Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Post MortemGroup 2

Team Members:

Mohammad Al-Amoudi

Ahmed Ali Babar

Effatsadat Faregh

Ravish Kalra

Shannon MacDonald

Scott Metrunec

Page 2: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 2/69

Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Table of Contents

Introduction.............................................................................................................................. Page 1

Where Things went Right & What Factors Contributed to the Success.................................. Page 1

Where Things went Wrong & Basic Causes of Why............................................................... Page 1

Areas Requiring Improvement................................................................................................. Page 2

Comparison of Original & Final Schedule and Resource Estimates........................................ Page 3

Meeting Minutes....................................................................................................................... Page 5

References................................................................................................................................ Page 67

List of Tables

Table 1 – Initial Task Timeline................................................................................................ Page 3 Table 2 – Budget by Personnel................................................................................................. Page 4

Page 3: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 3/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 1 of 67

Introduction

Considering that our team members were all very busy throughout the semester with full course loads, it is notsurprising that there were times when sections were rushed, or people were not able to get in touch with each

other. However, all assignments were completed on time and to a high standard of work, despite the difficulty

of getting all six members to collaborate on one assignment.

There were several key areas that our group was lacking in knowledge and experience. The numbers for our

finances were probably far from realistic due to the inexperience of our group in financial and research and

development matters. We also recognized the need for a larger staff for production and language expertise,

which was not identified earlier.

The factors listed below are what we thought we did well, and where we could have improved.

Where Things went Right & What Factors Contributed to the Success

  A Facebook group page maintained communication between group members, as well as allowed easy

reference to meeting minutes, submissions, and announcements.

  Meeting minutes were recorded and posted for review by all team members to ensure clarity of the tasks at

hand. As a result, even if someone could not attend a meeting, they were kept up to date.

  Work was posted to the group page to allow all team members to critique or applaud each other’s work.

This ensured the highest quality submissions.

  There were a variety of skills within our group which offered multi-faceted points of view pertaining to the

work at hand, resulting in submissions that were very thorough.

  Decision making strategies ensured that fairness was maintained among the team members.

Where Things went Wrong & Basic Causes of Why

  All team members are in their fourth year and have heavy course loads. It was hard to find time where

everyone was free, so we had to rely on the internet (Facebook group page) where we discussed our

progress. It may have been more beneficial to have more face-to-face meetings.

Page 4: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 4/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 2 of 67

  All members had many assignments that were due at different times, due to the different engineering

disciplines. This was understandable, so we would normally assign the task to another member who did not

have quite as much to do at the time, take over other member’s tasks.

  The biggest problem related to “working away from each other” was that certain numbers within our data

were discussed and revised, but not changed everywhere. Effort was made to give the task of reviewing the

numbers and continuity by one member.

  Lots of presentation work was done last minute (except for the final presentation) and it was evident that

the quality was not up to standards.

  Members would sometimes focus on not so important ideas and information that would waste time in the

meetings, effort was made to plan the meeting schedule and details discussed prior to the meetings to utilizetime effectively.

  We were de-motivated to attend classes and as a result the quality of work presented was not up to the

standard of the professor, we had to encourage one another

Areas Requiring Improvement

Initially, things went right and everything was discussed properly, but due to the busy and clashing schedules ofall the team members, there was a little miscommunication between the team members. Due to this

miscommunication, the ideas and sections to be written were not properly discussed before they were written

and therefore we had to go back and forth in the report to make everything consistent in the overall business.

Having more meetings would have saved us time that was wasted correcting errors that were a result of 

miscommunication.

To further improve the business plan, an addition of a person from a business management major would have

been very helpful as the current management team consisted of only engineers. A person from a business

background would have had a better understanding of marketing and business management, and therefore

would have assisted better in the management team.

Page 5: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 5/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 3 of 67

Comparison of Original and Final Schedule and Resource Estimates

The time table for our original plan was estimated as follows:

Priority

ranking

Task Description Team Members Time period (start-end)

1 Initial research and consultation on the basic idea

(how feasible is it?)

