Presentation to Select Committee on Public Services Briefing on Unproclaimed Roads and Road Maintenance Budgets 14 th August 2012 1

Upload: gary-boyer

Post on 04-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

Presentation to Select Committee on Public Services Briefing on Unproclaimed Roads and Road Maintenance Budgets 14 th August 2012. Presentation Outline. Proclamation of Roads Road Network Summary Road Expenditure History Progress to date (S’hamba Sonke Programme) Conclusion. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

Presentation to Select Committee on Public Services

Briefing on Unproclaimed Roads and Road Maintenance Budgets

14th August 2012

1

Page 2: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

1. Proclamation of Roads2. Road Network Summary3. Road Expenditure History4. Progress to date (S’hamba Sonke Programme)5. Conclusion

2

Page 3: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

3

Page 4: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

4

Proclaimed Roads Proclamation means that a specific authority of government takes

legal ownership and responsibility for the maintenance and development of that particular road network.

Unproclaimed Roads When a road is unproclaimed no roads authority among the spheres

of our government takes responsibility for its upkeep, even for minimal maintenance

Page 5: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

RISFSA process: ◦ Reclassify roads according to functional classes◦ Review administrative responsibility for roads◦ Develop a standard approach to road prioritisation

Progress◦ All provinces in process of reclassifying network

with municipalities◦ 2013/14 Assignment of administrative

responsibilities for roads

5

Page 6: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

Un-Proclaimed Roads = Public roads not formally maintained by any Authority

Page 7: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

National RoadsSecondary RoadsTertiary / other Roads

Main Road Categories in South AfricaMain Road Categories in South Africa

Status Quo of roads

Page 8: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

8

Authority Paved Gravel Total

  Length Data Length Data Length Data % Data

SANRAL 16,170 16,170 0 0 16,170 16,170 100

Provinces - 9 48,176 47,088 136,640103,73

3 184,816 150,820 82

Metros - 9 51,682 40,737 14,461 1,789 66,143 42,527 64

Municipalities 37,691 10,866 302,158 2,124 339,849 12,990 4

Total 153,719 114,861 453,259107,64

6 606,978 222,507

% Data 75 24 37

Page 9: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

9

Very Poor (km)

Poor (km) Fair (km) Good (km) Very Good (km) Total km with Data

% Network With Data

SANRAL 16,170 233 1,199 6,391 7,750 597 16,170 100EASTERN CAPE 5,878 372 1,197 1,957 1,113 551 5,190 88FREESTATE 6,313 52 309 1,847 3,071 1,029 6,308 100GAUTENG 3,449 109 368 1,118 1,431 373 3,398 99KWAZULU NATAL 6,749 1,406 1,948 2,335 965 96 6,750 100LIMPOPO 6,639 90 399 1,628 3,116 1,247 6,481 98MPUMALANGA 4,952 664 1,129 1,781 1,221 161 4,956 100NORTH WEST 5,551 481 1,111 2,176 1,477 261 5,505 99NORTHERN CAPE 2,539 97 227 955 1,057 202 2,539 100WESTERN CAPE 6,106 262 512 1,383 3,019 785 5,961 98

Totals km 64,346 3,766 8,399 21,570 24,220 5,303 63,258

Totals % 5.95 13.28 34.10 38.29 8.38 100

Visual Condition Data (km)2

Visual Condition Index Paved Roads - SANRAL + Provinces

Total Network Paved1Authority

0% 20% 40% 60% 80% 100%

SANRAL

EASTERN CAPE

FREESTATE

GAUTENG

KWAZULU NATAL

LIMPOPO

MPUMALANGA

NORTH WEST

NORTHERN CAPE

WESTERN CAPE

Au

tho

rity

Percentage of Network

Very Poor (km)

Poor (km)

Fair (km)

Good (km)

Very Good (km)

Page 10: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

Provincial and national roads infrastructure expenditure, 2005/06 – 2011/12 

ROAD AUTHORITY

( R million)

2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12

Outcome Preliminary

outcome Medium-term estimates

Eastern Cape 1,369 1,492 1,615 1,915 1,719 1,716 1,819

Free State 333 801 740 961 1,171 1,286 1,373Gauteng 610 658 1,079 1,398 1,678 1,745 1,959

