proceedings of the meeting of state level...
TRANSCRIPT
Secretary, SEAC Page 1 of 17
PROCEEDINGS OF THE MEETING OF STATE LEVEL EXPERT APPRAISAL
COMMITTEE, ODISHA HELD ON 18TH FEBRUARY, 2017
The SEAC met on 18th February, 2017 at 03:00 PM in the Conference Hall of Odisha State
Pollution Control Board, Bhubaneswar under the Chairmanship of Dr. B.K. Patnaik. The
following members were present in the meeting.
1. Dr. B.K. Patnaik - Chairman
2. Dr. Dibakar Swain - Member
3. Prof. P.K. Mohanty - Member
4. Dr. D.K. Rout - Member
5. Dr. S.K. Biswal - Member
6. Sri. B.C. Prusty - Member
7. Dr. S.C. Nayak - Member
8. Dr. R.C. Mohanty - Member
9. Sri. A.C. Mohanty - Member
10. Er. Sridhar Behera - Member
CONSIDERATION OF OLD PROPOSALS:
1. PROPOSAL FOR ENVIRONMENTAL CLEARANCE FOR 1.1 MTPA (PORTLAND SLAG
CEMENT & GROUND GRANULATED SLAG) CEMENT GRINDING UNIT AT VILLAGE
MUKUNDAPUR & BHUBANPUR, TAHASIL CHENDIPADA, DIST – ANGUL BY
M/S JINDAL STEEL & POWER LTD (TOR).
M/s Jindal Steel & Power Limited has proposed to setup 1.1 MTPA (Portland Slag Cement
and Ground Granulated Slag) Grinding Unit At village- Mukundpur & Bhubanpur, Tehsil-
Chendipada, District- Angul, Odisha adjacent to its existing 6.0 MTPA integrated steel plant.
The proposed project sites Latitude & Longitude are 20°52'05"N to 20°52'24"N and 85°
0'18"E to 85° 0'41"E respectively. No National Park/wild life sanctuary is involved in setting
up plant within 15 km radius of the project site. The site is about 14 km away from
nearest town Angul. Nearest railway station Kerjang is 3.5 km away from the proposed
project site. Nearest airport is Bhubaneswar about 109 km away from the proposed project
site. Total proposed project area is 32.775 Acre. Total Project Cost is Rs. 30720.08 Lakh. A
budget of ` 329.00 Lakhs and ` 76.00 Lakhs are earmarked towards Captial cost and
Recurring cost per annum respectively. Clinker, Gypsum, Granulated Slag and Coal fines
are the major raw materials for the proposed project.
Gaseous emission will be controlled by installing air pollution control equipments. Dust
suppression will be done by water sprinkling to control fugitive emissions due to
transportation activities. Water sprinkling will be done along the haul roads to control dust
arising from vehicular movement. Suitable type and capacities of bag filters will be
envisaged for the deducting system at Raw material handling points. Total water
requirement for the proposed project is of 500 M3/Day. Total power requirement for the
proposed project is 11 MVA. Domestic wastewater will be treated in septic tank and
discharged to soak pit. Zero discharge norms will be maintained in the proposed plant.
Dust from APC devices and Ash generated from Hot Air Generator will be reused in
process. Sludge from RWTP will be used for landscaping. Green belt will be developed in
10.82 Acres of the total plant area.
Secretary, SEAC Page 2 of 17
The Consultant M/s VISIONTEK CONSULTANCY SERVICES PVT. LTD., Bhubaneswar
made a detailed presentation on behalf of the proponent on 23.05.2016. The proponent
made an appeal to consider the project under B2 category as per guideline of MoEF&CC,
Govt. of India. The committee decided to take decision on the proposal after the project
proponent furnish certain information / documents. The proponent has furnished the same
and the SEAC verified the documents as follows:
Sl.
No.
Information Sought by
SEAC
Compliance furnished by the
proponent
Views of the
SEAC
1. Certificate from State
Pollution Control Board,
Odisha with respect to
distance of proposed site
from the boundary of
notified critically polluted
area of Talcher-Angul.
Odisha State Pollution Control
Board (OSPCB) vide letter dated
16.09.2016 has certified that the
proposed site of cement grinding
unit is located at a distance of 11.2
km from the boundary of Critically
ted Area (CPA) of Talcher- Angul.
Complied
2. Detailed status of land
acquisition for the
proposed cement plant
alongwith supportive land
documents and land
schedule.
Land required for the proposed
plant site is 32.775 Acres. As per
the letter from IDCO, the land can
be purchased directly from the land
owners. The land owners have
expressed interest for sale of land
of 21.605 acres to JSPL and
copies of the same are furnished.
Complied.
3. Detailed land use break
up
Land use breakup has not been furnished.
Land use breakup
of proposed 32.775
acres land for
cement plant has
to be furnished.
This land use
break up should
include the area
earmarked for
green belt.
4. Detailed justification with
respect to transportation
of raw-material and
finished product shall be
primarily through railway
and it should not be less
than 90% of the traffic
(inward & outward put
together ) to consider the
project as B2 category
The major input material for the
cement production is clinker
and Gypsum. Clinker required
for the process will be
transported by rail from the
sources located in Chhattisgarh
and /or Andhra Pradesh and
Gypsum shall be transported to
site through rail from Paradip
port. Entire production will be
sold in the markets of Bihar,
Jharkhand, West Bengal, North
East Andhra Pradesh and the
same will be transported
through rail, except for about
Complied
Secretary, SEAC Page 3 of 17
Sl.
No.
Information Sought by
SEAC
Compliance furnished by the
proponent
Views of the
SEAC
10% which will be transported
by road to Coastal Odisha. Rail
connection from Railway siding
of JSPL plant to Angul and
Kerajang stations will facilitate
transportation by rail.
In view of the above, more than 90
% of the traffic (inwards &
outwards put together) will be
through railways.
5. Detailed energy saving
measures vis-à-vis
utilization of solar energy
It has been proposed to install 50
nos. of Solar Street lights and
provide solar LED lighting in the
administrative building. The total
energy saving to be achieved
through this measure will be about
42661 units of electricity per
annum. Details furnished.
Complied
6. Coal requirement for the
cement grinding unit has
been proposed to be
higher side since, they will
use BF gas of steel for
heating purpose. It should
be re-calculated and
actual requirement is to
be submitted
The plant is proposed to be
operated by utilizing Blast Furnace
gas from the Steel plant. However,
during shut down/ maintenance of
the Blast Furnace, coal is proposed
to be used for heating purposes. In
exceptional circumstance, about
22,300 tonnes of raw coal with
GCV of 3400-3700 Kcal/ kg and
40-44% ash shall be required
instead of 23,100 Tons/Years as
submitted earlier.