Effat, Shannon 1 weeks = 10 hrs/head

(Sept. 20-26th)

2 Searching for spin off technologies Effat, Shannon 2weeks=10hrs/head

(Sept. 27th

- Oct. 10th)

2 looking for present and potential competitors Scott, Ahmed 2 weeks = 10 hrs/head

(Sept. 27th

- Oct. 10th)

2 Estimating the market (identifying the present

and potential costumers)

Mohammad, Ravish 3 weeks = 15hrs/head

(Sept. 27th

- Oct. 17th)3 Searching for the required technology, licences,

etc.Shannon, Effat 3 weeks = 15 hrs/head

(Oct.11th- Oct. 31st)

3 Estimate the time for Purchasing & receiving thenecessary equipment (licences, etc.)

Ahmed, Ravish 2weeks=10hrs/head(Oct.11th- Oct.24th)

4 Make an estimation on the final product price

(market sale price)

Scott, Mohammad 2weeks=10hrs/head

(Oct. 25th

-Nov. 7th)

5 Critical Risk/problem & Assumptions Scott, Shannon 1week=5hrs/head

(Nov. 8th

-Nov.14th)

5 Finding a suitable sale tactic Effat, Mohammad 1week=5hrs/head(Nov. 8th-Nov.14th)

5 Planning the operation cycle Ravish 1weeks=10hrs/head(Nov. 8th-Nov.14th)

5.5 Advertising the product Scott 2weeks=10hrs/head(Nov.8th-Nov. 21st)

5.5 Reaching current & potential investors Ahmed, Ravish 2weeks=10hrs/head

(Nov. 15th- Nov. 28th)

6 Setting up the basic organization/ define the key

management personnel’s responsibilities

Group 1week=5hrs/head

(Nov. 29th

-Dec. 5th)

6 Solving any possible potential legal issues Ahmed 1weeks=5hrs/head

(Nov. 29th

-Dec. 5th)

6 Defining the Management Compensation &

Ownership

Group 1week=5hrs/head

(Nov. 29th-Dec. 5th)

Table 1 – Initial Task Timeline

As the above table shows, for each task one or two people (and in some cases, the entire group as a whole) were

responsible to the accomplishment of the task.

Page 6: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 6/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 4 of 67

According to the original estimation, the following table was constructed to show the approximated required

time for each individual to fulfill his/her parts.

Budget by Personnel:

Person Team (Hours) Individual (Hours) Total

Effat 10 35 45

Shannon 10 35 45

Mohammad 10 30 40

Ahmed 10 35 45

Scott 10 35 45

Ravish 10 40 50

Table 2 – Budget by Personnel

However, we were unable to pursue our plan as closely as we had anticipated. The estimated time had to beadjusted throughout the term as each team member had to deal with his/her workloads from other courses as

well. Unexpected situations (especially during the exam period of the term) and sometimes underestimating the

required time for each task were the main two reasons for falling behind schedule. The parts of the plan that we

were unsuccessful to complete during the term are as follows:

  Finding a suitable strategy for advertising the product

  Reaching current and potential investors (basic research was done by the team, but a more accurate

investigation is required in order to proceed with the business plan )

  Finding a suitable sale tactic (although we had a sale strategy in our business plan, we didn’t have much

experience in this area, so it definitely needs to be looked at more closely by the appropriate expertise).

Also, due to the nature of any team work, sometimes some of the team members were lacking in their parts, so

some other team members were had to help them out. This issue caused the budget table (i.e. Table 2) to be very

different from what we thought we would have at the beginning. In the original budget table, time was

distributed very evenly, while what we ended up with wasn’t as evenly distributed.

Page 7: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 7/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 5 of 67

Meeting Minutes

It was difficult to match six schedules and find common free time for every person in the group. In order toavoid this hassle, an online Facebook group with very high privacy settings was used to conduct online

meetings and discussions. Along with this, free time at the end of the lecture was exploited to conduct frequent

meetings. The following are the meeting minutes and discussions conducted online over the period of the

course. These include both, online discussions, as well as meeting minutes from meetings conducted at the end

of the lecture.

