1 Pre-Bid Conference Geothermal Heat Pump Retrofit at 404 Aviation Boulevard, Santa Rosa, CA November 30, 2009

Upload: galena-barlow

Post on 01-Jan-2016

34 views

Category:

Documents


0 download

DESCRIPTION

Pre-Bid Conference. Geothermal Heat Pump Retrofit at 404 Aviation Boulevard, Santa Rosa, CA. November 30, 2009. Agenda. General Project Information Timeline from Bid to Site Scope of Work Owner Items of Concern Sequence of Work and Constraints Site Visit Sequence. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Pre-Bid Conference

1

Pre-Bid Conference

Geothermal Heat Pump Retrofit at 404 Aviation Boulevard, Santa Rosa, CA

November 30, 2009

Page 2: Pre-Bid Conference

2

Agenda

• General Project Information

• Timeline from Bid to Site

• Scope of Work

• Owner Items of Concern

• Sequence of Work and Constraints

• Site Visit Sequence

Page 3: Pre-Bid Conference

3

General Project Information

• 458 Days to Substantial Completion

• 486 Days to Final Completion

• Engineer’s Estimate: $2.3 to $3.1 million

• Contractor Experience Requirements (00200), explicit

mechanical experience for prime, explicit experience

for ground loop and electrical subs.

• Bid Submission “A”: 9AM December 10, 2009

• Bid Opening: 10AM December 10, 2010

Page 4: Pre-Bid Conference

4

General Project Information (cont’d)

• Questions Must Be Submitted in Writing

–Questions due ten days prior to bid due date

–May extend question deadline to December 2, 2009

–If necessary, Owner will issue addenda

• Substitutions (Section 01600) only considered during

bid period.

Page 5: Pre-Bid Conference

5

Timeline From Bid to Site

• Contractors submit Bids (valid for 90 days)

• Owner’s Board issues Notice of Award

• Owner issues Notice to Proceed (Commence Contract

Time)

• Contractor starts on Site upon meeting NTP demands.

–Work on-site cannot occur until critical submittals are

submitted and approved

Page 6: Pre-Bid Conference

6

General Scope of Work

• Provide Geothermal Heat Pump System

–120 vertical wells 400 feet deep

–Condenser water circulation system

–Demolish existing HVAC system

– 47 geothermal heat pumps

–Building Management System

–Start, Adjust, Test, and Balance

• Submission of Documentation

Page 7: Pre-Bid Conference

7

Items of Concern (to us)

• Public Building: Accessibility and visibility

• Building Occupied: Work Days and Hours (01100-1.8)

–Outdoors: M-F 6am-7pm

–Indoors: Thurs 6pm to Mon 5am

• <5,000 sq ft before 6pm Friday

• Contractual Provisions:

–All communication must be in writing, follow front end

protocol, and follow front end timelines.

• Submittals electronic

Page 8: Pre-Bid Conference

8

Sequencing and Constraints

• Housekeeping (01100-1.7.C)

–Maintain office cleanliness to preconstruction levels

by 5 a.m. Cover office items during indoor work.

• Detailed Work Sequence (01100-1.7.C)

–Condenser water loop and electrical complete

–Replace existing Bryant/Trane Units with new HPs

–Replace Carrier Unit AC1 with new HPs

–Replace Carrier Unit AC2 with new HPs

–Temporary operation with no outside air, with limits

Page 9: Pre-Bid Conference

9

Tour Sequence

• West Parking Lot

• East Parking Lot

• MCC Room

• Roof

• Occupied Areas

Page 10: Pre-Bid Conference

10

West Parking Lot

Page 11: Pre-Bid Conference

11

East Parking Lot

Page 12: Pre-Bid Conference

12

MCC Room

Page 13: Pre-Bid Conference

13

Roof

Page 14: Pre-Bid Conference

14

Occupied Areas