Block Planning is the planning or pre-assignment of resource capacities for products with specific attributes, with the purpose of using the capacities more rationally. The attributes are described using characteristics from the SAP system.
In block planning, you define blocks on a resource that have a specific duration and attributes, for example, a duration of 2 days per block on which you manufacture products in various alloys of the same alloy group.
A block is defined as a period of time, in which a resource processes one or more activities with the same attributes. The attributes are represented by CDP characteristics.
The maintenance of block definition is done in the master data of the resource
• Block basis definition: /n/SAPAPO/REST01• Block reference cycle: /n/SAPAPO/REST01k
The actual block schedule maintenance is done from planning board• Block schedule: /SAPAPO/CDPS0 with double-click on block• Extended block schedule: /SAPAPO/CDPS0 with heuristic “Extended Block
maintenance”
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
APO Resource: Block Planning
• Create block basis definitionYou specify the characteristic requirements for the class in the block basis definition. A block definition refers to the class, not the current resource. If you change the block basis definition, the system changes the characteristics requirements of all blocks that use this block basis definition for this class. If you delete a block basis definition, the system replaces all blocks on resources that have used this block basis definition by free blocks.
• Define reference cycleYou can group several block basis definitions with relative durations in a reference cycle, and use them for recurring block sequences.
• Create and process blocksYou can create the blocks individually with the corresponding block basis definitions, or add a predefined sequence of blocks using reference cycles. You can process the blocks you have created in a table or in a graph.
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
Block Planning: Settings
SAP_CDPBP_01: Plan blocks Rescheduling of activities on block-planned resources if block attributes have been changed.
SAP_CDPBP_02: Adjust and plan block limitsAdjust block to fill level
SAP_CDPBP_03: Enhanced block maintenance Insert/Delete blocks
Enhance; Shrink blocks by different units
Manage block settings
SAP_CDPBP_04: Block maintenance, access interactively Insert/Delete blocks
Enhance; Shrink blocks
Manage block settings
Material stages
Overview Scheduling Conversion Reporting
Block planning heuristics
Capacity Planning
Block planned casthouse resource
TLA6• Blocks per Alloy series (ALLIN_1_DIGIT)
10 charges of alloy 2xxx and 7xxx 30 charges of alloy 1xxx, 3xxx, 5xxx, 6xxx
TLA7• Blocks per Usage (Short billets or long
billets) Characteristic POUZITI_LB 8 charges for short billets 12 charges for long billets
ITS8-9• Block per main Alloy (ALLIN_4_DIGIT)
5 different block definitions
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
Decin Local Content
Step 8: Maintain blocks
Explanation: The block is defining a time period on a resource where only activities with specified characteristics can be scheduled. The block is defining as well wether it is fixed (no new orders); where the activities are to be scheduled (block border) and whether a block can be overbooked (%)
The actual maintenance job of blocks can be done out of the Planning Board (/n/SAPAPO/CDPSC0) or from the resource master (/n/SAPAPO/RES01)
Switch to tab “Intervals”
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
Step 8B: Maintain Blocks by ref cycle
Choose line where you want to change and press to insert a reference cycle
Specify • when to insert cycle
• How many times to insert
• Whether existing blocks are to be overwritten
• Downtimes to be considered
Press to insert
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
Step 8C: Maintain blocks
You can maintain the block schedule from the resource master and set additional fields of the blocks from there. But it is recommended to use the planning board for this daily maintenance
Press and define to display all fields
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
Step 8D: Additional settings of blocks
Block Is Protected
If you have set the protection indicator for a
block, you cannot change the properties of that block
on the maintenance screen.
NOT used by I2P
Schedule Component/Operations Dates for Block Limits
If you set this indicator, the system schedules component and operation dates on the block limits as follows:
Input and output component of operations in the block
The requirements date for the input components is scheduled to the start of the block, while the receipt date of the output components is scheduled to the end of the block.
Use the consumption type At Activity End for receipt components and At Activity Start for requirements components; do not use any offsets as the system will adjust the dates
accordingly at the block limits. System behavior may become unpredictable.
The predecessor and successor operations of operations in the block
The predecessor operations end at the start of the block at the latest, while the successor operations start at the end of the block at the earliest. The minimum intervals in the
relationships of the predecessor and successor relationships for operations in the block refer to the start or end of the block.
Use end-start relationships between the operations as the system will adjust the dates at the block limits accordingly. System behavior may become unpredictable.
Dependencies
Scheduling at block limits can be overwritten by the setting Schedule Operation on Block Limits in the strategy profile.
Input or output components with continuous consumption are not scheduled to block limits; the same applies to the minimum or maximum offsets in relationships.
The system will only schedule at block limits if the relevant activity lies in a compatible block.If the activity only partially lies in a compatible block, then the compatibility at the start of the block is valid for relationships to successor activities and requirements components, and the
compatibility at the end of the block is valid for the predecessor activities and receipt components.
This indicator cannot be set at the first or last block on the resource. If required, add additional blocks at the beginning or end if you want to use scheduling at block limits. If you delete
blocks, the indicator might be set for the first or last block. The system ignores this setting, however.
If you set this indicator, the system considers the temporal tolerance that you have defined for the blocks.
With block tolerance, the system can schedule an operation in the block in such a way that the operation extends beyond the
block limit in the planning direction. A prerequisite is that - depending on the planning direction - the start or end date of the operation lies within the block limit, and the operation does not
extend further than the tolerance beyond the block limit.
NOT USED
If a block is marked as fixed:
•The activities in the block can no longer be shifted.
•The activities will not be planned in this block if the
activities are scheduled again in a fixed block.
•No additional activities will be planned in this block.
Block schedule
Block schedule maintenance is done manually by using• Block schedule (double-click on block in planning board)
• Block maintenance heuristic (mark resource in Planning Board and choose “Enhanced Block Maintenance” Heurisitic
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
Mark resource
Choose menu “Functions””Heuristics””Enhanced Block
maitenance”
Enhanced Block maintenance
Material stages
Overview Capacity Planning
Scheduling Conversion Reporting
List of BlocksUtilization in % Assigned definition
Maintenance mode 2:If a block is enlarged either shrink
subsequent block or move subsequent blocks
Maintenance mode 1:How to enter change - either •Time•Equivalent (e.g. # melts)•Sequence
Allowed overload in %
Enter changed block size here (in unit
defined in Maintenance mode)
Schedule at block end
Insert BlockDelete Block
Insert Reference Cycle
Block schedule
When a block setup is changed the orders are not automatically re-scheduled. You need to run a schedule heuristic
E.g. within planning board mark resource, choose “Deallocate” and choose “Function” “Heuristics” “Schedule Operations”