Program Update. Gary Hoffman, P.E. Topics. Partnering Efforts PennDOT’s Strategic Focus Areas PennDOT’s Infrastructure Needs PennDOT’s Program Federal Reauthorization. Partnering Efforts. Quarterly Meetings Pursuing Consistency Expand Constructability Reviews Improving ECMS - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Program Update

Program UpdateProgram Update

Gary Hoffman, P.E.

Page 2: Program Update

Topics

Partnering Efforts PennDOT’s Strategic Focus Areas PennDOT’s Infrastructure Needs PennDOT’s Program Federal Reauthorization

Page 3: Program Update

Partnering Efforts

• Quarterly Meetings• Pursuing Consistency• Expand Constructability Reviews• Improving ECMS• Managing Letting Schedule• Implementing Innovation

Page 4: Program Update

PennDot’s Strategic Focus Areas

System Preservation

Management and Productivity

Quality of Life

Mobility

Safety

Page 5: Program Update

System PreservationSystem Preservation

“Maintenance First”

Bridge Structural Adequacy Reduce number of structurally deficient bridges

• PA’s structurally deficient bridges = 22%• National average for structurally deficient = 10%• Goal = match the national average within 20 yrs

Increase bridge preservation• Target: $350 M/year for rehab/replacement

$100 M/year for preservation

• Current Bridge Expenditure $300M

Page 6: Program Update

Infrastructure Needs

MAKING THE CASE FOR SYSTEM PRESERVATION

Page 7: Program Update

Pennsylvania’s Highway & Bridge Needs

• Highway Pavement:

• 6 Year Needs $ 18.0 Billion

• 6 Year Available Funds $ 13.2 Billion

• Gap $ 4.8 Billion

• Bridges:

• 6 Year Needs $ 3.3 Billion

• 6 Year Available Funds $ 1.8 Billion

• Gap $ 1.5 Billion

6 Year Funding GAP $ 6.3 Billion

Page 8: Program Update

2003 System PreservationInternational Roughness Index (IRI)

Good Fair Poor

Interstate 64% 29% 7%

NHS (Non-interstate) 59% 30% 11%

Non-NHS > 2000 ADT 63% 25% 12%

Page 9: Program Update

Pavement DeteriorationCurve

Programming Preservation Treatments for roads at key times will extend the life of the road greatly

Pavement Preservation

Page 10: Program Update

New Capacity vs. Preservation

24.5% 22.8%15.2%

28.3%19.1%

19.6%

47.2%58.1%

65.1%

0%

20%

40%

60%

80%

100%

01-04 TIP 03-06 TIP 05-08 TIP

Pe

rce

nta

ge

Preservation %

Operational %

New Capacity %

Statewide

Page 11: Program Update

Proposed Statewide Goal

• Improve all “POOR” NHS and Interstate miles

• Focus on Preservation instead of reconstruction to keep the good roads good

Page 12: Program Update

System Preservation Pennsylvania Bridge Facts

• Median Age > 50 yrs

• Average Life Span – 50 yrs

• Average Cost/Bridge - $1.25M

$1.25M X 9352 deficient bridges = $11.7 B

Page 13: Program Update

National Comparison(based on total deck area)

11.6%

8.0%6.0%

12.3%10.0%

21.9%

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

NATIONAL PENNDOT NJ NY OH VA

Structurally Deficient Bridges

Page 14: Program Update

PENNDOT Bridges: Age and Eligibility

0-10 11-20 21-30 31-40 41-50 51-60 61-70 >700

5

10

15

20

25

30

Dec

k A

rea

in M

sf

Age of Bridges

All PENNDOT Highway Bridges 8 ft and Over - Deck Area

Eligible for REPLACE

Eligible for REHAB

NOT Eligible

Page 15: Program Update

Trend in Structurally Deficient BridgesPENNDOT Bridges > 8 ft.

