Oracle Primavera P6 Help for Print First Half
Copyright 1997, 2012, Oracle and/or its affiliates. All rights reserved.
Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names
may be trademarks of their respective owners.
The Programs (which include both the software and documentation) contain proprietary
information; they are provided under a license agreement containing restrictions on use
and disclosure and are also protected by copyright, patent, and other intellectual and
industrial property laws. Reverse engineering, disassembly, or decompilation of the
Programs, except to the extent required to obtain interoperability with other
independently created software or as specified by law, is prohibited.
The information contained in this document is subject to change without notice. If you
find any problems in the documentation, please report them to us in writing. This
document is not warranted to be error-free. Except as may be expressly permitted in your
license agreement for these Programs, no part of these Programs may be reproduced or
transmitted in any form or by any means, electronic or mechanical, for any purpose.
The platform-specific hardware and software requirements included in this document
were current when this document was published. However, because new platforms and
operating system software versions might be certified after this document is published,
review the certification matrix on the My Oracle Support Web site for the most up-to-date
list of certified hardware platforms and operating system versions. The My Oracle Support
Web site is available at the following URL:
http://support.oracle.com/
If the Programs are delivered to the United States Government or anyone licensing or
using the Programs on behalf of the United States Government, the following notice is
applicable: U.S. GOVERNMENT RIGHTS Programs, software, databases, and related
documentation and technical data delivered to U.S. Government customers are
"commercial computer software" or "commercial technical data" pursuant to the
applicable Federal Acquisition Regulation and agency-specific supplemental
regulations. As such, use, duplication, disclosure, modification, and adaptation of the
Programs, including documentation and technical data, shall be subject to the licensing
restrictions set forth in the applicable Oracle license agreement, and, to the extent
applicable, the additional rights set forth in FAR 52.227-19, Commercial Computer
Software -- Restricted Rights (June 1987). Oracle USA, Inc., 500 Oracle Parkway,
Redwood City, CA 94065.
Copyright
-
Copyright
3
The Programs are not intended for use in any nuclear, aviation, mass transit, medical, or
other inherently dangerous applications. It shall be the licensee's responsibility to take all
appropriate fail-safe, backup, redundancy and other measures to ensure the safe use of
such applications if the Programs are used for such purposes, and we disclaim liability for
any damages caused by such use of the Programs.
The Programs may provide links to Web sites and access to content, products, and
services from third parties. Oracle is not responsible for the availability of, or any content
provided on, third-party Web sites. You bear all risks associated with the use of such
content. If you choose to purchase any products or services from a third party, the
relationship is directly between you and the third party. Oracle is not responsible for: (a)
the quality of third-party products or services; or (b) fulfilling any of the terms of the
agreement with the third party, including delivery of products or services and warranty
obligations related to purchased products or services. Oracle is not responsible for any
loss or damage of any sort that you may incur from dealing with any third party.
To view the list of third party technology disclosures related to this product, please see
the Commercial Notices and Disclosures document for the release.
-
5
Contents
Copyright ................................................................................................ 2
Preface ................................................................................................. 41
Where to Get Documentation .................................................................... 41
Where To Get Training ............................................................................ 44
Where to Get Support ............................................................................. 44
Documentation Accessibility ...................................................................... 45
Introduction............................................................................................ 47
About Oracle Primavera P6 Enterprise Project Portfolio Management ..................... 47
Working with the Oracle Primavera P6 EPPM Suite ........................................... 48
About P6 ......................................................................................... 51 About P6 Team Member Applications ........................................................ 52 About P6 Progress Reporter ................................................................... 53 About Oracle Universal Content Management .............................................. 54 About P6 Professional .......................................................................... 54 About Oracle BI Publisher and the OBIEE Platform ........................................ 55 About P6 Reporting Database ................................................................. 55 About P6 Analytics .............................................................................. 55 About the Oracle Business Process Management Suite .................................... 57 About the P6 Integration API .................................................................. 57 About P6 EPPM Web Services ................................................................. 58
What's New in P6 EPPM ............................................................................ 58
P6 Overview ........................................................................................... 59
Working with P6 .................................................................................... 59
Customizing the P6 User Experience ............................................................ 61
About Industry-Specific Field Names ......................................................... 62
About the User Interface .......................................................................... 63
Working with the P6 User Interface .......................................................... 63 About Screen Controls ....................................................................... 65 Working with the Main Menus .............................................................. 66 About the Most Recently Used List ........................................................ 67
Working with Tables ......................................................................... 68 About Columns (Fields)...................................................................... 69
Showing or Hiding Columns in a Table ................................................... 69 Selecting Items from a List of Available Items .......................................... 70 Working with Toolbars ...................................................................... 71 Customizing Toolbars ........................................................................ 72
Working with "Select a Value" Dialog Boxes ............................................. 72 Selecting Values from "Select a Value" Dialog Boxes .................................. 74
Working with Data in P6 .................................................................... 75 Working with Detail Windows .............................................................. 76
-
P6 Help
6
About Portlets ................................................................................ 78 About Data Entry Controls .................................................................. 78
About Security ...................................................................................... 78
Printing Pages Using P6 Printing Tools .......................................................... 79
Printing Pages Using Your Web Browser ........................................................ 80
About E-Mail Notifications ........................................................................ 80
Working with E-Mail Notifications ............................................................ 81 Sending Activity Views by E-Mail .......................................................... 82 Sending E-Mail about Documents .......................................................... 82 Sending E-Mail about Issues ................................................................ 83 Sending E-Mail about Milestones .......................................................... 83 Sending E-Mail about Timesheets to Resources ......................................... 84 Sending E-Mail Notifications about Resource Assignments ........................... 84 Sending E-Mail to a Project Manager ..................................................... 85 Sending E-Mail to Activity Resources ..................................................... 86 Sending E-Mail to Project Resources ...................................................... 86 Sending E-Mail to Resource Teams ........................................................ 87 Updating the Progress of Activities Using E-mail ....................................... 88
About Grouping and Sorting ...................................................................... 88
Working with Group and Sort Features ...................................................... 89 Grouping and Sorting Information ............................................................ 90
About Find, Search, and Filter Features ........................................................ 91
Working with Find, Search, and Filter Features ............................................ 91 Finding Entries ................................................................................ 92 Searching for Entries ........................................................................ 92 About Filters .................................................................................. 93 Working with Filters ......................................................................... 93
Filtering Data ................................................................................. 95
Pages Supporting Filters .................................................................... 96
Creating, Modifying, Saving, and Deleting Data ............................................... 97
