PRIME CONTRACTOR PERFORMANCESunset Rule Changes

Transportation Code, Sec. 223.012. Contractor Performance.

The commission shall adopt rules to:

develop a contractor performance evaluation process and an evaluation tool that:

– allows for the review of contractor bidding capacity to ensure that contractors meet each quality, safety, and timeliness standard established by the commission; and

– contains criteria for modifying a contractor’s bidding capacity for competitively bid highway improvement contracts when appropriate.

2

Transportation Code, Sec. 223.012. Contractor Performance.

3

Prime Contractor Evaluation ToolThe commission shall adopt rules to:

develop a contractor performance evaluation process and an evaluation tool that:

– allows for the review of contractor bidding capacity to ensure that contractors meet each quality, safety, and timeliness standard established by the commission; and

– contains criteria for modifying a contractor’s bidding capacity for competitively bid highway improvement contracts when appropriate.

Form 2707, “Contractor Evaluation Form”

4

Three categories, with three questions each:

Quality

Safety

TimelinessScores (1–3) should consider whether the contract provided sufficient time, as well as any events outside the contractor’s control.

PRIME CONTRACTOR PERFORMANCE EVALUATION PROCESS

5

Prime Contractor Evaluation Flow Chart

6

District Actions

Division Actions

PRC Actions

Prime Contractor Evaluation Flow Chart – District Actions

7

Contractor completes project or is scheduled to receive interim evaluation

Area Engineer completes Form 2707

Final – Meet with contractor, escalating eval as needed

Finished

Interim – Meet with contractor, escalating eval as needed

Score at or Above 2.0Request Project

Recovery Plan

Score Below 2.0

Performance Improves

Finished

Does Not Meet Expectations

Refer to PRC

DefaultDivision Advises

Prime Contractor Evaluation Process – District Actions

8

SiteManager Entry

Transportation Code, Sec. 223.012. Contractor Performance.

9

Prime Contractor Evaluation ToolThe commission shall adopt rules to:

develop a contractor performance evaluation process and an evaluation tool that:

– allows for the review of contractor bidding capacity to ensure that contractors meet each quality, safety, and timeliness standard established by the commission; and

– contains criteria for modifying a contractor’s bidding capacity forcompetitively bid highway improvement contracts when appropriate.

Prime Contractor Evaluation Flow Chart

10

District Actions

Division Actions

PRC Actions

11

Prime Contractor Evaluation Flow Chart – Division Actions

Division runs quarterly report on FINAL evals for all contractors.

Contractor Average at or Above 2.0

Finished

Contractor Average Below 2.0

Division Requests Corrective Action Plan

Performance Improves

Finished

Does Not Meet Expectations

Refer to Performance Review Committee

Performance Review Committee

Performance Review Committee – high-level group recommends actions for Deputy Executive Director’s decision.

5 possible recommendations:

– Take no action

– Reduce the contractor’s bidding capacity

– Prohibit the contractor from bidding on one or more projects

– Immediately suspend the contractor from bidding for a specified period

– Recommend not awarding contract to contractor12

13

Prime Contractor Evaluation Flow Chart – PRC Actions

PRC reviews full portfolio of contractor’s work.

Chief Engineer reviews recommendation.

Deputy Executive Director reviews recommendation and makes determination.

Finished

Directs No Further Action

Recommends Action

Concurs with Recommended

Action

Recommends No Action

Recommends No Action

Chief Engineer notifies PRC and contractor and implements action.

Directs ActionContractor may appeal to Executive Director within 15 days of notification.

Three Paths to Performance Review Committee

14

• Chief Engineer reviews recommendations and forwards concurrence to Deputy Executive Director • Deputy Executive Director determines actions• Contractor may appeal actions to Executive Director within 15 days of communication of action to

contractor.

Division conducts statewide quarterly review – average of contractor’s 10 most recent final evaluations

If contractor average falls below threshold, Division requires a Corrective Action Plan

Contractor has 120 days to improve performance

If Corrective Action Plan is not met, Division refers contractor to Committee

District requires Project Recovery Plan

If Project Recovery Plan is not met, or if the contractor is defaulted or , District refers contractor to Committee and notifies Division

Activities given in current Highway Improvement Contract Sanctions (43 TAC §9.107) that do not relate to default, ethics, or timeliness

Failure to execute a contract after award, unless contractor honors bid guaranty

Commission rejection of two or more bids by the contractor in the preceding 36 months due to contractor error

Project-Specific Portfolio Extra-Contractual

Transportation Code, Sec. 223.012. (Other Requirements)

The commission must consult with industry contractors

The adopted rules must:

–Provide an appeals process

–Include criteria for evaluations

–Give consideration of sufficient time

–Give consideration to events outside a contractor’s control

15

Summary

16

Sunset Commission Report – Require TxDOT to conduct contractor evaluations and consider past performance in determining bid capacity

Transportation Code §223.012 – TxDOT must develop a contractor performance evaluation process and an evaluation tool to ensure that contractors meet each quality, safety, and timeliness standard

Legislative Mandate

Collaborative – TxDOT and industry succeed together.

Use the evaluation as a tool for communication.

– If there are problem areas, use the interim to communicate how to get back on track.

– There should be no surprises on the final.

In case of major failure, PRC can take immediate action.

Another Tool in the Toolkit

DO NOT DISCLOSE – Attorney General opinion required

Treat evaluation forms like Form 599.

All forms must remain at the district with the project records.

Consultants may not copy or retain a completed evaluation form for their records.

Open Records

Division staff is here to help!

Construction – Carlos Rodriguez, Carmen Grasoi-Garcia, Eduardo Acosta

Maintenance – Alanna Bettis, Missy Lowe

Division Support

Questions?

17

Gina Gallegos, PE Tucker Ferguson, PECST Division Director Beaumont District Engineer(512) 416-2501 (409) [email protected] [email protected]