Complied
7. Water requirement
proposed is at higher
side. It is proposed to be
met from the treated
waste water of integrated
steel plant. It should be
justified with detailed
water balance
The water requirement for the
proposed plant has been revised
from 500 m3/day to 250 m3/day in
consultation with project consultant
and the same will be sourced from
the treated wastewater of Steel
Plant. JSPL is setting up a 500
m3/hr (12000 m3/day) RO based
Zero Liquid waste Discharge Plant
to treat the wastewater from
existing DRI plant, Coke oven,
Blast Furnace effluent and power
plant discharge at its Integrated
Steel plant at Angul. The quantity
required for the Cement Grinding is
a very small fraction (about 2%) of
Complied
Secretary, SEAC Page 4 of 17
Sl.
No.
Information Sought by
SEAC
Compliance furnished by the
proponent
Views of the
SEAC
this treated wastewater. Revised
water balance for 250 m3/day has
been furnished.
8. The proponent has to
justify the project as a
standalone cement plant
and not an integral part of
integrated steel plant as
there are common
facilities to be availed
from the integrated steel
plant such as railway
siding, water requirement,
raw material requirement
etc
The proposed Cement Grinding
unit will be installed and operated
by M/s JSPL Panther Cement
Limited, a company incorporated
under the Companies Act, 2013.
The incorporation certificate has
been furnished. The proposed
plant will be a standalone project
with dedicated human resources
for plant operation and sales
management. The grinding unit is
proposed to be located adjacent to
the existing steel plant of JSPL to
utilize slag from the steel plant and
minimize transport of raw
materials, etc. and use certain
common facilities such as raw
material yard, railway siding,
power, etc.
Complied
9. Copy of agreement with
JSPL regarding sharing of
power and water and rail
facilities
A copy of the MoU between M/s
JSPL Panther Cement Limited
&M/s JSPL for sharing common
facilities from the existing Steel
Plant is furnished. JSPL shall be
supplying power from its Captive
Power Plant and making available
treated water from the Steel Plant
for use in the Grinding unit.
Complied
The SEAC decided to consider the proposal after the proponent submit the following
information.
i) Land use breakup of proposed 32.775 acres land for cement plant has to be furnished.
This land use break up should include the area earmarked for green belt.
2. PROPOSAL OF M/S CHILIKA DISTILLERIES PVT. LTD. FOR ESTABLISHMENT OF 55
KLD GRAIN BASED DISTILLERIES AT – KANAKA, KHALLIKOTE, DIST - GANJAM.
(EC)
Chilika Distilleries Pvt. Ltd., proposes to establish a State-of-Art Grain based Distillery for
the production of 55 KLPD of the Alcohol and 2.2 MW captive power plants at Kanaka,
block Khallikote, District Ganjam, Odisha. Geographically, the site is located at 19° 34'43.83
N, 85°06' 42.17' E. NH-5 highway is at a distance of 0.5 km. Chilikahrada, Gopakunda,
Haridamula, Hajapata, Kankadakuda and Dalibati are the nearby villages situated at a
distance of 0.5, 0.7, 1.5, 2.7, 2.2 and 2.1 km respectively.
Secretary, SEAC Page 5 of 17
The proposed project falls under the item no. 5 (g) i.e. Distilleries and Category B (<60
KLPD Non molasses based industry). The cost of proposed project will be around ` 67.25
Crore including the cost towards construction of plant & building, plant machineries,
equipment & utilities. The cost towards Environmental Management Plan (EMP) will be
around ` 2.73 Crore.
The manufacturing of alcohol/spirit takes place in two stages; 1) fermentation and 2)
distillation. In the process, after grain milling, the milled raw material is subjected to
liquefaction methods which involves heating of aqueous starch slurry wherein the granular
starch in the slurry swells and bursts and dispersed starch molecules into the solution. Then
this liquefied slurry will be subjected to Fermentation. The fermentation will convert the
fermentable substrate into Alcohol. During Fermentation, sugars are broken down into the
Alcohol cogenerating Carbon Dioxide with release of significant amount of heat. After
fermentation is complete, fermenter wash is taken into distillation system where alcohol will
be separated and concentrated using principle of fractional distillation. The slope from
distillation will be taken to the decantation section. After decantation thick wet cake will be
sent to dryer and thin slope will be sent for evaporation. Concentrated syrup from
evaporation and thick cake from decantation will be dried in dryer and form product known
as DDGS.
Daily consumption of the raw material required to manufacture are Broken rice 136 TPD,
Liquefying Enzyme, Saccharifying Enzyme, Viscosity Reducing Enzyme, Yeast, Anti-
Bacterial Agent, Sodium Hydroxide Lye, Sulphuric Acid, Urea, Antifoaming Agent,
Sulphamic Acid and Nitric Acid.
As per the proposal total plot area for proposed project will be 31.162 acres. About 40.2% of
land i.e. 12.549 acres is being earmarked for green belt development. The Chilika Lake is at
a distance of more than 3 km and Costal line is at a distance of 14 km. Other places like
Nalaban Island- Chilika Bird Sanctuary is situated 22 km away from project boundary.
The required quantity of water shall be made available from the ground water source for
which permission form CGWA is available. Total fresh water requirement at initial stage will
be 1693 KLD and thereafter it will be around 508 KLD due to use of recycled water.
Total 332.75 TPD steam will be required for liquefaction, distillation, evaporation, drying and
de-aerator. Estimated electrical power requirement will be 2830 kWh. Boiler with the
capacity of 20 TPH will be installed. Fuel requirement is Indian Coal: 36,480 TPA and Rice
husk: 40,960 TPA. Man Power requirement is Skilled: 120, Unskilled /contract labor: 144
and total manpower: 264.
Air emissions/pollution during operation phase will be mainly form flue gases, manufacturing
process, material & ash handling and from vehicular movement. ESP shall be provided to
the Stack (stack height 40 m) to control the particulate matter emission into the air as main
pollution control measures.
Factory will be adopting Zero Liquid Discharge (ZLD) system. Spent wash coming out of
distillation unit will be passed through decanter and again concentrated in integrated
evaporation and then it will be sent to Dryer. The dried cake shall be (DDGS) used as cattle
feed. The process condensate will be treated in the Process Condensate Treatment Plant.
Treated effluent will meet prescribed standards and will be recycled.
DDGS from the dryer will be bagged and will be used as a cattle feed. Fly ash generated
from Boiler will be collected in the ash silos and sent to brick manufacturing units without
creating public nuisance. Yeast and ETP sludge will be used as manure.
Secretary, SEAC Page 6 of 17
The amended EIA notification vide SO-996(E ) dt. 10th April, 2015 stipulates the standard
TOR developed by the Ministry shall be the deemed approved TOR for the project or
activities if the EAC or SEAC unable to issue TORs within 30 days of acceptance of
application in prescribed form. They have submitted environmental clearance application on
3rd October, 2015 on online portal of MoEF&CC, Govt. of India, since they have not
received any communication from MoEF&CC, Govt. of India within a month, they have
conducted baseline environmental monitoring during November, 2015 to January, 2016 and
also carried out EIA study as per standard TOR as per the above amended EIA notification
10th April, 2015. They had applied for public hearing to the State Pollution Control Board,
Odisha accordingly. Public hearing was conducted on 27.7.2016.
