private sector development & financing of (power) projects & technology transfer
DESCRIPTION
UNFCCC MONTREAL WORKSHOP Innovative Options for Financing the Development & Transfer of Technologies. PRIVATE SECTOR DEVELOPMENT & FINANCING OF (POWER) PROJECTS & TECHNOLOGY TRANSFER Practical Experiences of Project Pre-Development & Financing in Sub-Saharan Africa. HERA. - PowerPoint PPT PresentationTRANSCRIPT
1
PRIVATE SECTOR DEVELOPMENT & FINANCINGOF (POWER) PROJECTS & TECHNOLOGY
TRANSFER
Practical Experiences of ProjectPre-Development & Financing in Sub-Saharan Africa
SEPTEMBER 2004
HERAI N T E R N A T I O N A L
UNFCCC MONTREAL WORKSHOP
Innovative Options for Financing the Development & Transfer of Technologies
2
CONTENTS
The Project Development Cycle
Pre-Development Phase Options Tools & Techniques Example Barriers
Development Phase & Financing Barriers Tools & Techniques Cost Issues
Integration as a Possible Response Possibilities of using Integration for financing
Wind Power in Africa
3
WHAT IS PRE-DEVELOPMENT?THE PROJECT DEVELOPMENT CYCLE
ProjectProjectDvpt.Dvpt.
PrePreFeasibilityFeasibility
PRE-DEVELOPMENT
• Can it work?• What conditions?• Which Partners?• Estimated Cost?• Refinancing Sources?• Initial Structuring
FeasibilityFeasibility ProjectProjectDvpt.Dvpt.
Imple-Imple-mentationmentation
DEVELOPMENT IMPLEMENT
• Business Plan / Bankable Feasibility• Technical Design & Specification• Scope of Work• Project Structure• Investment Consortium• Contractors & Suppliers
ProjectProjectIdeaIdea
• Need• Vision
4
PRE-DEVELOPMENT ISSUES
Pre-Development Costs need to be financed ca. 2% of total project costs Total Development Costs 5 % – 7 %
No Guarantee that Project will be implemented
Relatively high risk Return still uncertain
Venture Capital / Development Capital nature of investment
Long Term Project Development Horizon 2 – 5 Years
Pre-Development Phase
5
PRE-DEVELOPMENT OPTIONS
Public Sector Route Government / Donor funding of studies and initial development Public Procurement Processes (Tender) Time Scale / Efficiency Alternatives?
Private Sector Route Private Sector Developer
Hybrid Routes In practice most (power sector) projects are hybrids
Sponsor‘s Perspective / i.e. Government
Pre-Development Phase
6
PRE-DEVELOPMENT TOOLS
Usual Suspects Development Funds (Multilaterals) Grants & Subsidies Facilitators / Networks
Development Consortium Spread & Diversify Risk Public & Private Sector Partners Avoid Equipment Suppliers / Contractors if possible
Initial Analysis: Identification of strategic / special interests in the Project Who are the Stakeholders & Benefactors?
What can be done to make project more viable / attractive? Integration Linkage Increased value to Benefactors and Stakeholders
Pre-Development Phase
7
HOW DOES IT LOOK IN PRACTICE?
Multi-faceted Integrated Project Coal Mining & Export Railway Rehabilitation for Transport Coal Fired Power Generation at Mine Head Coal Terminal Upgrade
What were the Goals? Private Sector Financed Solution Participation of MZ Public & Private sectors Lowest possible burden on MZ PSB Maximum impact on connected sectors & local economy
Zambezi Valley Development Scheme
Pre-Development Phase
HEADS OF AGREEMENTHEADS OF AGREEMENTincorporating:
Objectives Warranties / Guarantees / Exclusivity Channels of Communications / Task Force Development Programme Deliverables Confidentiality / Non-Disclosure
Preparation of Feasibility Report and Implementation Plan
Pursue discussions with IFC / Multi-lateral and Private Funding Agencies
Collation and Transfer of DeliverablesAttendance in Task Force Activities / MeetingsParticipation in Sectorial Activities-- Coal Mining-- Railway / Port Operations-- Energy and Industrial Outlets-- Forestry & Agriculture
FEASIBILITY REPORTFEASIBILITY REPORT
ANDAND
IMPLEMENTATION PLANIMPLEMENTATION PLAN
DEVELOPMENT CONSORTIUM Developer / Investors
Operators Contractor
PUBLIC SECTOR Involved Ministries
Authorities & AgenciesParastatals
PRE-DEVELOPMENT PHASE
9
GETTING OVER THE BARRIERS
Development Consortium Self Funding of Pre-Development Risk (part /
majority) Project Design & Specification Commitment to provide equity at implementation
phase
Partnership with Public Sector Partners Parastatals as members of Development
Consortium (and later also the Implementation Consortia)
Equipment Supply & Contracting put out to tender Development Consortium retains operating
responsibility, and control Vital self-interest to ensure value for money Bears economic risk and takes return
Benchmarking
Pre-Development Phase
10
GETTING OVER THE BARRIERS (2)
Independent Integrator / Developer
