proj control n earned value method

Upload: dmugalloy

Post on 08-Aug-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/22/2019 Proj Control n Earned Value Method

    1/44

    Project Control and Evaluation

  • 8/22/2019 Proj Control n Earned Value Method

    2/44

    Definition

    To evaluate a project is to attempt to determine ifthe overall status of the work is acceptable interms of intended value to the client once the job

    is finished. Project evaluation appraises the progress and

    performance of a job and compares it to whatwas originally planned.

    That evaluation provides the basis formanagement decisions on how to proceed withthe project.

  • 8/22/2019 Proj Control n Earned Value Method

    3/44

    Purposes of Project Evaluation

    Improve project performance together with themanagement of the project.

    Ensure that quality of project work does not take a back seatto schedule and cost concerns.

    Reveal developing problems early so that action can betaken to deal with them.

    Identify areas where other projects (current or future)should be managed differently.

    Keep client(s) informed of project status. This can also help

    ensure that the completed project will meet the needs ofthe client.

    Reaffirm the organizations commitment to the project forthe benefit of project team members.

  • 8/22/2019 Proj Control n Earned Value Method

    4/44

    Conducting the Project Audit

    Ideally, a project audit should be

    conducted by an independent examiner,

    who can remain objective in theassessment of information.

    However, the audit must be conducted in

    a spirit of learning, rather than in aclimate of blame and punishment.

  • 8/22/2019 Proj Control n Earned Value Method

    5/44

    Contents of the Audit Report

    1. Current project status. This is best shown by performing anearned value analysis. However, when earned valueanalysis is not used, status should still be reported asaccurately as possible.

    2. Future status. This is a forecast of what is expected tohappen in the project. Are significant deviations expectedin schedule, cost, performance, or scope? If so, the natureof such changes should be specified.

    3. Status of critical tasks. The status of critical tasks,

    particularly those on the critical path, should be reported.Tasks that have high levels of technical risk should be givenspecial attention, as should those being performed byoutside vendors or subcontractors, over which the projectmanager may have limited control.

  • 8/22/2019 Proj Control n Earned Value Method

    6/44

    Contents of the Audit Report Cont

    4. Risk assessment. Have any risks been identified thathighlight potential for monetary loss, project failure, orother liabilities?

    5. Information relevant to other projects. What has beenlearned from this audit that can or should be applied toother projects, whether in progress or about to start?

    6. Limitations of the audit. What factors might limit thevalidity of the audit? Are any assumptions suspect? Are

    any data missing or suspected of contamination? Wasanyone uncooperative in providing information for theaudit?

  • 8/22/2019 Proj Control n Earned Value Method

    7/44

    Monitoring and Controlling Process

    Group

    At the program level, monitoring andcontrolling involves obtaining andconsolidating data on status and progress

    from individual projects or program packages(i.e., non project tasks).

    Monitoring also entails interfacing with theprogram governance structure to ensure theorganization has a clear picture of the currentbenefit delivery and expected future benefits.

  • 8/22/2019 Proj Control n Earned Value Method

    8/44

    Integrated Change Control

    Integrated Change Control is the

    process of coordinating changes

    across the entire program, includingchanges to cost, quality, schedule,

    and scope

  • 8/22/2019 Proj Control n Earned Value Method

    9/44

    Resource Control

    Resource Control is the process of managing allprogram resources, and their associated cost,according to the program management plan.

    It is the process of monitoring human resourcesto ensure that committed resources are madeavailable to the program consistent withcommitments, resources are allocated within the

    program according to the plan, and resources arereleased from the program as dictated by theplan.

  • 8/22/2019 Proj Control n Earned Value Method

    10/44

    Monitor and Control Program Work

    Monitor and Control Program Work is the processof collecting, measuring and consolidatingperformance information, and assessingmeasurements and trends to generate

    improvements. The Monitor and Control Program Work Process

    focuses on individual project reporting tounderstand each projects performance as it

    relates to the overall program, as well asreporting on non-project deliverables beingproduced at the program level.