The Consultant SMS Envocare Ltd, Pentagon P3, Magarpatta City, Hadapsar, Pune,
Maharashtra,, Bhubaneswar made a detailed presentation on behalf of the proponent on
05.10.2016. The committee decided to take decision on the proposal after the project
proponent furnish certain information / documents. The proponent has furnished the same
and the SEAC verified the documents as follows:
Sl.
No.
Information Sought by SEAC Compliance furnished by
the proponent
Views of the
SEAC
1. Detailed Energy balance. Not furnished. However, they
have intimated to install one
solar power plant within 1-2
years of the distillery
operation.
The proponent has
to give an
undertaking to use
solar energy of 5%
of total power
consumption.
2. Fly ash generation details and
proposed disposal mechanism.
Detail fly ash generation and
disposal mechanism has
been furnished. Ash storage
capacity is 165 CMD which is
having a provision of Silo
which will be transported to
the contractors for making
bricks and products.
Agreement copy for the same
has been furnished in EIA
report as Annexure-XVII.
They have to
submit detail
proposal for
temporary storage
of fly ash (other
than silo) within the
plant premises and
area earmarked for
the same. The
revised layout plan
(as stated above)
shall be submitted.
3. Rain fall data appear to be on
higher side. This has to be
rechecked and submitted.
Details of rainwater harvesting
for recharging and storage to be
submitted.
Average rain fall is 1272 mm
within a time span of 120
days of monsoon.
complied
4. The stack height to be
increased for better as per the
norms.
Proposed stack height is 40
meter. Detailed calculation
attached.
complied
5. Plantation shall be completed
within first 3 years and to
ensure minimum 33% green
cover.
They will develop 33 % of
greenbelt within first 3 years.
Complied
Secretary, SEAC Page 7 of 17
Sl.
No.
Information Sought by SEAC Compliance furnished by
the proponent
Views of the
SEAC
6. Boiler blow down is not included
in waste water generation. This
to be included and the disposal
of waste water to be spelled out.
Boiler blow down 9 m3 per
day will be utilized for cooling
tower makeup / ash
quenching.
Since, the
proponent has
suggested 100%
utilization of fly
ash, the scope of
the ash quenching
with better blow
down may not be
necessary. In that
context, 100%
utilization of waste
water needs to be
relooked.
7. Status of permission from water
resource department for drawal
of ground water. The project
proponent has to study the
impact of ground water drawal
to the tune of 508 KLD to
assess likely fluctuations in
water table.
They have obtained
permission from CGWA
for drawl of ground water.
Applied to the Department
of Water Resources, Govt.
of Odisha for drawl of
ground water. Copy of the
application made to the
DWR, Govt. of Odisha has
been furnished.
Hydrogeological study
report has been furnished.
complied
8. Detail plan and mechanism for
zero discharge
Detail plan and mechanism
for zero discharge has been
furnished.
complied
9. CO2 sequestration as carbon
foot print of the product is high
An industrial grade CO2
plant will be installed
within 1-2 years of
operation of the plant.
The raw CO2 generated
from the fermentation
would be purified and
stored as per norms,
which will further
transported for industrial
application like welding,
foundry etc.
Complied
10. Land schedule with kisam of
land alongwith land conversion
document for industrial purpose
Land schedule with kisam of
land alongwith land
conversion document for
industrial purpose has been
furnished.
complied
Secretary, SEAC Page 8 of 17
Sl.
No.
Information Sought by SEAC Compliance furnished by
the proponent
Views of the
SEAC
11. Solid waste stock piles to be
shown in layout map
Solid waste stock piles
mentioned in layout map as
per the EIA report.
Complied
12. DFO, Chilika and Chilika
Development Authority to be
kept informed about the
proposed project and copy of
the same to be submitted
They have intimated about
the project activity to the
DFO, Chilika and Chilika
Development Authority and
furnished copy of the same.
complied
The SEAC decided to consider the proposal after the proponent submit the following
information and after a field visit to the site.
i) The proponent has to give an undertaking to use solar energy of 5% of total power
consumption.
ii) They have to submit detail proposal for temporary storage of fly ash (other than silo)
within the plant premises and area earmarked for the same. The revised layout plan
(as stated above) shall be submitted.
iii) Since, the proponent has suggested 100% utilization of fly ash, the scope of the ash
quenching with better blow down may not be necessary. In that context, 100%
utilization of waste water needs to be relooked.
iv) A garland dyke to divert and channelize the storm water coming from the hillock
needs to be constructed.
3. EXPANSION OF PRODUCTION CAPACITY FOR CAUSTIC SODA FROM 72,000
TONS/ANNUM TO 105,000 TPA AND CONSEQUENTLY ITS BI-PRODUCTS AND VALUE
ADDED DERIVATIVES BY M/S GRASIM INDUSTRIES LTD., JAYASHREE, DIST-
GANJAM (TOR).
The proposal was considered by the committee to determine the “Terms of Reference
(TOR)” for undertaking detailed EIA study for the purpose of obtaining environmental
clearance in accordance with the provisions of the EIA Notification, 2006 and amendment
thereafter.
M/s Grasim Industries Ltd., Jayashree, Ganjam is engaged in the manufacturing of the
Caustic Soda Lye, Now, company proposes to increase production capacity by increasing
existing Caustic Soda Lye production and also plans to produce new products like Poly
Aluminium chloride, Calcium Chloride, Carbon Dioxide, Stable Bleaching powder and
Chlorinated Paraffin. The proponent has obtained EC from MoEF&CC, Govt. of India on
23.08.2007 for production of Caustic Soda 72,000 TPA under 1994 EIA Notification.
Membrane Cell technology being used since January 2011; same technology will be
adopted for proposed expansion unit. The unit is located at Ganjam Notified Area Council
(NAC), Ward No. 10 ; Block - Chhatrapur; Ganjam, Odisha. The Latitude: is 19°22'46.90"N
and Longitude: 85° 3'13.43"E. Rushikulya River- is 250 from main plant and NH-16 is 0.5
km. Total Land Area is 130 acres owned by Grasim Industries Limited. The Main Plant: area
is 130 Ac and area required for proposed expansion is 11.33 acres. Expansion unit will be
constructed within the vacant area of the Main Plant. Water requirement for the existing unit
is 2360 KLD. Source of water is ground water through 2 bore wells, located at Kalyanpur
Area. Proposed water requirement is 1140 KLD and source will be ground water. Existing
Secretary, SEAC Page 9 of 17
power requirement is 16 MW for plant and colony. Source is GRID supply from OPTCL.