Cutting, Copying, and Pasting Data .......................................................... 97 About Removing and Deleting Data .......................................................... 98
Deleting Entries .............................................................................. 99 Undoing Mistakes ............................................................................... 99
About Metrics and Calculations ................................................................. 100
Using Visual Indicators ........................................................................ 100
About Importing and Exporting Data ........................................................... 101
About Importing and Exporting Projects ................................................... 102
About P6 Help...................................................................................... 102
Viewing Help Content ......................................................................... 102 Working with P6 Help Topics ................................................................. 104
About Timesheets ................................................................................. 106
Working with Timesheets ..................................................................... 106 Approving or Rejecting Timesheets ......................................................... 107 Sending E-Mail about Timesheets to Resources ........................................... 108 Assigning a Project Manager Delegate for Timesheets ................................... 109
-
Contents
7
Assigning a Resource Manager Delegate for Timesheets ................................. 110
Dashboards and Workspaces ...................................................................... 113
About Dashboards, Workspaces, and Workgroups ............................................ 113
About Dashboards ................................................................................. 113
Working with Dashboards ..................................................................... 114 Creating Dashboards........................................................................... 117 Customizing Dashboards ...................................................................... 117
Configuring Dashboard Content .......................................................... 118 Configuring Dashboard Access ............................................................ 118 Configuring Dashboard Filters ............................................................ 119 Configuring Dashboard Layout ............................................................ 119 Showing and Hiding Dashboards .......................................................... 120
Working with Workflows in P6 ............................................................... 120
About Project Workspaces ....................................................................... 123
Working with Project Workspaces ........................................................... 124 Customizing Project Workspace ............................................................. 124
Configuring Workspace Content .......................................................... 124 Configuring Workspace Layout ............................................................ 125
Sending E-Mail to Project Resources ........................................................ 126 About Project Performance Metrics ......................................................... 127
Assessing Project Performance ........................................................... 127 Assessing Project Health ................................................................... 127 Customizing Project Statistics ............................................................ 128 Identifying Critical Activities Behind Schedule ........................................ 129 About Performance Thresholds ........................................................... 129 Working with Performance Thresholds .................................................. 130
About Milestones ............................................................................ 130 Sending E-Mail about Milestones ......................................................... 131
About Cost Performance Index (CPI) .................................................... 131 About Schedule Performance Index (SPI) ............................................... 132 About To-Complete Performance Index (TCPI) ........................................ 132
About Contract Management ................................................................. 132 Working with Contract Management ..................................................... 133 Opening the Contract Management Control Center ................................... 133 Linking P6 and Contract Management Projects ........................................ 134 Linking P6/P6 Professional and Contract Management Applications ............... 135
About Project Workgroups ....................................................................... 135
Working with Workgroups .................................................................... 135 Assigning Documents to Projects ......................................................... 135 Creating Workgroups ....................................................................... 136 Customizing Workgroups ................................................................... 137 Assigning Workgroup Activities ........................................................... 138 Creating Workgroup Issues ................................................................ 138 Sending E-Mail to Activity Resources .................................................... 139
About Portlets ..................................................................................... 140
Working with Portlets ......................................................................... 140 List of Portlets ............................................................................... 143 Customizing Portlets ........................................................................ 145
-
P6 Help
8
Customizing the My Risks Portlet ......................................................... 145
Customizing the Resource Analysis Chart Portlet ..................................... 145
Customizing the Open Requests for Resources Portlet ............................... 146
Customizing Portfolio View Portlets ..................................................... 146
Customizing Scorecard Portfolio View Portlets ........................................ 147 Analyzing Resource Team Usage in the Resource Team Summary Portlet ........ 147
Creating Portfolio View Portlets.......................................................... 148 Document Review and Workflow Portlets .............................................. 148 Participating in Document Reviews ...................................................... 149
Terminating Document Reviews .......................................................... 149
About Workflows ............................................................................ 150
Working with Workflows in P6 ............................................................ 150 Participating in Workflows ................................................................ 153 Linking the Cost Worksheet to Contract Management ................................ 154 Opening Projects from Dashboard Portlets ............................................. 155 Sending E-Mail to Resource Teams ....................................................... 155 Sending E-Mail Notifications about Resource Assignments .......................... 156 Creating Custom Portlets .................................................................. 156
Portfolios ............................................................................................. 159
About Portfolios ................................................................................... 159
Working with Portfolios .......................................................................... 159
Opening Portfolios ............................................................................. 160 Creating Portfolios ............................................................................. 160 Creating Projects While Working with Portfolios ......................................... 161 Creating Projects in a Portfolio View Scorecard Portlet ................................. 161 Creating Projects on the Portfolio Analysis Page ......................................... 162 Assigning Projects to a Portfolio ............................................................. 163 Defining Performance Thresholds ........................................................... 163
Portfolio Views .................................................................................... 165
About Portfolio Views ......................................................................... 165 Working with Portfolio Views ................................................................ 165
Creating Portfolio Views ................................................................... 166 Working with Portfolio View Scorecards.................................................... 167 Working with Portfolio View Bubble Charts ................................................ 169 Working with Portfolio View Pie Charts .................................................... 171 Working with Portfolio View Histograms ................................................... 173
Portfolio Scenarios ................................................................................ 175
About Portfolio Scenarios ..................................................................... 175 About What-if Analysis ........................................................................ 175 Working with Portfolio Scenarios ............................................................ 176
Creating Portfolio Scenarios .............................................................. 176 Sending E-Mail About Scenarios........................................................... 176
Capacity Planning ................................................................................. 177
About Capacity Planning ...................................................................... 177 Working with the Capacity Planning Page .................................................. 177
-
Contents
9
Analyzing Role Allocation (Capacity Planning) ......................................... 179
Projects ............................................................................................... 181
About Projects ..................................................................................... 181
