power plant design part iii
DESCRIPTION
ampota!!!! diesel power plant designTRANSCRIPT
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Location
Guinsiliban, Camiguin
Camiguin, the smallest province in Northern Mindanao (Region X), had a total population of 74,232 persons based on the results of the 2000 Census of Population and Housing. It was the second to the smallest in the Philippines in terms of population. It registered an annual growth rate of 1.88 percent from 1995 to 2000, higher than the 1.08 percent growth rate during the 1990 to 1995 period. If the current rate continues, the population of Camiguin was expected to double in 37 years.
The number of households rose to 14,826, higher by 1,352 households from the 1995 figure. The average household size was 5.0 persons (same as the national average), which was lower than the 1995 average of 5.04 persons.
Of the five municipalities in Camiguin, its capital Mambajao, which comprised 42 percent of the total provincial population, was the largest in terms of population size. Catarman, Mahinog, and Sagay followed with 21 percent, 17 percent and 14 percent, respectively. Of the total population, Guinsiliban had the least share (seven percent).
Camiguin had the least population in Northern Mindanao (Region X), contributing only 2.70 percent to the 2.7 million population of the region. At the national level, Camiguin shared 0.10 percent to the total Philippine population of 76.5 million as recorded in the Census 2000.
Of the total household population five years old and over, about two out of five persons had attended or completed elementary education. Thirty one percent had either attended or finished high school while 12 percent had attended college. Only four percent were academic degree holders. More than half of those who had attended or finished elementary education (53.1 percent) and post secondary (54.7 percent) were males. On the other hand, those who had attended or finished college, academic degree holders and post baccalaureate were predominantly females.
About 45 percent of the total population in Camiguin classified themselves as Cebuano. Kamigin/Kinamiging followed with 36 percent and the Boholanos, with 11 percent. The remaining three percent were either Binisaya or belonged to other ethnic groups.
There were 15,449 housing units in Camiguin, of which 14,735 were occupied. This registered an increase of 23.3 percentage points from 1990, a ratio of 1.01 household per occupied housing unit, and 5.03 persons per occupied housing unit. Almost all (98.6 percent) occupied housing units were single houses, an increase of 22 percentage points from the 1990 figure.
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Guinsiliban is 6.9% of total population of Camiguin therefore we can assume that out of 14,735 Occupied Housing Unit there are 1002 single houses which represents the majority of the building structures on Guinsiliban and a household population of 1023.
Demographic Data:
Total No. of Population: 5,092
Household Population: 1023
Structures:
(Group A)
Single House: 1002
Duplex: 6
(Group B)
Multi-Unit Residential: 3
Commercial/Industrial/Agricultural: 1
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Graphical Representation of Load
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Load Table (GROUP A)
Load Table (GROUP B)
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Total Power Consumption Table
25449.08kW-hr/day
Design Overview
Peak Load = 2357.16 kW, 2.35716mW
Plant Capacity: 3200 kW, 3.2mW
No. of Engines: 5
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Engine Capacity Number of Hours of Operation/day
Unit 1 – 800 kW 18 hours/day
Unit 2 – 800 kW 18 hours/day
Unit 3 – 800 kW 18 hours/day
Unit 4 – 800 kW 18 hours/day
Unit 5 – 800 kW Reserve
Schedule of Engine Operation
Time of Operation
Engine Operating
Time Interval
12AM - 6AM UNIT 1,2 & 3 6 hours6AM -12NN UNIT 2,3 & 4 6 hours12NN - 6PM UNIT 4,1 & 2 6 hours6PM - 12AM UNIT 3,4 & 1 6 hours
Each Unit has a 6 straight hours break.