Power Requirement after expansion is 28 MW. Backup power supply is 750 KVA + 180 KVA
DG sets. Existing and proposed manufacturing technology for Chlor alkali production is
Membrane Cell Technology. Primary raw materials are Salt (NaCl) and Water
(demineralized water). The product and bi-product of existing and proposed expansion
project is summarized as follows:
Name of product Production Capacity (TPA)
Existing (a) Proposed (b) Total (a + b)
Caustic Soda 72,000 33,000 105,000
Liquid Chlorine 46,350 26,650 73,000
Hydrochloric Acid 60,000 30,000 90,000
Hydrogen Gas- Million NM3 21.17 9.83 31.0
Sodium Hypochlorite 32400 1300 33700
Poly Aluminum - 73,000 73,000
Chloride- 10 % liquid
Calcium Chloride
-
18,250 18,250
Carbon dioxide - 7,300 7,300
Stable Bleaching Powder - 18,250 18,250
Chlorinated Paraffin’s - 18,250 18,250
The consultant M/s ERM India Private Ltd., Building 10A, 4th floor, DLF Cyber City,
Gurgaon made a detailed presentation on behalf of the proponent on 17.08.2016.
The EIA notification 14th September, 2006 and amendment thereafter and OM No.
J-13012/12/2013-IA-1I(I) dated 24th December, 2013 of MoEF&CC, Govt. of India stipulates
that chlor alkali plants with production capacity < 300 TPD and located outside notified
industrial area will be come under category B1 project. The proponent intimated that the
production activity of existing unit is a continuous process and carried out for throughout the
year i.e. 360 days. They will also go for 360 days production activity with a rated capacity of
291.7 TPD after expansion. The SEAC opined that they have to justify the 360 days
production activity for the existing plant with proper documents and submission of an
undertaking to this effect.
The proponent also requested to exempt public hearing as the unit has already conducted
public hearing while obtaining EC in the year 2007. The SEAC opined that as per EIA
Notification, 14th September, 2006 and amendment thereafter, there is no provision to
exempt public hearing as appealed by the proponent. Hence, the SEAC rejected the appeal
of the proponent.
The SEAC decided to issue TOR for preparation of EIA/EMP report after receipt of the
following from the proponent.
i) An undertaking to the effect that the production activity for the existing unit is carried
out for 360 days in a year along with documents such as returns filed to commercial
tax office /statutory compliance to Factories and Boilers for day-wise production for
last three years to Justify the 360 days production activity for the existing plant along
with production and maintenance plan.
Secretary, SEAC Page 10 of 17
The proponent has furnished the detailed document in support of the production activity for
360 days in a year. TOR was issued to the unit as per recommendation of the SEAC vide
No. 765 dtd. 9.12.2016.
The proponent has made an appeal with pollution load study report for exemption of public
hearing with a claim that pollution load will not increase due to the proposed expansion. The
SEAC decided to ask the proponent to come for a detailed presentation before the SEAC on
the pollution load study report to consider their appeal for exemption of public hearing.
4. PROPOSAL FOR ENVIRONMENTAL CLEARANCE FOR M/S UTKAL HEALTHCARE
PVT. LTD. OVER AN AREA OF 2.5 ACRES AT PLOT NO. 321 (P), KHATA NO. 610,
MOUZA CHANDRASEKHARPUR, NILADRIVIHAR, BHUBANESWAR WITH TOTAL
BUILT UP AREA 30747.46 M2 (EC).
1. This is a proposal for environmental clearance for M/s Utkal Health Care (P) Ltd, at plot
no. C/3, corresponding to revenue plot no. 321(P) khata no. 619, Mauza:
Chandrasekharpur, Niladrivihar, Bhubaneswar.3 Nos. D.G set (750 kva x2 & 500 kva x
1) to ensure uninterrupted supply. Total land area is 2.5 Ac. Total built-up area is
30747.46 sqm. There are 200 beds, 145 Nurses Dormitory Beds. Waste water
generation is 89KLD. Total water demand is 169KLD. Total domestic solid waste is 210
Kg/day and Bio-medical waste is 100 kg/day. Total power requirement is 1600 KW. The
building plan has been approved by BDA.
2. The SEAC in its meeting held on 25.08.2014 observed that the proponent has already
started construction activity without obtaining environmental clearance from SEIAA,
Odisha and this case was a violation of Environment (Protection) Act, 1986. The SEAC
recommended that the SEIAA, Odisha shall deal with the violation matter in accordance
with MoEF, Govt. of India OM No. J-11013/41/2006-IA.II(I) dt.12.12.2012 and dtd.
27.6.2013.
3. The SEAC also decided in the above meeting that the proposal will be returned to
SEIAA, Odisha with a request to initiate necessary action as above and SEAC will
consider the case after necessary action is initiated by SEIAA under intimation to SEAC.
4. The SEIAA, Odisha vide letter no. 2134, dated 27.10.2016 has intimated that the
Collector, Khurda has initiated legal action against the proponent for construction of the
project without environmental clearance.
5. The proponent was called for a presentation for consideration of environmental
clearance on merit basis.
The proponent made a detailed presentation before the SEAC on 15.12.2016. The
committee decided to take decision on the proposal after the project proponent furnish
certain information / documents. The proponent has furnished the same and the SEAC
verified the documents as follows:
Sl.
No.
Information Sought by
SEAC
Compliance
furnished by the
proponent
Views of the SEAC
1. Land schedule with
kisam of land of the
entire project area is to
be submitted.
Land schedule with
kisam of land has
been furnished.
The document furnished is silent
about the kisam of land. They
have to furnish a self-certified land
schedule with kissam of land.
Secretary, SEAC Page 11 of 17
Sl.
No.
Information Sought by
SEAC
Compliance
furnished by the
proponent
Views of the SEAC
2. Location map on the Full
scape Toposheet
(1:50,000) indicating
activities within 10 km
radius.
Map indicating the
activities within 10 km
radius has been
furnished.
The location map furnished by the
proponent is not indicating the
exact distance of the proposed
site from the boundary of the eco-
sensitive zone of Chandaka,
Dampada Wildlife Sanctuary. The
proponent has to submit a
certificate from the concerned
DFO about exact distance of the
proposed site from the boundary
of the eco-sensitive zone of
Chandaka, Dampada Wildlife
Sanctuary.
3. Greenbelt in layout map
with dimension
Greenbelt in layout
map with dimension
has been furnished.
Plantation area
provided 2140.50 m2
(21.37 % of plot area).
complied
4. Total built up area with
break-up for green belt
area and parking space.
- Do - complied
5. Final discharge point of
waste water to be
intimated
The waste water will
be treated in STP and
treated water will be
reused in toilet
flushing, gardening,
road washing and air
conditioning cooling
tower. They will
maintain zero
discharge of effluent.
complied
6. A detailed proposal for
treatment of Hospital
liquid waste water
Detailed proposal for
treatment of Hospital
liquid waste water has
been furnished.
complied
7. Permission status of
Water Resources
Department for drawl of
ground water
Copy of NoC obtained
from CGWA has been
furnished.
They have also to obtain
permission from the Department
of Water Resources, Govt. of
Odisha for drawl of ground water.
Status of such permission shall be
intimated.
8. Details of STP for
treatment of domestic
wastewater
Details of STP for
treatment of domestic
wastewater has been
complied
Secretary, SEAC Page 12 of 17
Sl.
No.
Information Sought by
SEAC
Compliance
furnished by the
proponent
Views of the SEAC
furnished.