Working with Projects ......................................................................... 181 Creating Projects .............................................................................. 182 Assigning Locations to Projects .............................................................. 182 Opening Projects or Templates .............................................................. 183 Opening Dependent Projects ................................................................. 184 Importing and Exporting Projects ........................................................... 185
Working with Primavera XML Project Import ........................................... 185 Working with Primavera XML Project Export ........................................... 187 Working with Microsoft Project Import ................................................. 189 Working with Microsoft Project Export .................................................. 191
About Opening a Project Exclusively ........................................................ 192 Opening Projects Exclusively.............................................................. 192 Removing the Exclusive Lock on Projects ............................................... 193
Working with Oracle ERP, Fusion PPM Bridge, and Other Integrated Solutions ....... 195 Sending Project Data to an ERP System ................................................. 196 Sending Project Data to Fusion ........................................................... 197
About Project Templates ........................................................................ 198
Working with Project Templates ............................................................ 198 Creating Project Templates .................................................................. 199
The EPS ............................................................................................. 200
About the Enterprise Project Structure (EPS) ............................................. 200 Working with the EPS ....................................................................... 200 Creating EPS Elements ..................................................................... 202 Configuring the EPS ......................................................................... 203 Opening Projects or Templates in the EPS ............................................. 203
About Projects ................................................................................. 204 Creating Projects ............................................................................ 204 Creating Projects from Existing Projects or Templates .............................. 205 Deleting Projects or EPS Elements ....................................................... 205 Customizing Detail Windows .............................................................. 206 Configuring Project Preferences ......................................................... 207 Configuring History Settings for P6 Analytics .......................................... 207
Configuring Project Calculations ......................................................... 207
Linking P6 and Contract Management Projects ........................................ 208
Configuring Project Defaults .............................................................. 208
Configuring General Project Preferences ............................................... 209
Configuring P6 Progress Reporter ........................................................ 209
Configuring Project Summarization and Publication Services ....................... 210
Configuring P6 Team Member Status Update Reviews ................................ 210
Configuring P6 Team Member Application View Preferences ....................... 211
Opening Projects or Templates ........................................................... 213 About Gantt Charts ............................................................................ 214
Working with the Activity Gantt Chart .................................................. 214
-
P6 Help
10
Configuring Gantt Charts .................................................................. 215 About Baselines ................................................................................ 216
Working with Baselines ..................................................................... 216 Creating Baselines .......................................................................... 218
About Summary Data .......................................................................... 219 Working with the Summarizer Service .................................................. 220 Summarizing Projects ...................................................................... 220
About Importing and Exporting Projects ................................................... 221 Importing and Exporting Projects ........................................................ 222 Exporting Projects using Microsoft Project XML ....................................... 222 Configuring Microsoft Project Templates ............................................... 222
Exporting Projects using Primavera XML Format ...................................... 223 Importing Projects using Microsoft Project XML ....................................... 223 Importing Projects using Primavera XML Format ...................................... 224 Exporting Projects to Excel ............................................................... 225
About Budgets .................................................................................. 225 Working with Budgets ...................................................................... 226 Establishing Budgets ........................................................................ 228 Creating Budget Change Requests ....................................................... 228 Approving or Denying Budget Change Requests ....................................... 229 About Spending and Benefit Plans ....................................................... 230 Working with Spending and Benefit Plans .............................................. 231
Configuring Spending and Benefit Plans ................................................ 233
About Return on Investment (ROI) ....................................................... 233
About Project Views ........................................................................... 234 Configuring EPS Views ...................................................................... 234 Configuring EPS View Columns ............................................................ 234
Configuring EPS View Grouping ........................................................... 235
Configuring EPS View Filters .............................................................. 236
Applying Filters .............................................................................. 236 Creating Filters .............................................................................. 237 Configuring Filters .......................................................................... 238 Configuring EPS View Gantt Chart Bars ................................................. 239
Configuring EPS View Gantt Chart ....................................................... 240
Configuring EPS View Access .............................................................. 240
About Columns (Fields) .................................................................... 240 About Grouping and Sorting ............................................................... 241 About Filters ................................................................................. 241
About Funding Sources ........................................................................ 241 Working with Funding Sources ............................................................ 241 Assigning Project Funding Sources ....................................................... 244
About Gantt Charts ............................................................................ 244 Configuring Gantt Charts .................................................................. 244 About Bars .................................................................................... 245
About Project Codes .......................................................................... 246 Assigning Project Codes .................................................................... 247
About P6 Progress Reporter .................................................................. 247 About Contract Management ................................................................. 248
-
Contents
11
Linking P6/P6 Professional and Contract Management Applications ............... 248
About Notebooks .................................................................................. 248
About Notebook Topics ....................................................................... 249 Working with Notebooks ...................................................................... 249 Assigning Notebook Topics ................................................................... 249
Activities ........................................................................................... 250
About Activities ................................................................................ 250 Working with Activities .................................................................... 250 Creating Activities .......................................................................... 251 Configuring General Activity Information ............................................... 252 Assigning Locations to Activities ......................................................... 253 Recalculating Assignment Costs .......................................................... 254 Sending Project Data to an ERP System ................................................. 254 Customizing Detail Windows .............................................................. 255 About Activity Types........................................................................ 256 About WBS Summary Activities ........................................................... 256 About Suspending and Resuming Activities ............................................. 257 About the Activity Table ................................................................... 257 About Activity Networks ................................................................... 257 Working with the Activity Network ...................................................... 258
About Calendar View ....................................................................... 259 Working with the Activity Calendar ...................................................... 260
