precommissioning test format

Upload: ashutosh2009

Post on 04-Jun-2018

257 views

Category:

Documents


5 download

TRANSCRIPT

  • 8/13/2019 Precommissioning Test Format

    1/72

    Page 1 of 72

    ASSAM ELECTRICITY GRID CORPORATION LIMITED

    PRECOMMISSIONING OF TRANSFORMER

    COMMISSIONING FORMATS

    DOC NO: SUBSTATION:

    Transformer BAY NO: EQUIPMENT IDENTIFICATION NO: DATE OF TESTING:

    Transformer Type: 2 Winding ICT

    Voltage level, kV 132/33 220/132 220/132/11 400/220/33

    Current (HV side): Current (LV side): Current (Tertiary):

    MVA RTING:

    A. CHECK LIST OF ELECTRICAL TESTS CARRIED OUT FOR TRANSFORMER

    Sl.No Name of Tests Performed (Yes/No)

    Test Results OK/Not OK

    1 Insulation resistance measurement 2 Vector group test & polarity check

    3 Short circuit impedance test 4 Magnetic balance test 5 Floating neutral voltage measurement 6 Magnetisation current test 7 Voltage ratio test 8 Insulation resistance measurements of bushing CT

    9 Continuity Test of Bushing CTs 10 Secondary winding resistance of bushing CT

    11 Polarity Test of Bushing CTs

    12 Current Ratio test 13 Magnetising curves performance 14 Contact Resistance measurement 15 TAN DELTA & CAPACITANCE Measurement of Bushings

    16 TAN DELTA & CAPACITANCE Measurement of WINDINGS

    17 Protection and alarm tests 18 Stability test of Differential and REF protection

    19 Frequency Response Analysis 20 Measurement of Winding Resistance

  • 8/13/2019 Precommissioning Test Format

    2/72

    Page 2 of 72

    Signature: Signature: Signature: Signature Name: Name: Name: Name: Designation: Designation: Designation: Designation: (Supplier Rep) Erection Agency: Site I/C, AEGCL T & C, AEGCL

    B. CHECKS AFTER RECEIPT OF TRANSFORMER AT SITE:

    a. N2 PRESSURE & DEW POINT RECORD

    Description N2 Pressure Dew Point Ambient Temp Remarks During Dispatch at factory After receipt at site

    DURING STORAGE AT SITE BEFORECOMM.

    NOTE: N2 pressure and dew point should be within permissible range as per graph provided by manufacturer. During storage at site, dew point has to be measured whenever any drop in N2 pressure is observed. During storage at site before commissioning, N2 pressure has to be measured daily and record to be maintained in a separate sheet.

    b. IMPACT RECORER ANALYSIS

    RECEIVED IN HEALTHY CONDITION AT SITE

    STATUS BRIEF ANALYSIS Yes No

    Analysis report Received from Manufacturer Before starting of erection

    Yes No

    Note: Impact Recorder should be detached from the Transformer/ Reactor preferably when the

    main unit has been placed on its foundation.

    c. CORE INSULATION CHECK

    INSULATION VALUE Between CCG Between CLG Between CCCL (Recommended value > 10 M Ohms)'

    Note: Shorting link between CC, CL & G to be removed and IR value to be taken between CCG, CLG

    & CCCL.

  • 8/13/2019 Precommissioning Test Format

    3/72

    Page 3 of 72

    C. CHECKS/ PRECAUTIONS DURING ERECTION

    i) Active part of transformer should minimum exposed to atmosphere

    ii) During exposure of active part of transformer to atmosphere:

    DRY AIR GENERATOR/ DRY AIR CYLINDERS USED :

    Yes No Remarks

    iii) WHILE ENTERING IN TRANSFORMER TANK, CHECK AVAILABILITY OF PROPER OXYGEN

    TRANSFORMER KEPT SEALED WITH N2 IN BETWEEN DIFFERENT ERECTION ACTIVITIES

    Yes No Remarks

    D. PRECOMMISSIONING CHECKS:

    Sl No

    DESCRIPTION STATUS REMARKS Yes No RECORD DEFICIENCIES, IF ANY

    1. Transformer and its auxiliaries are free from visible defects on physical inspection

    2. All fittings as per out line general arrangement drawing.

    3. Check main tank has been provided with double earthing

    4. Check neutral is grounded through separate connections. Ensure metallic requirements as per specification in earthing strips used

    5. Check that Marshalling box, OLTC driving gear, Diverter, Radiator bank, Pump & Fan motor etc has been earthed

    6. All nuts and bolts are tightened correctly as per specified torque (as per manufacturers recommendation)

    7. Check tightness of terminal connectors 8. Check levelling of transformer and its

    accessories 9. Erection completion certificate along with

    list of outstanding activities reviewed 10. Any paint removed / scratched in transit

    has been touched up 11. Bushings are clean and free from physical

    damages 12. Oil level is correct on all bushings

  • 8/13/2019 Precommissioning Test Format

    4/72

    Page 4 of 72

    13. Check hermetically sealing is intact in all bushings

    14. Check oil leakage through any joints / valves etc.

    15. Check oil drain valves are properly closed

    and locked. 16. Check oil level in Main / OLTC

    conservator tank 17. Check oil level at conservator matches

    with oil temperature of transformer 18. Check gear box oil level in OLTC 19. Check OTI and WTI pockets and replenish

    the oil , if required 20. check all valves for their opening &

    closing sequence 21. Check the colour of breather silica gel (

    blue when dry ) 22. Check availability of oil in the breather

    cup 23. Check all rollers are locked and tack

    welded with rails ( where ever applicable )

    24. Check bushing test tap is grounded 25. Check no debris , loose T & P and oil

    strains on and around the transformer 26. Check door seals of marshalling box is

    intact and all cable gland plates unused holes are sealed

    27. Check that pressure relief valve is correctly mounted

    28. Ensure unused secondary cores of bushing CT's, if any, has been shorted

    29. Check star point has been formed properly and grounded at one end only as per scheme

    30. Check that permanent and adequate lightning arrangements are ready

    31. Check that labelling and identification is permanent and satisfactory

    32. Check that buchholz relay is correctly mounted with arrow pointing towards conservator

    33. Check cables are properly fixed and ensure cable entry at the bottom

    34. Ensure all power and control cable terminals are tightened

    35. Check all cables and ferrules are provided with number as per cable schedule (cross feruling to be Checked)

    36. Check that all cables are correctly glanded

  • 8/13/2019 Precommissioning Test Format

    5/72

    Page 5 of 72

    37. Check external cabling from junction box to relay / control panel completed

    38. Check that air has been released from the radiators and their headers / OLTC buchholz relay /Main tank / tank/

    bushing turrets etc. 39. Check fire protection system & is

    adequate & ready 40. Check that CCCL& G are shorted 41. Check that all radiator bank valves on top

    and bottom headers are open 42. Change over operation of ac supply from

    Source i to Source ii checked 43. Check the flanges of bushing &

    OLTC for any crack after fixing 44. Check various interlocks provided with

    fire fighting as per the schematic ref. Drg no :__________

    DESCRIPTION OF INTERLOCKS CHECKED

    E. MEASUREMENT OF EARTH RESISTANCE OF ELECTRODE

    LOCATION 1 2 3 4 VALUE (Before connection to grid) VALUE (After connection to grid)

    NOTE: Value of Earth Resistance< 1.0 OHM

    F. CALIBRATION OF OTI & WTI PERFORMED AS PER PROCEDURE: Yes No

    G. DETAILS OF RELAYS/ CONTACTORS USED: SCHEMATIC DRAWING NO.: __________________

    Circuit Reference

    Make Serial No. Type Number of NO & NC contacts

    Number of AI, BI & BO

    NO NC AI BI+BO

    H. EVACUATING AND OIL FILLING:

    a) Before filling oil, each drum has been physically checked for free moisture and

    appearance: Yes No

    b) OIL FILTER MACHINE:

  • 8/13/2019 Precommissioning Test Format

    6/72

    Page 6 of 72

    i). Capacity : ii). Make : iii). Lubricating oil of vacuum pump changed or not : iv). Filter Packs cleaned or not : v). Whole filter machine flushed with fresh oil or not : vi). Vacuum obtained without load (milli bar) :

    c) VACUUM PUMP FOR EVACUATION OF TRANSFORMER:

    i). Lubricating Oil changed or not : ii). Vacuum obtained without load (milli bar) : iii). Diameter of vacuum hose (50 mm) : iv). Dry ice chamber employed or not :

    d) OIL STORAGE TANK:

    i). Inside painted or not : ii). Silica gel breather provided or not : iii). Any opening left uncovered : iv). Capacity of Storage tank (KL) : v). Cleanliness of inside of pipes/ hoses to the storage tank :

    e) EXPOSURE DURING ERECTION:

    i). Exposure hours during First day, Number of Hours: : a. N2 filled pressure (PSI or Bar) :

    b. Number of Hours under N2 : c. Ambient temperature : d. Relative Humidity : e. Weather (sunny/cloudy/stormy/rainy) :

    ii). Exposure hours during Second day, Number of Hours: : a. N2 filled pressure (PSI or Bar) : b. Number of Hours under N2 : c. Ambient temperature : d. Relative Humidity : e. Weather (sunny/cloudy/stormy/rainy) :

    iii). Exposure hours during Third day, Number of Hours: : a. N2 filled pressure (PSI or Bar) : b. Number of Hours under N2 : c. Ambient temperature : d. Relative Humidity : e. Weather (sunny/cloudy/stormy/rainy) :

    f) N2 SEALING IN CASE OF DELAY IN OIL FILLING:

    a. No. of Cylinders used for displacing the air inside the tank: b. N2 admitted from bottom valve

  • 8/13/2019 Precommissioning Test Format

    7/72

    Page 7 of 72

    a. Valve at diametrically opposite end at top kept open: b. No. of Cylinders used for building up 2 PSI (0.14 kg/cm 2)

    Inspection Item Date Time Checked Remarks 1. Tightness test a. Start evacuating on complete unit b. Stop evacuating at 3 mbar c. Pressure P1 in kPa, 1 hour after stop

    evacuating d. Pressure P2 in kPa, 0.5 hrs after

    reading P1 e. Leakage = (P2P1)X V= If >3.6, continue

    evacuating, V is the volume of oil as per name plate.

