    Project Management A Managerial Prospective

    PROJECT MANAGEMENT

  • 8/14/2019 Project Maagement

    2/81

    2Project Management A Managerial Prospective

    Management

    A process of working with people andresources to accomplish organizational

    goals.

    Getting things done through other people.

  • 8/14/2019 Project Maagement

    3/81

    3Project Management A Managerial Prospective

    Management (Contd)

    The process of achieving organizationalgoals through planning, organizing,

    leading, and controlling the human,physical, financial and informational

    resources of the organization.

  • 8/14/2019 Project Maagement

    4/81

    4Project Management A Managerial Prospective

    Managerial Functions

    Planning

    Organizing

    Leading

    Controlling

  • 8/14/2019 Project Maagement

    5/81

    5Project Management A Managerial Prospective

    Manager as a.

    Planner

    Organizer

    Leader

    Controller

    Motivator

    Facilitator

    Coordinator

    Problem Solver

    Decision Maker

    Negotiator

    Strategist

  • 8/14/2019 Project Maagement

    6/81

    6Project Management A Managerial Prospective

    What is a Problem.....

  • 8/14/2019 Project Maagement

    7/81

    7Project Management A Managerial Prospective

    Decision:

    The choice made from among alternatives.

    Decision making:The process of organizing a problem,

    generating and weighting alternativescoming to a decision and taking actionwith feedback.

  • 8/14/2019 Project Maagement

    8/81

    8Project Management A Managerial Prospective

    Conditions of Decision making: Certainty

    Risk

    Uncertainty

    Ambiguity

  • 8/14/2019 Project Maagement

    9/81

    9Project Management A Managerial Prospective

    Project

    Culture of a Project- Norms of an Organization

    - Conflicts

    Importance of Human Factor in Projects

    Project

  • 8/14/2019 Project Maagement

    10/81

    10Project Management A Managerial Prospective

    Project Management

    The process of controlling of a project from

    beginning to an end to achieve projectobjectives in a given time.

  • 8/14/2019 Project Maagement

    11/81

    11Project Management A Managerial Prospective

    Project Management (Contd)A project is a well-defined set of tasks/activities that must all

    be completed in order to meet the projects goals.

    Each task may be started/stoppedindependently

    Tasks must be performed in a givensequence

  • 8/14/2019 Project Maagement

    12/81

    12Project Management A Managerial Prospective

    Laws of Project Management

    Projects progress quickly until they are 90% complete.Then they remain at 90% complete forever.

    When things are going well, something will go wrong.

    When things just cant get worse, they will. When thingsappear to be going better, you have overlookedsomething.

    If project content is allowed to change freely, the rate of

    change will exceed the rate of progress. Project teams detest progress reporting because it

    manifests their lack of progress.

  • 8/14/2019 Project Maagement

    13/81

    13Project Management A Managerial Prospective

    Trade-offs in Project ManagementTrade-offs in Project Management

    Performance

    Cost Time

  • 8/14/2019 Project Maagement

    14/81

    14Project Management A Managerial Prospective

    Activity NetworksActivity Networks

    Which tasks have to be completed first?

    Which tasks rely on the results of othertasks?

    Which tasks generate results forsubsequent tasks

  • 8/14/2019 Project Maagement

    15/81

    15Project Management A Managerial Prospective

    Work Breakdown Structure(WBS)Work Breakdown Structure(WBS)

    A hierarchical decomposition of all the tasks to be

    accomplished for a project to be completed.

  • 8/14/2019 Project Maagement

    16/81

    16Project Management A Managerial Prospective

    A WBS is Not !!!A WBS is Not !!!

    An Organizational chart

    Not a flow chart showing temporal orlogical relationships among tasks

    A listing of skills required to complete the

    task

  • 8/14/2019 Project Maagement

    17/81

    17Project Management A Managerial Prospective

    Why do projects fail?Why do projects fail?

    Reliance on project management softwarerather than an understanding of project

    management principles Communication problems

    Failure to adequately adjust for changes

    during the course of the project

  • 8/14/2019 Project Maagement

    18/81

    18Project Management A Managerial Prospective

    Project Team and Its Required Area of Expertise

    Project Management

    1. Standard

    Regulation2.Projec

    t

    Enviro

    nment

    3.Gen

    eral

    Mana

    gement

    Kno

    wledg

    e&

    Sk

    ills

    A. Interpersonal

    Skills

  • 8/14/2019 Project Maagement

    19/81

    19Project Management A Managerial Prospective

    Standard:Standard:

    A document established by the consensusand approved by organized body.

