progress report as of september 22, 2011. i.project statusproject status ii.s-curves-curve...

3
PROGRESS REPORT As of September 22, 2011

Upload: carly-shirley

Post on 28-Mar-2015

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule

PROGRESS REPORTAs of September 22, 2011

Page 2: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule

PRESENTATION OUTLINE

I. Project StatusII. S-CurveIII. Revised Construction ScheduleIV. Manpower ProfileV. Monthly ReportVI. Progress Photos:– Earthworks– Barge Pier Construction– Seawall Construction

Page 3: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule

-END- THANK YOU