    2. VACUUM a. Pressure 0.13 kPa (1.3 mbar) reached b. Vacuum kept for Upto 145 kV, 12 Hour 145 kV & upto 220 kV, 24 Hours 3. OIL FILLING a. Oil filling is made b. Oil Conservator with Air Cell c. OLTC 4. STANDING TIME Upto 145 kV, 12 Hours 145 kV & upto 220 kV, 48 Hours

    G) RECORD OF DRYING OUT PROCESS:

    Drying out started on: Date: Time: Ambient Temp:

    (Hourly reading to be taken)

    Date Time Vacuum reading in

    Filtration machine

    Vacuum reading In transformer

    Tank

    OTI OF TANK

    Condensate Collected total

    /Rate

    Remarks & sign of supervising

    Engineer

    Record of filtration and Dry out shall be kept in a register and shall be made a part of the Pre commissioning document.

    H) INSULATION RESISTANCE MEASUREMENT: (USING 500 V MEGGER):

    Megger details:

    Validity of Calibration:

  • 8/13/2019 Precommissioning Test Format

    8/72

    Page 8 of 72

    Ambient temperature:

    Sl No Description Status Remarks, if any Yes No

    A Control Wiring

    B Tap Cganger Motor Control wiring

    C Cooling System Fan Motor Pump Motor Control Wiring

    NOTE: IR values should be > 50 M for cables

    I) INSULATION RESISTANCE MEASUREMENT: (USING 5000 V MEGGER):

    Megger details:

    Validity of Calibration:

    Ambient temperature: Temperature of OIL:

    Main Winding IR Value (M) AI=60ss/15 s PI=600s/60 s Temp. 15 Sec 60 Sec 600 sec

    Auto Transformer HV+IV to LV HV+IV to E

    LV to E 2 Winding Transformer HV to E LV to E HV to LV

    J) VECTOR GROUP TEST & POLARITY CKECKING

    CONNECT NEUTRAL POINT WITH EARTH, JOIN 1RI AND 3 RI TERMINALS, APPLY 415V, 3PHASE SUPPLY TO HV TERMINALS

    Terminal Voltage Measured Remarks 1R1 1Y1 1Y1 1B1 1B1 1R1 3B1 1B1 3B1 1Y1 3R1 N 3Y1 N 1R1 N 2R1 N

    2 Y1 N 2 B1 N

  • 8/13/2019 Precommissioning Test Format

    9/72

    Page 9 of 72

    ENSURE 2R1 N = 2Y1 N = 2B1 N = CONSTANT

    AS 3R1 N > 3B1 N > 3Y1 N, AND 3Y1 1B1 > 3B1 1B1

    VECTOR GROUP Ynaod1 IS CONFIRMED AND POLARITY VERIFIED

    K) MEASUREMENT OF WINDING RESISTANCE (IN OHM)

    Winding Resistance meter detail:

    Validity of calibration:

    Ambient Temperature: OTI reading: WTI reading:

    i). HV Side Measurement

    Tap position

    Wdg. Resistance, HVN Resistance at 75 0C Factory Value at 75 0C

    Remarks

    1R12R1 1Y12Y1 1B12B1 R Y B R Y B 1 2 3 4 5 6 7

    8 9b 10 11 12 13 14 15 16 17

    Factory Test Report Ref. NO:

    ii). INTERMEDIATE VOLTAGE SIDE:

    Between Winding Resistance At Site

    Resistance at 75 0C Remarks Site Factory

    2R1 N 2Y1 N 2B1 N

    iii). LOW VOLTAGE SIDE:

  • 8/13/2019 Precommissioning Test Format

    10/72

    Page 10 of 72

    Between Winding Resistance At Site

    Resistance at 75 0C Remarks Site Factory

    3R1 N3B1 3Y1 3R1 3B1 3Y1

    NOTE: LV WINDING RESISTANCE AT FACTORY MEASURED WITHOUT FORMATION OF DELTA. HOWEVER MEASUREMENTS CARRIED OUT AT SITE ARE AFTER FORMATION OF DELTA. HENCE A CORRECTION FACTOR OF 1.5 TIMES TO BE APPLIED IN SITE RESULTS.

    L) MAGNETIC BALANCE TEST:

    Apply single phase 230 V across one phase of HV winding terminal and neutral then measure voltage in other two HV terminals across neutral. Repeat the test for each of the three phases.

    Apply 1ph, 230V AC across (1) Voltage measured in Volts Remarks Between (2) Between (3) 2R1 N 2Y1 N 2B1 N 2Y1 N 2R1 N 2B1 N 2B1 N 2Y1 N 2R1 N

    M) FLOATING NEUTRAL VOLTAGE MEASUREMENT

    Disconnect the transformer neutral from the ground

    Apply 3 phase 415 volts to the high voltage winding and make the measurement in the IV winding

    with respect to neutral and neutral point to ground.

    Tap Position HV Winding Voltage Applied

    IV Winding Voltage Measured

    Remarks, if any

    Normal ( ) 1R N 2R N Normal ( ) 1Y N 2Y N Normal ( ) 1B N 2B N

    N Earth

    Apply 3 phase 415 volts to the intermediate voltage winding and make the measurement in the

    tertiary winding with respect to neutral and neutral point to ground.

    IV Winding Voltage Applied LV Winding Voltage Measured

    Remarks, if any

    2R N 3R N 2Y N 3Y N 2B N 3B N

    N Earth

    Check: After the test, neutral reconnected to Ground : Yes / No

    N) MAGNETISATION CURRENT TEST:

  • 8/13/2019 Precommissioning Test Format

    11/72

    Page 11 of 72

    Testing Instrument detail:

    Testing Instrument Calibration valid or not:

    Ambient temperature at the time of test:

    Temperature of OIL:

    i). APPLY 1PHASE AC SUPPLY ON HV TERMINALS AND KEEP IV & LV OPEN Tap Position Voltage

    Applied (V) Current Measured (mA)

    Factory test value

    Remarks

    Lowest ( ) R N R ph Y N Y ph B N B ph

    Normal ( ) R N R ph Y N Y ph B N B ph

    Highest ( ) R N R ph Y N Y ph B N B ph

    ii). APPLY 1PHASE AC SUPPLY ON IV TERMINALS AND KEEP HV & LV OPEN Tap Position Voltage applied

    (Volts) Current measured in LV side (mAmps)

    Remarks

    Normal ( ) 2R N 2Y N 2B N

    P) VOLTAGE RATIO TEST:

    Testing Instrument (TRM) detail: Testing Instrument Calibration valid or not: Ambient temperature at the time of test: Temperature of OIL:

    i). Ratio HV / IV

    Tap

    Pos

    Voltage applied Voltage measured Ratio Factory Ratio

    1RN 1YN 1BN 2RN 2YN 2BN R Y B R Y B 1 2 3 4 5 6 7 8 9 10 11 12

  • 8/13/2019 Precommissioning Test Format

    12/72

    Page 12 of 72

    13 14 15 16 17

    ii). RATIO : HV / LV

    Tap Position

    Voltage applied Voltage measured Ratio Factory Ratio 1RN 1YN 1BN 3RN 3YN 3BN R Y B R Y B

    Lowest Normal Highest

    iii). RATIO : IV / LV

    Tap Position

    Voltage applied Voltage measured Ratio Factory Ratio 2RN 2YN 2BN 3RN 3YN 3BN R Y B R Y B

    Lowest

    Q) OIL CHARACTERISTICS:

    Date: Time: Ambient Temp:

    OTI reading: WTI reading:

    Sample to be collected before Charging & following value to be achieved:

    BDV: Min 70 kV

    Moisture in PPM: Min 10

    Tan delta (90 0C): Max 0.1

    Resistivity: Min 6 x 10 12 Ohm cm

    Interfacial Tension at 27 0C: Min 0.035 N/m

    OIL Sample BDV (kV) Moisture (PPM)

    Tan delta Resistivity (Ohm cm)

    Inter facial tension (N/m)

    Remarks

    Main Tank Top Bottom OLTC

    R) DISSOLVE GAS ANALYSIS

    DISOLVE OIL SAMPLE SCHEDULE

  • 8/13/2019 Precommissioning Test Format

    13/72

    Page 13 of 72

    GASES Before Charging

    24 Hrs After Charging

    7 Days After Charging

    15 Days After Charging

    01 Month After Charging

    03 Month After Charging

    Total Gas% H2

    CH4 C2H4 C2H6 C2H2 CO CO2 O2 N2

    S) Test on OLTC:

    Sl No

    Description Status Remarks OK Not OK

    1 Visual inspection of equipment 2 Manual operation on all taps ( local ) with confirmation

    of the no. of revolutions and Locking at extreme taps 3 Over load device of driving motor 4 Local operation (Electrical) 5 Remote operation (Electrical) 6 Tap position indicator 7 Check operation with Master Follower scheme ( parallel

    operation ) 8 Out of step relay 9 Step by Step Contactor 10 Limit Switch 11 Winding resistance at all taps 12 Continuity test of winding during one Complete cycle of

    operation

    T) OPERATIONAL TEST OF OTHER EQUIPMENTS

    i). CHECKING OF COOLING EQUIPMENTS a) Rotation Direction of Pumps: OK Not Ok b) Rotation Direction of Fans: OK Not Ok

    ii). PROTECTION CHECKS Eqpt. Fan No

    Setting Value Pickup Value Single Phasing Prevention check

    1 2 3 4

    5 6

  • 8/13/2019 Precommissioning Test Format

    14/72

    Page 14 of 72

    7 8 9 10 11

    12 Pump No 1 2 3 4

    U) INSULATION RESISTANCE MEASUREMENT OF BUSHING CTs: (USING 500V MEGGER)

