pmp five sample questions

12
PMP® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Upload: osp-international-llc

Post on 08-May-2015

232 views

Category:

Education


0 download

DESCRIPTION

This presentation will showcase free sample PMP® questions that will help and guide you in studying for your PMP® exam

TRANSCRIPT

Page 1: PMP Five Sample Questions

PMP® Sample Questions

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Page 2: PMP Five Sample Questions

This presentation will showcase free sample PMP® questions that will help

and guide you in studying for your PMP® exam

Find more free sample questions when you visit www.free-pm-exam-questions.com

and free.pm-exam-simulator.com

Page 3: PMP Five Sample Questions

To calculate the total project cost, you use a technique that uses input values selected at random from probability distribution of possible cost. Which of the following options best describes this method?

a. Automated Schedule Development. b. Monte Carlo Analysis. c. Schedule Risk Analysis. d.e-Pert.

Sample PMP® Exam Question

HINT: This is a simulation technique.

Page 4: PMP Five Sample Questions

The correct answer is B Monte Carlo analysis is a simulation technique. It uses computer models and estimates of risk usually expressed as a probability distribution of possible costs or durations at a detailed work level.

Answer and Explanation

Page 5: PMP Five Sample Questions

Which of the following tasks will not be done by the processes in the planning process group?

a. Define and refine objectives. b. Plan the course of action required to attain

the objectives. c. Identify the project scope. d. Integrate people and other resources to

carry out the project management plan for the project.

Sample PMP® Exam Question

HINT: What is the function of the Direct and Manage Project Work process?

Page 6: PMP Five Sample Questions

The correct answer is D Integrating resources is the task of the Direct and Manage Project Work process that belongs to the executing process group.

Answer and Explanation

Page 7: PMP Five Sample Questions

A project manager is making a quantitative assessment of the probable cost of the resources required to complete the schedule activities. He considers inflation allowance and a special cost contingency reserve. Which type of estimation is this an example of?_x000D_

a. Parametric Estimation b. Activity Cost estimation c. Cost aggregation d.Funding Limit Reconciliation

Sample PMP® Exam Question

Hint: The PM is determining the activity costs and contingency reserve requirements.

Page 8: PMP Five Sample Questions

The correct answer is B The PM is determining the activity costs and contingency reserve requirements. This is a part of the Estimate Costs process.

Answer and Explanation

Page 9: PMP Five Sample Questions

The total actual cost incurred in accomplishing a task on the schedule activity is $650 and the earned value on the schedule activity is $900. What would the cost performance index indicate?

a. Cost overruns. b. Cost underrun. c. Cost as per estimation d.Project progress

Sample PMP® Exam Question

HINT: CPI = EV / AC

Page 10: PMP Five Sample Questions

The correct answer is B CPI=EV/AC, EV = 900, AC = 650. Therefore, CPI = 1.38. CPI > 1 indicates cost underrun.

Answer and Explanation

Page 11: PMP Five Sample Questions

Management decided to introduce a quality management program which required the employees to learn statistical process control techniques. The employees responded negatively to this change. What can be the probable reason for this?

a. They fear they will lose their job b. Threat of safety c. Change will lower their income d.Fear of the unknown

Sample PMP® Exam Question

HINT: This fear results in resistance to change

Page 12: PMP Five Sample Questions

The correct answer is D The employees are resisting because they are not familiar with the new technique. Fear of the unknown is a very common human characteristic. They fear that they will not be able to perform on the job. The PM should use his/her interpersonal skills to manage this resistance to change.

Answer and Explanation