pmp integration and scope management
TRANSCRIPT
-
7/27/2019 PMP Integration and Scope Management
1/60
Project Integration Management
Project Management
Professional - PMP
Presenter:Falik Sher, PMPeVentureSolutions (Pvt) Ltd.
-
7/27/2019 PMP Integration and Scope Management
2/60
Introduction
Project Integration Management includes theprocess and activities needed to identify,
define, combine unify and coordinate the
various processes and PM activities with the
PM process groups.
Project integration management entails making
choices about resources allocation, making
trade-offs among competing objectives and
alternatives and managing the
interdependencies among the PM knowledge
Areas.
-
7/27/2019 PMP Integration and Scope Management
3/60
Introduction
If you were asked "What is the main role of theproject manager?"
I guess the answer is to perform integration. While
the work of the project is being done, it is the teammembers' role to concentrate on completing thework packages. The project sponsor should beprotecting the project from changes and loss ofresources. It is the project manager's role to put allthe pieces of the project together into one cohesivewhole that gets the project done faster, cheaperand with fewer resources while meeting the projectobjectives.
-
7/27/2019 PMP Integration and Scope Management
4/60
Processes
The project Management processes are usuallypresented as discrete processes with definedinterfaces while, in practice, they overlap andinteract in ways that can't be completelydetailed.
Develop Project Charter
Develop Project Management Plan
Direct and Manage Project Execution
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase
-
7/27/2019 PMP Integration and Scope Management
5/60
Develop Project Charter
Develop Project Charter is the process of
developing a document that formally authorizes
a project or a phase and documenting initial
requirement that satisfy the stakeholders' needs
and expectations.It establishes a partnership between the
performing organization and the requesting
organization.
The approved project charter formally initiates
the project.
-
7/27/2019 PMP Integration and Scope Management
6/60
Develop Project Charter
Inputs: Project statement of Work
Business case
Contract
EEF
OPA
T and T: Expert Judgment
Output: Project Charter
-
7/27/2019 PMP Integration and Scope Management
7/60
Project Charter Data Flow
-
7/27/2019 PMP Integration and Scope Management
8/60
Develop Project Management Plan
Develop Project Management Plan is theprocess of documenting the actions necessaryto define, prepare, integrate and coordinate allsubsidiary plans.
The project management plan defines how theproject is executed, monitored & controlled andclosed.
The contents will vary depending upon theapplication area and complexity.
-
7/27/2019 PMP Integration and Scope Management
9/60
Develop Project Management Plan
Inputs: Project Charter
T and T: Expert Judgment
Output: Project Management Plan
-
7/27/2019 PMP Integration and Scope Management
10/60
-
7/27/2019 PMP Integration and Scope Management
11/60
Direct & Manage Project Execution
Staff, Train & Manage HR
Obtain, manage and use resources
Implement the plan methods, standards
Establish & manage project communication
channels
Generate project data
Issue change requests
Manage risks
Manage seller and suppliers
Collect and document lessons learned
-
7/27/2019 PMP Integration and Scope Management
12/60
Inputs: Project management plan
Approved change requests
EEF
OPA
T and T: Expert Judgment
Project management IS
Output: Deliverables
Work performance information
Change requests
Project Management Plan update
Project document update
Direct & Manage Project Execution
-
7/27/2019 PMP Integration and Scope Management
13/60
Direct&
Manage
ProjectE
xecution
Dataflo
w
-
7/27/2019 PMP Integration and Scope Management
14/60
Monitor & Control Project Work
Comparing actual performance
Determine any corrective/preventive actions
Identifying new risks and analyzing, tracking
and monitoring existing risks
Maintaining accurate, timely information base
Provide information to support status
reporting, measurement and forecasting
Forecasts to update current costs/ schedule Monitoring implementation of approved
changes
-
7/27/2019 PMP Integration and Scope Management
15/60
Inputs: Project Management Plan
Performance Reports
EEF
OPA
T and T: Expert Judgment
Output: Change RequestsProject Management Plan update
Project Document update
Monitor & Control Project Work
-
7/27/2019 PMP Integration and Scope Management
16/60
Monitor & Control Project Work
-
7/27/2019 PMP Integration and Scope Management
17/60
Monitor & Control Project Work
Project Management PlanPerformance Reports
Current status
Significant accomplishments for the period
Scheduled activities
Forecasts
Issues
EEFOPA
-
7/27/2019 PMP Integration and Scope Management
18/60
Monitor & Control Project Work
Change Requests Corrective action
preventive action
defect repair
Project Management Plan update
Project document update
-
7/27/2019 PMP Integration and Scope Management
19/60
Perform Integrated Change Control
Influencing the factors that circumvent
integrated change control
reviewing, analyzing and approving CRs
promptly
Managing approved changes
Maintaining the integrity of baselines
Reviewing, approving/denying recommended
corrective and preventive actions Coordinating changes
Impact analysis documentation
-
7/27/2019 PMP Integration and Scope Management
20/60
Inputs: Project Management Plan
Work Performance information
Change Requests
EEF
OPA
T and T: Expert Judgment
Change Control meetings
Output: Change Requests update
Project Management Plan update
Project Document update
Perform Integrated Change Control
-
7/27/2019 PMP Integration and Scope Management
21/60
Perform Integrated Change Control
-
7/27/2019 PMP Integration and Scope Management
22/60
Change Requests Many executing and M&C process produce
change requests. Corrective, preventive actionsand defect repairs.