    Between HV IV Neutral LV

    Rph Yph Bph Rph Yph Bph Rph Yph Bph Earth Core I Earth Core II Earth Core III Earth Core IV Core I Core II Core I Core III Core I Core IV Core II Core III Core II Core IV Core III Core IV

    V) CONTINUITY TEST OF BUSHING CT's

    Core Between Terminal

    HV IV Neutral LV Rph Yph Bph Rph Yph Bph Rph Yph Bph

    Core I 1S11S2 Core II 2S12S2 Core III 3S13S2 Core IV 4S14S2

    W) SECONDARY WINDING RESISTANCE OF BUSHING CT's (IN OHM)

    i). HV SIDE

    Core Between RPhase () YPhase( ) BPhase( ) Terminal Factory Site Factory Site Factory Site

    COREI 1S11S2 COREII 2S12S2 COREIII 3S13S2 COREIV 4S14S2

  • 8/13/2019 Precommissioning Test Format

    15/72

    Page 15 of 72

    ii). IV SIDE

    Core Between RPhase () YPhase( ) BPhase( ) Terminal Factory Site Factory Site Factory Site

    COREI 1S11S2

    COREII 2S12S2 COREIII 3S13S2 COREIV 4S14S2

    iii). LV SIDE

    Core Between RPhase () YPhase( ) BPhase( ) Terminal Factory Site Factory Site Factory Site

    COREI 1S11S2 COREII 2S12S2 COREIII 3S13S2

    COREIV 4S14S2

    iv). NEUTRAL SIDE

    Core Between NEUTRAL () Terminal Factory Site

    COREI 1S11S2

    X) POLARITY TEST OF BUSHING CT's : (With 1.5 V DC Supply)

    i). POLARITY OF HV & IV BCT

    CORE Between HV IV RPH YPH BPH RPH YPH BPH

    COREI 1S1(+ve) 1S2(ve) COREII 2S1(+ve) 2S2(ve) COREIII 3S1(+ve) 3S2(ve) COREIV 4S1(+ve) 4S2(ve)

    ii). POLARITY OF LV & Neutral BCT

    CORE Between LV Neutral RPH YPH BPH

    COREI 1S1(+ve) 1S2(ve) COREII 2S1(+ve) 2S2(ve) COREIII 3S1(+ve) 3S2(ve) COREIV 4S1(+ve) 4S2(ve)

    Y) CURRENT RATIO TEST: Measure current on secondary terminals

    i). R PHASE: HV SIDE

  • 8/13/2019 Precommissioning Test Format

    16/72

  • 8/13/2019 Precommissioning Test Format

    17/72

    Page 17 of 72

    iv). R PHASE: IV SIDE

    CORE

    S1 S2

    Primary

    %

    Current

    Actual

    Secondary

    Current

    Theoretical

    Ratio

    Actual

    Ratio

    %

    Error COREI (1S11S2)

    20% 40% 80%

    COREII (2S12S2)

    20% 40% 80%

    COREIII (3S13S2)

    20% 40% 80%

    COREIV

    (4S14S2)

    20%

    40% 80%

    v). Y PHASE: IV SIDE

    CORE S1 S2

    Primary %

    Current Actual

    Secondary Current

    Theoretical Ratio

    Actual Ratio

    % Error

    COREI (1S11S2)

    20% 40% 80%

    COREII (2S12S2)

    20% 40% 80%

    COREIII (3S13S2)

    20% 40% 80%

    COREIV (4S14S2)

    20% 40% 80%

    vi). B PHASE: IV SIDE

    CORE S1 S2

    Primary %

    Current Actual

    Secondary Current

    Theoretical Ratio

    Actual Ratio

    % Error

    COREI (1S11S2)

    20% 40% 80%

    COREII (2S12S2)

    20% 40% 80%

    COREIII (3S13S2)

    20% 40% 80%

  • 8/13/2019 Precommissioning Test Format

    18/72

    Page 18 of 72

    COREIV (4S14S2)

    20% 40% 80%

    Z) MAGNETISING CURVES PERFORMANCE:

    (NOT TO BE DONE FOR METERING CORE)

    KNEE POINT VOLTAGE (KVP) =

    i). R PHASE: HV SIDE VOLTAGE CURRENT MEASUREMENT (mA) To be applied Actual

    Value COREI COREII COREIII COREIV 1S11S2 2S12S2 3S13S2 4S14S2

    0.25 x KVP 0.50 x KVP 0.75 x KVP

    1.00 x KVP 1.10 x KVP

    ii). Y PHASE: HV SIDE VOLTAGE CURRENT MEASUREMENT (mA) To be applied Actual

    Value COREI COREII COREIII COREIV 1S11S2 2S12S2 3S13S2 4S14S2

    0.25 x KVP 0.50 x KVP 0.75 x KVP 1.00 x K

    VP 1.10 x KVP

    iii). B PHASE: HV SIDE VOLTAGE CURRENT MEASUREMENT (mA) To be applied Actual

    Value COREI COREII COREIII COREIV 1S11S2 2S12S2 3S13S2 4S14S2

    0.25 x KVP 0.50 x KVP 0.75 x KVP

    1.00 x KVP 1.10 x KVP

    iv). R PHASE: IV SIDE VOLTAGE CURRENT MEASUREMENT (mA) To be applied Actual

    Value COREI COREII COREIII COREIV 1S11S2 2S12S2 3S13S2 4S14S2

    0.25 x KVP 0.50 x KVP 0.75 x KVP 1.00 x KVP 1.10 x KVP

  • 8/13/2019 Precommissioning Test Format

    19/72

  • 8/13/2019 Precommissioning Test Format

    20/72

  • 8/13/2019 Precommissioning Test Format

    21/72

    Page 21 of 72

    2 kV HVIV/LV+G GST 10 kV 2 kV HVIV/LV

    with Guard GSTg

    10 kV 2 kV LV/HVIV+G GST

    10 kV 2 kV LV/HVIV

    with Guard GSTG

    10 kV

    AD) SHORT CIRCUIT IMPEDANCE TEST

    Testing Instrument detail:____________________________________________________

    Testing Instrument Calibration valid or not: ___________________

    Ambient temperature at the time of test: _______________

    Temperature of OIL: __________________

    i). HV TO IV

    Tap No.

    1U1 (R) 1V1 (Y) 1W1 (B) (IV OF R AND N SHORTED, LV OPEN)

    (IV OF Y AND N SHORTED, LV OPEN)

    (IV OF B AND N SHORTED, LV OPEN)

    Voltage (V) Current (A) Voltage (V) Current (A) Voltage(V) Current(A) LOWEST NORMAL HIGHEST

    ii). IV TO LV (NORMAL TAP) SUPPLY SHORT ALL 3 LV

    BUSHINGS, HV OPEN SHORT ALL 3 LV BUSHINGS, HV OPEN

    SHORT ALL 3 LV BUSHINGS, HV OPEN

    2U1 N ____________A 2V1N _____________A 2W1 N ____________A

    iii). HV TO LV (NORMAL TAP) SUPPLY SHORT ALL 3 LV

    BUSHINGS, HV OPEN SHORT ALL 3 LV BUSHINGS, HV OPEN

    SHORT ALL 3 LV BUSHINGS, HV OPEN

    1U1 N ____________A 1V1N _____________A 1W1 N ____________A

    AT LOWEST TAP SUPPLY SHORT ALL 3 LV

    BUSHINGS, HV OPEN SHORT ALL 3 LV BUSHINGS, HV OPEN

    SHORT ALL 3 LV BUSHINGS, HV OPEN

    1U1 N ____________A 1V1N _____________A 1W1 N ____________A

    AT HIGHEST TAP

  • 8/13/2019 Precommissioning Test Format

    22/72

  • 8/13/2019 Precommissioning Test Format

    23/72

    Page 23 of 72

    b. Source

    c. Pickup

    d. Slope

    e. Pickup Delay

    f. Reset Delay

    iii). OVER FLUXING PROTECTION:

    OVER FLUXING SETTINGS:

    a. Function Enabled

    b. Source

    c. Pickup

    d. Curves

    e. TD Multiplier

    f. T Reset

    iv). BACK UP PROTECTION:

    LV Side:

    a. Over current Settings:

    PS TMS HS

    __________ ______ _________

    b. Earth Fault Settings: PS TMS HS

    __________ ______ _________

    HV SIDE:

    c. Over current Settings:

    PS TMS HS

    __________ ______ _________

    d. Earth Fault Settings:

    PS TMS HS

    __________ ______ _________

    AG) STABILITY TEST OF DIFFERENTIAL & REF PROTECTION: OK/ Not OK

    NOTE : Prove the tripping of associated breakers by actual operation of the various devices and relays as per the schemes.

    AH) FREQUENCY RESPONSE ANALYSIS (FRA)

  • 8/13/2019 Precommissioning Test Format

    24/72

  • 8/13/2019 Precommissioning Test Format

    25/72

    Page 25 of 72

    iii). DOCUMENTS REGARDING SPARES, EQUIPMENT, O & M MANNUALS ETC AVAILABLE AT SITE FOR O & M PURPOSE: YES / NO

    iv). AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS" ARE AVAILABLE AT SITE: YES / NO

    Signature: Signature: Signature: Signature Name: Name: Name: Name: Designation: Designation: Designation: Designation: (Supplier Rep) Erection Agency: Site I/C, AEGCL T & C, AEGCL

  • 8/13/2019 Precommissioning Test Format

    26/72

    Page 26 of 72

    ASSAM ELECTRICITY GRID CORPORATION LIMITED

    PRECOMMISSIONING OF ISOLATOR AND GROUND SWITCH

    COMMISSIONING FORMATS

    DOC NO: SUBSTATION:

    BAY NO: DATE OF TESTING:

    EQUIPMENT SERIAL NO : RPhase___________ YPHASE____________B PHASE______________

    Type: MAKE:

    Voltage level, kV 33 132 220 400

    Current Carrying Capacity: ___________A

    Type of Operating Mechanism:

    Control Voltage:______________Volt DC

    1) DETAILS:

    SL

    No

    DESCRIPTION STATUS REMARKS, IF

    ANY

    YES NO

    1. Equipment is free from dirt/dust Foreign materials

    etc.