Page 8: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 8/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 6 of 67

Page 9: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 9/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 7 of 67

Page 10: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 10/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 8 of 67

Page 11: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 11/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 9 of 67

Page 12: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 12/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 10 of 67

Page 13: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 13/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 11 of 67

Page 14: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 14/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 12 of 67

Page 15: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 15/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 13 of 67

Page 16: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 16/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 14 of 67

Page 17: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 17/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 15 of 67

Page 18: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 18/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 16 of 67

Page 19: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 19/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 17 of 67

Page 20: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 20/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 18 of 67

Page 21: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 21/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 19 of 67

Page 22: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 22/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 20 of 67

Page 23: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 23/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 21 of 67

Page 24: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 24/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 22 of 67

Page 25: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 25/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 23 of 67

Page 26: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 26/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 24 of 67

Page 27: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 27/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 25 of 67

Page 28: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 28/69

Page 29: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 29/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 27 of 67

Page 30: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 30/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 28 of 67

MEETING MINUTES (October 13th, 2010)

-------------------------

Old Business:

- The section "Economics of the Business" Does not have to be completed (similar to "Financial Aspects")...

- If there are any new "References" make sure I get them BY TOMORROW AT 3:00 PM!

-------------------------

New Business:

- I will be uploading the MARKED "Business Opportunity Document". Take note of where we lost marks

(Market, Product, Technology). If an instance where we lost marks appears in your section, MAKE SURE IT'S

INCLUDED in your new section.

- I will be uploading a copy of the "Business Plan Proposal". Everyone PLEASE review it. If any changes need to

be made, let me know BY TOMORROW at 3:00 PM.

Future Presentations:

- Dehydrated Plan Presentation (Nov 1)

Page 31: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 31/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 29 of 67

--> Scott & Ravish

...- Business Plan Presentation (Nov 24)

--> Shannon & Mohamed

-------------------------

Next Assignment:

Dehydrated Business Plan / Progress Report Hard Copy (Nov 10)

-------------------------

Next Meeting:

October 15th, IN CLASS

- Scott will have necessary sections prepared for the "Dehydrated Business Plan" so that we may distribute them

between the team members.

- If you are not present, your tasks will not be your choice

Page 32: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 32/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 30 of 67

Page 33: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 33/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 31 of 67

Page 34: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 34/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 32 of 67

Page 35: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 35/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 33 of 67

Page 36: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 36/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 34 of 67

Page 37: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 37/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 35 of 67

Page 38: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 38/69

Page 39: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 39/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 37 of 67

Page 40: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 40/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 38 of 67

Page 41: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 41/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 39 of 67

Page 42: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 42/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 40 of 67

Page 43: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 43/69

Page 44: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 44/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 42 of 67

Page 45: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 45/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 43 of 67

Page 46: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 46/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 44 of 67

Page 47: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 47/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 45 of 67

Page 48: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 48/69

Page 49: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 49/69

Page 50: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 50/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 48 of 67

Page 51: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 51/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 49 of 67

Page 52: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 52/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 50 of 67

Page 53: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 53/69

Page 54: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 54/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 52 of 67

Page 55: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 55/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 53 of 67

Page 56: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 56/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 54 of 67

Page 57: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 57/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 55 of 67

Page 58: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 58/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 56 of 67

Page 59: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 59/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 57 of 67

Page 60: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 60/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 58 of 67

Page 61: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 61/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 59 of 67

Page 62: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 62/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 60 of 67

Page 63: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 63/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 61 of 67

Page 64: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 64/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 62 of 67

Page 65: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 65/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 63 of 67

Page 66: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 66/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

Page 64 of 67

Page 67: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 67/69

Page 68: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 68/69

Page 69: Post Mortem Complete

8/8/2019 Post Mortem Complete

http://slidepdf.com/reader/full/post-mortem-complete 69/69

  Eng M 402 – Project Management & Entrepreneurship

Post Mortem - Group 2

December 10th

, 2010

References

eClass –ENG M 402 – PROJ MGMT & ENTREPRENEURSHIP (LEC A1 Fa10). (n.d.).  EngG 402 – Post 

 Mortem – Group 6 – Human Power . Retrieved from

https://vista4.srv.ualberta.ca/webct/urw/lc5122011.tp0/cobaltMainFrame.dowebct