pmp sample questions set 3
DESCRIPTION
PMP Exam Sample QuestionsTRANSCRIPT
PMP® Sample
Questions
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the
development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every
attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam.
However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially
published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or
expressed by OSP International LLC.
This presentation will showcase free sample
PMP® questions that will help and guide
you in studying for your PMP® exam
Find more free sample questions when you visit
www.free-pm-exam-questions.com and
free.pm-exam-simulator.com
Which of the following diagramming techniques is a typical display of
Sensitivity Analysis?
a. Influence Diagram
b. Network Diagram
c. Fishbone Diagram
d.Tornado Diagram
Sample PMP® Exam Question
HINT: It compares relative importance and impact of variables that have a
high degree of uncertainty to those that are more stable.
The correct answer is D
One typical display of Sensitivity Analysis is
the Tornado Diagram, which is useful for
comparing the relative importance and
impact of variables that have a high degree
of uncertainty to those that are more
stable.
Answer and Explanation
Which of the following statements regarding WBS
templates is incorrect?
a. They are always present in Organizational
Process Assets.
b. They provide a starting point for WBS
creation.
c. They may help determine the appropriate
level of detail required.
d.They enhance cross-project WBS consistency.
Sample PMP® Exam Question
HINT:WBS templates can help you create your projectWBS.
The correct answer is A
WBS Templates can be found in
Organizational Process Assets but we
cannot say they will always be available.
Answer and Explanation
Project Integration Management consists of all of the following activities
except?
a. Develop Project Charter
b. Develop Project Management Plan
c. Perform Integrated Change Control
d.Collect Requirements
Sample PMP® Exam Question
HINT: Project Integration Management includes the processes and activities
to identify, define, combine, unify, and coordinate various processes and
activities.
The correct answer is D
Collect Requirements is not a process in
Project Integration Management. This
process is contained in Project Scope
Management.
Answer and Explanation
The risk shared between the buyer and the seller is determined by which of
the following?
a. The Scope of Work
b. The Teaming Agreement
c. The Contract Type
d.The Project Charter
Sample PMP® Exam Question
HINT: How can you control the project risk while
negotiating the scope of work with a seller?
The correct answer is C
The risk shared between the buyer and
seller is determined by the contract type.
For example, fixed-price contracts have a
higher risk for the seller while cost-
reimbursable contracts have a higher risk
for the buyer.
Answer and Explanation
You are developing your IT development project team. Some of the team
members need training on the latest software that you are using in your
project. Which of the following documents is most useful to find out the
information regarding the scheduled training for the team members?
a. Project Staff Assignments
b. Training Management Plan
c. Staffing Management Plan
d.Human Resource Plan
Sample PMP® Exam Question
HINT: Training needs are developed during the
early stages of planning.
The correct answer is D
The Human Resource Plan is used to
document details about training and
training schedules.
Answer and Explanation