9. Percentage of energy
used from solar / non-
conventional
(renewable) source
10% of the total
energy will be used
from solar source. A
technical proposal for
200 KW GRID tied
Solar PV power plant
has been furnished.
Complied
The SEAC decided to consider the proposal after the proponent submit the following
information.
i) The document furnished is silent about the kissam of land. They have to furnish a
self-certified land schedule with kissam of land.
ii) The location map furnished by the proponent is not indicating the exact distance of
the proposed site from the boundary of the eco-sensitive zone of Chandaka,
Dampada Wildlife Sanctuary. The proponent has to submit a certificate from the
concerned DFO about exact distance of the proposed site from the boundary of the
eco-sensitive zone of Chandaka, Dampada Wildlife Sanctuary.
iii) They have also to obtain permission from the Department of Water Resources, Govt.
of Odisha for drawl of ground water. Status of such permission shall be intimated.
5. PROPOSAL FOR ENVIRONMENTAL CLEARANCE FOR EXPANSION OF BED
CAPACITY FROM 300 BEDS TO 350 BEDS OF M/S APOLLO HOSPITALS ENTERPRISE
LIMITED, AT- SAINIK SCHOOL ROAD, BHUBANESWAR.
1. The Apollo group has an existing hospital in Bhubaneswar with 300 beds.
2. The site is located at Sainik School Road, Bhubaneswar, Odisha. The Geographical co-
ordinate of the project site is: Latitude - 20º18’21.22’’ N & Longitude - 85º49’56.86’’ E.
The project site is well connected with National Highway NH-5 & NH-203. The nearest
railway station is Bhubaneswar Railway station at a distance of approx 4.55 Km. The
nearest airport is Biju Patnaik Airport at a distance of approx. 6.77 Km from project site.
3. Environment Clearance has been obtain from SEIAA, Odisha vide letter no.
7439/SEIAA, dt. 28.10.2013. Consent to Operate has been obtain from SPCB, Odisha
vide letter no. 6521/IND-I-CON-6378, dated 05.04.2016. Water permission has been
obtained from P.H. Department. Agreement has been made with Sani Clean for
Biomedical Waste disposal. Waste water discharge permission to BMC drain has been
given by BMC. Bio-medical wastes Authorization from SPCB, Odisha vide letter no.
5722/SPCB/Authorization (BMW), dated 30.03.2015.
4. The proponent has applied for environmental clearance for expansion of bed capacity
from 300 beds to 350 beds.
5. A comparison statement of existing and proposed activities has been given below.
Secretary, SEAC Page 13 of 17
Existing Expansion Total
Hospital Bed 300 50 350
Plot Area 30351.42 sqm - 30351.42 sqm
Built up Area 21983.76 sqm 11250 sqm 33233.76 sqm
Parking Detail 7858 sqm
(Open Parking +
parking area for
handicapped)
3944 sqm
(Multi-Level Car
Parking) 11802.0 sqm
Water Requirement 234 KLD 34.5 KLD 268.5 KLD
Waste Water Generation 187.2 KLD 27.6 KLD 214.8 KLD
Bio-medical Waste 150 Kg/day 25 Kg/day 175 Kg/day
Solid Waste Generation 1000 Kg/day 90 Kg/day 1090 Kg/day
Power Requirement 1500 KVA 500 KVA 2000 KW
Project Cost 140 Crores 32 Crores 172 Crores
6. REQUIREMENT FOR THE PROJECT:
Water requirement:
The existing water use is 234.0 KLD which will be increased to 268.5 KLD by a quantity
of 34.5 KLD for the extra nos. of beds which will be sourced from Municipal water.
Waste Water Details:
It is expected that the project will generate 182.7 KLD of wastewater which will be in
STP. The wastewater will be treated in the STP of capacity of 270 KLD and the capacity
of Effluent Treatment Plant is 20% of the total waste water generation i.e. all
contaminated water amounting to 32.1 KLD will be in ETP.
Solid Waste Management:
From the existing project solid waste has been generated about 1000 kg/day and Solid
waste generated from the proposed project is 90 kg/day. BMC has collecting Solid
waste.
Biomedical Waste Management:
Bio-medical waste generation from Existing 300 beds is 150 Kg/d and Bio-medical
waste generation from Proposed 50 beds is 25 Kg/d. M/s Sani Clean has taken the
responsibility of collecting & treatment of Bio-Medical Waste generated.
Power requirement:
The daily power requirement for the hospital is preliminarily assessed as 2000 KVA
(Existing & Expansion) source from CESU of Odisha State Electricity Board. In order
to meet emergency power requirements during the grid failure, there is provision of 3
nos. of DG sets of 1010 KVA (2 nos.) and 750 KVA (1 nos.) capacities for power back
up in the Hospital Project.
Fire fighting Installations:
Fire fighting system will be installed as per recommendation of the Fire fighting Officer,
Odisha and as per the guideline of NBC (part-4).
7. The consultant M/s Centre for Envotech & Management Consultancy Pvt. Ltd.,
Bhubaneswar made a detailed presentation before the SEAC on 15.12.2016. The
committee decided to take decision on the proposal after the project proponent furnish
Secretary, SEAC Page 14 of 17
certain information / documents. The proponent has furnished the same and the SEAC
verified the documents as follows:
Sl.
No.
Information Sought by SEAC Compliance furnished by
the proponent
Views of the
SEAC
i) The built up area of Multi-level
parking area should be included
in built up area and total built up
area for expansion project to be
modified accordingly and
submitted.
Built up area of the proposed
building is 7306 m2 and built
up area of multi-level parking
is 3944 m2 so total built up
area of the proposed project
is 11250 m2 (including
parking). Modified form-I
incorporating revised builtup
area has been furnished.
Complied.
ii) Percentage of energy used
from solar / non-conventional
source
5% of total energy will be
used from solar / non-
conventional source.
Complied.
iii) Corrected water balance for the
existing and proposed
expansion with details of the
methodology /technology
adopted citing the reference.
The existing water used is
234 KLD which will be
increased to 268.5 KLD by
a quantity of 34.5 KLD for
proposed expansion.
Detailed water balance
furnished.
Complied.
iv) The proponent has proposed to
install an ETP for treatment of
bio-medical waste water. The
outlet of ETP is proposed to be
connected to inlet sump of the
existing STP. The committee
opined that since, STP has
been designed for treatment of
domestic waste water with
biological treatment system, the
addition of the treated water of
ETP at the inlet of STP will
adversely affect the biological
treatment system of the STP.
The proponent has to justify this
with technical information from
the technology supplier of the
STP & ETP with detailed flow
sheet of STP & ETP.
Detailed proposal of ETP with
flow diagram has been
furnished. STP and ETP flow
diagram also furnished.
Complied.