About Activity Views .......................................................................... 261 Working with Activity Views .............................................................. 261 Creating Activity or EPS Views ............................................................ 262 Configuring Activity Views ................................................................. 262 Configuring Activity View Columns ....................................................... 263
Configuring Activity View Grouping ...................................................... 264
Configuring Activity View Filters ......................................................... 265
Applying Filters .............................................................................. 266 Creating Filters .............................................................................. 266 Configuring Filters .......................................................................... 267 Configuring Activity View Gantt Chart Bars ............................................ 268
Configuring Activity View Gantt Chart .................................................. 269
Configuring Activity Network ............................................................. 270
Configuring Activity View Access ......................................................... 270
Sending Activity Views by E-Mail ......................................................... 271 About Columns (Fields) .................................................................... 271 About Filters ................................................................................. 272 About Grouping and Sorting ............................................................... 272
About Activity Codes .......................................................................... 272 Creating Activity Code Values for Activities ........................................... 272 Assigning Activity Code Values to Activities ............................................ 273
About Gantt Charts ............................................................................ 274 Working with the Activity Gantt Chart .................................................. 274 Configuring Gantt Charts .................................................................. 274 About Progress Spotlight ................................................................... 275 About Bars .................................................................................... 276
-
P6 Help
12
About Work Breakdown Structures (WBS) .................................................. 277 Working with WBS Elements .............................................................. 277 About Siblings and Children ............................................................... 279 Creating a WBS .............................................................................. 279 Creating a WBS from a Template......................................................... 280 Configuring General WBS Information ................................................... 280 Defining Earned Value Calculations for WBS Elements ............................... 281 Working with WBS Milestones ............................................................. 282 Working with WBS Categories ............................................................. 283
About Baselines ................................................................................ 284 Working with Baselines ..................................................................... 285 Creating Baselines .......................................................................... 287
About Scheduling Projects .................................................................... 288 Scheduling Projects ......................................................................... 288 Configuring General Scheduling Options ................................................ 289
Configuring Advanced Scheduling Options .............................................. 289
About Float ..................................................................................... 290 About Critical Path Activities ................................................................ 290
Working with Critical Activities .......................................................... 291 Creating Baselines .......................................................................... 295
About Schedule Preview ...................................................................... 296 Enabling Schedule Preview ................................................................ 296
About Resource Leveling ...................................................................... 297 Configuring Resource Leveling Options and Priorities ................................ 297 Leveling Project Resources ................................................................ 299
About Activity Progress ....................................................................... 300 About Updating Progress ................................................................... 300 Working with Updating Progress in a Browser Running P6 ........................... 300 Updating the Progress of Activities Using P6 ........................................... 301
About The Apply Actuals Feature ........................................................ 301
Working with the Apply Actuals Feature ................................................ 301 Applying Actuals to a Project ............................................................. 303 Working with Activity Updates by E-mail using E-mail Statusing Service ......... 304 Supporting E-mail Updates with E-mail Statusing Service ........................... 308
Updating the Progress of Activities Using E-mail ...................................... 309
Updating the Progress of Activities Using P6 Team Member Web .................. 310 Updating the Progress of Activities Using the P6 Team Member for iPhone App 310
About P6 Team Member Status Updates .................................................... 310 Working with P6 Team Member Status Updates ....................................... 311 Assigning a Status Reviewer to a WBS ................................................... 313 Selecting an Activity for Review ......................................................... 313 Reviewing Team Member Status Updates ............................................... 314 Sending E-mail to a Team Member About a Status Update .......................... 315 Viewing Team Member Status Updates History ........................................ 315
About the Auto Compute Actuals Feature.................................................. 316 Working with the Auto-Compute Actuals Feature ..................................... 316 Applying Auto Compute Actuals to Activities .......................................... 317
About Store Period Performance ............................................................ 318 Storing Period Performance ............................................................... 318
-
Contents
13
About Importing and Exporting Data ........................................................ 319 Importing Activities ......................................................................... 319 Exporting Activities to Excel .............................................................. 320 Creating Import Templates for Importing Activities .................................. 320
About Relationship Lines ..................................................................... 322 About Progress Lines .......................................................................... 322 About Resources ............................................................................... 322
Assigning Resources to an Activity ....................................................... 322 Assigning a Resource to Multiple Activities ............................................. 323 Configuring Activity Resources ........................................................... 324 Adding Activity Resource Estimates ..................................................... 324 Requesting Resources for Activities ..................................................... 325 Specifying Resource Assignment Rates .................................................. 325 Assigning Resource Curves to Resource or Role Assignments from the Activities Page ................................................................................................. 326 Assigning Resources to Unstaffed Activities ............................................ 326 Searching Resources ........................................................................ 327 About the Recalculate Assignment Costs Feature ..................................... 328 Recalculating Assignment Costs .......................................................... 329
Configuring Resource Leveling Options and Priorities ................................ 330 Leveling Project Resources ................................................................ 331 About the Check Resource Overallocation Service .................................... 332 Working with the Check Resource Overallocation Service ........................... 333
Checking for and Resolving Overallocated Resources ................................ 334
About Roles ..................................................................................... 335 Assigning Roles to an Activity ............................................................. 336 Assigning a Role to Multiple Activities ................................................... 336 Configuring Activity Roles ................................................................. 337
About Activity Owners ........................................................................ 337 Assigning an Activity Owner to an Activity ............................................. 337
About Documents .............................................................................. 338 Assigning Documents to Activities ........................................................ 338
About Expenses ................................................................................ 339 Creating Expenses ........................................................................... 339 Configuring Expenses ....................................................................... 339 Configuring Auto Compute Actuals for Expenses ...................................... 340
About Feedback ................................................................................ 340 Adding Feedback ............................................................................ 341 Adding the New Feedback Column ....................................................... 341 Acknowledging Feedback .................................................................. 342