  • 8/22/2019 Proj Control n Earned Value Method

    11/44

    Issue Management and Control

    Issue Management and Control is the process ofidentifying, tracking, and closing issues effectively toensure that stakeholder expectations are aligned withprogram activities and deliverables.

    This alignment can be accomplished by severalapproaches, including modification of requirements orthe program scope, adjusting organizational policies, orchanging stakeholder expectations.

    Issue Management and Control at the program level

    can also include addressing the issues escalated fromthe constituent projects that could not be resolved atthe project level.

  • 8/22/2019 Proj Control n Earned Value Method

    12/44

    Scope Control

    Scope Control is the process for controlling changes tothe program scope. This is a formal process foraccomplishing the following tasks:

    Capturing requested changes

    Evaluating each requested change Deciding the disposition of each requested change

    Communicating a decision to impacted stakeholders

    Archiving the change request and its supporting detail

    When a request is accepted, initiating the activitiesrequired to have the change incorporated into theprogram management plan.

  • 8/22/2019 Proj Control n Earned Value Method

    13/44

    Schedule Control

    Schedule Control is the process of ensuring that theprogram will produce its required deliverables andsolutions on time.

    The activities in this process include tracking the actualstart and finish of activities and milestones against theplanned timeline, and updating the plan so that thecomparison to the plan is always current.

    Schedule Control must work closely with the other

    program and portfolio control processes.

    It involves identifying not only slippages, but alsoopportunities.

  • 8/22/2019 Proj Control n Earned Value Method

    14/44

    Cost Control

    Cost Control is the process of controlling changes to, andproducing information from, the program budget.

    It is proactive, analyzing actual cost as incurred against theplan to identify variance from the plan, and, wherepossible, doing trend analysis to predict problem areasearly.

    It is also reactive, dealing with unanticipated events ornecessary but unplanned activities that affect the budgeteither negatively or positively.

    It is frequently thought of as merely holding down cost sothat the program remains on budget, or bringing it back tobudget when there is an overrun

  • 8/22/2019 Proj Control n Earned Value Method

    15/44

    Quality Control

    It is the process of monitoring specific program deliverablesand results to determine if they fulfill quality requirements.

    It identifies faulty outcomes and allows the elimination ofcauses of unsatisfactory performance at all stages of thequality loop, from the identification of needs to theassessment of whether the identified needs have beensatisfied or not.

    It ensures that quality plans are executed at project levels,via quality reviews and project management health checks.

    it is performed throughout the program. Program results include both products and services, such as

    deliverables, management results, and cost and scheduleperformance

  • 8/22/2019 Proj Control n Earned Value Method

    16/44

    Communications Control

    Communications Control is the process of managingcommunications to inform the stakeholders about theprogram and resolve issues of interest to them.

    The Communications Control Process ensures that policiesand procedures are received, recorded, and routed to theintended recipients (through the Information DistributionProcess).

    The scope and extent of this process is much wider at theprogram level than at the project level.

    Apart from the program sponsor, the other stakeholdersinvolved in a program could include product managers,financial managers, and senior management personnel,especially those involved in strategic planning.

  • 8/22/2019 Proj Control n Earned Value Method

    17/44

    Communications Control cont

    Furthermore, since programs tend to be of largersize, greater cost, and much longer in duration,proactive communication is required with the

    community at large. Such external communications will not only

    include addressing issues specific to a program,such as environmental issues, but also managing

    public and media relations at the social andpolitical level as may be appropriate to theprogram.

  • 8/22/2019 Proj Control n Earned Value Method

    18/44

    Performance Reporting

    It is the process of consolidating performance data toprovide stakeholders with information about how resourcesare being used to deliver program benefits.

    It aggregates all performance information across projectsand non-project activity to provide a clear picture of theprogram performance as a whole.

    This information is conveyed to the stakeholders by meansof the Information Distribution process to provide themwith needed status and deliverable information.