No vested interests - neither supplier, nor contractor nor investor
Only interest / goal is that the Project gets done
Mediates and co-ordinates
Brokers (forces) the compromises & the issues
Economic Logic & Project Success are sole drivers
Pre-Development Phase
11
THE BARRIERS
Developer(s) / Consortium required comfort that they would take benefit out of the Project assuming positive feasibility Return on investment in development costs & risks
Pressure for an early decision
Conflict with established procurement procedures
Political Unease & Resistance because of Issues of Control Value for Money Transparency
All of which were however addressed by the Structure
Project now being implemented in its constituent parts No integration Financed by PSB
Pre-Development Phase
12
MAIN BARRIERS TO FINANCING
Legislative & Regulatory Environment
Economic & Commercial Risks
Standard Tools are indispensable Multilaterals ECAs / Commercial Political Insurance Hedging
Identifying & Generating Secure Refinancing Streams Off-takers Integration
Development / Implementation Phase
IMPLEMENTATION PHASEPU
BLI
C S
EC
TO
RPU
BLI
C S
EC
TO
R
PARASTATALS
Debt Financing
- IFC - ECAs - Commercial banks
Interest
PrincipalRepaymentof Debt
On-goingMaintenanceCosts
Dividends
Global Scheme up to full Repayment of Debts and Return on Capital
EQUITYFUNDING
SPECIAL
PURPOSE
COMPANY
CONCESSIONS& ASSETS
$SECTOR: MININGSECTOR: MINING
Developer: Coal Miner (Commodities Trader)
Developer: Coal Miner (Commodities Trader)
GENERATEDGENERATEDOPERATING OPERATING
INCOMEINCOME
$
$
SECTOR: TRANSPORTATIONSECTOR: TRANSPORTATION
Developer: Railway OperatorRehabilitation: Contractor
Developer: Railway OperatorRehabilitation: Contractor
SECTOR: POWERSECTOR: POWER
Development: Utility Operator & Parastatal
Development: Utility Operator & Parastatal
PR
IVA
TE S
EC
TO
RPR
IVA
TE S
EC
TO
R
IMPLEMENTATIONCONSORTIUM
DeveloperInvestorsOperators
Contractors
MOZ. COMPANIES
14
REVENUES ARE THE KEY
Export of High Quality Coking Coal Arms length long term off-taking contract with
independent commodity trader Indexed to market prices: Security of Revenues Offshore Hard Currency Payments
PPA / Off-taking Agreements Industrial Users for base load Local Utility and International Utility Price was key (<2 cts / KWhr.) Export into SAPP
Operator Experience & Know-how Guarantee of operating targets
Equity Component
Development / Implementation Phase
15
Ranges of Energy Production Costs
0
2
4
6
8
10
12
14
16
Wind Hydro Gas Coal Nuclear Biomass
€-cent / KWh
PRICE ISSUES IN RELATION TO CHOICE OF
TECHNOLOGY (1)
Price Considerations in the Development Process
16
PRICE ISSUES IN RELATION TO CHOICE OF
TECHNOLOGY (2)
Price Considerations in the Development Process
500.000
750.000
1.000.000
1.250.000
1.500.000
1.750.000
USD / MW
CCGT Thermal Wind Hydro
COMPARISON OF CAPITAL COST OF NOMINAL PEAK CAPACITY
17
INTEGRATION AS A TOOL TO ADDRESS
PRICE ISSUES
Thermal Production Costs much lower (subsidy)
Ideas for Integration: Decentralised Locations (reduction of
transmission costs) Combination with Desalination Combination with establishment of refrigerated
processing & storage facilities for local fishing industries
Cooperation with white goods manufacturers for production of appliances with low voltage ratings
Wind Energy in RIM / MZ / ANG / TNZ
Development / Implementation Phase
€ cents 5 - 9 / KWhr make Wind Energy an apparently unattractive commercial proposition in Africa
18
EFFECTS OF INTEGRATION
Reduction of pure economic risks Increased Revenue Earnings diversification Foreign Currency Potential
Higher Added Value Increased benefits to a wider community of
stakeholders Nominal high price is made more acceptable Linkage
Increased Complexity
Development / Implementation Phase
Diversification & Increase of Revenue Streams for Repayment of Financing
Risk diversification (although increased in absolute terms)
19
CONCLUSIONS
Conclusions
Price of (new) Renewables Technology is the chief barrier No need to buy a Rolls Royce if a 2 CV also gets you there External cost argument is only partially accepted in Africa
Private Finance, Developers & Tools are available for pre-development phases of New Technology Projects Combination with existing tools and financing instruments
Need for increased flexibility for dealing with parties able & willing to take development risk Development of appropriate control mechanism Transparent criteria for calculation of return Further third party funding sources / funds
Potential of Project Integration to create Linkage and increase Stakeholder benefits Can be used to raise finance for a VW-Golf