19.5% 19.5%

22.6% 22.4% 22.2%

21.7%21.6%

21.9% 21.9%

8%

11%

13%

16%

18%

21%

23%

1998 1999 2000 2001 2002 2003 2004 2005 2006

% Structurally Deficient by Deck Area

National Average = 10%

Local Bridges > 20 ft = 26.9% in 2003

$150M/yr $300M/yr $450M/yr

Page 16: Program Update

Proposed Statewide Goal

• Reduce Structurally Deficient Bridges to the National Average of 10% by 2024

• Bridge preservation can reduce rehabilitation and replacement requirements

Page 17: Program Update

Bridge Modeling and Spending Needs

Page 18: Program Update

• Designate Bridge “Champion”

(Craig Beissel)

• Rebuild Legacy BMS System

• Participate in National Effort for

Robust Bridge Asset Management

System

• Bridge Bill Legislation

Improve Bridge ManagementImprove Bridge Management

Page 19: Program Update

Bridge NeedsAsset Management

• Preservation

- Fix leaky joints (expansion dams)

- Fix beam ends, bearings and supports

- Bridge Painting

- Deck patching/replacement

- Other

Page 20: Program Update

Annual Lettings

$1,550$1,550

$1,374.9$1,304.4

$1,349.7

$1,034.2

$1,331

$970

$0

$400

$800

$1,200

$1,600

1997 1998 1999 2000 2001 2002 2003 2004 2005

Actual To Date Projected

Millions

$1,300 $1,250

Page 21: Program Update

2004 Lettings

$400$350

$250 $273$200

$251

$400$425

$1,250$1,300

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Total

Projected Actual

Millions

Page 22: Program Update

2004 Large Projects

SR / SEC County Est. Cost Ant. Let Date

0078 / 17M Berks $ 50 M December

0022 / B02 Westmoreland $ 40 M December

0090 / B07 Erie > $ 20 M December

Page 23: Program Update

2005 Lettings

$400

$250$200

$400

$1,250

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Total

Projected

Millions

Page 24: Program Update

First Quarter 2005 Large Projects

SR / SEC County Est. Cost Ant. Let Date

0202 / 3IT Chester $ 15 M January

7301 / BRG Allegheny $ 30 M January

6006 / 272 Lackawanna < $ 10 M January

0291 / S11 Philadelphia < $ 10 M February

0208 / A00 Mercer $ 15 M March

0079 / A25 Allegheny $ 10 M March

0068 / 650 Clarion $ 15 M March

2122 / A03 Allegheny $ 20 M March

Page 25: Program Update

Second Quarter 2005 Large Projects

SR / SEC County Est. Cost Ant. Let Date

0309 / NW1 Lehigh < $ 10 M April

0309 / 101 Montgomery $ 65 M April

0022 / 491 Indiana $ 45 M April

0022 / B08 Westmoreland $ 25 M April

0209 / 021 Monroe $ 15 M May

0019 / A27 Allegheny $ 40 M May

1021 / 370 Luzerne $ 20 M June

0048 / A16 Allegheny $ 15 M June

Page 26: Program Update

Materials Usage

2003 2004 2005

Asphalt (Tons) 8.2 M 8.1 M 8.3 M

Concrete (CY) 740 k 660 k 670 k

Aggregate (Tons) 12.3 M 14.8 M 12.9 M

Page 27: Program Update

Number of Consultant Final Selections

75

113127

195224

140 143 138 140

0

50

100

150

200

250

1996 1997 1998 1999 2000 2001 2002 2003 2004

ACT 3

TEA 21Projected

Actual

127

To Date

Page 28: Program Update

Payouts to Consultants

128 129163

200

232264

301 307 310

0

50

100

150

200

250

300

350

1996 1997 1998 1999 2000 2001 2002 2003 2004

Millions

Projected

Actual

To Date

254

Page 29: Program Update

Federal Reauthorization (?)

• 5 short term extensions

• 8 mos. through May 2005

• Current extend ($36.8 + $1.8 B)

• Funding guarantees and firewalls

• Nothing during “lame duck”

• Reintroduced late-winter/early spring

Page 30: Program Update

Federal Reauthorization (?)

• Size Of Appropriation

• “Growth” of Appropriation Over Time

• Distribution Mechanism

• Earmarks

• Categorization/Flexibility

• Speak With “One Voice”

Page 31: Program Update

SIX YEAR PROGRAM (Pennsylvania’s Estimated Funding)

9.449.92

8.33

0

5

10

TEA-21 S 1072 HR 3550

BILL

DO

LLA

RS

(B

illio

ns)

Federal Reauthorization

20% vs. 40%

Page 32: Program Update

Questions ???