Page 1: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Pre-Proposal Meeting

REQUEST FOR PROPOSALS (RFP)

SOLID WASTE MANAGEMENT SERVICES

TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY

FACILITY

RFP # 12-0084

RFP ISSUED BY NEW HANOVER CO. NC December 9, 2011

Pre-Proposal Meeting -- Dec. 15, 2011

1

Page 2: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Introduction of the County Project Team

2

Page 3: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Issuance of this County RFP

• This RFP has only been issued to the two Qualified Contractors (QC’s) that were shortlisted as a result of the RFQ process.

• The County intends to select the best Proposal in accordance with the evaluation and selection process described in Section Six and Section Seven of the RFP.

3

Page 4: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

County RFP Schedule

4

Event Date Day

RFP available w/o Draft Agreement Dec. 9, 2011 Friday

Pre-Proposal Meeting and Site Tour – 9:00 a.m.

Dec, 15, 2011 Thursday

Issuance of Draft Agreement J an, 4, 2012 Wednesday

Additional Site Inspection(s) As Coordinated w/County

As Agreed Upon -

I ssuance of County Addenda During RFP Process

As Required -

Final RFP Clarifications/Questions Due to County

J an. 31, 2012 Tuesday

Final County RFP Addendum Issued Feb. 7, 2011 Tuesday

Proposals Due, addressed to: New Hanover County Manager’s Office Attn: Mr. Bruce Shell, County Manager 230 Government Center Drive, Suite 195 Wilmington, NC 28403

Feb. 21, 2012 Tuesday

This schedule is part of Exhibit 2 of the RFP!

Page 5: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

TOC Review1. Introduction

2. Background Information on County Solid Waste System

3. Project Description

4. Contractual Conditions

5. Financing

6. Qualifications of the Proposers

7. Evaluation and Selection Process

8. Proposal Submission Requirements

9. General Requirements

10. Proposal Forms

5

Page 6: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

APPENDIX A: Definitions

APPENDIX B: Forms• Form 1: Summary of the Phase 1 Retrofit Completion Work

Costs• Form 2: Itemized Phase 1 Design Build Improvement Costs • Form 3A: Total Phase 1 Management/Operations Costs• Form 3B: Itemized Phase 1 Management/Operations Costs • Form 4: Calculation of the Phase 1 Retrofit Debt Service

Payments• Forms 5: Drawdown Schedule of Phase 1 Design Build

Improvement Costs (for Publicly Financed Option)• Form 6A: Total Phase 2 Operating Charge• Form 6B: Itemized Phase 2 Operating Charge • Form 7: Proposed Annual Service Fee for Phase 2 • Form 8: Performance Guarantees• Form 9: Development of Major Equipment Replacement

and Renewal Fund

6

Page 7: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Appendix B Continued...

• Form 10: Phase 2 Guaranteed Maximum Utility Consumption

• Form 11: Electricity Revenue Sharing Proposal• Form 12: Non-Collusion Certification • Form 13: Nondiscrimination • Form 14: Indemnification Agreement • Form 15: Disclosure • Form 16: MWBE Forms & Instructions of County• Form 17: Detailed Facility and Equipment Data• Form 18: Performance Bond Affidavit from Surety• Form 19: Letter of Credit Affidavit from Provider• Form 20: Affidavit of Qualified Contractor as Proposer• Form 21: Company/Guarantor Letter of Intent• Form 22: Letter(s) of Intent

7

Page 8: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Proposals are requested for the following:

• The finance, design, improvement, retrofitting, construction and testing of the current three-line 500 TPD SEF located at 3002 Highway 421 North in New Hanover County; and

• After acceptance testing, operate and maintain the SEF for at least 20-years.

8

Page 9: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Phase 1 Retrofit Completion Work

• For the retrofit/upgrade and start-up operations of the SEF, the County requires that the Proposer provide a firm Total Phase 1 Construction Price for all of the design improvements, retrofitting, construction, permitting (as/if needed), start-up, and testing of the upgraded SEF (on Proposal Form 1); and

• corresponding Capital Component of the Service Fee (on Proposal Form 4).

As envisioned, this work is to bring the SEF capacity back up to the 500 Tons per Day (TPD) nominal capacity, as installed.

9

Page 10: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

County Proposal Preference

• In connection with its obligations to pass the Acceptance tests, the County would prefer that the proposer take the “as is“ condition risk of the existing facility and that the price for the Phase 1 Work reflect that risk.

• However, since after over two decades of operation, the SEF was taken out of service by the County on April 4th, 2011; the County will consider optional Proposals that limit or mitigate the proposer’s “as is” conditions risk and result in a lower construction price for the Phase 1 Work. Any such Proposal must be both specific and comprehensively presented.