    Requirement imposed by the Government bodies.

    Regulation:Regulation:

  • 8/14/2019 Project Maagement

    20/81

    20Project Management A Managerial Prospective

    Under Standing Project Environment

    Cultural & Social Environment:

    The teams need to understand how the project

    affect the people and how the people affect the

    project.

  • 8/14/2019 Project Maagement

    21/81

    21Project Management A Managerial Prospective

    Under Standing Project Environment(Contd)

    Physical Environment:

    Project people norms

    If the project will affect its physical surroundings, some team

    members should be knowledgeable about the local ecology and

    physical geography that could affect the project or be affected by

    the project.

  • 8/14/2019 Project Maagement

    22/81

    22Project Management A Managerial Prospective

    General Management Knowledge & Skill

    Financial Management & Accounting

    Purchasing & Procurement

    Sales & Marketing

    Contracts & Commercial Laws

    Logistics & Supply Chain

  • 8/14/2019 Project Maagement

    23/81

    23Project Management A Managerial Prospective

    Interpersonal Skills

    Communication

    Leadership

    Motivation

    Negotiation & Conflict Management

    Problem Solving

    MBO

  • 8/14/2019 Project Maagement

    24/81

    24Project Management A Managerial Prospective

    Cost Estimation

    Cost Budgeting

    Cost Controlling

    Project Cost Management

  • 8/14/2019 Project Maagement

    25/81

    25Project Management A Managerial Prospective

    Project Cost Management

    Project Cost Management includes theprocesses involved in planning,

    estimating, budgeting, and controllingcosts so that the project can be completed

    within the approved budget.

  • 8/14/2019 Project Maagement

    26/81

    26Project Management A Managerial Prospective

    Life Cycle Costing

    Cost Management should also consider theeffect of project decisions on the cost ofusing, maintaining and supporting the

    product, services or results. Life CycleCosting should improve decision makingand is used to reduce cost and execution

    time and to improve the quality andperformance of the project deliverable.

  • 8/14/2019 Project Maagement

    27/81

    27Project Management A Managerial Prospective

    Accounting Terminologies

    Opportunity Cost

    Sunk Cost

    Direct vs Indirect Project Cost

    Variable and Fixed Project Cost

    Controllable and Non-Controllable Project Cost

    Depreciation

  • 8/14/2019 Project Maagement

    28/81

    28Project Management A Managerial Prospective

    Cost Management Plan

    Process Description

    Reporting Formats

    Precision Levels

    Units of Measure

    Organizational Procedures LinksControl Thresholds

    Earned Value Rules

    Cost Management Plan

  • 8/14/2019 Project Maagement

    29/81

    29Project Management A Managerial Prospective

    Cost Estimating

    Developing an approximation of the costs

    of the resources needed to complete the

    project activities

  • 8/14/2019 Project Maagement

    30/81

    30Project Management A Managerial Prospective

    Cost Estimating (Contd)

    Input Tools & Techniques Output

    1. Enterprise Environmentalfactors

    2. Organizational ProcessAssets

    3. Project Scope Statement4. Work Breakdown Structure5. Project Management Plan

    Schedule managementplan

    Staffing management plan Risk register

    1. Analogous estimating2. Determine resource cost

    rates3. Bottom up estimating

    4. Project Managementsoftware5. Vendor bid Analysis6. Reserve Analysis7. Cost of Quality

    Activity cost estimates

  • 8/14/2019 Project Maagement

    31/81

    31Project Management A Managerial Prospective

    Reserve Analysis

    An analytical technique to determine theessential features and relationships of

    components in the project managementplan to establish a reserve for the

    schedule duration, budget, estimated cost

    or funds for a project.

  • 8/14/2019 Project Maagement

    32/81

    32Project Management A Managerial Prospective

    Activity Cost Estimate

    An activity cost estimate is a quantitativeassessment of the likely costs of the

    resources required to complete schedule

    activities.This includes but not limited to labor, materials,

    equipment, services, facilities, information

    technology and special category such as aninflation allowance or cost contingency reserve.

  • 8/14/2019 Project Maagement

    33/81

    33Project Management A Managerial Prospective

    Cost Budgeting

    Aggregating the estimated costs of

    individual activities or work packages to

    establish a cost baseline.

