presentation on current status of or plan for nuclear hrd … · · 2017-08-07presentation on...
TRANSCRIPT
Presentation on Current Status of Nuclear Programs Country: MALAYSIA
The 1st ASEAN+3 Senior Policymakers Course Korea, 8-14 July 2012
Presented by
Hamrah Mohd Ali ,
Ministry of Science, Technology and Innovation (MOSTI)
and Nor Shahbani Nordin,
Ministry of Energy, Green Technology and Water (KeTTHA).
Presentation Points
• Introduction
• Country Energy Profile.
• Government Policy on Nuclear Energy.
• Status of Nuclear Programs.
• Challenges in Developing Nuclear Power Program.
• Conclusions
Introduction
• Capital : Kuala Lumpur
• Official language : Malaysian
• Ethnic group : Malay - 50.4%
Chinese - 23.7%
Indigenous - 11.0%
India - 7.1%
• Government : Federal Parliamentary democracy
• Area : Total: 329,847 sq km
Land: 328,657 sq km
Water: 1,190 sq km
• Population : 28,334,13 (2010 Census)
Country Energy Profile
INSTALLED CAPACITY (MW) PEAK DEMAND
AS AT MEI
2011 (MW)
RESERVE
MARGIN (%)
Peninsular
Malaysia
TNB 7,096 32%
15,476
41% IPPs 14,777 68%
Total 21,873
Sabah SESB 437 37%
844
38% IPPs 733 63%
Total 1,170
Sarawak SEB 919 68%
1067
28% IPPs 430 32%
Total 1,349
15
System Capacity
FUEL MIX FOR PENINSULAR MALAYSIA
Peninsular Fuel Mix
Fuel Mix MW %
Gas 12,792 58.5
Coal 7,170 32.8
Hydro 1,911 8.7
Total Generation 21,817 100
Gas 58%
Coal 33%
Hydro 9%
6
consider nuclear energy as one of the options for electricity generation, post 2020 particularly in Peninsular Malaysia
set up Nuclear Power Development Steering Committee (JPPKN) and three (3) Working Committees
allocate RM25 million for a period of 3 years (2010 – 2012) to implement activities under JPPKN
Government Decision
adopt National Nuclear Policy as a guideline for the development of nuclear sector for electricity generation and non-electricity generation
The main players for this policy implementation are Ministry of Science, Technology and Innovation (MOSTI) and Ministry of Energy, Green Technology and Water (KeTTHA).
Y.A.B Prime Minister announced the establishment of Malaysia Nuclear Power Corporation (MNPC) as the NEPIO
To establish NEPIO as recommended by IAEA. NEPIO will replace the role and functions of JPPKN
ESTABLISHMENT
OF MALAYSIA
NUCLEAR POWER CORPORATION
(MNPC) AS A NEW
FULLY DEDICATED NUCLEAR ENERGY
PROGRAMME IMPLEMENTING ORGANISATION
(NEPIO)
Malaysia Nuclear Power Corporation (MNPC) registered under the Companies Act of Malaysia, and placed under the jurisdiction of the Prime Minister’s Department, as a new fully dedicated NEPIO, and officially launched by the Prime Minister to spearhead nuclear power deployment under the Economic Transformation Programme (ETP)
on 11th January 2011.
2011
ESTABLISHMENT OF MNPC AS NEPIO
9
Based on Memorandum of Association of MNPC under the Companies Act:
To plan, spearhead & coordinate the implementation of nuclear energy development programme for Malaysia
and to take the necessary action to realise the development of the first nuclear power plant in Malaysia;
To ensure the development of nuclear infrastructure for the country is in line with International Atomic Energy Agency (IAEA) guidelines
covering 19 key areas of national position, nuclear safety, management, funding & financing, legislative framework, safeguards,
regulatory framework, radiation protection, electrical grid, human resource development, stakeholder involvement,
site & supporting facilities, environmental protection, emergency planning, security & physical protection, nuclear fuel cycle, radioactive waste,
industrial involvement, and procurement; and,
To identify the company or special purpose vehicle (SPV) to be the owner and/or operator of nuclear power plant.