Note: The degree of risk shifting associated with such an optional proposal will be an important evaluation factor and such a proposal should clearly state how any as-is condition risk shifted to the County can be limited or mitigated by the County and

10

Page 11: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

RFP Appendices

• Appendix A: Definitions of terms Used in the RFP

• Appendix B: Forms• Appendix C: Draft Agreement

(expected to be issued in about 3 weeks)

11

Page 12: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Requests for Additional Information or Clarifications (see Section 1.6.2)

• Must be made in writing to the RFP Coordinator at the address below at any time but no later than 3 p.m. on January 31, 2012.

• Mr. John Hubbard

Director, Department of Environmental Management

Office: (910) 798-4403

[email protected]

12

Note: Date will be revised from 17th to 31st in Addendum No. 1

Page 13: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

SEF Aerial Photograph

13

Page 14: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

SEF Division• In 1984 the County started operating the waste-to-

energy facility now called the Sustainable Energy Facility, or SEF, which utilizes a mass-burn technology that generates steam for beneficial use.

• The SEF operates in accordance with North Carolina Department of Environment and Natural Resources (NCDENR or DENR) Solid Waste Permit No. 65-05-I.

• It is located approximately three (3) miles south of the landfill on US Highway 421 North.

• Prior to the lay-up and mothballing of the SEF in April 2011, the SEF employed 45 County personnel to operate and maintain three (3) boilers, two (2) generators, and the state-of-the-art pollution control equipment.

14

Page 15: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

SEF Technical Overview

• Two 100 ton-per-day units came on-line in 1984. The additional 300 ton-per-day unit became operational in 1991.

• The boilers produce superheated steam at 450 pounds per square inch (psi) at the header which is used to turn two (2) turbine generators.

• The two (2) generators have a combined gross capacity of 10.5 Megawatts (Mw). SEF powers itself prior to sending electricity into the grid. The interconnection equipment can receive a maximum of 10,000 KVA to the grid.

15

Page 16: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

WASTEC Throughput, Electricity and Natural Gas Consumption (Example)

16

Selected YearsWaste ReceivedWaste to WASTECAsh to Landfill

Electricity Nat. Gas Electricity Nat. Gas Electricity Nat. GasMonth (MWH) (MCF) (MWH) (MCF) (MWH) (MCF)

July 16 3,190 13 11,220 13 1,350 August 5 1,490 1 3,240 44 790

September 3 890 3 15,290 35 1,360 October 3 3,200 2 5,260 13 1,540

November 17 610 73 3,340 20 1,450 December 19 1,470 6 5,690 26 2,400

January 17 2,120 1 4,260 28 1,050 February 3 2,050 1 2,400 5 1,970 March 114 1,400 13 2,270 36 1,120 April 5 410 20 1,160 35 1,030 May 3 1,650 1 1,000 24 2,080 June 6 1,990 4 950 6 1,350

TOTAL 211 20,470 138 56,080 285 17,490

Total Utility Costs(Electricity, N.G, & Water)

(1) July and September of FY 97 high on Natural Gas use due to Hurricanes Bertha and Fran

134,136 130,632 129,604 48,791 53,564 47,530

$216,498 $418,129 $246,051 (1)

FY 96 FY 97 (1) FY 98132,250 133,400 128,029

Note: This page will be part of Addendum No. 1 Information

Page 17: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Phase 2 Guarantee

From Appendix A Definitions:

“Guaranteed Annual Throughput Capacity” means during the Phase 2 Operations Period, the Company will be able to handle at a minimum 150,000 tons/year of Solid Waste generated in the County.

17

Page 18: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

RFP Document Room

• The County has completed a variety of studies, and has compiled historical operating and maintenance data, the SEF permits and other materials which provide additional background information on the SEF for assistance in preparing any Proposal. These studies and information are accessible by the QC’s.

• Note: Instructions for accessing the RFP Document Room are set forth in Section 1.7.4.

18

Page 19: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Waste Composition Report

• A waste composition study has recently been completed by SCS for New Hanover County. A copy of the Executive Summary of that report is provided in the County on-line RFP Document Room that is accessible by the QC’s.

19

Page 20: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Section 3.1.1 Project Description

A general outline of the minimum design and/or performance criteria for the SEF, once renovated and upgraded is provided.

The Proposer must provide a retrofit facility that incorporates 23 specific items......

NOTE: Form 17 provides an extensive review of all of the key components that make up a waste-to-energy plant like the SEF. Form 17 is to be completed only for new equipment that the Company will install at the SEF as part of the Phase 1 Work. Data is not needed for existing equipment that is merely going to be repaired.