  • 8/14/2019 Project Maagement

    34/81

    34Project Management A Managerial Prospective

    Cost Budgeting

    Input Tools & Techniques Output

    1. Preliminary Scope Statement

    2. Work break down structure

    3. WBS dictionary

    4. Activity cost estimates

    5. Project Schedule

    6. Resource Calendar

    7. Contract

    8. Cost Management Plan

    1. Cost Aggregation

    2. Reserve Analysis

    3. Parametric

    Estimating

    4. Funding Limit

    Reconciliation

    1. Cost Baseline

    2. Project Funding Requirement

    3. Cost Management Plan (Up dates)

    4. Requested Changes

  • 8/14/2019 Project Maagement

    35/81

    35Project Management A Managerial Prospective

    Fund Limit Reconciliation

    Large variations in the periodic expenditure of

    funds are usually undesirable for organizational

    operations. Therefore the expenditure of funds is

    reconciled with the funding limits set by the

    customer or performing organization on the

    disbursement of the funds for the project.

  • 8/14/2019 Project Maagement

    36/81

    36Project Management A Managerial Prospective

    Budget

    The approval estimate for the project or any work breakdown

    structure component or any schedule activity.

    Cost BaselineThe cost base line is a time phased budget that is used as a basis

    against which to measure, monitor and control overall cost

    performance on the project. The cost baseline is the component

    of the project management plan.

  • 8/14/2019 Project Maagement

    37/81

    37Project Management A Managerial Prospective

    Project Funding Requirements

    Funding requirements, total and periodic (e.g. annual

    or quarterly) are derived from the cost baseline and

    can be established to exceed. Usually by a margin

    to allow for either early performance/progress or

    cost overruns. The total funds required are those

    included in the cost baseline plus the management

    contingencies reserve account.

  • 8/14/2019 Project Maagement

    38/81

    38Project Management A Managerial Prospective

    Cost Control

    Influencing the factor that create cost

    variances and controlling changes to the

    project budget.

  • 8/14/2019 Project Maagement

    39/81

    39Project Management A Managerial Prospective

    Cost Controls

    Budget at Completion (The amount youbudgeted for the entire project)

    Estimate at Completion (The amount that you

    expect that the total project to cost) Estimate to Complete (From the point on, how

    much more we expect the project to cost to finish theproject)

    Variance at Completion (How much over orunder budget we expect to have)

  • 8/14/2019 Project Maagement

    40/81

    40Project Management A Managerial Prospective

    Project Risk Management

    Project Risk Management includes the processes

    concerned with conducting risk management planning,

    identification, analysis, responses and monitoring and

    control on a project.

    The objective of the risk management is to increase the

    probability and impact of positive events and decreasethe probability and impact of events adverse to project

    objectives.

  • 8/14/2019 Project Maagement

    41/81

    41Project Management A Managerial Prospective

    Risk

    An uncertain event or condition that if it occurs has apositive or negative effect on a projects objectives.

    Triggers

    Indications that a risk has occurred or is about o occur. Triggers may be discovered in the risk identifications process

    and watched in the risk monitoring and control process. Triggers are some time called risk symptoms or warning signs.

  • 8/14/2019 Project Maagement

    42/81

    42Project Management A Managerial Prospective

    Project Risk Management

    Risk Management Planning

    Risk Identification

    Quantitative Risk Analysis Qualitative Risk Analysis

    Risk Response Planning

    Risk Monitoring & Controls

  • 8/14/2019 Project Maagement

    43/81

    43Project Management A Managerial Prospective

    Project Procurement ManagementProject Procurement Management Includes the

    process to purchase or acquire the products,services, or results needed from outside the

    project team to perform the work.

  • 8/14/2019 Project Maagement

    44/81

    44Project Management A Managerial Prospective

    Project Procurement Management

    1. Plan

    Purchase or

    Acquisition

    2. Make or Buy

    3. Plan

    Contracting

    1. Floatrequest/

    Tendering

    2. Receive Bid

    or Quote

    3. Selection ofvendor

    4. Contract

    awarding

    1. Contract

    Administratio

    n

    2. Managing

    Interfaceamong

    various

    providers

    1. Contract

    Closure

    2. Post

    procurement

    Audit

    3. Post

    performance

    evaluation

    Project ProcurementManagement

    Planning Executing Monitoring &

    Controlling

    Closing

  • 8/14/2019 Project Maagement

    45/81

    45Project Management A Managerial Prospective

    Plan Purchase or Acquisition

    Determination of What to purchase, why and

    when to purchase.