Design for Machine Foundation
For 800 kW Generator Set (Per Unit 1,2,3,4 and 5)
Mixture for Concrete Foundation:
Use 1:3:5 concrete mixture ratio (from PPE by F.T. Morse, Table 4-1 p.90)
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Soil Bearing Pressure:
Use 50-98 tones/m2 for compact clay (from PPE by F.T. Morse, Table 4-4 p.105)
Soil Bearing Pressure (Sb)
Weight of foundation
Where:
Wf = weight of the foundation, kgs
We = weight of the engine, kgs
e = empirical coefficient
n = engine speed, RPM
Use e = 0.11 (from PSME code, Table 2.4.2.3 (4), p.11)
Volume of foundation
Where:
Vf = volume of foundation [m3]
ρc = density of concrete = 2406 kg/m3
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Depth of Foundation
Where:
hf = depth of foundation [m]
Lf = length of foundation [m]
wf = width of the foundation [m]
Length of the foundation:
Where:
Lb = length of bedplate [m]
Le = length of engine [m]
Width of the foundation:
Where:
wb = width of bedplate [m]
we = width of the engine [m]
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Soil Stress
Soil Stress
Soil Stress
Foundation Materials:
Concrete Mixture Ratio = 1: 3: 5
X + 3x + 5x = 15.32 m3
9x = 15.32 m3
X = 15.32 m3/ 9
X = 1.70 m3
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
For cement:
1 x 6.2 x 1.70 m3 = 10.54 m3
For sand:
3 x 0.52 x 1.70 m3 = 2.65 m3
For gravel:
5 x 0.86 x 1.70 m3 = 7.31 m3
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
For Reinforcing Bar:
Using 14 mm diam. rebars
Flexure formula
Eccentricity from mid-base
Y1 = 1/2h = ½ (1.25m) = 0.625m
Y2 = 1/3h = 1/3(1.25m) = 0.42m
A1 = Lf x h = (5 m)(1.25 m) = 6.25 m2
A2 = ½ Lf x b
Where:
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
b
if b < wf, then wf = b; use b = wf = 2.5 m
A2 = ½ Lf x b = ½ (5 m)(2.5 m) = 6.25 m2
∑A = A1 + A2 = (6.25 + 6.25) m2 = 12.5 m2
∑AY = A1Y1 + A2Y2 = [(6.25)(0.625) + (6.25)(0.42)] m3 = 6.53 m3
C
m =
For Bolts:
Diameter = 1/8 x (bore) = 1/8 x (150mm) = 18.75 mm
Length = 7/8 x (stroke) = 7/8 x (160 mm) = 140 mm
Use L = 30D (from ASME code)
L = 30 (18.75 mm) = 562.5 mm
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
No. of bolts
Where:
Tbolts
From Table AT 7 – DME by V.M. Faires
Material: AISI 8630 (for connecting rods, bolts, shapes)
Sy = 100 ksi = 100, 000 psi; Fy = 7 (max. for shock)
Tbolts
No. of bolts
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Design for Fuel Tank
For 800 kW Generator Set (Per Unit 1, 2, 3, 4 and 5 )
Type of Oil: Diesel Fuel Oil
Specific Gravity = 0.917 @ 60°F
(From Power Plant Theory and Design by P.J. Potter, Table 5-4, and p.187)
Generator Output (EP) = 800 kW
Specific Fuel Consumption
Where:
BP
(For 1800 rpm & 494.73 kW Ave. Load)
(From Power Plant Theory and Design by P.J. Potter, Figure 9-27, p.445)
BP
Specific Fuel Consumption
Plant Operation = 24 hrs/day
Engine Operating Hours/day = 18 hrs/day
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Expected Fuel Delivery Schedule = every 15 days
% Rated Capacity
From PPE by F.T. Morse, Fig 6-15, p.164
Max. fuel consumption = 0.25 kg/kW-hr
Min. fuel consumption = 0.21 kg/kW-hr
Volume of Day Tank
Where:
mF = daily fuel consumption [kg/day]
ρF = density of fuel = 917 kg/m3
mF = max. fuel consumption x BP x engine operating hours/day
= (0.25 kg/kW-hr) (818 kW) (18 hrs/day)
= 3681 kg / day
Dimension of Day Tank
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
(From the above equation)
Assume:
HDT = 2DDT = 2 (1.37 m) = 2.74 m
Thickness of Fuel Day Tank
Where:
PT = pressure inside tank
Where:
γfuel = 8.996 kN/m3
PT = 2.74 m x 8.996 kN/m3 = 24.65 kN/m2 or kPa
Sy = Tensile Yield = 35,000 psi (from DME by V.M. Faires, Table AT 4, p.568)
F.S.y = Design factor of safety
