pm tools and techniques
TRANSCRIPT
Project Management InstituteNashville Symposium
Project Management Tools and Techniques - Building Commuter Rail on a Shoestring
Donelson
Riverfront
HermitageLebanon
Martha
Mt. Juliet
What is Project?
A temporary endeavor undertaken to create a unique product, service, or result.- Temporary: Projects are marked by a definite beginning and end
- Unique: The service or product is different in some distinguishing way from other products or services
What is Project Management?
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements
What is Project Management?
Project management can be applied to any project regardless of size, budget, or timeline. Some examples are:– Designing a mechanical device – Managing a marketing campaign – Building a bridge – Putting a satellite into orbit – Setting up an e-commerce Internet site OR…..– Building a Commuter Rail in Nashville TN
What is Project Management?
Needs and Expectations
of Stakeholders
Time Cost
Scope and Quality
RTA Overview
Regional focus incorporates nine-county region including Davidson County
Carpools, Vanpools, Relax & Ride Commuter Buses
Lead agency for Music City Star – Tennessee's first commuter rail
Project Partners / Stakeholders
Cities of Lebanon
City of Mt. Juliet
Metro Nashville/Davidson County
Wilson County
Tennessee Department of Transportation (TDOT)
the Nashville & Eastern Railroad Authority (NERA)
the Nashville & Eastern Railroad Corporation (NERC)
and the Nashville Metropolitan Transit Authority (MTA)
The Big Picture:Regional Transit Network
East Corridor Project Overview
32-mile existing single track section between Nashville and Lebanon
Track owned by a public agency, the Nashville & Eastern Railroad Authority
3 trains daily in peak a.m. and p.m.
Peak period reverse train to Mt. Juliet with off-peak reverse service to Lebanon
Goal of 1,500 daily riders
Baseline?
Completed Preliminary Engineering and Environmental Assessment in 1999
Received a Finding of No Significant Impact (FONSI) in 2000
Received approval from the Federal Transit Administration (FTA) to enter into Final Design in June 2001
Disagreement amount the Board on the scope of the project
Wilson County wanted reverse peak commute
What Baseline?
Estimates for the necessary improvements to accommodate reverse peak commute were double the original capital estimate
No baseline scope, estimate or schedule
When final design kicked off in May 2002, there were “several” versions of the budget floating around
Defined WBS / Scope / Budget
The main objective was to have the Board adopt a baseline budget, scope and schedule
A Work Breakdown Structure was developed
A cost loaded schedule was developed
A baseline scope was adopted
Development of Baseline Documents
This enabled everyone to be working from the same documents and provide a baseline for the Board of Directors
Notebooks were assembled with the baseline documents and site layouts for each station
Allyson’s famous sayings “There is only one budget” and “Hope is not a strategy!”
Set Funding Determines Budget and Scope
Funding for project
– FTA 5309 “New Starts” funds $24,000,000
– FHWA funds for stations 7,373,851
– TDOT assistance 10% of local match 4,098,332
– Local Governments 4,098,332
– Total Budgeted Costs $39,570,515
Scope Must Be Managed During the Design Phase
Scope Management
– With baseline documents – a change control process is needed to monitor and control changes
– A configuration management process was developed and implemented early in the project
Lessons Learned from Seattle – Contract Administration
Lessons Learned / Contract Management
– Lessons Learned were applied from previous projects
– Design to budget terms were put in the Design contract
– Penalties and re-design at no cost clauses were added
– This was useful in several areas – signals and stations
Risk Assessment / Mitigation
Risk Management
– Early in preliminary engineering it was determined that used cars would be acquired from MARC (Maryland Administration for Rail Commuters)
– MARC was retiring the vehicles rather than investing to upgrade to meet the latest Safety Hazard criteria for passenger cars
– A major investment would have to made to bring the cars to Federal Railroad Administration standards as well as meet the Americans with Disabilities Act
Risk Assessment / Mitigation
Initial Cost
Per Unit
Rehabilitation Cost
(Minimal)
Useful Life
(Years)
Annual Maintenance Cost
FRA Complian
ce
ADA Complian
tDwell Time Per Station
Meets Clean Air Standards
Cars
MARC (single level) $20,000 $25K-250K 5 $15K-$20K No No 3 minutes N/A
Coment (single level) $200,000 $25K-250K 7 $15K-$20K No No 3 minutes N/A
Chicago METRA (bi-level) $250,000 $25K-250K 7 $60K-$65K No No 2 minutes N/A
New (bi-level) $1,900,000 $0 40 $63,000 Yes Yes 40 seconds N/A
Locomotives
E9 (used) $150,000 $100K-$1M 5 $84,000 No N/A N/A No
F-40 (used) $250,000 $100K-$1M 8 $84,000 No N/A N/A No
F-59 (new) $3,000,000 $0 25 $75,000 Yes N/A N/A Yes
Team Work/ Communication
QA Consultant former employee of Metra in Chicago
Served as Project Manager for fleet overhaul in 1999 and 2000
Had contacts in Chicago - Put RTA in touch with Metra in Chicago
RTA was able to get “first pick” of the fleet they were retiring
Acquired the passenger cars and coaches at no cost!