    Make or Buy Analysis

    It is a general management technique that can be used to determine

    whether a particular product or service can be produced by the project

    team or buy from the market.

  • 8/14/2019 Project Maagement

    46/81

    46Project Management A Managerial Prospective

    ContractA contract is normally binding agreement that obliges the seller to

    provide the specified product and obligates the buyer to pay for it.

    Contract Fundamentals

    A contract may be written or oral and is both a legal

    document and a relationship between the parties

  • 8/14/2019 Project Maagement

    47/81

    47Project Management A Managerial Prospective

    Type of Contract

    Fixed Price of

    Lump-Sum ContractsCost Reimbursable

    Contracts

    Time & Material

    Contract

    Contracts

  • 8/14/2019 Project Maagement

    48/81

  • 8/14/2019 Project Maagement

    49/81

    49Project Management A Managerial Prospective

    Fixed Price or Lump-Sum Contract

    A type of contract involving a fixed total price for a well definedproduct.

    Fixed price contracts may also include incentives for meeting orexceeding project objective such as schedule targets.

    Cost Reimbursable Contracts

    A type of contract involving payment by the buyer to the seller for the sellersactual cost plus a fee typically representing sellers profit. These type ofcontracts often includes some incentive clauses.

    Time & Material Contract

    A type of contract that is a hybrid contractual agreement containingaspects of both i.e. Fixed price & Cost Reimbursable Contracts

  • 8/14/2019 Project Maagement

    50/81

    50Project Management A Managerial Prospective

    Contract Type Selection

    What Contract type might best suit the project?

    Degree of Cost and Schedule Risk

    How Complex is the requirement Cost & Price Analysis

    Urgency of the Deliverables

    Frequency of Changes

    Degree of definition of the statement of the work

  • 8/14/2019 Project Maagement

    51/81

    51Project Management A Managerial Prospective

    Project Evaluation and Review Technique(PERT) /Critical Path Method (CPM)

    Graphical display of interrelationships amongactivities and the order of project activities

    Allows estimates of completion time and cost

  • 8/14/2019 Project Maagement

    52/81

    52Project Management A Managerial Prospective

    PERT / CPM

    1. List activities and duration; develop WBS.

    2. Order activities through use of Gannt chart.

    3. Develop immediate precedent activities.

    4. Draw project graph.

    5. Calculate early start / early finish.

    6. Calculate late start / late finish.

    7. Determine critical path using slack time.8. Crash project

  • 8/14/2019 Project Maagement

    53/81

    53Project Management A Managerial Prospective

    Example(Build a new mountain bike)

    A major manufacturer of bicycles is planning to enter the

    high-end market for mountain bikes by designing a new,

    state-of-the-art mountain bike. The bicycle is to be a

    completely new design, and management has directed

    the design team to incorporate the latest technology in

    every facet of the productframe, gears, wheels,brakes, and so onyet keep the price of the bike within

    $100 of leading competitors prices.

    A ti iti & D ti Ti

  • 8/14/2019 Project Maagement

    54/81

    Activities & Duration Times

    Activity Expected Duration(months)

    A Do preliminary market analysis 1.0

    B Develop preliminary market designs 3.0

    C Do preliminary manufacturing study 1.0

    D Evaluate and select best product design 1.0

    E Develop detailed marketing plans 1.0

    F Design manufacturing process 3.0

    G Develop detailed product design 3.0

    H Build and test prototype 1.0

    I Finalize product design 1.5

    J Order components 1.0

    K Order production equipment 3.0

    L Install production equipment 2.0

  • 8/14/2019 Project Maagement

    55/81

    55Project Management A Managerial Prospective

    Work Breakdown Structure (WBS)

    The set of independent tasks or work packagesthat constitute a project

    Hierarchy of sub-projects that make of the totalproject

    Useful for controlling costs, time, and resourceallocation

    Partial Work Breakdown Structure

  • 8/14/2019 Project Maagement

    56/81

    56Project Management A Managerial Prospective

    Partial Work Breakdown Structure(for step G)