F.S.y = 3 (for stainless steel from DME by V.M. Faires Table 1.1, p.20)
n = 75%
Storage Tank for 30 days operation
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Dimension of Storage Tank
(From the above equation)
Assume:
HST = 2DST = 2 (4.25 m) = 8.5 m
Material for Fuel Tank: AISI No. 321 (stainless steel)
Thickness of Fuel Storage Tank
Where:
PT = pressure inside tank
Where:
γfuel = 8.996 kN/m3
PT = 8.5 m x 8.996 kN/m3 = 76.46 kN/m2 or kPa
Sy = Tensile Yield = 48,000 psi (from DME by V.M. Faires, Table AT 7, p.576)
F.S.y = Design factor of safety
F.S.y = 2 (for stainless steel from DME by V.M. Faires Table 1.1, p.20)
n = 75%
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Transfer Pump from Fuel Storage Pump to Day Tank
Assumption:
Desired Operating Time for Fuel Pump = 1 hr/day
ηp = 72%
Power input for Unit 1, 2, 3, 4 and 5
Where:
EPi = electrical power input [kW] or [hp]
γfuel = 8.996 kN/m3
TDH = total dynamic head [m]
Q = volume flow rate [m3/s
Where:
VDT = volume of fuel at day tank [m3/s]t = time of pump operation [sec]
= 0.00111 m3/s
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
1 hp is used for unit 1 transfer pump
Design for Heat Exchanger
For 800 kW Generator Set (Per Unit 1, 2, 3, 4 & 5)
Theoretical and Actual Limits of Cooling Water and Jacket Water
(From PPE by F.T. Morse, p.178)
tji = jacket water inlet temperature = 37.8 °C
tjo = jacket water outlet temperature = 65.6 °C
tcwi = cooling water inlet temperature = 32.2°C
tcwo = cooling water outlet temperature = 54.4 °C
LMTD
Δtmax = (65.6 – 54.4) °C = 11.2 °C
Δtmin = (37.8 – 32.2) °C = 5.6 °C
LMTD
Qj = mj x cpj x Δtj
Where:
Qj = heat rejected from jacket water = 358.9 kW (from catalog)
mj = mass of jacket water
Δtj = temp. Difference of jacket water= (65.6 – 37.8) °C = 27.8 °C
Cpj = 4.187 kJ / kg-K (for water)
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
A
Where:
A = surface area of heat exchanger
U = overall coefficient of heat transfer
LMTD = log mean temp. Difference
Solving for U (from PPT & D by P.J. Potter, Fig. 8-9, p.351 and p. 352)
Where:
= coefficient of heat transfer
Ft = temp. Correction factor
Fm = tube material and thickness correction factor
Fc = cleanliness factor
Fp = prime mover factor
Tube Specifications:
Material: Aluminum Brass 18 BWG ¾”
Water Velocity = 9 ft/s
Ft = 1.08
Fm = 0.96
Fc = 0.85
Fp = 1.0
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
C = 270
Where:
mcw = mj = 11,088 kg/hr
υ = specific volume of circulating water @ t
From steam table @ 51.7 °C (by interpolation)
υ = 1.01295 L/kg
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
From PPT & D by P.J. Potter, p. 357
“For each ¾” No. 18 BWG tube will pass 1.042 GPM/1 fps”
Where:
0.1963 ft2/lin. ft = outside surface area of ¾” tube (18 BWG)
(From PPT & D by P.J. Potter, Table 8-1, p.353)
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Design for Cooling Tower
For 800 kW Generator (Per Unit 1, 2, 3, 4 and 5)
BP = 818 kW = 1,096.51 hp
Installation Data:
t2 = engine water into heat exchanger (in) = 65.6 °C
t1 = engine water into heat exchanger (out) = 37.8 °C
tb = cooling water to heat exchanger = 32.2 °C
ta = cooling water to heat exchanger = 48.9 °C (max. state of humidified air)
Make-up water = 15.6 °C ; 29.4 °C DB & 21.1 °C WB (@ atmospheric condition)
Using the formula (from PPE by F.T Morse, eq. 6-16, p. 178)
Where:
W = cooling water [1 / hr)
Bhp = rated brake horsepower
t1 & t2 = inlet & outlet water temperatures [°C]
Let ww = water flow in the cooling tower circuit
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
From PPE by F.T. Morse, p. 181
The theoretical maximum humidified state of the air leaving is 48.9 ° C at 100 % humidity.