    2. Equipment is free from all visible defects on physical

    inspection

    3. Support structures, marshalling box Has been

    provided with two earthing Pads / points

    4. All nuts and bolts are tightened correctly as per

    specified torque

    5. Equipment erection is complete in all respect as per

    instruction manual (attach remaining activities, if

    any)

    6. Permanent isolator levelling and identification is

    done

    7. Levelling and alignment of structure and base frame

    is checked

  • 8/13/2019 Precommissioning Test Format

    27/72

    Page 27 of 72

    8. Control box / marshalling kiosk is free from any

    physical defects

    9. Tightness of nuts bolts of terminal connectors are

    checked

    10. Auxiliary contacts and relays have been cleaned and

    free from rust / damage

    11. Corona rings are provided and properly fixed

    12. Cable termination and tightness checked and unused

    holes sealed

    13. External cabling is completed in all respect

    14. All the cable identification tags provided and all

    cores are provided with identification ferrules at

    M.B.

    15. All moving parts are lubricated

    16. Alignment of isolator already made and locking bolt

    provided, if any

    17. Freeness of manual operation is OK

    18. Greasing has been made on the main contacts

    according to the manufacturers instruction

    19. Functional checking of auxiliary Contacts for

    indications and interlocks

    20. Erection completion certificate along with list of

    outstanding activities reviewed

    21. All spare wires to be kept with ferrules but not

    terminated at the terminal blocks

    22. Earth switch connected to earth through braided wires

    23. Interlocks checked as per approved scheme with all

    combinations

    24. Check that earth switch blade alignment In condition

    is at sufficient distant from Isolator

    25. Check that operation and positioning of the limit

    switch & the auxiliary contacts assembly are ok

    26. Check that all three phase isolators are Closing &

  • 8/13/2019 Precommissioning Test Format

    28/72

  • 8/13/2019 Precommissioning Test Format

    29/72

  • 8/13/2019 Precommissioning Test Format

    30/72

    Page 30 of 72

    ACROSS PHASE

    RPhase ( ) YPhase( ) BPhase( )

    MAIN CONTACT (MALE & FEMALE)

    (GROUND SWITCH)

    c) Resistance of Operating Coil ____________________

    d) Resistance of Interlocking Coil ____________________

    6) FINAL DOCUMENTATION REVIEW:

    a) FINAL DOCUMENT OF PRECOMMISSIONING CHECKS

    REVIEWED AND APPROVED: YES / NO

    b) DOCUMENTS REGARDING SPARES, EQUIPMENT, O & M

    MANNUALS ETC AVAILABLE AT SITE FOR O & M PURPOSE: YES / NO

    c) AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"

    ARE AVAILABLE AT SITE: YES / NO

    Signature: Signature: Signature: Signature Name: Name: Name: Name: Designation: Designation: Designation: Designation: (Supplier Rep) Erection Agency: Site I/C, AEGCL T & C, AEGCL

  • 8/13/2019 Precommissioning Test Format

    31/72

    Page 31 of 72

    ASSAM ELECTRICITY GRID CORPORATION LIMITED

    PRECOMMISSIONING OF WAVE TRAP

    COMMISSIONING FORMATS

    DOC NO: SUBSTATION:

    BAY NO: DATE OF TESTING:

    EQUIPMENT SERIAL NO: RPhase___________ YPHASE____________B PHASE______________

    Type: MAKE:

    Voltage level, kV 132 220 400

    Current rating: ___________A

    mH Rating: BAND WIDTH:

    1. DETAILS : CHECKLIST / TESTING

    SL

    No

    DESCRIPTION STATUS REMARKS, IF

    ANY

    YES NO

    1. Equipment is free from dirt/dust Foreign materials etc.

    2. Equipment is free from all visible defects on physical

    inspection

    3. Support structures, has been provided with two

    earthing Pads / points

    4. All nuts and bolts are tightened correctly as per

    specified torque

    5. Permanent isolator levelling and identification is

    done

    6. Levelling and alignment of structure and base frame

    is checked

    7. All insulators & line matching unit are free from any

    physical defects

    8. Tightness of nuts / bolts of terminal connectors are

    checked

  • 8/13/2019 Precommissioning Test Format

    32/72

    Page 32 of 72

    9. Erection completion certificate along with list of

    outstanding activities reviewed

    10. Check that the tuning unit and Arrestor are properly

    tightened And free from any damage

    2. INSULATION RESISTANCE MEASUREMENT:

    SL

    NO

    BETWEEN MEGGER PHASE Permissive

    Value RPHASE YPHASE BPHASE

    Upper Terminal

    & Earth

    5000 V 1000 M

    LA of the Wave Trap

    500 V 1 M

    3. CONTACT RESISTANCE MEASUREMENT:

    THE VALUE SHOULD NOT MORE THAN 5 PER CONNECTOR / JOINT

    SL

    No ACROSS

    PHASE

    RPhase ( ) YPhase ( ) BPhase ( )

    1 Upper Terminal

    2 Bottom Terminal

    4. FINAL DOCUMENTATION REVIEW :

    a) Final document of pre commissioning checks Reviewed and Approved: YES / NO

    b) Documents regarding spares, equipment, O& M Manuals etc. available at site for o & m purpose: YES / NO

    c) After modification, if any, "as built drawings" are available at site: YES / NO

    Signature: Signature: Signature: Signature Name: Name: Name: Name: Designation: Designation: Designation: Designation: (Supplier Rep) Erection Agency: Site I/C, AEGCL T & C, AEGCL

  • 8/13/2019 Precommissioning Test Format

    33/72

    Page 33 of 72

    ASSAM ELECTRICITY GRID CORPORATION LIMITED

    PRECOMMISSIONING OF SF6 CIRCUIT BREAKER

    COMMISSIONING FORMATS

    DOC NO: SUBSTATION:

    BAY NAME / NO:

    DATE OF ERECTION: DATE OF ENERZIZATION:

    EQUIPMENT SERIAL NO: RPhase___________ YPHASE____________B PHASE______________

    SERIAL NO (FOR GO TYPE):

    Type: MAKE:

    Voltage level, kV 33 132 220 400

    Current rating: ___________A RATED BREAKING CAPACITY:

    CONTROL VOLTAGE:

    DETAILS : CHECKLIST / TESTING

    SL No DESCRIPTION STATUS REMARKS,RECORD DEFICIENCIES, IF ANY

    YES NO

    1. Equipment is free from dirt/dust Foreign materials etc.

    2. Equipment is free from all visible defects on physical inspection

    3. Support structures, has been provided with two earthing Pads / points

    4. All nuts and bolts are tightened correctly as per specified torque

    5. Equipment erection is complete in all respect & erection completion Certificate along with list of Outstanding activities reviewed. (ATTACH REMAINING ACTIVITIES,IF ANY)

    6. Permanent pole levelling and Identification is done

    7. Levelling and alignment of structure and base frame is checked

    8. Control box / marshalling kiosk is free from any

  • 8/13/2019 Precommissioning Test Format

    34/72

    Page 34 of 72

    physical defects

    9. Tightness of nuts bolts of terminal connectors are checked

    10. i) Auxiliary contacts and relays have been cleaned and free from rust /damage ii) All spare wires to be kept with ferrules but not terminated at the terminal blocks iii) Check all the valves in the SF6 pipe line are tightened, dilo coupling are tightened.

    11. Slow and power closing operation and opening done. (wherever applicable)

    12. Operating System

    a) Closing

    i). Hydraulic ii).

    Spring

    iii). Pneumatic b) Opening

    i). Hydraulic ii). Spring iii). Pneumatic

    12.1. HYDRAULIC SYSTEM

    12.1.1. ACCUMULATOR

    a) Make

    b) Serial No: Rph: YPh BPh

    c) Type

    d) Year of Manufacture

    12.1.2. PUMP DETAILS

    a) Make b) Type c) Sl. No d) Volt e) Ampere f) HP/KW g) Year of Manufacture

    12.1.3. DETAILS OF RELAYS/CONTACTORS USED: SCHEMATIC DRAWING NO :____________

    CIRCUIT REFERENCE MAKE Serial No. TYPE NO + NC

    Oil Pressure monitor

    Closing lockout

  • 8/13/2019 Precommissioning Test Format

    35/72

    Page 35 of 72

    Auto reclosing lockout

    General lockout

    AntiPumping contactor

    Pole discrepancy timer

    Auxiliary

    Power contactor

    Others

    12.1.4. OPERATION CHECK:

    Date of filling hydraulic oil: ____________________

    Type of hydraulic oil: _____________________

    Venting of Hydraulic System is done:

    a) Pump ___________________

    b) Pilot Valve ___________________

    c) Accumulator ___________________

    d) Hydraulic Mechanism ___________________

    PREFILLING PRESSURE OF N2 FACTORY TEST SITE TEST

    IN ACCUMULATOR ( BAR at Deg.C) _______at 0

    C ______at 0

    C

    Pump running time for charging

    Hydraulic system from initial pressure _________ MIN ________

    to working pressure

    CHECKING SAFETY VALVE (OPEN/CLOSE) _________ BAR ________

    HYDRAULIC PRESSURE DROP FOR 1 HR

    BREAKER ON POSITION _________ BAR _______

    BREAKER OFF POSITION _________ BAR _______

    OIL PRESSURE MONITOR

    PUMP ON / OFF BAR _________ BAR _______

    PUMP RUNNING TIME _________ SEC _______

    AUTO RECLOSING LOCKOUT (OIL)

  • 8/13/2019 Precommissioning Test Format

    36/72

    Page 36 of 72

    FACTORY TEST SITE TEST

    PRESSURE CONTACT __________MAKE/BREAK _________ BAR _______

    CLOSING LOCKOUT (OIL)