About Duration Types ......................................................................... 342 Working with Duration Types ............................................................. 343
About Constraints .............................................................................. 343 Working with Activity Constraints ........................................................ 344
About Issues .................................................................................... 345 Creating Activity Issues .................................................................... 345 Configuring Activity Issues ................................................................. 346
About Notebooks ............................................................................... 346 Working with Notebooks ................................................................... 346
About Notebook Topics ....................................................................... 347
-
P6 Help
14
Assigning Notebook Topics ................................................................ 347 About Relationships ........................................................................... 347
Creating Activity Relationships ........................................................... 348 Configuring Activity Relationships ....................................................... 349 Assigning Predecessor Relationships ..................................................... 349 Configuring Predecessor Relationships .................................................. 350 Assigning Successor Relationships ........................................................ 351 Configuring Successor Relationships ..................................................... 351
About Risks ..................................................................................... 352 Working with Project Risks ................................................................ 352 Assigning a Risk to an Activity ............................................................ 354
About Steps ..................................................................................... 355 Working with Activity Steps ............................................................... 355 Creating Activity Steps ..................................................................... 356 Configuring Activity Steps ................................................................. 356
About Step Templates......................................................................... 357 Adding Activity Steps from a Step Template ........................................... 357
About Trace Logic ............................................................................. 358 Viewing Relationships with Trace Logic ................................................. 358
About Budgets .................................................................................. 359 Creating Budget Change Requests ....................................................... 359 Approving or Denying Budget Change Requests ....................................... 360
About Earned Value ........................................................................... 361 Configuring WBS Earned Value ............................................................ 361
About Milestones ............................................................................... 362 Creating WBS Milestones ................................................................... 362
Team Usage ........................................................................................ 363
About Team Usage ............................................................................. 363 Customizing Team Usage .................................................................. 363 Assigning Resources to Unstaffed Activities ............................................ 364 Exporting Team Usage Spreadsheets .................................................... 364 Searching Resources ........................................................................ 365 Sending E-Mail to a Project Manager .................................................... 366
Issues ................................................................................................ 367
About Issues .................................................................................... 367 Working with Issues ......................................................................... 367 Creating Project Issues ..................................................................... 368 Configuring Project Issues ................................................................. 369 Customizing Project Issues ................................................................ 369 Assigning Related Items to Issues ........................................................ 370 Sending E-Mail about Issues ............................................................... 371
About Issue Codes ............................................................................. 371 Assigning Issue Codes ....................................................................... 372
About Issue Forms ............................................................................. 372 Creating Issue Forms ....................................................................... 372 Assigning Projects to Issue Forms ........................................................ 373
Risks ................................................................................................. 374
About Risks ..................................................................................... 374 Risk Enterprise Data ........................................................................... 374
Working with Risks Enterprise Data ...................................................... 374
-
Contents
15
Configuring Risk Enterprise Data ......................................................... 375 Risk Thresholds .............................................................................. 375 About Risk Thresholds ...................................................................... 375
Working with Risk Thresholds ............................................................. 376 Creating Risk Thresholds ................................................................... 377 Modifying Risk Thresholds ................................................................. 378 Risk Scoring Matrices ....................................................................... 379 About Risk Scoring Matrices ............................................................... 379
Working with Risk Scoring Matrices ...................................................... 380 Creating Risk Scoring Matrices ............................................................ 383 Assigning a Risk Scoring Matrix to a Project ............................................ 384
Assigning a Risk Scoring Matrix to a Project from the Enterprise Data Pane ..... 384 Assigning a Risk Scoring Matrix to a Project from the EPS Page .................... 385 Assigning a Risk Scoring Matrix to a Project from the Portfolios Section ......... 385 Risk Categories .............................................................................. 386 About Risk Categories ...................................................................... 386
Creating Risk Categories ................................................................... 386 Risk UDFs ..................................................................................... 387 About Risk User Defined Fields ........................................................... 387
Creating Risk UDFs .......................................................................... 387 Project Risks .................................................................................... 387
Working with Project Risks ................................................................ 387 Managing Project Risks ..................................................................... 389 Creating Project Risks ...................................................................... 389
Adding Detailed Project-Level Risks ..................................................... 390 Adding Project Risks to Activities ........................................................ 391 Adding High-Level Project Risks .......................................................... 392 Assigning a Risk to an Activity ............................................................ 393
Risk Response Plans ......................................................................... 393
About Risk Response Plans................................................................. 393 Working with Risk Response Plans ....................................................... 394 Developing a Risk Response Plan ......................................................... 395 Adding Risk Response Plans ............................................................... 395 Adding Risk Response Plan Action Items ................................................ 396 Assigning Activities to Risk Response Plan Action Items ............................. 397 Exporting Risk Data ......................................................................... 397
About Documents.................................................................................. 398
Working with Documents without the Content Repository .............................. 398 Adding Documents to a Project without the Content Repository .................. 399 Configuring Document Details without the Content Repository .................... 399 Assigning Related Items to Documents without the Content Repository .......... 400
Sending E-Mail about Documents without the Content Repository ................. 400 Working with Documents with a Content Repository ..................................... 401
About the Document Content Repository ............................................... 402 Creating Document Templates ........................................................... 403 Copying Documents from Existing Templates .......................................... 404 Adding Documents to a Project and Storing Them in the Content Repository ... 404 Adding Documents to a Project from the Content Repository ...................... 405
-
P6 Help
16
Configuring Document Details ............................................................ 406 Assigning Related Items to Documents .................................................. 407