    Mountain

    Bike

    WheelSystems

    GearingSystems

    FrameSystems

    Seat SystemsBrake

    Systems

    Hubs

    Rims &Spokes

    Gears &Chains

    Derailleur &Shifters

    Fork SystemFrame

    Structure

    BearingSystems

    TubingStructure

    JoiningSystems

    Tubing

    Cover &Padding

    SeatStructure

    Calipers

    Levers &Cables

    G tt Ch t

  • 8/14/2019 Project Maagement

    57/81

    57Project Management A Managerial Prospective

    Gantt Chart(for mountain bike development project)

    A Do preliminary market analysis

    B Develop preliminary market designs

    C Do preliminary manufacturing study

    D Evaluate and select best product design

    E Develop detailed marketing plans

    F Design manufacturing process

    G Develop detailed product design

    H Build and test prototype

    I Finalize product design

    J Order components

    K Order production equipment

    L Install production equipment

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

    Time in Months

    Precedence Relationships

  • 8/14/2019 Project Maagement

    58/81

    Precedence Relationships

    Activity ImmediatePredecessor

    A Do preliminary market analysis --

    B Develop preliminary market designs A

    C Do preliminary manufacturing study A

    D Evaluate and select best product design B, C

    E Develop detailed marketing plans D

    F Design manufacturing process D

    G Develop detailed product design D

    H Build and test prototype G

    I Finalize product design F, H

    J Order components I

    K Order production equipment I

    L Install production equipment E, J, K

  • 8/14/2019 Project Maagement

    59/81

    59Project Management A Managerial Prospective

    A

    C

    B

    D

    ES EF

    LS LF

    (Duration)

    ES = Early Start

    EF = Early Finish

    LS = Late Start

    LF = Late Finish

    PERT / CPM Chart Structure

  • 8/14/2019 Project Maagement

    60/81

    Project Management A Managerial Prospective

    A

    C

    B

    D

    E

    F

    G H

    I J

    K

    L

    PERT / CPM Chart

  • 8/14/2019 Project Maagement

    61/81

    Project Management A Managerial Prospective

    A(1)

    C(1)

    B(3)

    D(1)

    E(1)

    F(3)

    G(3) H(1)

    I(1.5) J(1)

    K(3)

    L(2)

    0 1

    1 4

    1 2

    5 6

    5 8

    5 8

    9 10.5

    8 9

    10.5 11.5

    10.5 13.5

    13.5 15.5

    4?Or2?4 5

    Early Start / Early Finish(start with A)

  • 8/14/2019 Project Maagement

    62/81

    Project Management A Managerial Prospective

    0 1

    1 4

    1 2

    5 6

    5 8

    5 8

    9 10.5

    8 9

    10.5 11.5

    10.5 13.5

    13.5 15.5

    4 5

    Late Start / Late Finish(start with L)

    A(1)

    C(1)

    B(3)

    D(1)

    E(1)

    F(3)

    G(3) H(1)

    I(1.5) J(1)

    K(3)

    L(2)

    13.5 15.5

    12.5 13.5

    10.5 13.5

    9 10.5

    8 95 8

    6 9

    12.5 13.5

    4 5

    3 4

    1 4

    0 1

  • 8/14/2019 Project Maagement

    63/81

    63Project Management A Managerial Prospective

    Calculating Slack Time to Find the Critical Path

    Slack time tells us how long a particular activity can bedelayed without delaying the entire project

    Assumption: All preceding activities completed as early

    as possible

    Slack = LS ES or Slack = LF-EF

  • 8/14/2019 Project Maagement

    64/81

    64Project Management A Managerial Prospective

    Calculating Slack Time

    Activity Duration ES EF LS LF SlackA 1 0 1 0 1 0

    B 3 1 4 1 4 0

    C 1 1 2 3 4 2

    D 1 4 5 4 5 0

    E 1 5 6 12.5 13.5 7.5

    F 3 5 8 6 9 1G 3 5 8 5 8 0

    H 1 8 9 8 9 0

    I 1.5 9 10.5 9 10.5 0

    J 1 10.5 11.5 12.5 13.5 2

    K 3 10.5 13.5 10.5 13.5 0

    L 2 13.5 15.5 13.5 15.5 0

    The critical path lies through those activities with no slack time.