    Additionally, this information is provided to stakeholders ofthe program and its constituent projects for the purpose ofproviding them with general and background informationabout the programs performance.

  • 8/22/2019 Proj Control n Earned Value Method

    19/44

    Risk Monitoring and Control

    Risk Monitoring and Control is the process of

    tracking identified program risks, identifying

    new risks to the program, executing risk

    response plans, and evaluating theireffectiveness in reducing risk through the

    program life cycle.

    They include oversight of risks and responsesat the project level within the program.

  • 8/22/2019 Proj Control n Earned Value Method

    20/44

    Risk Monitoring and Control cont

    Risk Monitoring and Control is an ongoing process.

    Risk monitoring involves tracking program-level riskscurrently identified in the risk response plan andidentifying new risks that emerge during the executionof the program, for example, unresolved project-levelrisks that demand resolution at the program level.

    It includes determining whether new risks havedeveloped, current risks have changed, risks have been

    triggered, risk responses are in effect where necessaryand are effective, and if program assumptions are stillvalid.

  • 8/22/2019 Proj Control n Earned Value Method

    21/44

    Program Contract Administration

    Program contract administration is the process

    of managing the relationship with sellers and

    buyers at the program level, excluding such

    processes performed at the component level.

    The process includes purchases and

    procurement of outside resources that span

    the program domain and that are not coveredby a specific project.

  • 8/22/2019 Proj Control n Earned Value Method

    22/44

    Program Contract Administration cont

    The program management team must be aware of thelegal, political, and managerial implications duringimplementation, since contractual issues can affectdeadlines, have legal and costly consequences, and can

    produce adverse publicity. The team must effectively communicate with sponsors,

    sellers, governing bodies, and the project and programmanagement teams.

    At the program level, program contract administrationrelies on the interaction of other program and projectprocesses.

  • 8/22/2019 Proj Control n Earned Value Method

    23/44

    Closing Process Group

    The Closing Process Group formalizes acceptanceof products, services, or results that bring theprogram, or a project within a program, to

    completion. The Closing Process Group includes the processes

    required to terminate formally all the activities ofa program, finalize closure of a project within the

    program and hand-off the completed product toothers, or to close a cancelled program or projectwithin the program.

  • 8/22/2019 Proj Control n Earned Value Method

    24/44

    Closing Process Group cont

    The purposes of the Closing Processes include the following:

    To demonstrate that all program benefits have beendelivered and that the scope of work has been fulfilled orto document the current state in the case of earlytermination

    To demonstrate that contractual obligations with the sellerand/or the customer have been met or to document thecurrent state in the case of early termination

    To demonstrate that all payments to the seller or from the

    customer have been delivered or to document the currentstate in the case of early termination

  • 8/22/2019 Proj Control n Earned Value Method

    25/44

    Closing Process Group cont

    To release all human resources and to demonstrate that allother resources have either been made available to otheractivities, sold, discarded, returned to the owner,transferred to the organization maintaining the product orservice, or transferred to the customer, or otherwise

    disposed of To demonstrate that all required documentation has been

    archived in the manner prescribed by the programmanagement plan, or to document the current state in thecase of early termination

    To demonstrate that any intellectual property developedduring the course of the program has been captured anddocumented for future use, in a manner that ensures legalprotection of this valuable asset

  • 8/22/2019 Proj Control n Earned Value Method

    26/44

    Closing Process Group cont

    To transition ongoing activities such as

    product support, service management, or

    customer support from a project or the

    program to an operational support function

    To leave in place a legacy of operational

    benefit sustainment, deriving optimum value

    from the work accomplished by the program.

  • 8/22/2019 Proj Control n Earned Value Method

    27/44

    Closing Process Group cont

    Program closure activities happen throughout

    the program, not just at program completion.

    As specific projects and other activities are

    completed, closing activities must occur.

    Otherwise, valuable program information will

    be lost, and there is a potential that the

    program will not meet its closure obligations.

  • 8/22/2019 Proj Control n Earned Value Method

    28/44

    Close Program

    Close Program is the process of formalizing theacceptance of the programs outcome by the sponsoror customer.