20

Page 21: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Ash Residue and LF Use• The Company will be responsible for the loading and

transportation of Ash from the SEF to the County Landfill. • The Company will be responsible for unloading the Ash

at the Landfill in an area designated by County staff. • The cost of the disposal of Ash, up to the Ash Quantity

Guarantee, will be borne by the County. • Landfill-related disposal costs, for Ash in excess of said

Ash Quantity Guarantee, will be to the account of the Company.

• The disposal cost at the County Landfill for this excess will be equal to the then current tipping fee per Ton charged by the County.

• The County will, at all times during the term of the Agreement, provide the County Landfill for the disposal of Ash and other Unacceptable Waste, except Hazardous Waste.

21

Page 22: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Terminology of the RFP

Phase 1 Retrofit Completion Work and, upon successful completion of the Performance Test, then operate and maintain the SEF during the Phase 2 Commercial Operations Period.

22

Page 23: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Section 3.5 Phase 2 – Commercial Operations (a thru s)

Immediately after the Commercial Operations Date, the specific responsibilities and activities of the Company at the SEF during the 20-year Phase 2: Commercial Operations Period, are expected to include, at a minimum, the items set forth in (a) – (s) in Section 3.5

23

Page 24: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Phase 1 Retrofit Period Price: for Construction and Operations

• Each Proposal must contain a total price (Total Phase 1 Price) for the Phase 1 Retrofit Completion Work Costs (Proposal Form 1) and a Guaranteed Phase 1 Work Period to the Scheduled Acceptance Date (Proposal Form 8).

• The Company must provide all services, labor, materials, supplies, personnel and equipment necessary for it to fulfill its obligations related to the Phase 1 Work for the Total Phase 1 Management/Operations Costs set forth in Proposal Form 3A.

24

Page 25: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Phase 1 Interim Service Fee(Section 4.2.3 of RFP)

• The County will pay an Interim Service Fee (Proposal Form 1) to the Company for each Ton of Acceptable Waste received and processed at the SEF until the Phase 1 Acceptance Date has occurred.

• The Interim Service Fee should only represent costs to be incurred by the Company that are not included in the Total Phase 1 Management/Operations Costs set forth in Proposal Form 3A (Item B) but are included in Proposal Form 3B.

25

Note: Section 4.2.3 incorrectly referred to Form 3A and will be noted in Addendum No. 1, when issued.

Page 26: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Performance Guarantees • The Project must be designed and constructed to

meet Performance Guarantees, as specified in Proposal Form 8, commencing on the Phase 1 Acceptance Date and continuing throughout the Term of the Agreement.

• The Agreement will contain a description of the procedures for conducting the Performance Tests and the criteria for determining whether the Project has satisfied them.

• The Acceptance Date will not occur until the Project has satisfied the Performance Test and all conditions associated with Phase 1.

26

Page 27: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Performance Bonds

The Company must provide

(i) a performance bond from an A-rated surety Company, in an amount equal to not less than the price for all of Phase 1 Work; and

(ii) a labor and material payment bond from an A-rated surety Company acceptable to the County in an amount equal to not less than 100% of the price for the Phase 1 Work.

27

Page 28: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Renewable Letter of Credit

• The Company must provide an annually renewable letter of credit in the amount of $5,000,000 to provide assurance of performance following the Contract Date and during the Term of the Agreement.

28

Page 29: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Guaranty• Each Proposal must provide that a Project

Guarantor will unconditionally, and without limitation as to amount, guarantee the Company's performance of its obligations under the Agreement.

• The Project Guarantee must remain in effect during the term of the Agreement, including both Phase 1 Work and Phase 2 Work, as applicable.

• Each Proposal must identify the Project Guarantor...using Form 21.

29

Page 30: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Phase 2• Beginning on the Phase 2 Operations Commencement

Date, the Company will be obligated to accept and dispose of all Acceptable Waste delivered to the Company by the County and its haulers, subject to certain rejection rights specified in the Agreement.

• The County will pay a Service Fee (each month after the Acceptance Date) for disposal of Acceptable Waste accepted and processed by the Company at the Facility.

• As negotiated, the principal components of the Service Fee will consist of: – a Capital Component (Proposer to use Form 4), – a Phase 2 Operating Charge (Proposer to use Form 6A), and – Pass-Through Costs (to the extent identified in the Draft

Agreement).

30

Page 31: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

PPA Revenues & Credits

• The County will enter into a power purchase agreement (PPA) for the sale of electricity produced by the SEF. The County will keep all PPA revenues and revenues associated with the sale of environmental attributes related to the electricity produced.

• The County will consider sharing a portion of revenues received for quantities of electricity generated in excess of the Company’s electricity production guarantee (Proposal Form 11).

31

Page 32: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

SEF Hours of Service (Section 4.2.16 of the RFP)

• The County will provide staff at the SEF scale house to cover the receipt of Solid Waste from 6:30 a.m. to 5:00 p.m., Monday through Friday, and 6:30 a.m. to 12:00 p.m. on Saturday.

