  • 8/10/2019 Primavera Final Ppt_class

    1/22

    PRIMAVERAProject management softwares

    2013C45-Sahil Nagpal2013B45-Manjeet Maini2013A65-Surabhi Vartak2013A51-Rohang Adhikari2013A54-Satish Channareddy

  • 8/10/2019 Primavera Final Ppt_class

    2/22

    PROJECT MANAGEMENT

    Identifying requirements Addressing stakeholdersneeds, concerns and expectations as the project is

    planned and executed

    Communicating to stakeholders

    Managing them to succeed in the project

    Balancing project constraints:Scope (both project and product)

    Quality

    Schedule (Time)

    Budget (cost)

    Resources (People, Machines)

    RisksA project evolves and requirements may change

    Progressive elaboration and improving the PM plan

  • 8/10/2019 Primavera Final Ppt_class

    3/22

    PRIMAVERA PROJECT

    MANAGEMENT MODULE

    Primavera was launched in 1983 by Primavera Systems Inc. and was

    acquired by Oracle Corporationin 2008. The latest version of Primavera is

    8.3 of Primavera P6 Enterprise Project Portfolio Management

    The Project Management module enables us organization to store and

    manage its projects in a central location. The module supports workbreakdown structures (WBS), organizational breakdown structures (OBS),

    user-defined fields and codes, critical-path-method (CPM) scheduling, and

    resource leveling.

    http://en.wikipedia.org/wiki/Oracle_Corporationhttp://en.wikipedia.org/wiki/Oracle_Corporationhttp://en.wikipedia.org/wiki/Oracle_Corporationhttp://en.wikipedia.org/wiki/Oracle_Corporation
  • 8/10/2019 Primavera Final Ppt_class

    4/22

    BENEFITS

    Management benefits Ensures thoroughly control of deadlines and the provisioning of resourcesassigned to the projects at organization level and accurately describes the

    progression and identifies the key events

    Provides unitary and structured insights for all the ongoing investments

    Allows finding the blind spots of the investments and making corrective decision

    in real-time.User benefits Automatically retrieves the information from the quotes/cost estimates programs;

    Tracks down to the smallest detail the execution stage of the works and the

    settlements, and allows comparing the execution stage to the initial planning

    Provides information about the project progress stages as tables and Gantt

    charts

    Tracks, coordinates and corrects by scenario method

    Provides real-time information for fast and objective decisions;

    Builds "What If"-type analyses.

  • 8/10/2019 Primavera Final Ppt_class

    5/22

    Cost benefits

    Ensures features for risk

    management, documentmanagement or alerting in case of

    exceeding the costs, terms or time;

    Analyzes the contractors'

    performance via economic efficiency

    indicators (Earned Value and ROI-

    type analyses) Makes available completely

    assessed terms, costs and

    resources;

    Automatically matches the spent item

    quantities to the work's physical

    stage (the payments can be done

    depending on the achievements).

    Decreases the project execution time

    by 22-27% and achieves a savings of

    15% of the total cost of the project

  • 8/10/2019 Primavera Final Ppt_class

    6/22

    2.Primavera ToolsStructuring Projects - Planning

    Setting-up and define EPS (Enterprise Project Structure).

    Add a project to the EPS hierarchy.

    Defining WBS (Work breakdown structure) to the Project.

    Defining OBS (Organizational breakdown structure)

    Defining Resources.

    Create Calendar for Activities & Resources.

    Add activities to WBS.

    Input activity details. Schedule project.

    Updating progress after project starts.

    Preview / Print reports (Default / Custom made reports).

    Executing Projects Monitoring & Implementation

    Delay Analysis EV Analysis against baseline

    Reports

    Revising Projects - Modifications

    Revise baseline

    Status change & Much more

    (EPS)Enterprise Project

    Structure

    Projects

    (WBS)Work Breakdown

    Structure

    Activities

    (OBS)Organisational

    BreakdownStructures

  • 8/10/2019 Primavera Final Ppt_class

    7/22

    2.1 OBS (Organizational Breakdown Structure)

    The organizational breakdown structure (OBS)

    is a global hierarchy that represents the

    managers responsible for the projects in

    enterprise.