However, a
condition to be
stipulated in the
environmental
clearance that the
proponent shall
neutralize the ETP
water before
sending to the inlet
of STP for further
treatment.
v) Certified copy of the latest
Monitoring Report of the
Regional Office of the
MoEF&CC, Govt. of India,
Bhubaneswar as per circular
dated 30th May, 2012 on the
Certified copy of the latest
Monitoring Report of the
Regional Office of the
MoEF&CC, Govt. of India,
Bhubaneswar is furnished.
Complied.
Secretary, SEAC Page 15 of 17
Sl.
No.
Information Sought by SEAC Compliance furnished by
the proponent
Views of the
SEAC
status of compliance of
conditions stipulated in the
previous environmental
clearance shall be provided. In
addition, status of compliance
of Consent to Operate
conditions for the ongoing /
existing operation of the project
from SPCB shall be submitted.
vi) Green belt dimension to be
mentioned and reflected in the
layout map approved by the
BDA along with species and
numbers thereof.
Green belt area details has
been furnished. Total
greenbelt area is 6115 m2
(20% of the plot area). Layout
map indicating green areas
has been furnished.
Complied.
vii) Land schedule with kisam of
land of the entire project area is
to be submitted.
Land schedule with kisam of
land is furnished. Complied.
8. Considering the information furnished by the proponent and presentation made by the
consultant M/s. Centre for Envotech and Management Consultancy Pvt. Ltd,
Bhubaneswar on behalf of the project proponent, the SEAC recommended for grant of
environmental clearance for the project valid for a period of 7 years with stipulated
conditions as per Annexure – I
6. PROPOSAL FOR ENVIRONMENTAL CLEARANCE TO SET UP OF LPG BOTTLING
PLANT OF STORAGE CAPACITY OF 3X300 MT LOCATED AT BARKANI VILLAGE,
BOLANGIR BLOCK, BOLANGIR DISTRICT OF M/S BHARAT PETROLEUM
CORPORATION LTD. – APPEAL BY THE PROPONENT FOR EXEMPTION OF PUBLIC
HEARING.
The proposal was considered by the committee to determine the “Terms of Reference
(TOR)” for undertaking detailed EIA study for the purpose of obtaining environmental
clearance in accordance with the provisions of the EIA Notification, 2006 and amendment
thereafter.
M/s Bharat Petroleum Corporation Limited (BPCL) has proposed to set up a new LPG
storage and Bottling Plant at Plot no: 12, Khata no:109 & 111, Rev plot no: 93(P), 902(P) at
IDCO Growth centre PH- II, Barkani Village, Bolangir Block, Bolangir District, Odisha State
with a storage capacity of 3 X 300 MT and the LPG bottling throughput of 88,000 TPA.
The current proposal has been submitted to State Environmental Impact Assessment
Authority for the proposed bulk capacity of LPG storage (900MT) and the LPG bottling
throughput of 88,000 TPA through 1 Electronic Carousel having 24 LPG Filling
Stations in two shifts. Hence, the present proposal is classified under Schedule 6(b) &
Category ‘B’ according to EIA Notification 2006 & subsequent amendments.
Land Area of 23.12 acres has been leased to M/s BPCL for 90 years by IDCO Growth
centre PH- II. IDCO contains all infrastructure facilities necessary for the LPG bottling Plant.
Secretary, SEAC Page 16 of 17
The project site is well connected by road and rail network. The project site is located at the
distance of 4.4 km from NH 26 which connects Raipur in Chhattisgarh and passes through
Odisha. Bolangir Railway Station is located at the distance of 6.2 km (SSE). JSPL Airport is
located at the distance of 160 km (E).
LPG from M/s BPCL (Odisha) will be received through bullet trucks & stored in mounded
bullets of capacity 3 x 300MT (Total 900MT).
LPG transported via bullet trucks is received at the Bottling Plant is unloaded through truck
unloading bays and stored in 900 MT Mounded Bullets (3 x 300 MT). Bulk LPG is pumped
through pipeline to 1 x 24 electronic carousel type filling machines where LPG is filled into
cylinders of 5 kg, 14.2 kg, 19 kg and 47.5 kg. Filled cylinders are then loaded in to stack
trucks for onward movement to LPG distributors for distribution of cylinders to house-
hold/end-use customers.
Project Cost for the proposed LPG Bottling Plant at IDCO Growth centre PH- II, Barkani
village is estimated to be around Rs. 100 Crores.
Water requirement for the bottling plant will be around 10 KLD which will be sourced through
Ground Water (Bore well). Sewage will be disposed through septic tanks & soaks pits.
Washing water generated from cylinder washing will be diverted to sedimentation traps fitted
with oil separator & clarified water will be reused for cylinder washing.
The total manpower requirement will be 120 persons which includes, 20 Permanent staff
and 100 contract labourers.
Electrical Requirement: 375 KV will be required for this LPG BP and the same shall be
supplied by Odisha State Electricity Board (OSEB). In case of power failure, 375 KV
Diesel Generation (DG) set for feeding the main plant operations and another 125 KV
DG set for taking care of plant lighting requirements.
As per the corporate policy, 5% of the project cost will be used for CSR for various
activities.
Storm water drains will be developed to collect run-off water from paved areas.
Recharge pits will set up at the site to harvest run-off water.
Hazardous waste generated from D.G set operation will be disposed to OSPCB
Authorized Recyclers.
Fire fighting Measures will be provided as per OISD Norms. Onsite and Offsite disaster
management plan will be prepared.
The plant will be a storage of LPG and filling in to cylinders, there will not be any major
impacts on air, water, flora-fauna and nearby population, however the operation of the
plant will give rise to better LPG penetration in various districts of Odisha and bring down
the demand supply gap for LPG. Adequate green belt will be developed on 33% of total
plot area within the plant to mitigate the pollution arising due to movement of vehicles.
Baseline environmental data of air quality, surface and ground water quality, soil
characteristics is carried out during October to December 2016, AAQ monitoring is done
at 8 locations and confirmed to NAAQS standards of CPCB. Six ground water and two
surface water sampling is done, Soil characteristics for 7 locations are also carried out.
The plant is situated inside a notified industrial estate, hence Public Hearing is
exempted.
Secretary, SEAC Page 17 of 17
Health check-up of working persons, for identifying occupational health hazards will be
conducted during the operation phase.
Detailed post environmental monitoring plan for comprising of Air, Water, Noise & Soil
Environment will be formulated and will be implemented.
Considering the information / documents furnished by the proponent and presentation made by
the consultant M/s ABC Techno Labs India Private Ltd., Chennai on behalf of the project
proponent, the SEAC issued the TORs for undertaking detailed EIA study vide letter No. 777 dt.
13.12.2016.
The proponent has requested for exemption of public hearing as per the point
7(ii) of the EIA notification 2006 with a claim that the location of the project is
with in notified industrial area notified by the Industries Department, Govt. of
Odisha.
The proponent has also furnished copy of the notification of Industries
Department and land allotment letter of IDCO for this purpose.
The OM of MoEF&CC, Govt. of India, dated 10.12.2014 stipulates that the
exemption of the public hearing is available to the projects or activities or
units located within the Industrial Estates or Parks, which were notified prior
to 14.09.2006 i.e. the EIA Notification, 2006 coming in to force.