    However, administrative closure should not wait until

    the program has completed the execution process. Projects under the program need to be closed before

    the program is closed.

    As each project or each non-project activity closes, theClose Program Process should be performed to captureinformation and records, archive them, communicatethe closure event and status, and obtain sponsor orcustomer sign-off.

  • 8/22/2019 Proj Control n Earned Value Method

    29/44

    Component Closure

    Component Closure is the process of performingprogram management activities to close out a projector other non-project activity within the program.

    Program component closure deals with these closure

    issues at the program level, that is, it is informed byand performed at a higher level than normal projectclosure occurring at the project level.

    This process involves validating and ensuring that the

    project closure has indeed taken place at the projectlevel.

  • 8/22/2019 Proj Control n Earned Value Method

    30/44

    Component Closure cont

    The resources that become available may be reallocated to othercomponents that are either active or awaiting activation within theprogram.

    Project records must be closed and archived as needed.Communications to a larger or different set of stakeholders than

    those at the project level may be needed, as well. The information required for this process is obtained from each of

    the projects or work packages.

    For a program, component closure will normally be done at the endof the project life cycle.

    However, project closure may need to be done if a project is beingterminated before the completion of its life cycle. This can be theresult of a program benefits review or changes in the externalenvironment.

  • 8/22/2019 Proj Control n Earned Value Method

    31/44

    Contract Closure

    Contract Closure is the process of closing out a contract executedduring the program and on behalf of the program, in accordancewith the contracts terms and conditions.

    This process also applies to cases of premature contracttermination.

    Contract Closure involves both product verification (i.e., verifyingthat the work was done) and the updating of all contract records.

    In the case of premature termination, it involves documentation ofactual work performed plus work not performed, the circumstancesthat caused termination, and the updating of all contract records.

    Contract records are important and include the contract itself andother relevant documentation, such as progress reports, financialrecords, invoices, and payment records.

    These are often kept in a contract file, which should be part of thecomplete program file.

  • 8/22/2019 Proj Control n Earned Value Method

    32/44

    Contract Closure cont

    In the case of premature termination, it involvesdocumentation of actual work performed pluswork not performed, the circumstances thatcaused termination, and the updating of all

    contract records. Contract records are important and include the

    contract itself and other relevant documentation,such as progress reports, financial records,

    invoices, and payment records. These are often kept in a contract file, which

    should be part of the complete program file.

  • 8/22/2019 Proj Control n Earned Value Method

    33/44

    Contract Closure cont

    Contract documentation is also important

    should a procurement audit or legal action be

    initiated.

    Such an audit is a structured review of the

    procurement process from procurement

    planning through contract administration.

    In case of legal action, accurate and complete

    documentation is critical for swift resolution

  • 8/22/2019 Proj Control n Earned Value Method

    34/44

    Project closure

    All projects eventually end.

    Some end successfully, others end in disasters.

    Some common reasons why projects end poorly are:

    changing market conditions,

    lack of cooperation from clients, lack of management

    support,

    lack of resources,

    politics, technical problems, and

    poor management.

  • 8/22/2019 Proj Control n Earned Value Method

    35/44

    Learning From Past Experience

    The lessons-learned documentcaptures thesuccesses, challenges, and other information of aproject.

    Managers of similar projects in the future can

    refer to what is in the document and,consequently, operate more efficiently andeffectively.

    The lessons-learned document not only

    communicates useful information to futureproject managers, but also helps to identify theirown strengths and weaknesses.

  • 8/22/2019 Proj Control n Earned Value Method

    36/44

    Learning From Past Experience cont

    Advantages for the project manager:1. He ensures that the data are useful. This task is easy since he has

    collected reliable, valid measures throughout the project.

    2. He identifies other sources of information. Since he collected andorganized data throughout the project, this action is easy. He

    especially uses the information in the project history files.3. He assigns someone on the noncritical path to do the preliminary

    work for preparing the document.