    The OBS usually reflects the management

    structure of organization, from top-level

    personnel down through the various levels

    constituting your business. We can associate the responsible managers

    with their areas of the EPS either nodes or

    individual projects.

    Structure of the organization, from top-level

    personnel down through the various levels.

    Constraints: Maximum of 25 levels can becreated.

    Maximum character length of an OBS element

    is 100.

    President

    Regd. Office

    Engineering

    ProjectAdministration

    Sr. GM

    GM

    Sr.Manager

    Design

    Design Engineer

    Finance

    GM Finance

    HRD & Admin

    Sites

    Project Manager

    Planning &Billing Engineer

    EngineerExecution

  • 8/10/2019 Primavera Final Ppt_class

    8/22

    2.2 EPS (Enterprise Project Structure)

    EPS create/edit form :

    The Enterprise Project Structure (EPS) forms the hierarchical structure of your database of projects.

    Each EPS node (or folder) can be subdivided into multiple levels to represent the work that needs to be

    done in your organization. The number of levels and their structure depend on the scope of your projects

    and how you want to summarize data.

    Perform top down budgeting. Organize OBS and WBS into one common structure.

    Manage multiple projects.

    Adding project to EPS hierarchy. We can organize unlimited number of Projects in EPS in groups.

  • 8/10/2019 Primavera Final Ppt_class

    9/22

    2.3 Creating Calendars

    Create and assign calendars to each

    resource and each activity. These

    calendars define the available work-hours

    in each calendar day. We can also specifynational holidays, your organization's

    holidays, project-specific work/non-

    workdays, and resource vacation days.

    Calendar assignments are used for

    activity scheduling, tracking, and resource

    leveling.

    Global: Contains calendar that apply to all

    projects.

    Resource: Separate pool of calendars for

    each resource.

    Project: Separate pool of calendars for

    each project.

  • 8/10/2019 Primavera Final Ppt_class

    10/22

    2.4 WBS (Work Breakdown Structure)

    A WBS is a hierarchy of

    work that must be

    accomplished to completea project, which defines a

    product or service to be

    produced.

    The WBS is structured in

    levels of work detail,beginning with the

    deliverable itself, and is

    then separated into

    identifiable work elements.

    Maximum of 50 levels are

    available.

    Activities are fundamental

    work elements of a project.

    They are the lowest level of

    Work Breakdown Structure.

    Project

    Civil Works

    Buildings

    Ware House

    Foundation

    Superstructure

    Finishing Works

    Admin Building

    Roads & Drains

    Equipment Fdns

    Mech. Works

    Tanks

    Fire Water Tank

    Diesel Tank

    Piping

  • 8/10/2019 Primavera Final Ppt_class

    11/22

    2.5 Defining Resources.

    Resources include the personnel and equipment that perform work on

    activities across all projects. Resources are generally reused between

    activities and/or projects.

  • 8/10/2019 Primavera Final Ppt_class

    12/22

    2.6 Adding activity to WBS

    WBS

    Task / ActivityActivity Detail form

  • 8/10/2019 Primavera Final Ppt_class

    13/22

    Activity ID, Name & Type of activity.

    Start, Finish Dates (Early, Late).

    Steps of an Activity (Breakdown the activity to smaller units).

    Relationship between activities (Predecessor, Successor). Resource Assignment (Labor, Non-Labor & Material)

    Activity Calendar.

    Constraints.

    Status of activity (Actual start & finish dates, % of progress).

    Expenses.

    Any other comments, notes etc.

    List of common Inputs / Information to be given to an activity

    Project schedule can be calculatedone of two ways: when we choosethe Scheduling command or eachtime we make a change that affectsschedule dates.

    The Critical Path Method (CPM)scheduling technique is used tocalculate project schedules. CPMuses activity durations andrelationships between activities tocalculate the project schedule.

    2.7 Scheduling Project

  • 8/10/2019 Primavera Final Ppt_class

    14/22

    To update the progress of the individual activity, the following inputs are to be given in the activity detail form.

    1. Start Date (If activity is started)

    2. Finish Date (If activity is completed)

    3. % of duration completed (if activity is in progress)4. Remaining duration to complete the activity

    Updating Progress EV Analysis

  • 8/10/2019 Primavera Final Ppt_class

    15/22

    Objective

    Problem statement:

    Plan college admissions drive SNAP-IT with SCMHRD.

