PROJECT BRIEFING ON SECTION 16 STATION FOR PHILEO DAMANSARA 1

4 JULY 2013

PACKAGE V4 : SECTION 17 - SEMANTAN

Topics of Discussion

• Introducing Mass Rapid Transit

• Section 16 MRT Station

• Entrance A

• Typical Cross Section at Section 16 Station

• Construction Activities & Schedule

• Traffic Management Plan

• Working Hours

2

3

MASS RAPID TRANSIT

• Location: Section 17 – Semantan Portal

• Length: 6.6km

• No. of Stations: 3 nos

Section 16

Pusat Bandar Damansara (PBD)

Semantan

• No. of piers: 199 nos

4

PROJECT INFORMATION

PACKAGE V4 – SECTION 17 TO SEMANTAN PORTAL

BANGSAR

SECTION 17

KGPA

BUKIT DAMANSARA V4

V4

V3

VICTORIA

STATION

5

SECTION 16 MRT STATION

6

• The station is an island type platform served by 2

entrances, Entrance A on the south and B on the north.

• A multi-storey park and ride shall be constructed as support

facility at north-east of the station.

• Entrance A is located near Phileo Damansara / SIBKL

buildings connected to the station by an overhead

pedestrian link bridge over Sprint Highway

7

SECTION 16 MRT STATION INFORMATION

8

BHP

SECTION 17

PETRONAS

LINK BRIDGE SPANNING

OVER SPRINT HIGHWAY

ENTRANCE A

ENTRANCE B

PHILEO

DAMANSARA 1

SIBKL MULTISTOREY

PARK & RIDE

SECTION 16 MRT STATION

- FLOOR PLAN OF STATION

AND RELATED STRUCTURES

9

10

ARTIST IMPRESSION - DAY VIEW

11

ARTIST IMPRESSION - NIGHT VIEW

ENTRANCE A

12

SITE LOGISTIC PLAN FOR ENTRANCE A

13

SIBKL

PHILEO DAMANSARA 1

LEGEND

EXISTING TRAFFIC

TRAFFIC FLOW

AT SITE

14

ENTRANCE A – REAR PHOTO

- PHILEO DAMANSARA ENTRANCE

15

ENTRANCE A – REAR PHOTO

- PHILEO DAMANSARA SIDE LANE DRIVEWAY

- EXIT FORM CAR PARK

±3.050M ENTRANCE A

SETBACKLINE FROM R.O.W

16

ENTRANCE A – REAR PHOTO

- PHILEO DAMANSARA ENTRANCE

17

CONSTRUCTION SCHEDULE

CONSTRUCTION SCHEDULE

SECTION 16 STATION

DESCRIPTION START FINISH

PIERS & VIADUCT JULY 2012 DEC 2016

STATION APRIL 2013 JAN 2016

ENTRANCE A MAY 2013 JUN 2015

ENTRANCE B NOV 2013 JAN 2016

LINK BRIDGE OCT 2013 FEB 2014

CONSTRUCTION ACTIVITIES

19

20

• Piling works

• Earthworks / Excavation

• Concreting Activities

• Construction Vehicles

• Construction Equipment

NAIM ENGINEERING SDN BHD WILL BE MONITORING DUST, NOISE AND AIR QUALITY AT ALL TIMES.

GENERAL CONSTRUCTION ACTIVITIES

TRAFFIC MANAGEMENT PLAN

21

22

TANDAS

SEPTICTANK

KABINPEJABAT

KONTENASETOR

SETOR BAHAN /TAPAK FABRIKASI

PINTUMASUK

WAS

H TR

OUG

H

PAPAN TANDAPROJEK

working area

•Reduce existing lanes width upon authorities’ approval.

•Install proper traffic and safety signage’s at visible locations.

•Maintain cleanliness adjacent to construction area.

•Sufficient flagman and signaling during critical activities.

•Approval from authority will be obtained for any night works required.

23

MEASURES WILL BE TAKEN FOR TRAFFIC MANAGEMENT

WORKING HOURS

24

25

Normal working hours: 7am – 7pm

Boring & micropile: 8am – 10pm

WORKING HOURS AT SECTION 16 STATION

For project information, please call : • MRT Hotline at 1800-82-6868

• Sunway Construction Sdn. Bhd. contact person,

Ms. Liyana Yusoff – Executive Communications

012-2955993, [email protected]

En. Wan Mohd Izzuddin – Project Manager (NAIM)

019-3320 315, [email protected]

Mr. Chin Yuen Hin – Manager

019-6641 112, [email protected]

• MMC-Gamuda (PDP) contact person,

Mr. Chandra Kumar – Liaison Manager 019-336 2629 , [email protected]

En. Noor Azlan Salleh – Project Manager

019-233 6090, [email protected]

26

27

ALL INFORMATION CONTAIN HEREIN IS SUBJECT TO CHANGES