PROJECT BRIEFING ON SECTION 16 STATION FOR PHILEO DAMANSARA 1
4 JULY 2013
PACKAGE V4 : SECTION 17 - SEMANTAN
Topics of Discussion
• Introducing Mass Rapid Transit
• Section 16 MRT Station
• Entrance A
• Typical Cross Section at Section 16 Station
• Construction Activities & Schedule
• Traffic Management Plan
• Working Hours
2
• Location: Section 17 – Semantan Portal
• Length: 6.6km
• No. of Stations: 3 nos
Section 16
Pusat Bandar Damansara (PBD)
Semantan
• No. of piers: 199 nos
4
PROJECT INFORMATION
PACKAGE V4 – SECTION 17 TO SEMANTAN PORTAL
BANGSAR
SECTION 17
KGPA
BUKIT DAMANSARA V4
V4
V3
VICTORIA
STATION
5
• The station is an island type platform served by 2
entrances, Entrance A on the south and B on the north.
• A multi-storey park and ride shall be constructed as support
facility at north-east of the station.
• Entrance A is located near Phileo Damansara / SIBKL
buildings connected to the station by an overhead
pedestrian link bridge over Sprint Highway
7
SECTION 16 MRT STATION INFORMATION
8
BHP
SECTION 17
PETRONAS
LINK BRIDGE SPANNING
OVER SPRINT HIGHWAY
ENTRANCE A
ENTRANCE B
PHILEO
DAMANSARA 1
SIBKL MULTISTOREY
PARK & RIDE
SECTION 16 MRT STATION
SITE LOGISTIC PLAN FOR ENTRANCE A
13
SIBKL
PHILEO DAMANSARA 1
LEGEND
EXISTING TRAFFIC
TRAFFIC FLOW
AT SITE
15
ENTRANCE A – REAR PHOTO
- PHILEO DAMANSARA SIDE LANE DRIVEWAY
- EXIT FORM CAR PARK
±3.050M ENTRANCE A
SETBACKLINE FROM R.O.W
CONSTRUCTION SCHEDULE
SECTION 16 STATION
DESCRIPTION START FINISH
PIERS & VIADUCT JULY 2012 DEC 2016
STATION APRIL 2013 JAN 2016
ENTRANCE A MAY 2013 JUN 2015
ENTRANCE B NOV 2013 JAN 2016
LINK BRIDGE OCT 2013 FEB 2014
20
• Piling works
• Earthworks / Excavation
• Concreting Activities
• Construction Vehicles
• Construction Equipment
NAIM ENGINEERING SDN BHD WILL BE MONITORING DUST, NOISE AND AIR QUALITY AT ALL TIMES.
GENERAL CONSTRUCTION ACTIVITIES
22
TANDAS
SEPTICTANK
KABINPEJABAT
KONTENASETOR
SETOR BAHAN /TAPAK FABRIKASI
PINTUMASUK
WAS
H TR
OUG
H
PAPAN TANDAPROJEK
working area
•Reduce existing lanes width upon authorities’ approval.
•Install proper traffic and safety signage’s at visible locations.
•Maintain cleanliness adjacent to construction area.
•Sufficient flagman and signaling during critical activities.
•Approval from authority will be obtained for any night works required.
23
MEASURES WILL BE TAKEN FOR TRAFFIC MANAGEMENT
25
Normal working hours: 7am – 7pm
Boring & micropile: 8am – 10pm
WORKING HOURS AT SECTION 16 STATION
For project information, please call : • MRT Hotline at 1800-82-6868
• Sunway Construction Sdn. Bhd. contact person,
Ms. Liyana Yusoff – Executive Communications
012-2955993, [email protected]
En. Wan Mohd Izzuddin – Project Manager (NAIM)
019-3320 315, [email protected]
Mr. Chin Yuen Hin – Manager
019-6641 112, [email protected]
• MMC-Gamuda (PDP) contact person,
Mr. Chandra Kumar – Liaison Manager 019-336 2629 , [email protected]
En. Noor Azlan Salleh – Project Manager
019-233 6090, [email protected]
26