    What is SNAP-IT:

    Pan India drive to boost SCMHRD applications and clear aspirant doubts &

    queries regarding SNAP & SCMHRD.

    Objective:

    To enumerate and logically arrange all the activities required for SNAP-ITin a Work Breakdown Structure (WBS), along with resources and

    responsibilities assigned to each of those.

    Approach:

    Using Primavera

    Prepare OBS> Create WBS> Create activities and assign to WBS> Assign

    Relationships between activities> Assign Resources & Responsibilities

  • 8/10/2019 Primavera Final Ppt_class

    16/22

    Work Breakdown

    Structure (WBS)Project Calendar

  • 8/10/2019 Primavera Final Ppt_class

    17/22

    SNAP IT

    Formationof

    AdmissionsTeam

    Branding

    SocialMedia

    Mails Phone &Print Media

    Planning &Execution

    VolunteerTeam

    Selection

    PPT & TrangModule

    Trng ofVolunteer

    s

    DocketPreparation

    CitySelection& Travel

    HallBooking

    Seminar

    Finance

    Procurement

    Logistics

    DocketMaterial

    FlexPrinting

    Work Breakdown Structure (WBS)

  • 8/10/2019 Primavera Final Ppt_class

    18/22

    Work Breakdown Structure

    WBS(Screenshot from Primavera)

  • 8/10/2019 Primavera Final Ppt_class

    19/22

    Gantt Chart

    (Screenshot from Primavera)

  • 8/10/2019 Primavera Final Ppt_class

    20/22

    Activity Codes

    Code Department Responsibility

    Code Values Admissions Team DirectorCode Values Branding Member-1

    Code Values Planning & Execution Member-2

    Code Values Finance Member-3

    Code Values Logistics Member-4

    Admissions

    Team

    Logistics

    volunteer

    Presentation

    Volunteer

    Max. limits 6 13 26

    Rate - 400 400

    Resources

  • 8/10/2019 Primavera Final Ppt_class

    21/22

    S No Activity Desc. Duration Relationship WBS Resource

    1 Brainstorming 15 P & E AD(6)

    2 Volunteer selection form 1 1fs Volunteer Team selection AD(6)

    3 Volunteer sign up 4 2fs Volunteer Team selection AD(1)

    4 Volunteers Interview 3 3fs Volunteer Team selection AD(6)

    5 Volunteers finalization 2 4fsVolunteer Team selection

    AD(2)

    6 PPt preperation 10 1fs Ppt & Training Module AD(2)

    7 Training module preparation 10 1fs Ppt & Training Module AD(2)

    8 Training of volunteers 10 6fs,7fs Training of volunteers AD(6),LV(13),PV(26)

    9 Inviting quotations 5 1fs Procurement AD(1)

    10 Vendor selection 5 9fs Procurement AD(1)

    11 PO release 10 10fs Procurement AD(1)

    12 Procurement of material 10 11fs Procurement AD(2)13 Docket preparation 4 12fs Docket Preparation AD(6),LV(5),PV(12)

    14 HTML-Mail Drafting 7 1fs Mails AD(1)

    15 Sending mails to aspirants 2 14fs Mails AD(1)

    16 Pagalguy thread preparation & managing 30 14fs Social Media AD(1)

    17 Facebook page preparation & managing 30 14fs Social Media AD(1)

    18 Twitter account preparation & managing 30 14fs Social Media AD(1)

    19 Video upload on you tube 30 14fs Social Media AD(1)

    20 Selection of cities 5 1fs City selection & Travel AD(3)

    21 Calling for hall booking 20 20fs City selection & Travel AD(2)

    22 Hall booking payments 15 21fs Hall booking AD(1)

    23 Travel arrangement confirmation of volunteers 5 9fs,20fs City selection & Travel AD(1),LV(13),PV(26)

    24 Sending fliplets to aspirants 15 1fs Phone & Print Media AD(2)

    25 Presentation at venue 5 23fs Seminar AD(6),LV(13),PV(26)

    26 Flex designing & printing 10 10fs Flex printing AD(2)

    27 Finalization of docket material 10 10fs Docket Material AD(5)

  • 8/10/2019 Primavera Final Ppt_class

    22/22