    PRESSURE CONTACT __________MAKE/BREAK _________ BAR _______

    GENERAL LOCKOUT (OIL)

    PRESSURE CONTACT __________MAKE/BREAK _________ BAR _______

    CHECKING ANTI PUMPING CONTACTOR

    PRESSURE CONTACT __________MAKE/BREAK OK / NOT OK

    CHECKING LOSS OF NITROGEN

    PRESSURE CONTACT __________MAKE/BREAK OK / NOT OK

    12.1.5. OIL PRESSURE DROP DURING OPERATIONS AND PUMP RUNNING TIME IN SECONDS

    Sl

    No

    Description Factory Test

    Value

    Site Test

    Value

    1 Pressure before operation, BAR

    Pressure after Closing operation, BAR

    Pump running time, Sec

    2 Pressure before operation, BAR

    Pressure after Opening operation, BAR

    Pump running time, Sec

    3 Pressure before operation, BAR

    Pressure after Close/Open operation, BAR

    Pump running time, Sec 4 Pressure before operation, BAR

    Pressure after Open Close Open operation, BAR

    Pump running time, Sec

    12.2. SPRING OPERATING SYSTEM

    12.2.1. MOTOR DETAILS:

    Make: Type: Serial No:

    Volt: Ampere: HP/KW:

  • 8/13/2019 Precommissioning Test Format

    37/72

    Page 37 of 72

    Thermal Overload Setting:

    DC current taken by Motor for charging the Spring _______________Amp

    12.2.2. DETAILS OF RELAYS/CONTACTORS USED: SCHEMATIC DRAWING NO :____________

    CIRCUIT REFERENCE MAKE Serial No. TYPE NO + NC

    Oil Pressure monitor

    Closing lockout

    Auto reclosing lockout

    General lockout

    AntiPumping contactor

    Pole discrepancy timer

    Auxiliary

    Power contactor

    Others

    12.2.3. SPRING OPERATING TIME:

    TIME TAKEN BY THE SPRING TO CHARGE FULLY AFTER CLOSING OF BREAKER

    DETAILS R PHASE YPHASE BPHASE

    Factory Site Factory Site Factory Site Charging time

    13. SF6 DENSITY MONITOR DETAILS

    Quantity of SF6 Gas Filled

    Make ACTUAL AS PER SPEC Remark

    Model RPh YPh BPh RPh YPh BPh

    Serial No Rph:

    Yph:

    BPh:

    13.1. SF6 DENSITY MONITOR SETTINGS

    PHASE DETAILS BLOCKING DEBLOCKING SF6 GAS FILLED AT

    __________BAR

    AT _________ 0C ON

    ____/_____/_____

    Factory Site Factory Site

    RPH Refill Alarm

    Operation Block

  • 8/13/2019 Precommissioning Test Format

    38/72

    Page 38 of 72

    YPH Refill Alarm

    Operation Block

    BPH Refill Alarm

    Operation Block

    13.2. MEASUREMENT OF DEW POINT OF SF6 GAS :

    SL NO Description Measured Value

    Minimum value of Dew Point as

    per SF6 Gas supplier/Manufacturer

    of CB

    NOTE: Dew point measurement of SF6 gas needs to be done pole wise in close loop method without any wastage of sf6 gas.

    13.3. LEAKAGE CHECK:

    Sl No Description PHASE

    RPhase YPhase BPhase

    A Initial filling of SF6 Gas at _____0C

    (AS per Temp. correction chart) _____BAR _____BAR _____BAR

    B Drop in SF6 Gas Pressure in 24 Hrs _____BAR _____BAR _____BAR

    C Filling pressure at ________ 0C (After all testing)

    _____BAR _____BAR _____BAR

    D Additional leakage test by covering Individual joint with Polythene

    Yes / No Yes / No Yes / No

    14. COIL RESISTANCE MEASUREMENT:

    SL NO PHASE COIL MEASURED VALUE ()

    SERIES RESISTOR ()

    TOTAL ()

    A RPhase TRIP COIL I TRIP COIL II CLOSE COIL

    B Y Phase TRIP COIL I TRIP COIL II CLOSE COIL

    C BPhase TRIP COIL I TRIP COIL II CLOSE COIL

    15. CIRCUITARY / OPEARTIONAL CHECKS:

  • 8/13/2019 Precommissioning Test Format

    39/72

    Page 39 of 72

    SL NO CIRCUIT REFERENCE CIRCUITRY CHECK OPERATIONAL CHECK LOCAL REMOTE LOCAL REMOTE

    A Tripping through TCI B Tripping through TCII C Closing circuit

    D ANTI PUMPING OPERATION (Close Open operation)

    E POLE Discrepancy feature F Breaker Position Indication G Heater in Switch Cubicle H Heater in Control Cubicle I Illumination in Switch Cubicle J Illumination in Control Cubicle

    NOTE : In case wiring for remote operation is not ready, please indicate terminal number along

    with wire ferrule number in switch cubicle where remote cables shall be terminated. Remote operation can be checked from these terminals.

    16. OPERATING TIME ( IN MILLISECONDS ):

    PHASE BREAK CLOSE OPEN CLOSE OPEN USING TRIPI TRIPII TRIPI TRIPII

    RPH Main Contact BREAKI RPH PIR

    AUXILIARY Contact RPH Main Contact

    BREAKII RPH PIR AUXILIARY Contact YPH Main Contact

    BREAKI YPH PIR AUXILIARY Contact YPH Main Contact

    BREAKII YPH PIR AUXILIARY Contact BPH Main Contact

    BREAKI BPH PIR AUXILIARY Contact

    BPH Main Contact BREAKII BPH PIR AUXILIARY Contact

    17. IR VALUE OF CONTROL CIRCUIT: (Use 500 V Megger)

    Before Meggering isolate DC for Trip Coil I & II and Closing Coil

    COIL DETAIL MEASURED VALUE (M)

    RPhase Trip Coil I

    RPhase Trip Coil II

    RPhase Closing Coil II

  • 8/13/2019 Precommissioning Test Format

    40/72

    Page 40 of 72

    YPhase Trip Coil I

    YPhase Trip Coil II

    YPhase Closing Coil II

    BPhase Trip Coil I

    BPhase Trip Coil II

    BPhase Closing Coil II

    18. IR VALUE WITH BREAKER OPEN: (Using 5000 V Megger)

    ACROSS OPEN CONTACT MEASUREMENT VALUE (M) RPhase Break I RPhase Break II YPhase Break I YPhase Break II BPhase Break I BPhase Break II

    19. IR VALUE WITH RESPECT TO EARTH WITH BREAKER CLOSED, EARTH SWITCH AND ISOLATOR

    OPEN : (USING 5000 VOLT MEGGER)

    BETWEEN MEASUREMENT VALUE (M)

    RPHASE and EARTH

    YPHASE and EARTH BPHASE and EARTH

    20. MINIMUM PICKUP VOLTAGE OF COILS:

    COIL DETAILS MEASUREMENT VALUE (V) RPhase Trip Coil I RPhase Trip Coil II

    RPhase Closing Coil

    YPhase Trip Coil I YPhase Trip Coil II

    YPhase Closing Coil BPhase Trip Coil I

    BPhase Trip Coil II

    BPhase Closing Coil

    21. GRADING CAPACITOR:

    21.1. DETAILS

  • 8/13/2019 Precommissioning Test Format

    41/72

    Page 41 of 72

    DETAILS INTERRUPTER 1 INTERRUPTER 2

    R Y B R Y B

    MAKE

    Serial No.

    Capacitance value

    Year of Manufacture

    21.2. CAPACITANCE AND TAN DELTA MEASUREMENT: (To be done on UST mode)

    DESCRIPTION INTERRUPTER 1 INTERRUPTER 2

    R Y B R Y B

    CAPACITANCE:

    SITE

    FACTORY

    TAN DELTA:

    FACTORY

    SITE

    22. CONTACT RESISTANCE MEASUREMENT:

    SL

    NO

    PHASE ACROSS EACH POLE INTERRUPTER 1 INTERRUPTER 2

    FACTORY SITE FACTORY SITE FACTORY SITE

    1 RPhase

    2 YPhase

    3 BPhase

    23. BREAKER OPERATION COUNTER READING:

    Sl No

    PHASE COUNTER TYPE

    READING DATE

    ELECTRICAL MECHANICAL1 RPhase 2 YPhase 3 BPhase

    24. CHECK FOR ANNUNCIATION IN CONTROL ROOM:

    (As per the following formats and record the reading)

  • 8/13/2019 Precommissioning Test Format

    42/72

    Page 42 of 72

    Sl NO

    DESCRIPTION OF TEST

    SOURCE OF INITIATION

    WINDOW/HMI DESCRIPTION

    RESULT REMARKS OK NOT

    OK 1 Switch off the DC

    source in control

    cubicle

    Control cubicle DC

    Switch ON/OFF

    Source I/II DC Fail, AC Fail

    2 Switch off the AC source in control cubicle

    Control cubicle AC Switch ON/OFF

    Source I/II DC Fail, AC Fail

    3 Short the ALARM contacts of SF6 GAS Density Monitor R Phase DENSITY

    MONITOR SF6 GAS DENSITY LOW

    YPhase DENSITY MONITOR

    SF6 GAS DENSITY LOW

    BPhase DENSITY MONITOR

    SF6 GAS DENSITY LOW

    4 Remove the cable connected to Density Monitor RPhase DENSITY

    MONITOR OPERATION/CLOSING LOCKOUT

    YPhase DENSITY MONITOR

    OPERATION/CLOSING LOCKOUT

    BPhase DENSITY MONITOR

    OPERATION/CLOSING LOCKOUT

    5 Give Tripping command to RPh only and check the operation of Pole Discrepancy Relay

    PD Relay at CB Cubicle

    Breaker Pole Discrepancy

    6 Give Tripping command to YPh only and check the operation of Pole Discrepancy Relay

    PD Relay at CB Cubicle

    Breaker Pole Discrepancy

    7 Give Tripping command to YPh only and check the operation of Pole Discrepancy Relay

    PD Relay at CB Cubicle

    Breaker Pole Discrepancy

    8 Close the breaker and Trip through Protection which are applicable

    Protection relay as per scheme

    Breaker Auto Trip

    NOTE: The tripping details are to be checked as per the Scheme approved by design.

