

(Organization Chart)

Project Manager

Project Executive

Logistic Officer

IT Staff

General logistic Staff

Staff 1 Staff 2

Project Marketing Executive

Staff 1

Staff 2

Project Accounting Executive

Staff 1

Project Human Resources Executive

Staff 1

Project Director

Page 35: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

7) Risks

Page 36: Project management plan for Global Project Management Conference (GPM)

E-Sis

CompanyRisk

Nr.Risk Description Possibility

Impact/

SeverityRisk Management Plan/ Mitigation Strategy

1Over costing more than the budget

allocated Medium High

The budget is limited. Thus, Marketing team should define

advertising strategy to guarantee that at least the pre-

registration of 4000 fees. Part of money collected would

help in preparation of the conference.

2 Lack of funding High High Ask for JICA and METI financial support

3 Delay on schedule Medium MediumOrganize meeting with facility staff members before the

conference

4 Guest Speakers cancelations Low HighAsk to the guest speaker confirmation and update speaker as

cancellation occur

5Lack of audience/ reduced

number of participantsMedium High

- Advertising

- Create a Website for a conference

- -Online Registration

- Inviting famous Guest Speakers

(Specialists in Project Management)

- High participation of Project Management Association of

Japan

6 Natural Disaster (Eg. Earthquake) Low HighPrepare an emergency plan for quickly evacuation in case of

natural disaster

7

Delay on logistics (Catering,

accommodation and

transportation)

Medium High

Update to Catering Service about the final number of

participants, according to pre-registration. Logistics Officer

must in permanent contact with the Hotels contracted.

8Equipment problems (Computer

and High Medium Allocate an IT staff

9Equipment problems (Computer,

projectors and printers) High Medium Allocate an IT staff

Page 37: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

8) Stakeholders

Page 38: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Stakeholders

Stakeholders

IUJ Project Team(Project Owner)

Project Director (Yuichi Naito)

Project Executive (Jey Rajasekera)

Primary Contractor

Cosponsor

Niigata Prefecture Government

Ministry of Economy, Trade and Industry

(METI)

Japan International Corporation (JICA)

Project Management Association of Japan

Public Companies General participants

Page 39: Project management plan for Global Project Management Conference (GPM)

E-Sis

Company

Thank You!