Rail Fleet – total cost $575,000
• Three recently rebuilt former Amtrak Locomotives – purchased in October, 2004
• Seven coaches and four cab cars acquired by transfer of federal interest from Chicago’s Metra operation –
received in June, 2004
• Repainting of equipment and ADA compliance refit
Interior Railcar
Bi-level gallery cars with seating on both levels
Each seat can easily be reversed to allow passengers to ride facingeither direction
Can also configure seats for groups
Managing Stakeholder Expectations
Riverfront Station
– The original station concept taken to preliminary engineering was very “minimalist”
– The east corridor is the only corridor that will terminate at Riverfront
– Low budget – limited funds
– During the 30% design review, Metro Nashville determined the Riverfront station should more of a flagship station
– A “presence” in the downtown was desired
Stakeholder Involvement
Meetings held with Metro Nashville
– A series of meeting were held with representatives Metro planning, public works, ADA Compliance, parks, the Mayor’s office and the Civic Design Center
– A new concept was developed
– All parties had buy-in on the new concept
New Concept presents New Obstacles
The revised concept extended the footprint of the station beyond the footprint covered in the Environmental Assessment
A Supplemental Environmental Assessment was needed for the extended foot print
The extended foot print is on “park” property owned by the Army Corps of Engineers and leased to Metro Nashville
New Concept presents New Obstacles
During the Phase I cultural review of the supplemental EA, a “discovery” was identified
The “discovery” was that of a Brennan Foundry, also known as the Claiborne Machine Works
This foundry had a significant role during the Civil War as a munitions plant
Specialized in the production of iron cannons
This foundry manufactured 71 cannons for the Confederate government between 1861 and the fall of Nashville in 1862
Team Work
Based on this information, a Phase II archeological excavation was conducted
Due to the excavation being on Park Land – all Native American tribes had to be notified – FTA handled this activity for the RTA
We were able to use Metro Nashville purchasing department and on-call excavation contractors to expedite the process and avoid the time to competitively bid the work
The archeologist was brought in under the design consultant’s contract
The excavation was completed within 1 week
Team Work
The excavation uncovered the foundation of the foundry and the walls
The excavation determined the foundry was deep enough so that our construction of the station would not impact the historical resource
A Finding of No Significant Impact was Issued by the FTA
Nashville Riverfront – 1880s
Brennan Foundry ca. 1864
Nashville Riverfront
Nashville Riverfront
Ferry Building Foundation, Nashville Riverfront
Artifacts from Ferry Building Nashville Riverfront
Team Work
Metro Nashville agreed to pay for “betterment” of the station
The structure is designed to resembled typical train depots at the turn of the century, in Tennessee
Obstacle– FTA Civil Rights Office’s Interpretation of the American with
Disabilities Act Situation
– During PE the project had determined to use the mini-high platform with bridge plates for boarding of mobility impaired passengers
– This is the model used by all commuter rail passenger service implemented since 1992
– There was over $6 million in grant funds that had the potential of lapsing (meaning lost) if the Civil Rights Office did not approve the grant
Operational / Structural Infeasibility for Level Boarding
The Federal Railroad Administration (FRA) defers to standards defined by the States, including the State of Tennessee, and published as a standard in the American Railway Engineering and Maintenance-of Way Association (AREMA) guidelines for the safety of railway workers. These are the requirements that the NERC must operate within
Alternatives under Exception 2
Communications
The FTA Civil Rights team came to Nashville
A face to face meeting was held between the Civil Rights Office and the disabled community
A meeting was held between the Project Management Team and the Civil Rights team
Approval was granted on concept and use of mini-high platforms and bridge plates
Lessons Learned –face to face communication is very important
Project Management Tools – Team Work / Communications
Risk Mitigation / Innovative Contracting
Situation
– To avoid further cost escalation due to delays, construction needed to begin in summer 2004
– All federal funding had not been appropriated
– A construction implementation plan and obligation plan were developed to mitigate the risk of beginning construction and then having to “place project on hold” and pay delay claims to contractors
– A plan was developed to phase construction into 2 phases with all work from Nashville to Mt. Juliet in Phase 1 and all work from Mt. Juliet to Lebanon in Phase 2
Risk Transference
Risk Mitigation & Innovative Contracting – To enable the contractors bidding to provide prices good for
180 days, all the steel (rail) was removed from the bid package
– RTA purchased the steel (rail) directly removing this risk items from the contractors so they could provide pricing without the unknown fluctuations of the steel prices
Moving Ahead with Construction
Construction would be awarded in phases
This effectively dealt with the funding obstacles
Construction began on November 8, 2004
Over 145,000 feet of rail was installed
53% of the route is new rail
Situation– All bids for stations came in approximately 45% over the engineer’s
estimates
– The construction market and prices for concrete and steel were extremely volatile at that time
Value Engineering & Contracting Ideas– The contract duration was increased so that the costs could be reduced
– Value Engineering ideas were implemented to reduce the cost by replacing paving with chip and seal, reducing the thickness of the concrete on the sidewalks, reducing the number of shelters and working with a property owner to only acquire the amount of land needed versus the entire parcel
Risk Management
Value Engineering & Contracting Ideas– Changed the typical curb section from full curb and gutter to a post curb
which enabled us to put paving back in at no cost
– The project team also decided to use parking ticket machines for platform ticket sales, which are approximately $16,000 / unit as opposed to standard fare collection equipment used at other properties which range from $100,0000 / unit to $500,000 / unit.
Risk Management
Track Rehabilitation
80% of the rail is now continuous welded rail
Approximately 1 out of 3 ties was replaced
Results; a smoother safer ride with less maintenance
Increased maximum passenger speed to 59 mph
Bridges
3 Bridges Rehabilitated
7 Bridges Replaced
4 New Bridges
Signals
All public grade crossing were upgraded with warning systems between Nashville and Lebanon
Centralized Train Control (CTC) was installed between Nashville and Lebanon
Trains are dispatched out of the Lebanon Yard Office
Stations
All Aboard!!!!
Titans Trains
Appreciating the Riders!
Questions?
Remember to LOOK LOOK both ways,LISTEN LISTEN for the sounds of a train,
stop and yield to any oncoming train –
If we all LOOKLOOK and LISTENLISTEN, we will LIVELIVE!
Operation Lifesaver ®