Progress Report 2013

Baltic Retreat 2013 NCU Estonia 6th September 2013

Taisi ValdloThe NCU of Estonia

Page 2: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Overview • Total allocation for Estonia is CHF 39 920 000, total net amount available is

CHF 37 920 000

• 18 project agreements have been signed covering the total CHF 37 920 000 (100% of the total allocation).

• Reimbursements together with advance payments have been received in the amount of ~ CHF 17 173 939,31 (45%)

• Due to the end of commitment period on 14th June 2012, an amendment No II of Annex 1 to the Framework Agreement was signed on 7th June 2012. The amendment concerned reallocations in the section of Thematic Focus and Indicative Financial Allocations and no new eligible projects were included.

Page 3: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Completed projectsProject Grant (CHF) Implementation period

Project Preparation Facility 107 377,86 23.02.2009-31.07.2011 Project completion report approved on 30.01.2012

Judges conference in Tartu 91 625,76

02.06.2010-31.12.2010

Project completion report approved on 26.04.2011

Automated gait orthosis treatment

344 341,4508.11.2010-31.08.2011

Project completion report approved on 13.12.2011

License plate recognition system on public roads

460 000

25.04.2011 – 31.03.2013

Project completion report submitted to Switzerland on

01.07.2013

Improvement of court hearings 550 000

10.02.2012-31.07.2013 Project completion report is being

prepared

Page 4: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Project Grant (CHF) Implementation period

Procurement of forensic science equipment

3 500 000 28.05.2009 – 31.12.2014 Utilising reserves

Financial reporting and auditing standards

1 800 00023.01.2009 – 31.01.2014

Procurement issues. Prolongation is being drafted

Building children’s homes for children without parental care

5 640 000 08.11.2010-31.08.2011Utilising reserves

Ambulances and the integrated national communication system of alarm services

1 280 00025.02.2010 – 30.06.2014

Procurement issues and software development

Information and communication technology systems of Emergency Respond Centre

2 013 99425.02.2010 – 31.12.2014

Procurement issues and software development. Utilising reserves.

Increasing fire safety in nursing homes and hospitals 1 390 431

30.11.2010– 31.12.2013Procurement issues. Prolongation

is being drafted

Semi-compulsory treatment for

drug-addicted offenders950 000

03.08.2011-31.12.2014Issues with getting patients to

treatment

Page 5: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Project Grant (CHF) Implementation period

AFM microscopy 250 000 24.11.2011-31.12.2013

Energy efficiency in public buildings and development of new building standards

6 500 00025.05.2012 – 30.11.2015Issues with procurements.

Won’t affect deadline.

Enhancing public environmental

monitoring capacities

8 500 00024.11.2011-31.07.2015

NGO Fund2 500 000

24.11.2011-31.07.2015

Scholarship Fund1 973 337

15.05.2009-31.12.2016

Technical Assistance 85 000 15.05.2009-13.06.2017

Page 6: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Publicity

• The webpage introducing the Estonian-Swiss cooperation programme can be found by visiting www.fin.ee/shveits (or www.swiss-contribution.ee which leads to the previously mentioned page in English and in Estonian). The webpage contains main information on the projects, agreements and other relevant information concerning implementation of the Estonian-Swiss cooperation programme.

• Administrative bodies communicate important information through special mailing lists which enable quick communication of information concerning general issues of the cooperation programme

• In order to reach the right target group the promotion concerning the projects is also done through specific channels like professional unions, information lists etc.

Page 7: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Opening ceremony of Viljandi and Saarepeedi Children’s Homes – March 9, 2012

2 family houses have been constructed and furnished in Viljandi. The children (15 per house) have moved into the houses. 2 family houses have been constructed and furnished in Saarepeedi . The children (16) have moved into the houses.

The opening ceremony of both Saarepeedi and Viljandi family houses took place on March 9th 2012. Minister of Social Affairs of Estonia Mr Hanno Pevkur handing

over the ceremonial key on the opening ceremony of the Saarepeedi Children’s Homes on 9th March 2012

Page 8: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Opening Ceremony of the Juuru Children’s Homes – October 30, 2012

Väätsa

5 family houses have been constructed and furnished in Juuru. 19 children have moved into the houses. Some children are still to be relocated..

Page 9: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Opening Ceremony of Elva Children’s Homes – December 21st 2012

Minister of Social Affairs of Estonia Mr Taavi Rõivas opens the ceremony on 21st December 2012. 2 family houses have been constructed and furnished in Elva. The children (16 per house) have moved into the houses and have settled in.

Page 10: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Monitoring

• Intermediate Body– Eligibility check (incl. copies of the invoices)– Monitoring of results– Spot checks

• Paying Authority– Check of Reimbursement Request and Financial Progress section in Interim Report (list of

expenditures)– Spot checks

• NCU– Check of Interim Reports (comparing physical progress and financial progress, list of

expenditures, compliance with the agreement)– Steering committee meetings– Spot checks – Monitoring of Annual Reports (cooperating with the State Budget

Department)

Page 11: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Steering commitee meetings

• Project steering commitee meetings take place in the environmental monitoring programme, fire safety project, energy efficiency project, treatment of drug offenders project, and a joint steering committe for Emergency Respond Centre’s and ambulances project.

• The meetings take place quarterly or each half year.

• This year (2013) there has been eight steering committe meetings.

• NCU representative and when possible a SCO representative will attend the meetings as observers.

Page 12: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Site Visits

• Nationally the responsibility for conducting site visits is on the Intermediate Bodies.

• They plan the visits and inform the NCU of the date, giving the NCU and/or SCO an opportunity to participate.

Page 13: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Ministy of Environment’s site visit photos – sub-project 5 – July 23 2013

The plane carrying the airborne spectrometer in Tallinn airport. Whenever there is wheather , the plane will fly.

Page 14: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Photos of the installed videoconferencing equipment

Page 15: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Working plan for 2013

Page 16: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

2013 and beyond

• Implementation of all the projects has started in 2012. Our goal is to conclude all projects of the Cooperation Programme by the end of 2015.

• Prolongations– Finalising the prolongation of the Fire Safety project and the Financial

Reporting project is underway.

– Treatment for drug offenders project will definately be prolonged in 2014.

• Completions– AFM-MFM microscopy project is on schedule to complete their activities

on 31st December 2013.

– Scheduled to be completed by 31st December 2014 - Increasing fire safety project, ambulances and the integrated national communication system of alarm services project, information and communication systems of Emergency Respond Centre project and the procurement of forensic science equipment project

Page 17: Progress Report 2013 Baltic Retreat 2013 NCU Estonia 6th September 2013 Taisi Valdlo The NCU of Estonia

Thank you for your attention!