  • 8/14/2019 Project Maagement

    65/81

    Project Management A Managerial Prospective

    Critical Path

    1 2

    5 6

    5 8 10.5 11.5

    C(1)

    E(1)

    F(3) J(1)

    12.5 13.56 9

    12.5 13.5

    3 4

    9 10.5

    0 1

    1 4

    5 8

    9 10.5

    8 9 10.5 13.5

    13.5 15.5

    4 5

    A(1)

    B(3)

    D(1)

    G(3) H(1)

    I(1.5)

    K(3)

    L(2)

    13.5 15.5

    10.5 13.58 95 8

    4 5

    1 4

    0 1

  • 8/14/2019 Project Maagement

    66/81

    66Project Management A Managerial Prospective

    Project Crashing

    (Accounting for the Time/ Cost Trade-off)

    What if the project cant be completed within thetargeted time?

    Can the project be shortened by adding moreresources?

    If so, do the necessary resources exist?

  • 8/14/2019 Project Maagement

    67/81

    67Project Management A Managerial Prospective

    Project Crashing (Crunching)

    1. Determine if critical path (CP) falls withintargeted time. If yes, stop.

    2. If no, compute crash cost per time period foreach activity.

    3. Select activity on CP with lowest crash costand crash.

    4. Re-compute CP and check to see if within

    targeted time.5. Repeat as necessary.

  • 8/14/2019 Project Maagement

    68/81

    68Project Management A Managerial Prospective

    Critical Path Enumeration

    A-B-D-E-L 8A-B-D-F-I-J-L 12.5A-B-D-F-I-K-L 14.5A-B-D-G-H-I-J-L 13.5A-B-D-G-H-I-K-L 15.5

    A-C-D-E-L 6A-C-D-F-I-J-L 10.5A-C-D-F-I-K-L 12.5A-C-D-G-H-I-J-L 11.5A-C-D-G-H-I-K-L 13.5

  • 8/14/2019 Project Maagement

    69/81

    69Project Management A Managerial Prospective

    Critical Path CrashingA-B-D-E-L 8A-B-D-F-I-J-L 12.5A-B-D-F-I-K-L 14.5

    A-B-D-G-H-I-J-L 13.513A-B-D-G-H-I-K-L 15.515A-C-D-E-L 6A-C-D-F-I-J-L 10.5A-C-D-F-I-K-L 12.5

    A-C-D-G-H-I-J-L 11.511A-C-D-G-H-I-K-L 13.513

    Spent $20 to shorten0.5 months

    Critical Path Crashing

  • 8/14/2019 Project Maagement

    70/81

    70Project Management A Managerial Prospective

    Critical Path Crashing

    A-B-D-E-L 8A-B-D-F-I-J-L 12.5A-B-D-F-I-K-L 14.5

    A-B-D-G-H-I-J-L 1311A-B-D-G-H-I-K-L 1513A-C-D-E-L 6A-C-D-F-I-J-L 10.5A-C-D-F-I-K-L 12.5

    A-C-D-G-H-I-J-L 119A-C-D-G-H-I-K-L 1311

    New CP

    (1)

    (2)

    (2)

    (2)

    (3)

    Critical Path Crashing

  • 8/14/2019 Project Maagement

    71/81

    71Project Management A Managerial Prospective

    Critical Path Crashing

    A-B-D-E-L 86A-B-D-F-I-J-L 12.510.5A-B-D-F-I-K-L 14.512.5

    A-B-D-G-H-I-J-L 119A-B-D-G-H-I-K-L 11A-C-D-E-L 6A-C-D-F-I-J-L 10.5

    A-C-D-F-I-K-L 12.5A-C-D-G-H-I-J-L 9A-C-D-G-H-I-K-L 11

    B and I can both be crashed for$60pick one

    (I picked B)

  • 8/14/2019 Project Maagement

    72/81

    72Project Management A Managerial Prospective

    Critical Path crashingA-B-D-E-L 6

    A-B-D-F-I-J-L 10.59.5A-B-D-F-I-K-L 12.511.5A-B-D-G-H-I-J-L 98

    A-B-D-G-H-I-K-L 11 10A-C-D-E-L 6

    A-C-D-F-I-J-L 10.59.5A-C-D-F-I-K-L 12.511.5

    A-C-D-G-H-I-J-L 98A-C-D-G-H-I-K-L 1110

  • 8/14/2019 Project Maagement

    73/81

    73Project Management A Managerial Prospective

    Treating Time as Probabilistic

    What if the time estimates for completion ofproject activities arent certain?

    optimistic time

    most likely time

    pessimistic time

  • 8/14/2019 Project Maagement

    74/81

    74Project Management A Managerial Prospective

    Using Time Estimates

    1. Calculate ET = Expected Time for eachactivity.

    2. Use ET to determine CP and, if necessary, tocrash the project.

    3. Determine variance of expected time for eachactivity.

    4. Calculate Z and determine probability project

    will be completed by a desired time.