Checking Out Documents .................................................................. 407 Checking In Documents .................................................................... 408 Sending E-Mail about Documents ......................................................... 409 Assigning Documents to Workgroups ..................................................... 409 Creating Document Folders ............................................................... 410
About Document Reviews .................................................................. 410 Working With Document Reviews ........................................................ 411
Reviewing Documents ...................................................................... 412
Creating Document Reviews .............................................................. 413
Participating in Document Reviews ...................................................... 414
Terminating Document Reviews .......................................................... 414
Searching for Documents .................................................................. 415 Searching for Documents (Advanced Search) .......................................... 415
Searching for Documents (Quick Search) ............................................... 416
Viewing Documents ......................................................................... 417 Downloading Documents ................................................................... 417
About Project Scheduled Services .............................................................. 418
Creating Project Scheduled Services ........................................................ 418 Configuring Project Scheduled Services .................................................... 418
About Publication Services and Reporting ..................................................... 419
Working with Publication Services for Reporting.......................................... 420 Publishing P6 Data for Reports ........................................................... 423 Defining Publication Periods .............................................................. 423
Enabling Automatic Publishing of P6 Project Data for Reports ..................... 424
Enabling Automatic Publishing of P6 Global Data for Reports ...................... 426
Configuring Publication Service Settings for Projects ................................ 426
Manually Publishing P6 Project Data for Reports ...................................... 427
Manually Publishing P6 Global Data for Reports ....................................... 428
Resources ............................................................................................ 429
Roles ................................................................................................ 429
About Roles ..................................................................................... 429 Creating Roles .................................................................................. 429 Assigning a Resource to a Role ............................................................... 430 Assigning a Role Team to a Role ............................................................. 431 Assigning Rates to Roles ...................................................................... 432 Assigning Work Limits to Roles ............................................................... 432
Role Teams ......................................................................................... 433
About Role Teams ............................................................................. 433 Creating Role Teams .......................................................................... 433 Assigning a Role to a Role Team ............................................................. 433
Resources ........................................................................................... 434
-
Contents
17
About Resources ............................................................................... 434 Adding Resources .............................................................................. 434 Assigning a Role to a Resource ............................................................... 435 Assigning a Resource Team to a Resource ................................................. 436 Configuring Resource Settings ............................................................... 437 Assigning Calendars to Resources ........................................................... 437 Assigning Locations to Resources ............................................................ 438 Configuring Timesheet Reporting for Resources .......................................... 439
Configuring Resource Settings for Timesheet Reporting ............................. 439 Assigning Resource Codes ..................................................................... 440 Assigning Resource Rates ..................................................................... 441 Creating Import Templates for Importing Resources ..................................... 441 Importing Resource Data ..................................................................... 442 Deleting Resources ............................................................................ 443
Resource Teams ................................................................................... 444
About Resource Teams ........................................................................ 444 Creating Resource Teams ..................................................................... 444 Assigning a Resource to a Resource Team ................................................. 445
Resource Assignments ............................................................................ 445
About Resource Assignments ................................................................. 445 Working with Resource Assignments in the Gantt Chart ................................. 445
Viewing Resource Assignments in a Gantt Chart ...................................... 446 Configuring the Resources Assignments Gantt Chart Bars ........................... 446 Setting the Resources Detailed Assignments Gantt Chart Timescale .............. 447 Modifying Resource Assignment Dates in the Gantt Chart ........................... 448
Assigning a Resource to an Activity Assignment ........................................... 448 Viewing Assignment Unit and Cost Spreads ................................................ 449 Exporting Resource Assignment Data ....................................................... 450 Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page .............................................................................. 451 Applying the Progress Spotlight to the Resources Assignments View .................. 451
Resource Planning ................................................................................. 452
About Resource Planning ..................................................................... 452 Customizing the Resource Planning Spreadsheet ......................................... 453 Assigning Projects or WBS Elements to Resources or Roles .............................. 454 Assigning Resources or Roles to Projects or WBS Elements .............................. 455 Modifying Resource or Role Assignment Dates ............................................. 456 Allocating Units or the Percentage of Available Units to Resources or Roles ......... 457 Synchronizing Resource Planning Dates .................................................... 458 Splitting a Resource or Role Assignment ................................................... 459 Categorizing Resource or Role Assignments using Status Codes ........................ 460 Exporting the Resource Planning Spreadsheet ............................................ 461
Resource Analysis ................................................................................. 461
About Resource Analysis ...................................................................... 461 Analyzing Resource Allocations .............................................................. 462 Assigning Resources to Unstaffed Activities ............................................... 463 Viewing Role Usage ............................................................................ 464
-
P6 Help
18
Viewing Resource Usage ...................................................................... 465 Exporting Resource or Role Usage Data .................................................... 467
Exporting Resource Data ......................................................................... 468
Exporting Resource Administration Data ................................................... 468 Exporting Resource Assignment Data ....................................................... 469 Exporting the Resource Planning Spreadsheet ............................................ 469 Exporting Resource or Role Usage Data .................................................... 470
Reports ............................................................................................... 473
About Reports ...................................................................................... 473
Working with Reports ......................................................................... 474 Scheduling Reports .......................................................................... 475 Running Reports On-Demand .............................................................. 476 Exporting a List of Reports ................................................................ 477 Viewing the Report Run History .......................................................... 478
About Publication Services and Reporting ..................................................... 478
Working with Publication Services for Reporting.......................................... 479 Publishing P6 Data for Reports ........................................................... 482 Defining Publication Periods .............................................................. 482
Enabling Automatic Publishing of P6 Project Data for Reports ..................... 483
Enabling Automatic Publishing of P6 Global Data for Reports ...................... 485
Configuring Publication Service Settings for Projects ................................ 485
Manually Publishing P6 Project Data for Reports ...................................... 486
Manually Publishing P6 Global Data for Reports ....................................... 487
Administration ....................................................................................... 489
About Administration ............................................................................. 489
About My Preferences ............................................................................ 490
