production of thermoelectric power from solid waste of some educational institutions of lahore by...
TRANSCRIPT
PRODUCTION OF THERMOELECTRIC PRODUCTION OF THERMOELECTRIC
POWER FROM SOLID WASTE OF SOME POWER FROM SOLID WASTE OF SOME
EDUCATIONAL INSTITUTIONS OF EDUCATIONAL INSTITUTIONS OF
LAHORELAHORE
ByBy
Mohammad Rafiq Khan Mohammad Rafiq Khan
Lahore School of EconomicsLahore School of Economics
INTRODUCTIONINTRODUCTION
The study was undertaken with the following objectives in mind:The study was undertaken with the following objectives in mind:
Safe and techno-economic disposal of solid waste produced in Safe and techno-economic disposal of solid waste produced in the the
scheduled educational institutionsscheduled educational institutions Study of the feasibility of production of thermo-electric power from Study of the feasibility of production of thermo-electric power from the the
biomass of solid waste biomass of solid waste Later extension of the study to higher levels such as village, town,Later extension of the study to higher levels such as village, town, and and
national city levelnational city level Recommendations to all concerned for effective solid waste Recommendations to all concerned for effective solid waste
management and production of thermoelectric power to eliminatemanagement and production of thermoelectric power to eliminate
power in Pakistanpower in Pakistan
METHODOLOGY OF RESEARCHMETHODOLOGY OF RESEARCH Collection of DataCollection of Data Processing of DataProcessing of Data Interpretation of ResultsInterpretation of Results
The preliminary enquiry revealed that the total waste produced inThe preliminary enquiry revealed that the total waste produced in
the scheduled institutions were approximately as follows:the scheduled institutions were approximately as follows: LSELSE 200 Tons per Annum200 Tons per Annum LUMS LUMS 500 Tons per Annum500 Tons per Annum KC KC 200 Tons per Annum200 Tons per Annum GCU GCU 720 Tons per Annum 720 Tons per Annum
Description of Detailed Methodology inDescription of Detailed Methodology in
(1) Khan MR and Pervez, F. 2009. Production of (1) Khan MR and Pervez, F. 2009. Production of Thermoelectric Power from the Solid Wastes of Kinnaird Thermoelectric Power from the Solid Wastes of Kinnaird College, Environ Monitor, IX (9&10): 14-28College, Environ Monitor, IX (9&10): 14-28
(2) Khan, MR and Sheikh, S. 2010. Production of (2) Khan, MR and Sheikh, S. 2010. Production of Thermoelectric Power from Solid Waste: A Case of Lahore Thermoelectric Power from Solid Waste: A Case of Lahore School of EconomicsSchool of Economics, , International Energy Journal 11:51-64International Energy Journal 11:51-64
One related to the actual waste of the institutions and One related to the actual waste of the institutions and
second to the amounts that had the likelihood of second to the amounts that had the likelihood of
qualifying the projects as feasible for subsequent qualifying the projects as feasible for subsequent
implementation are reported in Table 1 and 2.implementation are reported in Table 1 and 2.
The two sets of projects;
Table 1: Table 1: Bases and requisites of alternative Bases and requisites of alternative projects (Assessed weight of solid waste)projects (Assessed weight of solid waste)
AlternativesAlternatives 11 22 33 44 55 66
Solid Solid Waste-Tons/AnnumWaste-Tons/Annum
200200 200200 500500 500500 720720 720720
Cost of LandCost of Land IncludedIncluded ExcludedExcluded IncludedIncluded ExcludedExcluded IncludedIncluded ExcludedExcluded
Live Steam TemperatureLive Steam Temperature 600C600Co o to 650Cto 650Coo 600C600Co o to 650Cto 650Coo 600C600Co o to 650Cto 650Coo
Live Steam PressureLive Steam Pressure 70–80 kg/cm²70–80 kg/cm² 70–80 kg/cm²70–80 kg/cm² 70–80 kg/cm²70–80 kg/cm²
Fuel Steam RatioFuel Steam Ratio 1:71:7 1:71:7 1:71:7
Steam ProducedSteam Produced 1,400 Ton/Annum1,400 Ton/Annum 4,200 Ton/Annum4,200 Ton/Annum 4.200 Ton/Annum4.200 Ton/Annum
Multistage TurbineMultistage Turbine Light DutyLight Duty Light DutyLight Duty Light DutyLight Duty
Steam Consumption/ kWSteam Consumption/ kW 5 kg/kW5 kg/kW 5 kg/kW5 kg/kW 5 kg/kW5 kg/kW
Electricity ProducedElectricity Produced 280,000 kW/Ann.280,000 kW/Ann. 700,000 kW/Annum700,000 kW/Annum 1,008,000 kW/Annum1,008,000 kW/Annum
Steam Produced /hrSteam Produced /hr 0.16 Ton/hr0.16 Ton/hr 0.4050 Ton/hr0.4050 Ton/hr 0.5832 Ton/hr0.5832 Ton/hr
Electricity Produced/HrElectricity Produced/Hr 32-40 kW32-40 kW 81.10 kW81.10 kW 116 kW116 kW