• No County scale house personnel will be available at the SEF for receiving Solid Waste on Sunday, “Saturday afternoon” or the four Holidays days noted above on which the Landfill is “officially” closed.

Note: However, Section 4.3 indicates that the County will work with the selected Company to provide a means of entrance to the Landfill when the Landfill is normally closed.

“ “ = new text that will be noted in Addendum No. 1

32

Page 33: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

County-Owned SEF Spare Parts/Maintenance Equipment

• As noted on page 35, the County currently owns in excess of $1 million of spare parts and a lot of maintenance equipment that is currently on-site at the SEF

33

Page 34: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Qualifications

Section 7.3 --- the Proposer’s financial and technical qualification’s will be evaluated from the Proposal documentation requested in Section Six and Section Eight of the RFP.

34

Page 35: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Proposal Evaluation - Technical

• Significant factors in the evaluation will include but may not be limited to: – Quality and durability of proposed materials and

equipment;– Construction approach including sequencing;– Operation, Maintenance and Management Plans;– Environmental controls demonstrated by criteria and

non-criteria emission limit guarantees and overall Facility design;

– Operational efficiency demonstrated by energy recovery efficiency, equipment and personnel use, factors, and guaranteed utility consumption;

– Staffing Plan;– Commercial reliability; and – Performance capabilities.

35

Page 36: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Proposal Evaluation–Business Aspects

• As part of the evaluation, the County will review and consider the business aspects of the Proposals including, but not limited to:– The exceptions taken to the Draft Agreement;– Performance guarantees proposed by the Proposer;– Guaranteed schedule; and– Plan of finance

36

Page 37: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Proposal Evaluation-Economic• The economic evaluation will include, among other

items: – an analysis of all of the construction-related costs related to the

Phase 1 Design/Built Improvements, – the annual Capital Component associated with the Phase 1

Work, – the construction drawdown schedule, – the Phase 1 Management/Operations Fee, – the Phase 2 Operating Charge, – the revenue sharing proposal, – the Guaranteed Annual Throughput Capacity and Guaranteed

Electricity Production, and any other cost-related factors.

• The County will evaluate the life-cycle costs associated with each Proposal.

• A base case set of assumptions will be developed by the County and the County may consider sensitivity analyses.

37

Page 38: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Proposal SubmissionThree documents as follows: • Document I: Consisting of -

– Executive Summary - Section I (w/Form 22)

• Document II: Consisting of - – Qualifications Update - Section II– Project’s Technical Proposal – Section III– Management Proposal - Section IV – w/Forms 8,10 and 17

• Document III: Consisting of - – Business Proposal - Section V – Cost Proposal – Section VI– with all remaining Forms provided in the RFP

38

Page 39: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Number of Copies of the Proposal

• One (1) original• Nine (9) hard copies...numbered

39

Page 40: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Proposal Price Adjustments

As stated in Section 10.1: • The Company agrees that all costs in the Proposal are

firm. • The Total Phase 1 Price set forth on Proposal Form 1

will escalate from the date that is 120 days following the Proposal Due Date if the Agreement is not executed by such date through and until the actual Contract Date in accordance with the escalation index identified in the Draft Agreement.

• The Phase 2 Operating Charge will escalate from the Proposal Due Date in accordance with the escalation index identified in the Draft Agreement (as such escalation adjustment may be modified pursuant to Proposal Form 6A).

40

Page 41: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

County RFP Schedule

41

Event Date Day

RFP available w/o Draft Agreement Dec. 9, 2011 Friday

Pre-Proposal Meeting and Site Tour – 9:00 a.m.

Dec, 15, 2011 Thursday

Issuance of Draft Agreement J an, 4, 2012 Wednesday

Additional Site Inspection(s) As Coordinated w/County

As Agreed Upon -

I ssuance of County Addenda During RFP Process

As Required -

Final RFP Clarifications/Questions Due to County

J an. 31, 2012 Tuesday

Final County RFP Addendum Issued Feb. 7, 2011 Tuesday

Proposals Due, addressed to: New Hanover County Manager’s Office Attn: Mr. Bruce Shell, County Manager 230 Government Center Drive, Suite 195 Wilmington, NC 28403

Feb. 21, 2012 Tuesday

This schedule is part of Exhibit 2 of the RFP!

Page 42: Pre-Proposal Meeting REQUEST FOR PROPOSALS (RFP) SOLID WASTE MANAGEMENT SERVICES TO INCLUDE RETROFITTING AND OPERATION OF WASTE TO ENERGY FACILITY RFP

Thank You

• Additional Questions and Open Discussion Period, as applicable

• Then, tour of the SEF and County Landfill

42