    25. Operation time measurement of pole discrepancy relay:

    26.

    Mechanical close interlock checked (wherever applicable): Yes / No

  • 8/13/2019 Precommissioning Test Format

    43/72

  • 8/13/2019 Precommissioning Test Format

    44/72

  • 8/13/2019 Precommissioning Test Format

    45/72

    Page 45 of 72

    vii). All fittings as per Out line General Arrangement drawing.

    viii). Levelling and alignment of structure and base frame is checked

    ix). Erection completion certificate along

    with list of outstanding activities Reviewed

    x). Any paint removed / scratched in transit has been touched up

    xi). Check primary polarity of CT,s erected as per relevant drawing.

    xii). Check hermetically sealing is intact

    xiii). Check the oil level and leakage through any joints / Sec. Terminals

    xiv). Check oil drain valve is properly

    Closed and locked. xv). Oil Level & Oil sampling

    xvi). N2 pressure checked (wherever applicable)

    xvii). Oil level on top chamber gauge glass

    xviii). BDV of oil sample taken from tank bottom drain valve ( only if Nitrogen Pressure is measured zero )

    xix). All the cable identification tags provided and all cores are provided with identification ferrules at M.B.

    xx). Check secondary cable end box is properly fixed and ensure cable entry at the bottom and unused holes sealed

    xxi). Ensure interpole cabling is completed And check the continuity.

    xxii). Check the IR value of secondary cable

    xxiii). Check external cabling from junction box to relay / control panel completed

    xxiv). Ensure unused secondary cores, if any, has been shorted

    xxv). Check star point has been formed properly and grounded at one end only

    xxvi). Check spark gap setting in P1 terminal (wherever provided/ possible) Permanent pole levelling and identification markings made

    xxvii). Check TAN DELTA test tap is properly earthed

    xxviii). Check that lugs used in secondary circuit are of ring type

    xxix). Check direction of PRIMARY (P1/ P2) w.r.t.

  • 8/13/2019 Precommissioning Test Format

    46/72

    Page 46 of 72

    BUS/LINE on erection xxx). Provision of bimetallic strips (Cu +AL)

    ensured wherever applicable

    2.0 INSULATION RESISTANCE MEASUREMENT: ( USING 5KV MEGGER)

    Sl No. of Megger:

    Make:

    Calibration valid up to: _____/______/______

    Ambient temperature:_______ 0C

    Relative Humidity:

    NOTE: A) Remove the connected earthing to system involving CT under test

    B) Disconnect the connected terminals of CT M.Box

    C) Permissible values is 1000 M.

    SL No

    CORE PHASE RPhase (M) YPhase (M) BPhase (M)

    1 PRIMARY CORE I 2 PRIMARY CORE II 3 PRIMARY CORE III 4 PRIMARY CORE IV 5 PRIMARY CORE V 6 PRIMARY EARTH

    3.0 INSULATION RESISTANCE MEASUREMENT: (Using 500 V Megger)

    Sl No. of Megger:

    Make:

    Calibration valid up to: _____/______/______

    Ambient temperature:_______ 0C

    a)

    SL No

    CORE PHASE RPhase (M) YPhase (M) BPhase (M)

    1 CORE I Earth 2 CORE II Earth 3 CORE III Earth 4 CORE IV Earth 5 CORE V Earth 6 EARTH Earth

    b)

    SL No

    CORE PHASE RPhase (M) YPhase (M) BPhase (M)

  • 8/13/2019 Precommissioning Test Format

    47/72

  • 8/13/2019 Precommissioning Test Format

    48/72

  • 8/13/2019 Precommissioning Test Format

    49/72

    Page 49 of 72

    10 kV

    b) TAN DELTA MEASUREMENT

    VOLTAGE TAN DELTA (MEASURED VALUE) REMARKS

    RPhase YPhase BPhase

    FACTORY SITE FACTORY SITE FACTORY SITE

    2 kV

    10 kV

    8.0 CURRENT RATIO TEST

    Sl No. of Test Kit:

    Make:

    Primary Current Range: VA Burden:

    Calibration valid up to: _____/______/______

    Date of Testing: ______/______/______

    Ambient temperature:_______ 0C

    a) R PHASE

    CORE PRIMARY CURRENT SECONDARYCURRENT

    THERITICALRATIO

    ACTUAL RATIO

    % OF ERROR% ACTUAL

    COREI (1S11S2)

    20% 40% 80%

    COREII (2S1 2S2)

    20% 40% 80%

    COREIII (3S13S2)

    20% 40% 80%

    COREIV

    (4S14S2)

    20%

    40% 80%

    COREV (5S15S2)

    20% 40% 80%

    COREI (1S11S3)

    20% 40% 80%

    COREII (2S1 2S3)

    20% 40% 80%

    COREIII (3S13S3)

    20% 40%

  • 8/13/2019 Precommissioning Test Format

    50/72

    Page 50 of 72

    80% COREIV (4S14S3)

    20% 40% 80%

    COREV

    (5S15S3)

    20%

    40% 80%

    COREI (1S11S4)

    20% 40% 80%

    COREII (2S1 2S4)

    20% 40% 80%

    COREIII (3S13S4)

    20% 40% 80%

    COREIV (4S14S4)

    20% 40% 80%

    COREV (5S15S4)

    20% 40% 80%

    b) Y PHASE

    CORE PRIMARY CURRENT SECONDARYCURRENT

    THERITICALRATIO

    ACTUAL RATIO

    % OF ERROR

    % ACTUAL COREI (1S11S2)

    20% 40% 80%

    COREII (2S1 2S2)

    20% 40% 80%

    COREIII (3S13S2)

    20% 40% 80%

    COREIV

    (4S14S2)

    20%

    40% 80%

    COREV (5S15S2)

    20% 40% 80%

    COREI (1S11S3)

    20% 40% 80%

    COREII (2S1 2S3)

    20% 40% 80%

    COREIII (3S13S3)

    20% 40%

  • 8/13/2019 Precommissioning Test Format

    51/72

    Page 51 of 72

    80% COREIV (4S14S3)

    20% 40% 80%

    COREV

    (5S15S3)

    20%

    40% 80%

    COREI (1S11S4)

    20% 40% 80%

    COREII (2S1 2S4)

    20% 40% 80%

    COREIII (3S13S4)

    20% 40% 80%

    COREIV (4S14S4)

    20% 40% 80%

    COREV (5S15S4)

    20% 40% 80%

    c) BPHASE

    CORE PRIMARY CURRENT SECONDARYCURRENT

    THERITICALRATIO

    ACTUAL RATIO

    % OF ERROR

    % ACTUAL COREI (1S11S2)

    20% 40% 80%

    COREII (2S1 2S2)

    20% 40% 80%

    COREIII (3S13S2)

    20% 40% 80%

    COREIV

    (4S14S2)

    20%

    40% 80%

    COREV (5S15S2)

    20% 40% 80%

    COREI (1S11S3)

    20% 40% 80%

    COREII (2S1 2S3)

    20% 40% 80%

    COREIII (3S13S3)

    20% 40%

  • 8/13/2019 Precommissioning Test Format

    52/72

    Page 52 of 72

    80% COREIV (4S14S3)

    20% 40% 80%

    COREV

    (5S15S3)

    20%

    40% 80%

    COREI (1S11S4)

    20% 40% 80%

    COREII (2S1 2S4)

    20% 40% 80%

    COREIII (3S13S4)

    20% 40% 80%

    COREIV (4S14S4)

    20% 40% 80%

    COREV (5S15S4)

    20% 40% 80%

    9.0 MAGNETISING CURVES PERFORMANCE

    KNEE POINT VOLTAGE ( KVp ) _______________ VOLT

    Sl No. of Test Kit:

    Make:

    Calibration valid up to: _____/______/______

    Date of Testing: ______/______/______

    Ambient temperature:_______ 0C

    a) R PHASE

    VOLTAGE CURRENT MEASUREMENT (mA) To be

    applied

    Actual

    Value

    COREI COREII COREIII COREIV COREV

    1S11S2 2S1 2S2 3S13S2 4S14S2 5S15S2 0.25xKVP Not to

    apply for Metering Core

    0.5xKVP 0.75xKVP 1.00xKVP 1.10xKVP

    b) Y PHASE

    VOLTAGE CURRENT MEASUREMENT (mA) To be applied

    Actual Value

    COREI COREII COREIII COREIV COREV 1S11S2 2S1 2S2 3S13S2 4S14S2 5S15S2

    0.25xKVP Not to

  • 8/13/2019 Precommissioning Test Format

    53/72

    Page 53 of 72

    0.5xKVP apply for Metering Core

    0.75xKVP 1.00xKVP 1.10xKVP

    c) B PHASE

    VOLTAGE CURRENT MEASUREMENT (mA) To be applied

    Actual Value

    COREI COREII COREIII COREIV COREV 1S11S2 2S1 2S2 3S13S2 4S14S2 5S15S2

    0.25xKVP Not to apply for Metering Core

    0.5xKVP 0.75xKVP 1.00xKVP 1.10xKVP

    NOTE :

    1.0 CT should not saturate at 110 % of knee point voltage ( KVp )

    2.0 If knee point voltage is not mentioned then knee point current may be taken into

    consideration

    10.0 CONTACT RESISTANCE MEASUREMENT

    Details of Test Kit:

    CONTACT RESISTANCE RPhase ( ) YPhase( ) BPhase( )

    Across terminal P1

    Across terminal P2

    NOTE : The value of contact resistance should not be more than 10 PER JOINT /

    CONNECTOR.

