  • 8/4/2019 Project Implementation Control

    1/22

    Copyright Wondershare Software

    Project Implementation andProject Implementation and

    ControlControl

    Presented by:

  • 8/4/2019 Project Implementation Control

    2/22

    Copyright Wondershare Software

    INTRODUCTIONINTRODUCTION

    BackgroundBackground Any real project is very complex. Many of

    the issues of project management are too

    difficult to be solved.

    This paper presents a structured approach

    for execution, monitoring and control of

    project activities at operational level.

    Many technologies and methods are

    developed for successful monitoring and

    control to lead the project to success.

  • 8/4/2019 Project Implementation Control

    3/22

    Copyright Wondershare Software

    Setting up an efficient control system

    the efficient management framework

    including :

    a. Reporting structure

    b. Assessing progress

    c. Communication system

  • 8/4/2019 Project Implementation Control

    4/22

    Copyright Wondershare Software

    PROJECT EXECUTION PROCESSPROJECT EXECUTION PROCESS

  • 8/4/2019 Project Implementation Control

    5/22

    Copyright Wondershare Software

    CLASSIFICATION AND PRIORITIZATIONCLASSIFICATION AND PRIORITIZATION

    Some of the characteristics of activities are as follows:

    y Effect on other activities

    y Technology Content and Quality Requirement

    y Requirement of Coordination

    y Coordination with External Agencies

    C = c1w1+ c2w2 + c3w3+c4w4

    C= criticality index of activity

    c1, c2, c3, c4 are rating of activity on different process characteristics

    W1 ,w2 , w3 , w4 are weights assigned to thesecharacteristics.

  • 8/4/2019 Project Implementation Control

    6/22

    Copyright Wondershare Software

    PrePre--Review for Activity ExecutionReview for Activity Execution

    Index to determine the level of readiness

    for executing an activity can be expressed

    as under.

    R = r1w1+ r2w2 + r3w3+ r4w4

    Where R is readiness index for executing an

    activity, r1, r2, r3 and r4 are rating of

    current preparation level for executing an

    activity on different parameters and w1,

    w2, w3 and w4 are corresponding weights

    assigned to these parameters.

  • 8/4/2019 Project Implementation Control

    7/22

    Copyright Wondershare Software

    PLAN, ISSUES, AND DECISIONSPLAN, ISSUES, AND DECISIONS

    DESIGN

    METHODOLOGY INPUT

    TIME SCHEDULE

    PLAN

  • 8/4/2019 Project Implementation Control

    8/22

    Copyright Wondershare Software

    PLAN, ISSUES, DECISIONSPLAN, ISSUES, DECISIONS

  • 8/4/2019 Project Implementation Control

    9/22

    Copyright Wondershare Software

    PLAN, ISSUES, AND DECISIONSPLAN, ISSUES, AND DECISIONS

  • 8/4/2019 Project Implementation Control

    10/22

    Copyright Wondershare Software

    DECISION MAKING FOR ACTIVITYDECISION MAKING FOR ACTIVITY

    EXECUTIONEXECUTION

    According to Siomn (1960), the decision makingprocess consists of 3 phases :

    1. Intelligence Phase2. Design Phase

    3. Choice Phase

  • 8/4/2019 Project Implementation Control

    11/22

    Copyright Wondershare Software

    STRUCTURED DOCUMENTATIONSTRUCTURED DOCUMENTATION

  • 8/4/2019 Project Implementation Control

    12/22

    Copyright Wondershare Software

    STRUCTURED DOCUMENTATIONSTRUCTURED DOCUMENTATION

  • 8/4/2019 Project Implementation Control

    13/22

    Copyright Wondershare Software

    Time and cost monitor and control

    1. Ranking the priority of monitoring

    - rank the activity

    - monitoring the activities with no free

    float remaining

    - monitoring the activities with less

    than a specified float

    - monitoring high risky activities

    -monitoring the activities using critical

    resources

  • 8/4/2019 Project Implementation Control

    14/22

    Copyright Wondershare Software

    2. Method of time control

    - CPM

    avoids delay or can shorten the time

    activitiesa. increasing resource levels

    b. improving resource efficiency

    c. shorten critical path timescales tobring a project back on target

  • 8/4/2019 Project Implementation Control

    15/22

    Copyright Wondershare Software

    - Non delay approach

    adjusts various resources when urgency burstinto the activity on the critical path.

    - Precedence requirementScheduling the activities based on the

    availability of the process.

    - Optimal timing

    determine the optimal frequency of the

    monitoring and reviewing to different

  • 8/4/2019 Project Implementation Control

    16/22

    Copyright Wondershare Software

    - Crashing

    minimization of the pessimistic time estimate

    in PERT (Program Evaluation and Review

    Technique) networks by investing additional

    amounts of money in the activities on the

    critical path.

  • 8/4/2019 Project Implementation Control

    17/22

    Copyright Wondershare Software

    3. Methods of cost control

    To control these cost, managers should first setup a cost control system to:

    a) Allocate responsibilities for administration

    and analysis of financial data

    b) Ensure all costs are properly allocated

    against project codes

    c) Ensure all costs are genuinely in pursuit of

    project activities

    d) Ensure contractors payments areauthorized

    e) Check that other projects are not using

    the budget

  • 8/4/2019 Project Implementation Control

    18/22

    Copyright Wondershare Software

    4. Change monitor and control

    An effective change control system should beestablished to ensure change procedure is

    clear and unambiguous and easy for employee

    to request a change

  • 8/4/2019 Project Implementation Control

    19/22

    Copyright Wondershare Software

    Special case ofSpecial case of A Performance Measurement View of ITA Performance Measurement View of IT

    Project ManagementProject Management

    `The MCDA-C is a development of themulticriteria decision aiding methodology(MCDA), as a way to give support to decisionmakers in complex, conflicting, uncertaincontexts, where the decision makers want toimprove their understanding of the situation(Ensslin et al., in press).

    `This methodology enables the organization to

    improve its decisions process and choose theprojects that contribute most to theorganizations success.

  • 8/4/2019 Project Implementation Control

    20/22

    Construction of the multicriteria

    model - procedures

    Fig 1. The MCDAFig 1. The MCDA--C decision aiding phasesC decision aiding phases

  • 8/4/2019 Project Implementation Control

    21/22

    Copyright Wondershare Software

    Multicriteria model of projectMulticriteria model of project

    evaluationevaluation

    Step 1 : Contextualization

    Step 2 : Hierarchical structure of value

    Step 3 : Construction of descriptors

    Step 4 : independence analysis

    Step 5 : Construction of values functions

    and indentification of conversion rates Step 6 : Identification of impact profile of

    alternatives

    Step 7 : Sensitivity analysis

  • 8/4/2019 Project Implementation Control

    22/22

    Copyright Wondershare Software

    ConclusionConclusion

    A successful project can be predicted by :

    Criticality and Readiness index of each

    activity for selective monitoring and control Recognize and rank the important factors

    affecting time and budget target.

    Use MCDA-C software