Working with My Preferences ................................................................ 490 Customizing My Preferences Global Preferences .......................................... 491
Customizing Global Currency Preferences .............................................. 491 Customizing Global Date Format Preferences ......................................... 492 Customizing Global General Preferences ............................................... 492 Customizing Global Issues Preferences .................................................. 493 Customizing Global Performance Threshold Preferences ............................ 493 Customizing Global Project Score Preferences ........................................ 493 Customizing Global Resources Preferences ............................................ 494 Customizing Global Row Number Preferences ......................................... 494 Customizing Global Time Units Format Preferences .................................. 495 Sending E-Mail Notifications about Resource Assignments .......................... 496
Customizing My Preferences View Preferences ............................................ 496 Changing Your Own Password ................................................................ 497
About My Calendar ................................................................................ 498
Configuring My Calendar ...................................................................... 498 Setting Work Hours Per Time Period for My Calendar ................................ 498 Configuring the Standard Work Week for My Calendar ............................... 499 Modifying Calendar Days on My Calendar ............................................... 499 Importing Events to My Calendar ......................................................... 499
-
Contents
19
About Application Settings ....................................................................... 500
Working with Application Settings .......................................................... 501 Configuring Data Limits Settings ............................................................. 502 Configuring Earned Value Settings .......................................................... 502
Defining Earned Value Calculations for WBS Elements ............................... 503 Configuring General Settings ................................................................. 503 Configuring ID Lengths Settings .............................................................. 504 Configuring Summarization Periods ......................................................... 505 Configuring General Settings ................................................................. 505 Configuring Timesheets Settings............................................................. 506 Configuring Time Periods Settings........................................................... 506
About Enterprise Data ............................................................................ 507
Working with Enterprise Data ................................................................ 508 About Baseline Types.......................................................................... 509
Creating Baseline Types.................................................................... 509 About Funding Sources ........................................................................ 510
Creating Funding Sources .................................................................. 510 About Notebook Topics ....................................................................... 510
Creating Notebook Topics ................................................................. 511 About Calendars ............................................................................... 511
Working with Calendars .................................................................... 511 Creating Global Calendars ................................................................. 512 Configuring Global Calendars ............................................................. 513 Setting Work Hours Per Time Period for Global Calendars .......................... 513
Configuring the Standard Work Week for Global Calendars ......................... 513
Modifying Calendar Days on Global Calendars ......................................... 513
Setting the Default Global Calendar ..................................................... 514
Creating Project Calendars ................................................................ 514 Configuring Project Calendars ............................................................ 515 Assigning a Base Calendar to a Project Calendar ...................................... 515
Setting Work Hours Per Period for a Project Calendar ............................... 516
Configuring the Standard Work Week for Project Calendars ........................ 516
Modifying Calendar Days on Project Calendars ........................................ 517
Changing a Project Calendar to a Global Calendar ................................... 517
Creating Resource Calendars .............................................................. 518 Configuring Resource Calendars .......................................................... 518 Assigning a Base Calendar to a Resource Calendar.................................... 519
Assigning a Resource to a Resource Calendar .......................................... 519
Setting Work Hours Per Time Period for a Resource Calendar ...................... 520
Configuring the Standard Work Week for Resource Calendars ...................... 520
Modifying Calendar Days ................................................................... 521
Changing the Calendar Type .............................................................. 521
About Locations ................................................................................ 522 Creating Locations .......................................................................... 522
-
P6 Help
20
Importing Locations ......................................................................... 523 Creating Import Templates for Importing Locations .................................. 523
About Project Codes .......................................................................... 524 Creating Project Codes..................................................................... 524 Creating Project Code Values ............................................................. 524 Configuring Project Codes ................................................................. 525 Configuring Project Code Values ......................................................... 526
About User Defined Fields .................................................................... 526 Working with User Defined Fields ........................................................ 526 Creating Project UDFs ...................................................................... 527 Defining Formulas for User Defined Fields.............................................. 528 Defining Indicators for User Defined Fields ............................................ 528 Defining Statements for User Defined Fields ........................................... 529 Creating WBS UDFs .......................................................................... 530 Creating Activity UDFs ..................................................................... 531 Creating Expense UDFs ..................................................................... 531 Creating Step UDFs ......................................................................... 531 Creating Risk UDFs .......................................................................... 532 Creating Issue UDFs ......................................................................... 532 Creating Document UDFs .................................................................. 532 Creating Assignment UDFs ................................................................. 533 Creating Resource UDFs .................................................................... 533
About Work Breakdown Structures (WBS) .................................................. 533 Working with WBS Categories ............................................................. 534 Creating WBS Categories ................................................................... 536
About Activity Codes .......................................................................... 536 Working with Activity Codes .............................................................. 537 Creating Activity Codes .................................................................... 538 Creating Activity Code Values ............................................................ 539 Configuring Activity Code Values ......................................................... 540
About Cost Accounts .......................................................................... 541 Creating Cost Accounts .................................................................... 541
About Expenses ................................................................................ 542 Creating Expense Categories .............................................................. 542
About Step Templates......................................................................... 543 Creating Step Templates .................................................................. 543 Configuring Step Templates ............................................................... 543
About Risks ..................................................................................... 544 Working with Risks Enterprise Data ...................................................... 544 Configuring Risk Enterprise Data ......................................................... 545 About Risk Scoring Matrices ............................................................... 545 Working with Risk Scoring Matrices ...................................................... 546
Creating Risk Scoring Matrices ............................................................ 549
Assigning a Risk Scoring Matrix to a Project ............................................ 550
Assigning a Risk Scoring Matrix to a Project from the Enterprise Data Pane ..... 550
Assigning a Risk Scoring Matrix to a Project from the EPS Page .................... 551
Assigning a Risk Scoring Matrix to a Project from the Portfolios Section ......... 551
About Risk Thresholds ...................................................................... 552 Working with Risk Thresholds ............................................................. 552
-
Contents
21
Creating Risk Thresholds ................................................................... 554