Usually corrective and preventive actions don't
affect the baselines, but the performance
Change Control meetings CCB is responsible for meeting and reviewing the
change requests and approving/ rejecting changerequests.
All decisions made by CCB are documented andcommunicated to all stakeholders
Perform Integrated Change Control
-
7/27/2019 PMP Integration and Scope Management
23/60
Close Project or Phase
Actions and activities to satisfy completion or
exit criteria for the phase or project
Actions and activities to transfer the project
product, service or result to next phase or toproduction/operations
Activities needed to collect project/phaserecords. Audit project success or failure, gather
lessons learned and archive project info for
future use.
-
7/27/2019 PMP Integration and Scope Management
24/60
Inputs: Project Management Plan
Accepted deliverables
OPA
T and T: Expert Judgment
Output: Final product, service or result
OPA updates
Close Project or Phase
-
7/27/2019 PMP Integration and Scope Management
25/60
Close Project or Phase
-
7/27/2019 PMP Integration and Scope Management
26/60
Accepted Deliverables
Those deliverables that have been accepted
through the verify scope process
Final Product service or Result the output refers to the transition of the final
product, service or result that the project was
authorized to produce.
Close Project or Phase
-
7/27/2019 PMP Integration and Scope Management
27/60
Break
Break
-
7/27/2019 PMP Integration and Scope Management
28/60
Project Scope Management
Project Management
Professional - PMP
Presenter:Falik Sher, PMPeVentureSolutions (Pvt) Ltd.
-
7/27/2019 PMP Integration and Scope Management
29/60
Introduction
Project Scope management includes the
processes required to ensure that the project
includes all the work required and only the work
required to complete the project successfully.
Collect Requirement
Define Scope
Create WBS
Verify Scope
Control Scope
-
7/27/2019 PMP Integration and Scope Management
30/60
Collect Requirements
Collect requirements is the process of defining
and documenting stakeholder's need to meet
the project objectives.
Requirements include the quantified and
documented needs and expectations of thesponsor, customer and other stakeholders.
The development of requirements begins with
an analysis of the information contained in the
project charter.
-
7/27/2019 PMP Integration and Scope Management
31/60
Inputs: Project Charter
Stakeholder register
T and T: Interviews
Focus groups
Facilitated workshops
Group creativity techniques
Group decision making techniques
Questionnaires and surveys
Observations
Prototypes
Output: Requirement documentation
Requirement management plan
Requirement traceability matrix
Collect Requirements
-
7/27/2019 PMP Integration and Scope Management
32/60
Collect Requirements
Stakeholder Register
Register is used to identify the stakeholders who
can provide information on detailed project and
product requirements.
Identifying all people or organizations impacted by
the project and documenting relevant information
regarding their interests, involvement and impact
on project success.
Stakeholders may be at different levels within the
organizations and may possess different authoritylevels or may be external to performing
organization for the project.
-
7/27/2019 PMP Integration and Scope Management
33/60
Collect Requirements
Interview
an interview is a formal approach to discover information fromstakeholders by talking to the directly.
Focus GroupsFocus groups bring together prequalified stakeholders and
subject matter expert to learn about their expectations andattitudes about a proposed product, service or result.
Facilitated Workshopsworkshops are considered a primary technique for quicklydefining cross-functional requirement and reconcilingstakeholder differences.Because of their interactive group nature, well-facilitatedsessions can build trust, foster relationships and improvecommunication among the participants which can lead toincreased stakeholder consensus.
-
7/27/2019 PMP Integration and Scope Management
34/60
Collect Requirements
Group creativity TechniquesSeveral group activities can be organized toidentify project and product requirements
nominal group technique - voting
the Delphi technique - expert answers
idea/mind mapping - single map - commonality &differences
affinity diagram - sorted into groups
Group decision Making Techniquesunanimity - agreesmajority - major supports
plurality - largest block support without majority
dictatorship - ...........