The SEAC decided to call the proponent for a detail presentation / discussion with all
relevant documents to justify the location of the plant within industrial estate.
DR. B. K PATNAIK DR. R. C MOHANTY DR. S. C NAYAK PROF. P. K. MOHANTY DR. D. K. ROUT
CHAIRMAN MEMBER, SEAC MEMBER, SEAC MEMBER, SEAC MEMBER, SEAC
SRI A. C MOHANTY SRI S. BEHERA SRI D. SWAIN SRI B. C. PRUSTY DR. S.K. BISWAL MEMBER, SEAC MEMBER, SEAC MEMBER, SEAC MEMBER, SEAC MEMBER, SEAC
APPROVED
CHAIRMAN, SEAC
Secretary, SEAC Page 1 of 6
ANNEXURE -I
CONDITIONS TO BE STIPULATED IN ENVIRONMENTAL CLEARANCE FOR EXPANSION OF BED CAPACITY FROM 300 BEDS TO 350 BEDS OF M/S APOLLO HOSPITALS ENTERPRISE LIMITED, AT- SAINIK SCHOOL ROAD, BHUBANESWAR WITH PROPOSED BUILT UP AREA 11250 M2.
I. SPECIFIC CONDITIONS:
A. CONSTRUCTION PHASE:
1. Construction site should be adequately barricaded before the construction begins.
2. Installation of dual pipe plumbing for supplying fresh water for drinking, cooking and
bathing etc. and other for supply of recycled water for flushing, landscape irrigation,
car washing, thermal cooling, conditioning etc. shall be done.
3. As proposed, 21 nos. of rain water harvesting pits for artificial ground water recharge
shall be installed as per CGWB guidelines.
4. Water demand during construction should be reduced by use of pre-mixed concrete,
curing agents and other best practices referred.
5. Any hazardous waste generated during construction phase, should be disposed off as
per applicable rules and norms with necessary approvals of the State Pollution
Control Board.
6. No ground water shall be extracted for the project work at any stage during the
construction phase. If ground water will be used during construction phase, they shall
obtain permission from the Water Resource Department.
7. Considering the peak water consumption of the occupants, the design of the water
supply system and the sewage disposal system of the project should be based on the
provisions of water consumption.
8. Provision shall be made for the housing of construction labourers within the site with
all necessary infrastructure and facilities such as fuel for cooking, mobile toilets,
mobile STP, safe drinking water, medical health care, crèche etc. The housing may
be in the form of temporary structures to be removed after the completion of the
project.
9. A First-Aid room will be provided in the project site both during construction and
operation of the project.
10. All the top soil excavated during construction activities should be stored separately for
use in land filling, horticulture/landscape development within the project site.
11. Disposal of muck during construction phase should not create any adverse effect on
the neighboring communities and will be disposed off taking the necessary
precautions for general safety and health aspects of people only in approved sites
with the approval of competent authority.
12. Construction spoils, including bituminous material and other hazardous materials
should not be allowed to contaminate watercourses, ground water and dump sites by
following safe dumping / disposal practice as per statutory rules and norms with
necessary approval of the Odisha State Pollution Control Board.
Secretary, SEAC Page 2 of 6
13. The fuel for diesel generator sets to be used during construction phase shall use low
sulfur diesel fuel and should conform to Environment (Protection) Rules 1986
prescribed for air emission and noise standards.
14. The diesel required for operating DG sets shall be stored in underground tanks and, if
required, clearance from the Chief Controller of Explosives shall be taken.
15. Vehicles used for bringing construction materials to the site should be in good
condition and should have a pollution check certificate, covered and conform to
statutory air and noise emission standards and should be operated only during non-
peak hours of the day.
16. Ambient noise levels should conform to residential standards both during day and
night. Incremental pollution loads on the ambient air and noise quality should be
closely monitored during construction phase. Adequate measures should be taken to
reduce ambient air and noise level during construction phase, so as to conform to the
stipulated standards by CPCB/ OPCB.
17. Fly ash bricks should be used as building material in the construction as per the
provisions of Fly Ash Notification of September, 1999 and as amended thereafter.
18. Ready mixed concrete would be used in building construction.
19. Storm water control and its re-use should be as per CGWB and BIS standards for
these applications.
20. Fixtures for showers, toilet flushing and drinking water should be of low flow type and
restricted to requirements by use of aerators, avoiding wastage pressure reducing
devices or sensor based controls.
21. Use of glass may be maximum upto 40% of total outer wall area to reduce the energy
consumption and load on air-conditioning. If necessary, high quality double glass with
special reflective coating may be used in the windows.
22. Roof should meet the prescribed requirement as per Energy Conservation Building
Code by using appropriate thermal insulation material.
23. Opaque wall should meet prescriptive requirements as per Energy Conservation
Building Code.
24. The approval of the competent authority shall be obtained for structural safety of the
buildings due to earthquake, adequacy of firefighting equipments etc. as per National
Building Code of India, 2005 including protection measures from lightning etc.
25. Regular supervision of the above and other measures for monitoring should be in
place all through the construction phase to avoid disturbances and pollution to the
surroundings.
B. OPERATION PHASE:
1. Fresh water requirement shall not exceed 268.5 m3/day.
2. The quantity of fresh water usage, water recycling and rainwater harvesting shall be
measured and recorded to monitor the water balance as projected by the project
proponent. The record shall be submitted to the SEIAA, Odisha and the Regional
Office, MoEF&CC along with six monthly Monitoring reports.
3. Solid waste shall be collected, treated disposed in accordance with the Solid Waste
(Management & Handling) Rules, 2016.
Secretary, SEAC Page 3 of 6
4. Solid waste shall be segregated into biodegradable, recyclable and inert category.
Biodegradable waste shall be composted indigenously in Organic Waste Converter
and the other waste categories shall be disposed suitably.
5. Bio-medical waste shall be collected, treated and disposed in accordance with Bio-
medical Waste Management Rules, 2016.
6. No ground water shall be used during the operation phase. If ground water will be
used during operation phase, they shall obtain permission from the Water Resources
Department.
7. The proponent shall install an Effluent Treatment Plant (ETP) of capacity 50 KLD for
treatment of effluent from different sources of hospital. The treated water from the
ETP shall be neutralized for public health prior to other treatment processes. The
treated waste water from the ETP shall only be allowed to join with treated water of
STP after filter feed tank
8. Treatment of 100% grey water by decentralized treatment should be done. Treated
waste water from STP of 270 KLD capacity shall be recycled / reused to the
maximum extent possible. Discharge of unused treated waste water shall conform to
the norms and standards of the Odisha State Pollution Control Board. Necessary
measures should be taken to mitigate the odour problem from STP.
9. In no case there should be any discharge of treated effluent to outside of the project
premises.
10. The STP sludge should not be dried nor incinerated within the project site and should
be disposed off as per the norms of SPCB, Odisha.
11. The STP must treat all kinds of pollutants present in it and its capacity should take
into account the entire load of sewage generated from the hospital.