    11.0 DGA TEST OF CT OIL (AFTER ONE MONTH OF COMMISSIONING)

    (Sample to be taken at 250 ml bottle)

    DISOLVE GAS RPHASE YPHASE BPHASE REMARKS Total Gas% H2 CH4 C2H4 C2H6 C2H2 CO CO2 O2 N2

  • 8/13/2019 Precommissioning Test Format

    54/72

    Page 54 of 72

    12.0 FINAL DOCUMENTATION REVIEW :

    a) Final document of pre commissioning checks Reviewed and Approved: YES / NO

    b) Documents regarding spares, equipment, O& M Manuals etc. available at site for o & m purpose: YES / NO

    c) After modification, if any, "as built drawings" are available at site: YES / NO

    Signature: Signature: Signature: Signature Name: Name: Name: Name:

    Designation: Designation: Designation: Designation: (Supplier Rep) Erection Agency: Site I/C, AEGCL T & C, AEGCL

  • 8/13/2019 Precommissioning Test Format

    55/72

    Page 55 of 72

    ASSAM ELECTRICITY GRID CORPORATION LIMITED

    PRECOMMISSIONING OF CAPACITOR VOLTAGE TRANSFORMER

    COMMISSIONING FORMATS

    DOC NO: SUBSTATION:

    BAY NAME / NO:

    DATE OF ERECTION: DATE OF ENERZIZATION:

    Voltage level, kV 132 220 400

    DETAILS OF EQUIPMENT:

    DESCRIPTION RPHASE YPHASE BPHASE PURCHASE ORDER NO MAKE TYPE SERIAL NO CAPACITANCE (pF)

    SECONDARY DETAILS:

    DESCRIPTION WINDINGI WINDINGII WINDINGIII VOLTAGE (V) VA BURDEN (VA) CLASS PURPOSE

    1.0 DETAILS OF CHECK LIST:

    SL No

    DESCRIPTION STATUS REMARKS RECORD DEFICENCIES, IF ANY

    YES NO

    i). Equipment is cleaned and free from Dust / Dirt foreign materials etc.

    ii). Equipment is free from all visible defects on physical inspection

    iii). Check CVT tank has been provided With double earthing

    iv). Check that CVT Marshalling Box is earthed v). All nuts and bolts are tightened

    correctly as per specified torque vi). Check tightness of terminal connector vii). All fittings as per Out line

    General Arrangement drawing.

  • 8/13/2019 Precommissioning Test Format

    56/72

    Page 56 of 72

    viii). Levelling and Identification marking is carried out.

    ix). Levelling and alignment of structure and base frame is checked

    x). Erection completion certificate along

    with list of outstanding activities Reviewed

    xi). Any paint removed / scratched in transit has been touched up

    xii). Sl. No of HV CAPACITOR identical to the Sl.no mentioned on RATING & DIG. PLATE

    xiii). Ensure brass vent plug between stacks of CVT's is removed

    xiv). Check the oil level and leakage through any joints / Sec. Terminals

    xv). Check oil drain valve is properly

    Closed and locked. xvi). Oil Level on tank Gauge Glass xvii). BDV of oil sample taken from tank

    bottom drain valve xviii). Check secondary cable end box is

    properly fixed and ensure cable entry at the bottom and unused holes sealed

    xix). Ensure H.F terminal of unused phases has been earthed and no load on H.F terminal bushing

    xx). Check RATING / HEALTHINESS of Fuses at CVT M.B and CVT terminal box.

    xxi). Check that the neutral point is earthed xxii). Ensure interpole cabling is completed

    and check the continuity xxiii). Check the IR value of secondary cable xxiv). Check external cabling from junction box to

    relay / control panel completed xxv). All the cable identification tags provided and

    all cores are provided with identification ferrules at M.B.

    2.0 CONTINUITY OF WINDING: (After removing Earth Link 1, 2 & 3)

    Sl No BETWEEN TERMINAL OK NOT OK A 1a 1n B 2a 2n C 3a 3n

    3.0 INSULATION RESISTANCE MEASUREMENT: (Using 5 kV Megger)

    Details of Megger:

  • 8/13/2019 Precommissioning Test Format

    57/72

    Page 57 of 72

    SL No: Type: Make:

    Ambient Temperature: __________ 0C

    Sl No BETWEEN MEASURED VALUE (M) R Phase Y Phase B Phase

    i) Primary Secondary CORE 1 ii) Primary Secondary CORE 2 iii) Primary Secondary CORE 3 iv) Primary Earth

    4.0 INSULATION RESISTANCE MEASUREMENT: (Using 500 V Megger)

    Details of Megger:

    Sl No BETWEEN MEASURED VALUE (M) R Phase Y Phase B Phase

    i) Secondary CORE 1 Earth ii) Secondary CORE 2 Earth iii) Secondary CORE 3 Earth iv) CORE 1 CORE 2 v) CORE 1 CORE 3 vi) CORE 2 CORE 3

    5.0 VOLTAGE RATIO TEST:

    Details of Testing Instruments:

    PHASE PRIMARY SECONDARY VOLTAGE THEORITICALRATIO

    ACTUAL RATIO % ERROR Between Value FACTORY SITE

    R 1a 1n

    2a 2n

    3a 3n

    Y 1a 1n 2a 2n 3a 3n

    B

    1a 1n

    2a 2n 3a 3n

    NOTE : 1. Apply voltage of the order of 500 V or more across line capacitor ( top flange ) to earth link 2. Ensure all earth links connected

    6.0 TAN DELTA AND CAPACITANCE MEASUREMENT

    Sl No. of Test Kit:

    Make:

  • 8/13/2019 Precommissioning Test Format

    58/72

    Page 58 of 72

    Serial No:

    Calibration valid up to: _____/______/______

    Date of Testing: ______/______/______

    Ambient temperature:_______ 0C

    a) CAPACITANCE MEASRUEMENT

    VOLTAGE CAPACITANCE (MEASURED VALUE) REMARKS

    RPhase YPhase BPhase

    FACTORY SITE FACTORY SITE FACTORY SITE

    2 kV

    10 kV

    a) TAN DELTA MEASUREMENT

    VOLTAGE TAN DELTA (MEASURED VALUE) REMARKS

    RPhase YPhase BPhase

    FACTORY SITE FACTORY SITE FACTORY SITE

    2 kV

    10 kV

    7.0 FINAL DOCUMENTATION REVIEW :

    d) Final document of pre commissioning checks Reviewed and Approved: YES / NO

    e) Documents regarding spares, equipment, O& M Manuals etc. available at site for o & m purpose: YES / NO

    f) After modification, if any, "as built drawings" are available at site: YES / NO

    Signature: Signature: Signature: Signature Name: Name: Name: Name: Designation: Designation: Designation: Designation: (Supplier Rep) Erection Agency: Site I/C, AEGCL T & C, AEGCL

  • 8/13/2019 Precommissioning Test Format

    59/72

    Page 59 of 72

    ASSAM ELECTRICITY GRID CORPORATION LIMITED

    PRECOMMISSIONING OF SURGE ARRESTER

    COMMISSIONING FORMATS

    DOC NO: SUBSTATION:

    BAY NAME / NO:

    DATE OF ERECTION: DATE OF ENERZIZATION:

    Voltage level, kV 33 132 220 400

    DETAILS OF EQUIPMENT:

    DESCRIPTION RPHASE YPHASE BPHASE PURCHASE ORDER NO MAKE TYPE SERIAL NO RATING

    1.0 DETAILS: CHECK LIST / TESTING

    SL No

    DESCRIPTION STATUS REMARKS RECORD DEFICENCIES, IF ANY

    YES NO

    i). Equipment is cleaned and free from Dust / Dirt foreign materials etc.

    ii). Equipment is free from all visible defects on physical inspection

    iii). Support structures have been provided with double earth

    iv). All nuts and bolts are tightened correctly as per specified torque

    v). Equipment erection is complete in all respect (ATTACH REMAINING ACTIVITIES,IF ANY)

    vi). Levelling and Identification marking is carried out.

    vii). Levelling and alignment of structure and base frame is checked

    viii). All insulators & Surge counter are free from any physical defects

    ix). Check tightness of all nuts & bolts and terminal connector

    x). Erection completion certificate along with list of outstanding activities

  • 8/13/2019 Precommissioning Test Format

    60/72

    Page 60 of 72

    reviewed xi). Check one end of surge counter is connected

    to the bottom of la stack and one end of surge counter has been earth

    xii). The direction of the exhaust vent ports away

    from the protected equipment and other arrester poles

    xiii). Clearance from the arrester to earthed objects and from the arrester pole to another arrester pole maintained as per Outline drawing and all erection has been done as per approved drawing.

    xiv). Check the serial no. and sequence of LA parts for erection in multi stack LA

    xv). Check the alignment of Corona Ring xvi). Check on charging, the Surge Counter

    pointer is in green zone

    2.0 INSULATION RESISTANCE MEASUREMENT: (Using 5 kV Megger)

    Sl No. of Test Kit:

    Make:

    Calibration valid up to: _____/______/______

    Date of Testing: ______/______/______

    Ambient temperature:_______0C

    Sl No BETWEEN PHASE RPhase (M) YPhase (M) BPhase (M)

    a 1st Stack Earth b 2nd Stack Earth c 3 rd Stack Earth d 4 th Stack Earth e 5 th Stack Earth

    f 6th

    Stack Earth

    3.0 SURGE COUNTER READING:

    Sl No READING PHASE RPhase YPhase BPhase

    a Counter Serial No. b Counter Make c Counter Reading

    4.0 CAPACITANCE & TAN DELTA MEASUREMENT:

  • 8/13/2019 Precommissioning Test Format

    61/72

    Page 61 of 72

    Sl No. of Test Kit:

    Make:

    Calibration valid up to: _____/______/______

    Date of Testing: ______/______/______

    Ambient temperature:_______ 0C

    VOLTAGE STACK CAPACITANCE TAN DELTA REMARKS 2 kV TOP

    MIDDLE 1 MIDDLE 2 BOTTOM

    10 kV TOP MIDDLE 1 MIDDLE 2 BOTTOM

    5.0 CHECKING OF HEALTHINESS OF SURGE MONITOR : OK / NOT OK

    6.0 FINAL DOCUMENTATION REVIEW :

    g) Final document of pre commissioning checks Reviewed and Approved: YES / NO

    h) Documents regarding spares, equipment, O& M Manuals etc. available at site for o & m purpose: YES / NO

    i) After modification, if any, "as built drawings" are available at site: YES / NO