KwaZulu-Natal 1,682 1,856 2,360 4,117 3,684 3,862 4,207

Limpopo 1,152 1,139 1,442 1,385 1,574 1,892 2,141

Mpumalanga 723 688 993 1,115 1,089 1,321 1,469Northern Cape 177 236 365 436 459 573 627

North West 605 689 677 730 825 914 981

Western Cape 962 1,285 1,346 1,380 1,703 1,655 1,707

Total provincial 7,613 8,844 10,619 13,438 13,902 14,965 16,284

National (non-toll) 1,783 2,380 3,403 5,176 5,649 7,023 8,193

Total 9,396 11,225 14,022 18,614 19,551 21,988 24,478

Source: National Treasury10

Page 11: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

11

The Roads Development The Roads Development Plan for RoadsPlan for Roads

(Adopted by all Provinces@ (Adopted by all Provinces@ MINMEC in February 2011)MINMEC in February 2011)

Page 12: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

12

Increase investment in maintenance of key arterial routes to support the rural

economy

Increased focus in the cost efficient use of labour absorptive methodologies in road

construction and maintenance;

Know your network: A focused attention on deployment of local resources to support

road network asset management

Improving Access to Schools and Clinics and other public facilities

Delivering a Safe Road environment

Page 13: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

13

Province Programme Description Budget Rm

EC Area Wide (Regional Contracts) Routine road maintenance using length-man system (household contractors). 175,391,778

FS Contractor Development The roads department recruited 100 emerging contractors of 1 to 2 CE CIDB registration level to do routine road maintenance projects.

34,072,667

GP Routine road maintenance Routine road maintenance305,989,374

KZN Zibambele ( doing it yourself) Maintenance of rural roads using household contractorsRoutine roads maintenance

221,708,726

LP Tsela Tshweu (good road) Routine road maintenance programme 3,501,086

MP Siyatentela (we are trying) Routine road maintenance programme 44,288,856

NC Routine road maintenance Routine road maintenance 29,481,302

NW Rephelele (live for us) Routine road maintenance programme 213,111,206

WC Routine road maintenance Projects to exited Vukuphile learnership contractors. 154,910,718

Total Investment on Road Maintenance 1,152,974,411

Page 14: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

Province LengthFunding Requirement

R’bn

Eastern Cape 2 516 20 203 480 000

Free State 3 305 15 683 500 000

Gauteng 1 940 1 683 794 876

KwaZulu Natal 1 392 2 605 973 732

Limpopo 2 138 1 692 750 000

Mpumalanga 1 862 5 307 080 659

Northern Cape 4 283 2 161 695 934

North West 538 306 423 000

Western Cape 6 452 6 067 537 000

Total 2 4 425 R 55 712 235 201

Province MTEF (bn) Total % Total

2007/08 2008/09 2009/10

Eastern Cape R 1,515 R 1,566 R 1,605 R 4,686 13.16%

Free State R 932 R 1,124 R 1,223 R 3,279 9.21%

Gauteng R 877 R 1,110 R 1,240 R 3,227 9.07%

KZN R 2,359 R 2,797 R 3,405 R 8,561 24.05%

Limpopo R 1,528 R 1,699 R 1,936 R 5,163 14.50%

Mpumalanga R 939 R 940 R 1,049 R 2,928 8.23%

Northern Cape R 363 R 419 R 484 R 1,266 3.56%

North-West R 645 R 923 R 1,140 R 2,708 7.61%

Western Cape R 1,224 R 1,236 R 1,319 R 3,779 10.62%

TOTAL R 10,382 R 11,814 R 13,401 R 35,597 100.00%

funding short-fall of R20,115b on funding levels only for secondary strategic roads…..