    This includes collecting documents and data, as well as preparingthe draft. This approach allows the project manager to handleconcurrent activities during project closure.

  • 8/22/2019 Proj Control n Earned Value Method

    37/44

    Learning From Past Experience cont

    4. He solicits input from project participants forideas and information to include in the

    document. This ensures a more objective andcomplete document. He has team membersreview the draft to preclude any biased content.

    5. He submits the document to senior

    management, whose responsibility is to ensurethat it is not forgotten and apply its contents tosimilar projects in the future.

  • 8/22/2019 Proj Control n Earned Value Method

    38/44

    Releasing People and Equipment

    At closure, the project manager must release

    the people who have worked on the project.

    Releasing people is not simple.

    If released inefficiently and ineffectively,

    morale problems can occur. If theres a feeling

    of pending disaster, people may depart

    prematurely and leave tasks unfinished.

  • 8/22/2019 Proj Control n Earned Value Method

    39/44

    Releasing People and Equipment cont

    Since it is a matrix environment, the projectmanager knows that prematurely releasingpeople may mean losing them permanently.

    So he reviews the responsibility matrices andschedule to determine the remaining work.

    He then releases only those without work,since people sitting idle will in time interferewith the others productivity, spread rumors,or add unnecessary labor costs.

  • 8/22/2019 Proj Control n Earned Value Method

    40/44

    Recognizing and Rewarding People

    No project is complete without recognition foroutstanding performance.

    While conceptually simple, the project managerknows in reality its implementation is difficult. He

    must decide whether to reward individuals or theteam or both, what the most meaningfulrecognitions would be, and what rewards arewithin his power.

    These are difficult to determine; still he followssome basic principles when giving recognitionand rewards.

  • 8/22/2019 Proj Control n Earned Value Method

    41/44

    Recognizing and Rewarding People

    cont1. He strives for objectivity. He uses objective criteria for measuring

    results. It is hard to forget the past or divorce yourself from thepersonalities of the individuals. The only way to avoid thosecircumstances is to be as objective as possible.

    2. He determines the values and behaviors he wants to reward. He

    rewards these values and behaviors that best satisfy those of thecompany.

    3. He remembers the expectancy theory. Expectancy theory states thatsuccessful performance depends on peoples expectations ofrewards, whether extrinsic or intrinsic. In other words, a personsexpenditure of effort depends on his or her expectations of reward.

    If a person expects a financial reward and receives a nonfinancialone, morale might fall and productivity decline.

  • 8/22/2019 Proj Control n Earned Value Method

    42/44

    Recognizing and Rewarding People

    cont4. He appears fair and consistent. If several people gave outstanding

    performances, he gives them equal recognition and rewards. Eventhe appearance of being unfair or inconsistent can cheapen arecognition or reward.

    5. He is timely. He presents the recognitions and rewards within a

    reasonable time to gain maximum motivational value. If he givesrecognitions or rewards long after completing a milestone, forexample, they lose their meaning and impact.

    6. He does not rely on monetary rewards. In fact, he avoids them.Money provides only short-term satisfaction and can prove divisive,especially if a person feels shortchanged. He uses a variety of

    nonfinancial rewards, from plaques to dinners to trips. For manyproject managers in a matrix environment, such rewards may be allthey are entitled to dispense.

  • 8/22/2019 Proj Control n Earned Value Method

    43/44

    Project Closure Report

    A Project Closure Report is a document which

    formalizes the closure of the project.

    It provides confirmation that the criteria for

    customer acceptance have been met and

    requests sign-off from the Project Sponsor to

    close the project.

  • 8/22/2019 Proj Control n Earned Value Method

    44/44

    Project Closure Report cont

    A Project Closure Report includes:

    A formal list of completion criteria

    Confirmation that each completion criterion has beenmet

    A list of outstanding business activities, risks and issues

    A set of closure actions (to hand over projectdeliverables / documentation, terminate suppliers,

    release resources and undertake closurecommunication)

    A request for project closure approval.