powerstream: penetanguishene microgrid project · powerstream: penetanguishene microgrid project...
TRANSCRIPT
PowerStream: Penetanguishene MicrogridProject
SHUVO CHOWDHURY
Smart Grid Project Lead
19th January, 2017
Who are we
• Leading energy company that is also the 2nd largest municipally-owned LDC in Ontario.
• Provides service to more than 380,000 customersresiding or owning a business in 15 communities
• Employs over 500 employees.
• Has more than $1.3 billion in assets.
• Jointly owned by the municipalities of Barrie, Markham and Vaughan.
• Currently undergoing a merger with three other utilities in the Greater Toronto Hamilton Area
C&I Microgrid (Right Here!)
• Low Voltage
• 3 Phase• Multiple Energy Assets
Residential• Low Voltage
• Split phase 120/240V
• Multiple Energy Assets
Grid Scale Microgrid
• Distribution Voltage
• 3 Phase• Multiple Energy Assets
Scaling Up
Scaling Down
What we do
The Why
Build a new line
and/or additional
redundancies
Try something
New: a Microgrid
Project Goals
• Most outages at Penetanguishene are under 10 minutes; Eliminate these outages
• Assess the system as a asset deferral strategy
• Develop algorithms for the Microgrid Controller
• Enter the market as a microgrid solutions provider
What we did at Penetanguishene
• 750kVA/500kWh Li-Ion
Battery System
• 5 circuit automatic
switches to facilitate
FDIR
• 1 Step Voltage Regulator
to correct voltage issues
• Advanced Microgrid
Controller (MiDAS)
• Autonomous function &
SCADA integration
Technology
• Samsung SDI Batteries (Li-Ion)
• Individual Cell Monitoring
• Automatic Voltage Equalization
• Rack Level BMS
• Master BMS
• Up to 2C discharge/charge
• Integral fire suppression and HVAC
Technology
• POSCO ICT Power Conversion System (PCS)
• 750KVA, 4 Quadrant inverter
• IEEE 1547 Compliant
• Integrated Area Level Controller
• 600VDC nominal
• 350VAC nominal
• Integral fire suppression and HVAC
Technology
• Others:
75kV SVR 5 Automatic
Switches
Switchgear,
Transformer, Vacuum
Circuit breakers, etc.
Local Control/Server Room
Project Timeline
• September 2014: PowerStream & Korea Electric Power Corporation Sign an MOU
• Ground Breaking August 28, 2015
• Detailed design complete September 2015
• FAT complete October 2015
• SAT complete April 2016
• Official Launch: 29th June 2016
Project Timeline
MOU Signing: September 2014
Ground Breaking: August 2015
Detailed Design
Factory Acceptance Test (FAT)
250kVA Modules
PCS Control Modules
Loss of grid
PCS Anti-Islanding
Factory Acceptance Test (FAT)
• Conditions tested: UV, OV, OC, UF, OF
• Black Start
• Seamless transfer
• Other equipment included in the FAT:
Fire Suppression and control in the containers
Visit to Samsung SDI battery manufacturing facility
Visit to circuit switch manufacturing facility
Engineering, Construction & Procurement
• Perhaps the most conventional part of the project
• Completed in just under 9 months. Much of it in the winter
Proposed site
Battery Container
Show Room
PCS Container VCB, Transformers, Switchgear & Load Bank
Site after construction
Site Acceptance Test (SAT)
• The longest and most challenging part of the project
• 24 tests in the original plan
• Over 120 tests in the finalized plan
• Over 6 weeks to develop & 2 weeks to execute
Site Acceptance Test (SAT)
20
FDIR : Normal Condition
21
FDIR : Fault & Alarm Occurs
22
FDIR : Fault Detection
23
FDIR : Fault Isolation
24
FDIR : Restoration using backup feeders
25
FDIR : Restoration using backup ESS
What does it do?
What does it do?
What does it do?
What does it do?
Learnings
• It works!
• Still early stages; need to pursue other value propositions
• Extensive EM&V scheduled & ongoing
• Demand data integration was easy; price, not so much
• Surprises: no outage yet!
Follow-up
• What’s next?
– Commercial deployment inside and outside PowerStream service territory
– True islanding test
– Performance analysis
Questions?