-
7/27/2019 PMP Integration and Scope Management
35/60
Questionnaires and Surveys
Written sets of questions designed to quickly accumulateinformation from a wide number of respondents.
Observations
Observations provide a direct way of viewing individuals intheir environment and how they perform their jobs or tasks.
This is helpful when people that use the product havedifficulty or reluctant to write their requirements.
Prototypes
Incremental working model presentation to stakeholders
Collect Requirements
-
7/27/2019 PMP Integration and Scope Management
36/60
Requirement Documentation Describes how individual requirements meet the business
need for the project.
May start at high level and progressively more detailed asmore is known.
Before baseline requirement must be UNAMBIOUGUS(Measurable & Testable), traceable, complete, consistentand acceptablebusiness need objectives
functional requirement non-functional requirement
Quality Acceptance criteria
Business rules impact to others
support and training assumptions and constraints
Collect Requirements
-
7/27/2019 PMP Integration and Scope Management
37/60
Requirement Management Plan
Documents how requirements will be analyzed, documented andmanaged throughout the project
How requirements activities will be planned, tracked and reported.
configuration management - CR
Prioritization process
Product metrics - rationale for using such metrics
traceability structure - what should be on traceability matrix
Requirement traceability Matrix Table that links requirements to their origin and traces them
throughout the project life cycle.
Req. to business needs, opportunities goals and objectives Req. to project scope/WBS
Req. to design
Req. to development
Req. to test scenarios
High level requirements to more detailed
Collect Requirements
-
7/27/2019 PMP Integration and Scope Management
38/60
Defining Scope
The preparation of a detailed project scope
statement is critical to project success and buildsupon the major deliverables, assumption and
constraints that are documented during project
initiation.
During planning the project scope is defined and
described with greater specificity as more
information about the project is known.
Existing risks assumptions and constraints areanalyzed for completeness.
-
7/27/2019 PMP Integration and Scope Management
39/60
Inputs: Project Charter
Requirement DocumentationOPA
T and T: Expert Judgment
Product AnalysisAlternative Identification
Facilitated workshops
Output: Project Scope Statement
Project document update
Defining Scope
-
7/27/2019 PMP Integration and Scope Management
40/60
Defining Scope
-
7/27/2019 PMP Integration and Scope Management
41/60
Defining Scope
Product analysis
For projects that have product as deliverables as
opposed to a service or result, product analysis can
be effective tool.
Each application area has one or more generally
accepted methods and translating high-levelproduct description into tangible deliverables.
Alternative Identification
Identifying alternatives is a technique used to
generate different approaches to execute and
perform the work the project.
-
7/27/2019 PMP Integration and Scope Management
42/60
Defining Scope
Project Scope Statement Product Scope Description Product Acceptance criteria
Project Deliverables
Project exclusions
Project constraints Project assumptions
Project Document updates Stakeholder register
Requirements documentation
Requirement traceability matrix
-
7/27/2019 PMP Integration and Scope Management
43/60
Create WBS
Create WBS is the process of subdividing project
deliverables and project work into smaller moremanageable components.
The WBS is a deliverable-oriented hierarchical
decomposition of the work to be executed by the projectteam to accomplish the project objectives and create the
required deliverables .
The planned work is contained within the lowest levelWBS components, which are called work packages. A
work package can be scheduled, cost estimated and
monitored and controlled.
C WBS
-
7/27/2019 PMP Integration and Scope Management
44/60
Create WBS
Inputs: Project scope statement
Requirements documentation
OPA
T and T: Decomposition
Output: WBS
WBS DictionaryScope baseline
Project document updates
C t WBS
-
7/27/2019 PMP Integration and Scope Management
45/60
Create WBS
Decomposition
is the subdivision of project deliverables into smallermore manageable components until the work anddeliverables are defined to the work package level.
the work package level is the lowest level in the WBS
and is the point at which the cost and activitydurations for the work can be reliably estimated andmanaged.
Identifying and analyzing the deliverables and related work
Structuring and organizing the WBSDecomposing the upper WBS into lower level detailed.
Developing and assigning identification codes to the WBS
Verifying that the degree of decomposition of the work isnecessary
C t WBS
-
7/27/2019 PMP Integration and Scope Management
46/60
Create WBS
WBS
The WBS is deliverable-oriented hierarchical decomposition of thework to be executed by the project team to accomplish the projectobjectives and create the required deliverables with each descendinglevel of the WBS representing an increasingly detailed definition ofthe project work.
The WBS is finalized by establishing control accounts for the work
packages and unique identifier from a code of accounts.