    Signature: Signature: Signature: Signature Name: Name: Name: Name: Designation: Designation: Designation: Designation: (Supplier Rep) Erection Agency: Site I/C, AEGCL T & C, AEGCL

  • 8/13/2019 Precommissioning Test Format

    62/72

    Page 62 of 72

    ASSAM ELECTRICITY GRID CORPORATION LIMITED

    PRECOMMISSIONING OF 220 kV LINE RELAY & CONTROL PANEL

    COMMISSIONING FORMATS

    DOC NO: SUBSTATION:

    BAY NAME / NO:

    DATE OF ERECTION: DATE OF ENERZIZATION:

    Voltage level, kV 33 132 220 400

    DETAILS OF EQUIPMENT:

    Make: Year of Manufacture:

    Purchase Order No:

    Type of Panel: Swing Simplex/Simplex/Duplex DC Auxiliary Voltage:

    Panel Overall Dimensions:

    Relay Specifications Details:

    Sl No

    Relay Type Make Relay Ordering Code

    Relay Compatibility

    Type & Nos. of Communication Ports

    No. of Analogue Channel

    Nos. of BI & BO

    IEC 61850

    Modbus RJ 45 Serial BI BO

    1 Main 1 2 Main 2 3 Line

    Differential

    1.0 DETAILS: CHECK LIST / TESTING

    a. Wiring

    Sl No

    As per norms Yes No Remarks

    1 Wiring done using PVC insulated 650 grade single-core multi strands annealed copper conductor flexiblewire.

    2 2.5 Sqmm Red, Yellow, Blue & Black for CT Circuit3 2.5 Sqmm Red, Yellow, Blue & Black for PT Circuit4 2.5 Sqmm for 240V AC circuits5 1.5 Sqmm Grey for DC circuits

  • 8/13/2019 Precommissioning Test Format

    63/72

    Page 63 of 72

    6 1.5 Sqmm Black for AC circuits7 2.5 Sqmm Green for Earthing Circuit

    b. EARTHING:

    Sl No

    As per norms Yes No Remarks

    1 1 no. Copper Bar of size 25 x 6 mm will be runthroughout the board

    2 Earthing between equipments will be looped &finally terminated in Earth bar

    3 Earth bar coupling link of copper will be provided between adjacent panels

    c. AC DISTRIBUTION:

    Sl No

    As per norms Yes No Remarks

    1 Checking of AC Supervision Relay2

    d. DC DISTRIBUTION

    e. VOLTAGE SELECTION RELAYS

    Sl No

    As per norms Yes No Remarks

    1 75 A2 75 B

    3 Check VTSS (BPT-LPT)

    Sl No

    As per norms Yes No Remarks

    1 Checking of DC Supervision Relay2 Source-13 Source-24 Changeover between Sources

    a) Electro Mechanical switch b) Through changeover relays

  • 8/13/2019 Precommissioning Test Format

    64/72

    Page 64 of 72

    f. METERING CIRCUIT

    Sl No

    As per norms Yes No Remarks

    1 W Meter2 VAR Meter3 V Meter4 A Meter5 TVM Meter

    g. SYNCHRONISING CIRCUIT

    Sl

    No

    As per norms Yes No Remarks

    1 Bus PT Supply Circuit2 Line CVT Supply Circuit

    h. CT CIRCUIT

    Sl No

    As per norms Yes No Remarks

    1 Metering CircuitStar PointContinuityEarthing should be either at CT JB or at Panel end

    2 Main Protection CircuitStar PointContinuityEarthing should be either at CT JB or at Panel end

    3 B/U Protection CircuitStar PointContinuityEarthing should be either at CT JB or at Panel end

    4 BBP Protection CircuitStar PointContinuityEarthing should be either at CT JB or at Panel end

    i. Input Circuit

  • 8/13/2019 Precommissioning Test Format

    65/72

    Page 65 of 72

    Sl No

    As per norms Yes No Remarks

    1 Main/TBC CB R phase Open2 Main/TBC CB Y phase Open3 Main/TBC CB B phase Open4 Main/TBC CB Ready for A/R5 Carrier Out of Service

    Sl No

    As per norms Yes No Remarks

    6 External LBB/ A/R InitiationR phaseY phaseB phase

    7 A/R Switch ON8 Carrier Channel I Healthy

    Carrier Channel II Healthy9 Carrier Channel I Received10 SOTF Initiation11 A/R Block12 Main CB Open Status

    R phaseY phase

    B phase13 TBC CB Open StatusR phaseY phaseB phase

    14 Main CB Ready for A/R15 TBC CB Ready for A/R

    j. Carrier circuit

    Sl No

    As per norms Yes No Remarks

    1 Carrier Channel I Received2 Carrier Channel I Healthy3 Carrier Channel I Send

    Carrier Channel II Send4 Carrier Channel II Received5 Carrier Channel II Healthy6 Carrier Channel I Send

    Carrier Channel II Send7 Direct Trip Received

    Channel I

  • 8/13/2019 Precommissioning Test Format

    66/72

    Page 66 of 72

    Channel II8 Direct Trip Send

    Channel IChannel II

    910

    k. Single Phase/ Three Phase Initiation Circuit

    Sl No

    As per norms Yes No Remarks

    1 1 Trip R- : 86 R11 Trip Y- : 86 Y11 Trip B- : 86 B1

    2 1 Trip R- : 86 R21 Trip Y- : 86 Y21 Trip B- : 86 B2

    3 Master Trip Relay : 86 A OptdDistance Prot Optd.B/U Protection Optd.DT Received Ch-IDT Received Ch-II

    Master Trip Relay : 86 B OptdDistance Prot Optd.B/U Protection Optd.DT Received Ch-IDT Received Ch-II

    4 Auxiliary Trip Relay: 86 X (RL-1) Optd.Auxiliary Trip Relay: 86 X (RL-2) Optd.

    l. LBB Trip Relay Circuit

    Sl No

    As per norms Yes No Remarks

    1 LBB -96 Realy Optd.2 Check all the Trip Extensions as per scheme

    i)ii)iii)iv)

    v)vi)

  • 8/13/2019 Precommissioning Test Format

    67/72

    Page 67 of 72

    vii)

    m. CB Closing & Manual Trip Circuit

    Sl No

    As per norms Yes No Remarks

    1 DC Supply-1 to CBDC Supply-2 to CB

    2 Auto Reclose/ Remote Close3 Manual Trip-1 (TC-1)/ (TC-2)

    n. CB TC-1 / TC 2 Circuit (Protection Trip/Post Close Supn) & Pre CloseSupervision

    Sl No

    As per norms Yes No Remarks

    1 1- Optd. From Main Prot. Relay

    2 Group A Trip Optd.

    Group B Trip Optd.

    3 LBB/ BB Optd.

    4 195 R

    195 Y

    195 B

    o. TTX Contact Multiplication Circuit (Related to TTS)

  • 8/13/2019 Precommissioning Test Format

    68/72

    Page 68 of 72

    Sl No

    As per norms Yes No Remarks

    1 TTX 1

    TTX 2

    TTX3

    2

    p. TBC TRIPPING CIRCUITSl

    NoAs per norms Yes No Remarks

    1 86 A Extension

    86 B extension

    1- Trip Optd. From Main Protection RelayR

    Y

    B

    2 To LBB Initiation TBC

    86 R1

    86 Y1

    86 B1

    86 R2

    86 Y2

    86 B2

    q. ISOLATOR CONTROL CIRCUIT

    Sl No

    As per norms Yes No Remarks

    1 89 A Close

  • 8/13/2019 Precommissioning Test Format

    69/72

    Page 69 of 72

    89 A Open

    89 B Close

    89 B Open

    89 C Close

    89 C Open

    89 D Close

    89 D Open

    r. INDICATION CIRCUITSl

    NoAs per norms Yes No Remarks

    1 CB OpenCB CloseCB Auto TripCB Spring Charged89 A Open89 B Close89 B Open89 BE Close

    89 BE Open89 C Close89 C Open89 D Close89 D Open89 DE1 Close89 DE1 Open89 DE2 Close89 DE2 Open

    2 Line Hot R- Healthy

    Line Hot Y- HealthyLine Hot B- Healthy

    s. ANNUNCIATION CIRCUITSl

    NoAs per norms Yes No Remarks

    1 DC Fail2 AC Fail3 Main Dist Prot. Optd.4 O/C & E/F Optd.5 DEF/ SOTF Optd.

  • 8/13/2019 Precommissioning Test Format

    70/72

    Page 70 of 72

    6 Carrier CH-I & II Fail7 A/R Optd.8 Power Swing Detected9 Panel AC Supply Fail10 LBB/BB Optd.11 Numerical Relay Faulty12 DT Received Ch-I & II13 CB TC-1 faulty14 CB TC-2 faulty15 SF6 Low Alarm16 SF6 Lock Out

    t. Main Distance Protection Relay

    Sl No

    As per norms Yes No Remarks

    1 Check CT Circuit (If any Mismatch)

    2 Check PT Circuit (If any Mismatch)

    3 Zone Reach Test

    4 LBB

    5 SOTF Optd.

    6 Carrier Send

    7 A/Ri) AR Optd

  • 8/13/2019 Precommissioning Test Format

    71/72

  • 8/13/2019 Precommissioning Test Format

    72/72

    20 High Set

    v. ISOLATOR INTERLOCK CIRCUIT

    Sl No

    As per norms Yes No Remarks

    1 89 A Interlock

    2 89 B Interlock

    3 89 BE Interlock

    4 89 DE1 Interlock

    5 89 DE2 Interlock

    6 89 D Interlock

    7 89 C Interlock