TASKS OF MNPC
10
Malaysia Nuclear Power Corporation
MNPC to plan, spearhead and coordinate the implementation of nuclear
energy development ( targeted by 2021 as per ETP Nuclear Timeline)
MNPC is in a temporary form, specific responsibilities are still with
each agencies e.g regulatory body, R&D institution
Some of the highlight…
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Preparation Phase Decision Phase
Implementation Phase Launch
Regulatory Framework Preparation
Permits & Safety Analysis
Operation Permits & Safety Reports
Pre-Feasibility Study (PFS)
Pro
ject
Dev
elop
men
t
Feasibility Study (PFS)
Basic & Detailed Design
Bid Invitation & Evaluation
Contract Award & Vendor Procurement
Site Grading & Excavation
Construction
Commissioning
Signing/Ratifying or Acceding to International Instruments & Legislative Development
Site Investigations
Site Permit
Construction Permit
Preliminary Safety Analysis Report (PSAR)
Pre-Operational Baseline Radiological Data Gathering
Final Safety Analysis Report (PSAR) for Operating Licence
Operator Training
Continuous Stakeholder Involvement, Public Information, Human Capital, Industrial & Technological Development Pro
gra
mm
e &
Reg
ula
tory
D
evel
opm
ent
NUCLEAR POWER DEVELOPMENT PLANING
12
KE
Y
PLA
YE
RS
MNPC as NEPIO
SPV Owner/Operator Regulator
[conceptual & not to scale]
Source: adapted & updated from Malaysia’s National Key Economic Areas (NKEA) Laboratory 2010
•Nuclear Power Infrastructure Development Plan (NPIDP) being developed by consultants to MNPC; •Self-assessment of 19 Infrastructure Issues with the same consultant; •Public Communications Kick-Start Strategy being developed by consultants; •Possibility of engaging Malaysian university with strong credentials in creative communications for public communication; •Malaysian universities developing & starting nuclear-related courses.
•Legal & Regulatory Study undertaken by consultant to MNPC from June 2011 to Sept 2012; •Phase 1 of L&R Study completed with proposed new governance structure & draft comprehensive nuclear law to be tabled in Parliament by Sept 2012, and Nuclear Power Regulatory Infrastructure Development Plan (NPRIDP), all submitted to IAEA for review/comment; •Phase 2 of L&R Study currently undertaken for formulation of regulations.
•Consultant engaged by MNPC to undertake Formulation of NPIDP; Full Feasibility Study; Detailed investigations of
potential plant sites; Preparation of Bid
Documents; SPV Owner/Operator &
financing options; for 21-month period from January 2012;
•All of the above studies are on-going, except for delay in detailed site investigations; •Training programme to be provided by the consultant at the home office in USA.
PROGRAMME DEVELOPMENT
LEGAL & REGULATORY DEVELOPMENT
PROJECT DEVELOPMENT
Status of Nuclear Power Programme
13
▪ Public opinion survey to identify priority segments & concerns
▪ Awareness projects ▪ Transparency in project implementation
Public Acceptance
▪ Promote public acceptance
▪ Fast-track process & government priority International Governance
▪ Sign/ratify relevant treaties & conventions
▪ Align on international best practices ▪ Top-down mandate to accelerate process ▪ Engage foreign experts to assess
site & construction permit applications
Regulatory Context
▪ Put in place detailed regulations
▪ Public information programme ▪ Option for localities to bid to host
nuclear power plants & facilities as in Japan & Republic of Korea
Nuclear Plant Site Acquisition
▪ Acquire approval for plant sites ▪ Obtain public support in locality
▪ Negotiate with vendors based on timeline Construction Timeline
▪ Require best-in-class timeline from vendors
Potential Resolution Challenge
▪ Combine low-cost & market financing (e.g. sovereign-guaranteed export credits, foreign equity, commercial loans, including Islamic financing)
Project Financing
▪ Obtain low-cost financing
KEY CHALLENGES
14 Source: Malaysia’s National Key Economic Areas (NKEA) Laboratory 2010
CONCLUSIONS
• To address all challenges before Government make a firm decision on NPProgramme
• Important to address integrated plan on Human Capital Development on NPProgramme
• Need to ensure sustainable development in the electricity sector
• Holistic and comprehensive approach in meeting the challenges – Long Term Energy Master Plan
•
Thank you…