    Using Time Estimates

  • 8/14/2019 Project Maagement

    75/81

    75Project Management A Managerial Prospective

    Using Time Estimates

    Variable definitionsa = optimistic time for activity

    m = most likely time for activity

    b = pessimistic time for activityET = expected time of each activity

    2 = variance of ET for each activity

    TE= expected project completion time (CP time)

    D = desired project completion time

    CP

    2= sum of variances along CP

  • 8/14/2019 Project Maagement

    76/81

    Using Time Estimates

    1. Calculate ET for each activity

    2. Calculate TE = (ETs) along CP3. Determine variances

    4. Calculate Z (use App. E (p. 742) or NORMSDIST in Excel)

    a 4m bET

    6

    + +=

    2

    2 b a

    6

    =

    E

    2

    CP

    D TZ

    =

    Using Time Estimates

  • 8/14/2019 Project Maagement

    77/81

    77Project Management A Managerial Prospective

    Using Time Estimates

    Optimistic Most Likely Pessimistic Expected Time Variance of ETActivity a m b ET 2A 0.5 1 1.5 1 0.028

    B 2.5 3 3.5 3 0.028

    C 0.5 0.75 1 0.75 0.007

    D 0.5 1 1.5 1 0.028

    E 0.5 0.75 1 0.75 0.007

    F 2 2.5 3 2.5 0.028G 2 4 6 4 0.444

    H 1 2 3 2 0.111

    I 0.5 1.5 2.5 1.5 0.111

    J 0.5 1 1.5 1 0.028

    K 1 2 3 2 0.111

    L 1 1.5 2 1.5 0.028

  • 8/14/2019 Project Maagement

    78/81

    Project Management A Managerial Prospective

    A(1)

    C(.75)

    B(3)

    D(1)

    E(.75)

    F(2.5)

    G(4) H(2)

    I(1.5) J(1)

    K(2)

    L(1.5)

    0 1

    1 4

    1 1.75

    5 5.75

    5 7.5

    5 9

    11 12.5

    9 11

    12.5 13.5

    12.5 14.5

    14.5 164 5

    Early Start / Early FinishUsing ET

    0 1

    1 4

    3.25 4

    4 5

    13.75 14.5

    8.5 11

    5 9

    11 12.5

    9 11 12.514.5

    13.5 14.5

    14.5 16

    Using Time Estimates

  • 8/14/2019 Project Maagement

    79/81

    Using Time EstimatesCritical Path

    Activity ET 2 ES EF LS LF SlackA 1 0.028 0 1 0 1 0

    B 3 0.028 1 4 1 4 0

    C 0.75 0.007 1 1.75 3.25 4 2.25

    D 1 0.028 4 5 4 5 0

    E 0.75 0.007 5 5.75 13.75 14.5 8.75

    F 2.5 0.028 5 7.5 8.5 11 3.5

    G 4 0.444 5 9 5 9 0

    H 2 0.111 9 11 9 11 0I 1.5 0.111 11 12.5 11 12.5 0

    J 1 0.028 12.5 13.5 13.5 14.5 1

    K 2 0.111 12.5 14.5 12.5 14.5 0

    L 1.5 0.028 14.5 16 14.5 16 0

    Critical Path: A-B-D-G-H-I-K-L

    TE = 1+3+1+4+2+1.5+2+1.5 = 16

    CP = .028+.028+.028+.444+.111+.111+.111+.028 = .889

    Note: individual variances contain rounding errorsee imbedded Excel worksheet above,double click and scroll down

  • 8/14/2019 Project Maagement

    80/81

    80Project Management A Managerial Prospective

    Using Time Estimates

    E

    2

    CP

    T 16

    .889

    D 12

    12 16Z 4.24 ~ 4.0

    .889

    =

    =

    =

    = =

    Using Appendix E, p. 742,probability project will be completed

    in 12 months is .00003 or .003%

    Using NORMSDIST(4.24) in Excel,probability project will be completedin 12 months is .0011%

    See calculations in imbedded Excelfile on previous slide.

  • 8/14/2019 Project Maagement

    81/81

    The End