WBS DictionaryThe WBS dictionary is a document generated by the create WBSprocess that supports the WBS. This provide detailed descriptions of
the components in the WBS, including work packages and controlaccounts.Code of account identifier
Description of work
Responsible organization
Verify Scope
-
7/27/2019 PMP Integration and Scope Management
47/60
Verify Scope is the process of formalizing
acceptances of the completed project deliverables.
Verifying scope includes reviewing deliverables with
the customer or sponsor.
Scope verification differs from quality control. Scopeverification is primarily concerned with acceptance of
the deliverables.
Quality control is generally performed before scope
verification, but these two processes can beperformed in parallel.
Verify Scope
Verify Scope
-
7/27/2019 PMP Integration and Scope Management
48/60
Verify Scope
Inputs: Project management plan
Requirement documentation
Requirement traceability matrix
Validated deliverables
T and T: Inspection
Output: Accepted deliverables
Change requests
Project document updates
Verify Scope
-
7/27/2019 PMP Integration and Scope Management
49/60
Verify Scope
Verify Scope
-
7/27/2019 PMP Integration and Scope Management
50/60
Verify Scope
Project management plan
Project scope statement
WBS
WBS dictionary
Requirement documentation
The requirement documentation lists all the project product,
technical and other types of requirements that must be
present for the project and product along with theiracceptances criteria.
Verify Scope
-
7/27/2019 PMP Integration and Scope Management
51/60
Requirement traceability matrix
The requirements traceability matrix links
requirements to their origin and tracks the
throughout the project life cycle.
Validated deliverables
Validated deliverables have been completed and
checked for correctness by the performs qualitycontrol process
Verify Scope
Verify Scope
-
7/27/2019 PMP Integration and Scope Management
52/60
Inspection
Inspection includes activities such as measuringexamining and verifying to determine whether workand deliverables meet requirements and productacceptance criteria. Inspections are sometimescalled reviews, product reviews, audits andwalkthroughs.
Accepted deliverables
Deliverables that meet the acceptance criteria areformally signed off and approved by the customeror sponsor. Formal documentation received fromthe customer or sponsor acknowledging.
Verify Scope
Verify Scope
-
7/27/2019 PMP Integration and Scope Management
53/60
Change requests
Those completed deliverables that have not been
formally accepted are documented, along with the
reasons for non-acceptance. These deliverables
may required a change request for defect repair.
Project document updates
Project documents that may be updated as a result
of the verify scope process include any documents
that define the product or report status on product
completion.
Verify Scope
Control Scope
-
7/27/2019 PMP Integration and Scope Management
54/60
Control scope is the process of monitoring the
status of the project and product scope andmanaging changes to the scope baseline.
Controlling the project scope ensures all
requested changes and recommendedcorrective or preventive actions are processed
through the Perform integrated change control
process.Uncontrolled changes are often referred to as
project scope creep
Control Scope
Control Scope
-
7/27/2019 PMP Integration and Scope Management
55/60
Control Scope
Inputs: Work performance information
Requirement documentation
Requirement Traceability matrix
Organizational process assets
T and T: Variance analysis
Output: Work performance measurements
OPA updates
Project Management Plan
Project document updates
Control Scope
-
7/27/2019 PMP Integration and Scope Management
56/60
Control Scope
Control Scope
-
7/27/2019 PMP Integration and Scope Management
57/60
Project Management Plan
Scope baseline Scope management plan
Change management plan
Configuration management plan
Requirements management plan
Work Performance information information about project progress, such as which
deliverables have started their progress and whichdeliverables have finished
Organizational Process Assets Existing formal and informal scope control-related
policies, procedures and guidelines
Monitoring and reporting methods to be used
Control Scope
Control Scope
-
7/27/2019 PMP Integration and Scope Management
58/60
Variance Analysis
Project performance measurements are used to assess themagnitude of variation from the original scope baseline.
Work performance measurement Measurements can includes planned vs actual technical
performance or other scope performance measurements. this
information is documented and communicated to stakeholders.OPA Updates
Causes of variances
Corrective actions chosen and reasons
Other lessons learned
Change Requests Analysis of scope performance can result in a change request to the
scope baseline or other components of the project managementplan.
Control Scope
Control Scope
-
7/27/2019 PMP Integration and Scope Management
59/60
Project Management Plan UpdatesScope baseline updates
Other baseline updates
if the approved change requests have an effect
on the project scope then the corresponding costbaseline and schedule baselines are revised andreissued to reflect the approved changes.
Project Document UpdatesRequirements documentation
requirements traceability matrix
Control Scope
-
7/27/2019 PMP Integration and Scope Management
60/60