Table 2: Table 2: Bases and requisites of alternative Bases and requisites of alternative projects (Increased weight of solid waste)projects (Increased weight of solid waste)
AlternativesAlternatives 77 88 99 1010
Solid Waste-Tons/AnnumSolid Waste-Tons/Annum 600600 600600 1,0001,000 1,0001,000
Cost of LandCost of Land IncludedIncluded ExcludedExcluded IncludedIncluded ExcludedExcluded
Live Steam TemperatureLive Steam Temperature 600C600Co o to 650Cto 650Coo 600C600Co o to 650Cto 650Coo
Live Steam PressureLive Steam Pressure 70–80 kg/cm²70–80 kg/cm² 70–80 kg/cm²70–80 kg/cm²
Fuel Steam RatioFuel Steam Ratio 1:71:7 1:71:7
Steam ProducedSteam Produced 4,200 Ton/Annum4,200 Ton/Annum 7,000 Ton/Annum7,000 Ton/Annum
Multistage TurbineMultistage Turbine Light DutyLight Duty Heavy DutyHeavy Duty
Steam Consumption/ kWSteam Consumption/ kW 5 kg/kW5 kg/kW 5 kg/kW5 kg/kW
Electricity ProducedElectricity Produced 840,000 kW/Annum840,000 kW/Annum 1,400,000 kW/Annum1,400,000 kW/Annum
Steam Produced /hrSteam Produced /hr 0.486 Ton0.486 Ton 0.81Ton/hr0.81Ton/hr
Electricity Produced/hrElectricity Produced/hr 97.22 kW97.22 kW 162kW162kW
RESULTSRESULTSNature and Composition of Solid Waste Nature and Composition of Solid Waste
Sub-Processes at Sugar MillSub-Processes at Sugar Mill
Bagasse StorageBagasse Storage
Transport to the BoilerTransport to the Boiler
BoilersBoilers
Turbines Turbines Supply of ElectricitySupply of Electricity
Figure 1: Figure 1: Flow sheet showing the sub-processes Flow sheet showing the sub-processes in the process of production of electricity from in the process of production of electricity from bagasse bagasse
Transport to boiler
Bagasse Storage
Turbine
Supply of electricity
Boiler
Figure 2: Figure 2: Flow Sheet of Bagasse Transport to Flow Sheet of Bagasse Transport to BoilerBoiler
Figure 3: Figure 3: Flow Sheet of Boiler-Supplied by Flow Sheet of Boiler-Supplied by Pattoki Sugar Mill Pattoki Sugar Mill
Figure 4: Figure 4: Flow Sheet of Turbine-Supplied by Pattoki Flow Sheet of Turbine-Supplied by Pattoki Sugar Mill Sugar Mill
Sub-processes of the Project: Same as above except the Sub-processes of the Project: Same as above except the
substitution of Bagasse by Solid wastesubstitution of Bagasse by Solid waste
Turbine
Supply of electricity
Transport to boil
Solid Waste
Boiler
Figure.5: Flow sheet diagram of the designed project.
RESULTS OF COST ANALYSISRESULTS OF COST ANALYSIS
The integrated results of cost analysis are computed in Table 3 to 6.The integrated results of cost analysis are computed in Table 3 to 6.
Alt. PV of Benefits
PV of Costs.
BCR NPV Initial Investment
Annual Return
PBP-Years
1 190,196 1,206,599 0.15 –1,016,403 920,950 -7,455 Infinite
2 190,196 539,933 0.35 –349,737 264,167 --7,455 Infinite
8 562,967 539,933 1.04 23,034 264,167 53,212 5.
10 935,738 539,933 1.73 395,805 264,167 110,100 2.39
Table 3: Computation of results of evaluation of alternatives- for LSE (US$)
Table 4: Table 4: Computation of results of evaluation Computation of results of evaluation of alternatives for KC (Rupees)of alternatives for KC (Rupees)
Alt. PV of Benefits
PV of Costs BCR NPV Initial Investment
Annual Return
PBP-Years
1 190,196 4,539,933 0.04 – 4,349.737 4,264,167 -7,455 Infinite
2 190,196 539,933 0.35 –349,737 264,167 --7,455 Infinite
8 562,967 539,933 1.04 23,034 264,167 53,212 5
10 935,738 539,933 1.73 395,805 264,167 110,100 2.39
Table 5: Table 5: Computation of results of evaluation of Computation of results of evaluation of alternatives for LUMS (Rupees) alternatives for LUMS (Rupees)
Alt. PV of Benefits
PV of Costs BCR NPV Initial Investment
Annual Return
PBP Years
3 469,774 1,739,933 0.26 - 1,270,159 1,464,167 34,267 42.7
4 469.774 539,933 0.87 – 70,159 264,167 34,267 7.7
8 562,967 539,933 1.04 23,034 264,167 53,212 5.
10 935,738 539,933 1.73 395,805 264,167 110,100 2.39
Table 6: Table 6: Computation of results of evaluation of Computation of results of evaluation of alternatives for GCU (Rupees)alternatives for GCU (Rupees)
Alt. PV of Benefits
PV of Costs BCR NPV Initial Investment
Annual Return
PBPYears
5 674,798 7,206,503 .0.09 –6,531,795 6,930,833 67,633 102
6 674,798 548,266 1.23 126,532 264,167 67,633 3.90
8 562,967 539,933 1.04 23,034 264,167 53,212 5
10 615,738 539,933 1.73 395.805 264,167 110,100 2.39
DISCUSSIONDISCUSSION
Lahore School of EconomicsLahore School of Economics
Kanaird CollegeKanaird College
Lahore University of Management SciencesLahore University of Management Sciences
Government College & University LahoreGovernment College & University Lahore
CONCLUSIVE REMARKSCONCLUSIVE REMARKS