Modifying Risk Thresholds ................................................................. 555
About Risk Categories ...................................................................... 556 Creating Risk Categories ................................................................... 556
About Issues .................................................................................... 556 Creating Issue Codes ........................................................................ 557 Creating Issue Code Values ................................................................ 557
About Document Categories and Statuses .................................................. 558 Creating Document Categories ........................................................... 558 Creating Document Statuses .............................................................. 558
About Currencies............................................................................... 559 Adding a Currency .......................................................................... 559 Defining a Base Currency .................................................................. 560
About Financial Periods ....................................................................... 560 Creating Financial Periods ................................................................. 560 Creating a Financial Period Batch ........................................................ 561
About Overhead Codes ........................................................................ 562 Creating Overhead Codes .................................................................. 562
About Timesheet Periods ..................................................................... 563 Creating Timesheet Periods ............................................................... 563
About Resource and Role Rate Types ....................................................... 563 Configuring Resource and Role Rate Types ............................................. 564
About Resource Codes ........................................................................ 564 Creating Resource Codes .................................................................. 564 Creating Resource Code Values ........................................................... 565
About Resource Curves ........................................................................ 565 Defining Resource Curves .................................................................. 565
About Units of Measure ....................................................................... 566 Creating Units of Measure ................................................................. 566
About User Access ................................................................................. 567
About Users ..................................................................................... 567 The Default Admin Superuser ............................................................. 568 Creating User Accounts for P6 EPPM ..................................................... 568 Adding Users in Native Authentication Mode ........................................... 569
Adding Users in LDAP or SSO Authentication Mode .................................... 570
Configuring User Access .................................................................... 571 Assigning Associated Resources ........................................................... 572
Assigning Global Security Profiles ........................................................ 572
Assigning Module Access ................................................................... 573
Assigning OBS Elements to Users ......................................................... 573
Assigning Resource Access ................................................................. 574
Assigning User Interface Views ........................................................... 575
Changing Passwords......................................................................... 575 Changing User Passwords .................................................................. 575
Counting Users ............................................................................... 576 Deactivating User Accounts ............................................................... 576
-
P6 Help
22
Deleting User Accounts .................................................................... 577 About the OBS .................................................................................. 577
Creating an OBS ............................................................................. 577 Assigning Users to an OBS .................................................................. 578
About Security Profiles ........................................................................ 579 Working with Security Profiles ............................................................ 580 Creating Global Security Profiles ......................................................... 581 Creating Project Security Profiles ........................................................ 582
About User Interface Views ...................................................................... 583
Working with User Interface Views .......................................................... 583 Creating User Interface Views ............................................................... 584 Configuring User Interface Views ............................................................ 586
About User Sessions ............................................................................... 587
Resetting User Sessions ....................................................................... 587
About Publication Services and Reporting ..................................................... 588
Working with Publication Services for Reporting.......................................... 589 Publishing P6 Data for Reports ........................................................... 592 Defining Publication Periods .............................................................. 592
Enabling Automatic Publishing of P6 Project Data for Reports ..................... 593
Enabling Automatic Publishing of P6 Global Data for Reports ...................... 595
Configuring Publication Service Settings for Projects ................................ 595
Manually Publishing P6 Project Data for Reports ...................................... 596
Manually Publishing P6 Global Data for Reports ....................................... 597
CSH .................................................................................................... 598
Access Tab of the Create Filter Dialog Box of the Assignments Page ...................... 598
Access Tab of the Create or Modify Filter Dialog Box ........................................ 598
Access Tab of the Customize Activity View Dialog Box ...................................... 599
Access Tab of the Customize Dashboard Page ................................................ 599
Access Tab of the Customize EPS View Dialog Box ........................................... 600
Access Tab of the Customize Resources Assignments View Dialog Box of the Assignments Page ....................................................................................................... 600
Access Tab of the Issue Forms Page ............................................................ 601
Action Required Tab of the Document Reviews Portlet of the Dashboards Page ........ 602
Action Required Tab of the Workflows Portlet of the Dashboards Page .................. 603
Activities Detail Window of the Project Security Profiles Page ............................ 606
Activities Detail Window of the Risks Page .................................................... 607
Activities Page ..................................................................................... 611
Activities Portlet of the Workgroup Workspace Page ........................................ 613
Activities Work Area of the Timesheet Approval Page ....................................... 614
Activity Calendar Format of the Activities Page .............................................. 617
Activity Codes - EPS Page ........................................................................ 619
Activity Codes - Global Page..................................................................... 620
Activity Codes - Project Page ................................................................... 621
-
Contents
23
Activity Codes Details Page of the Activity Form Page ...................................... 622
Activity Codes Page ............................................................................... 622
Activity Details Dialog Box ....................................................................... 623
Activity Details Dialog Box of the Resource Staffing Dialog Box ............................ 624
Activity Details of the Resources Dialog Box .................................................. 625
Activity Editing Tab of the User Interface View Details Page ............................... 626
Activity Form Page ................................................................................ 626
Activity Gantt Chart Format of the Activities Page .......................................... 628
Activity List for WBS Dialog Box ................................................................. 630
Activity Network Format of the Activities Page .............................................. 631
Activity Tab of the Modify Template Dialog Box of the Import/Export Project Dialog Box632
Activity Table Format of the Activities Page .................................................. 634
Activity UDFs Page ................................................................................ 636
Add Activity Expenses Page of the Activity Form Page ...................................... 636
Add Folder Dialog Box ............................................................................ 637
Add Issue Page ..................................................................................... 638
Add Location Dialog Box of the Locations Page ............................................... 640
Add or Edit Service Dialog Box of the Project Scheduled Services Page .................. 642
Add Steps Page of the Activity Form Page ..................................................... 643
Add User Dialog Box............................................................................... 644
Add Users from LDAP Dialog Box of the Users Page .......................................... 645
Administration Detail Window of the Global Security Profiles Page ....................... 647
Administration Page .............................................................................. 648
Advanc