Assume 5.5 °C differential and 90% RH
From Psychometric Chart @ 29.4 °C DB & 21.1 °C WB:
SH1 = 0.0123 kg
h1 = 79.088 kJ/kg
Using the formula (from PPE by F.T Morse, eq. 6-19 & 6-20, p. 182)
Where:
Td = dry bulb temperature [°C] = (48.9 – 5.5) °C = 43.4 °C
RH = percent relative humidity
Ps = saturation pressure of water vapor @ td
Pa = atmospheric pressure [kg/cm2]
hg = enthalpy at td, dry and saturated [J/kg]
From Steam Table @ 43.4 °C:
Ps = 0.0895 kg/cm2 (converted value)
Hg = 2,580,140 J/kg
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Using the formula (from PPE by F.T Morse, eq. 6-17 & 6-18, p. 177)
Mass balance for cooling tower:
Heat balance for cooling tower
Ww = 1.7 kg water / kg dry air (from above equation)
From Psychometric Chart
Since υair @ 29.4 °C & 21.1 °C = 0.862 m3/kg
= 60 %
From PPE by F.T. Morse, p. 182
Recommended Type: Natural Draft Cooling Tower
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Cooling Tower Pipe
; QCTP = mcw (υf @ 32.2 °C)
From Steam Table (by interpolation)
υf = 1.00506 L/kg = 0.0010506 m3/kg
Velocity of water @ HX = Velocity of water at cooling tower
9 ft/s = 2.74 m/s
;
Material Specification (from PSME code, p.200)
Size: 1 ½ in. Inside Dia.: 1.5 in Wall thickness: 0.2 in
Schedule: 80x Outside Dia.: 1.9 in
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Cooling Tower Pump
PCT = (QCTP)(γwater)(TDH)
Assume z = 2 m ; TDH = 2 m
PCT = (0.00324 m3/s)(9.807 kN/m3)(2 m) = 0.064 kW = 0.085 hp
Assume ηp = 75 %
Fan Power of Cooling Tower
Fan Capacity
QA = mAυA
Where:
mA = mass of air = 1.59 kg/s
υA = specific vol. of air
ρA = density of air @ standard condition = 1.2 kg/m3
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Cooling Tower Floor Area
Concentration of Water = 80 L/min-m2
;
Variable Load Calculations
(We use 3200kW from catalog 800kw X 4 genset)
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Catalogue
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Perspective View
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Side View
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Top View
List of Materials
Materials QuantityCement 3675Gravel 435Anchor Bolts 1/8 x 7/8 3315Renforcing Bars 14mm x 20ft 65Aluminum Brass Tube 3/4" 120
List of Equipments
Equipment Quantity800kW Diesel Genset (IDLC 800-2M) 5
Fuel Transfer Pump 1hp 5
Cooling Tower Pump 0.11hp 10
Cooling Water Fan 0.27hp 10
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Heat Exchanger
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Cooling Tower
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Fuel Tank
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Machine Foundation
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Rizal Technological University
Boni Ave., Mandaluyong City
College of Engineering and Industrial Technology
Mechanical Engineering Department
In partial fulfillment
Of the course requirements on
ME 54L - Power Plant Design Lab
Submitted by:
Submitted to:
Engr. Gerry Cabrera
Submitted on:
March 14, 2011