12. The project proponent will ensure that under no circumstances, the environment is
polluted due to non-functioning / under performance of sewerage disposal system of
the project.
13. Diesel power generating sets proposed as source of back-up power for lifts elevators
and common area illumination during operation phase should be of enclosed type and
conform to Environment Protection (EP) rules 1986. The height of the stack of DG
sets should be equal to the height needed for the combined capacity of all proposed
DG sets put together and should be more than the highest building height. Low sulfur
diesel should be used. The location of the DG sets may be decided in consultation
with Odisha State Pollution Control Board. Care may be taken to avoid disposal of
smoke /pollutants from DG sets in the residential area. Low sulfur diesel oil (LDO or
HSD) is to be used in DG set.
14. Noise should be controlled to ensure that it does not exceed the prescribed
standards. During night time, the noise levels measured at the boundary of the sites
shall be restricted to the permissible levels to comply with the prevalent regulations.
15. Green-belt & avenue plantation of trees over the area of 6115 m2 shall be done using
native tree species/shrubs improving greenery & keeping in view aesthetics
considerations in the whole complex. Professional landscape architects should be
engaged to design the green layout to provide for multi-tier plantation and green
fencing all around, mitigating various environmental pollutants like dust, noise,
emissions etc.
Secretary, SEAC Page 4 of 6
16. Weep holes in the compound walls shall be provided to ensure natural drainage of
excessive rain water in the project area during the monsoon period after the
harvesting operations. Care must be taken so that there is no water logging in the
territory and drainage is 100%.
17. Traffic congestion near the entry and exit points from the roads adjoining the
proposed project site must be avoided. Traffic congestion shall be avoided inside the
project site. The area ear- marked for parking shall not be used for any other purpose.
Alternate entry and exit must be provided to handle excess traffic and emergency
situations.
18. A report on the energy conservation measures confirming to energy conservation
norms finalized by the Bureau of Energy Efficiency should be prepared incorporating
details about building materials & technology, R& U Factors etc. and submitted to the
SEIAA, Odisha in three months’ time before operation/ habitation.
19. The proponent shall use atleast 5% of non-conventional energy (solar energy).
20. Central lighting and street lighting shall be based on solar power. Provisions of solar
hot water storage / supplies at the roof top may be made as per statutory norms of
CPCB/MoEF&CC/SPCB, Odisha.
21. Energy conservation measures like installation of LED for lighting the areas outside
the building should be integral part of the project design and should be in place before
project commissioning. Discarded bulbs should be properly collected and disposed
off/sent for recycling as per the prevailing guidelines/ rules of the regulatory authority
to avoid toxic contamination. Use of solar panels be adopted to the maximum extent
possible, especially for street lights.
II. GENERAL CONDITIONS:
1. The project proponent shall comply with all the conditions stipulated in the building
approval letter.
2. The applicant (Project proponent) will take necessary measures for prevention,
control and mitigation of Air Pollution, Water Pollution, Noise Pollution and Land
Pollution including solid waste management as mentioned by them in Form-1, Form-
1A, and Environment Management Plan (EMP) in compliance with the prescribed
statutory norms and standards.
3. The applicant will take statutory clearance/approval/permissions from the concerned
authorities in respect of the project as and when required.
4. The applicant will submit half-yearly compliance report on post-environmental
monitoring in respect of the stipulated terms and conditions in the Environmental
Clearance to the State Environmental Impact Assessment Authority (SEIAA), Odisha,
on 1st June and 1st December of each calendar year.
5. The project proponent shall comply to all the conditions stipulated by the Fire
Prevention Officer, Odisha.
6. The applicant will adopt the prescribed norms, and standards provided in the National
Building Code of India, 2005.
7. A copy of the environmental clearance letter shall also be displayed on the website of
the concerned State Pollution Control Board. The EC letter shall also be displayed at
Secretary, SEAC Page 5 of 6
the Regional office. District Industries Centre and Collector’s Office/ Tehsildar’s Office
for 30 days.
8. The funds earmarked for environmental protection measures shall be kept in separate
account and shall not be diverted for other purpose. Year-wise expenditure shall be
reported to the SEIAA, Odisha.
9. Officials from the Regional Office of MoEF&CC, Bhubaneswar would be monitoring
the implementation of environmental safeguards should be given full cooperation,
facilities and documents/data by the project proponents during their inspection. A
complete set of all entire document submitted to SEIAA, Odisha should be forwarded
to the Regional Office of MOEF&CC, Bhubaneswar.
10. In the case of any change(s) in the scope of the project, the project would require a
fresh appraisal by the SEIAA, Odisha.
11. The SEIAA, Odisha reserves the right to add additional safeguard measures
subsequently, if found necessary, and to take action including revoking of the
environment clearance under the provisions of the Environmental (Protection) Act,
1986, to ensure effective implementation of the suggested safeguard measures in a
time bound and satisfactory manner.
12. All other statutory clearances shall be obtained, as applicable by project proponents
from the respective competent authorities.
13. These stipulations would be enforced among others under the provisions of Water
(Prevention and Control of Pollution) Act, 1974, the Air (Prevention and Control of
Pollution) act 1981, the Environment (Protection) Act, 1986, the Public Liability
(Insurance) Act, 1991 and EIA Notification, 2006.
14. The project proponent should advertise in at least two local Newspapers widely
circulated in the region, one of which shall be in the vernacular language informing
that the project has been accorded Environmental clearance and project has been
accorded Environmental Clearance and copies of clearance letters are available with
the state Pollution Control Board and may also be seen on the website of the SEIAA,
Odisha. The advertisement should be made within Seven days from the date of
receipt of the Clearance letter and a copy of the same should be forwarded to the
Regional Office of MoEF&CC, Govt. of India at Bhubaneswar.
15. A copy of the clearance letter shall be sent by the proponent to concerned Panchayat,
Zilla Parisad/Municipal Corporation, Urban Local Body and the Local NGO, if any,
from whom suggestions/ representations, if any, were received while processing the
proposal, the clearance letter shall also be put on the website of the company the
proponent.
16. The proponents shall upload the status of compliance of the stipulated EC conditions,
including results of monitored data on their website and shall update the same
periodically. It shall simultaneously be sent to the Regional Offices of MoEF&CC,
Bhubaneswar the respective Zonal Office of CPCB and the SPCB. The criteria
pollutant levels namely; PM10, PM2.5, SO2, NOx (ambient levels as well as stack
emissions) or critical sectoral parameters, indicated for the projects shall be
monitored and displayed at a convenient location near the main gate of the company
in the public domain.
Secretary, SEAC Page 6 of 6
17. Any appeal against this clearance shall lie with the National Green Tribunal, if
preferred, within a period of 30 days as prescribed under Section 16 of the National
Green Tribunal Act, 2010.
18. The above mentioned stipulated conditions shall be complied in a time-bound
manner. Failure to comply with any of the conditions mentioned above may result in
cancellation of this environmental clearance and attract action under the provisions of
Environment (Protection) Act, 1986.