Current funding levels for entire network

Funding needs on identified Secondary Strategic Roads

therefore

Page 15: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

Sustain Backlog TotalEASTERN CAPE 32,218 R 3,852,349,045 R 1,169,828,064 R 5,022,177,109

FREESTATE 27,638 R 3,958,334,888 R 307,075,536 R 4,265,410,424GAUTENG 5,344 R 1,911,078,323 R 27,294,192 R 1,938,372,515KWAZULU NATAL 21,186 R 4,016,266,750 R 4,055,112,000 R 8,071,378,750LIMPOPO 22,035 R 3,981,303,860 R 221,703,552 R 4,203,007,412MPUMALANGA 13,840 R 2,903,099,488 R 1,668,883,920 R 4,571,983,408NORTH WEST 20,512 R 3,382,803,995 R 1,139,203,104 R 4,522,007,099NORTHERN CAPE 25,743 R 1,968,399,993 R 334,146,096 R 2,302,546,089WESTERN CAPE 16,300 R 3,559,705,418 R 146,794,896 R 3,706,500,314

Totals km 184,816 R 29,533,341,758 R 9,070,041,360 R 38,603,383,118

Authority Total Network Maintenance Budget Per Year

Estimated Total Maintnance Budget Requirement per Year

Paved Roads Inputs  

Routine Maintenance Cost per km/yr R 40,000

Periodic Maintenance Cost per km R 900,000

Periodic Maintenance Interval in years 10

Rehabilitation Cost per km R 8,000,000

Rehabilitation interval in years 25

Rehabilitation Backlog Address Period 5

Overhead Costs as % of Total Budget 20

Gravel Roads Inputs  

Routine Blading Cost per km R 125

Number of Blades Per Year 6

Regraveling Cost per km R 200,000

Regraveling Interval in years 8

Upgrade to Paved Road per km R 6,000,000

Gravel Network that needs Upgrade to Paved % 2

Upgrade Backlog Address Period (yrs) 10

Overhead Costs as % of Total Budget 20

Page 16: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

Provincial Road Provincial Road Maintenance Grant Maintenance Grant Allocations Allocations

16

Includes disaster management grant

Page 17: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

17

ProvinceNumber of Projects

funded by PRMG (as per

IRM)

Number of

Gazetted Projects

Number of Projects

still to be gazetted

Eastern Cape 184 98 86

Free State14 14 0

Gauteng 33 33 0

Kwazulu Natal 44 44 0

Limpopo 79 74 5

Mpumalanga 53 52 1

Northern Cape 50 19 31

North West 391 61 330

Western Cape 22 28 -6

TOTAL 870 423 447

Page 18: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

18

ProvinceNo. of

Projects

Budget Allocation 2011/12

Expenditure % SpentTargets for Work Opportuni

Work Opportunities Created

Full Time Equivalent Targets

No. of Full Time Equivalent

Eastern Cape 98 1,034,086 1,048,622 101% 32,965 28,489 20,736 4,970 Free state 14 447,165 340,806 76% 10,370 6,795 4,890 2,037 Gauteng 33 566,917 137,985 24% 5,636 2,134 2,134 665 KwaZulu Natal 44 1,236,648 1,357,466 110% 57,000 50,848 22,578 15,160 Limpopo 74 934,208 777,042 83% 23,876 37,307 10,145 25,501 Mpumalanga 52 1,016,603 1,180,210 116% 15,740 6,997 8,346 2,524 Northern Cape 19 308,760 457,460 148% 1,568 1,704 741 966 North West 61 501,826 258,942 52% 6,427 424 2,142 814 Western Cape 28 411,141 411,141 100% 1,375 21,420 597 7,452 Totals 423 6,457,354 5,969,674 92% 154,957 156,118 72,309 60,089

Page 19: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and

19

Annual Target 2011/12

Actual 2011/12

Annual Target 2011/12

Actual 2011/12

EASTERN CAPE 116,000 146,654 40,000 21,949

FREE STATE 396,000 433,800 - -

GAUTENG 14,986 14,986 1,042 1,506

KZN PROVINCE 165,000 241,012 100,000 100,520

LIMPOPO 555,100 473,633 128,000 75,356

MPUMALANGA 263,388 263,388 34,718 34,718

NORTHEN CAPE 2,144 127,237 120,000 58,840

WESTERN CAPE 22,500 22,500 281 281

TOTAL 1,535,118 1,723,210 424,041 293,170

PROVINCE NAME

BlacktopPatching (m2 ) Road Blading (km)

Page 20: Presentation to Select Committee on Public Services Briefing on  Unproclaimed  Roads and