Planning Electrical Infrastructure in Changing Times
Peter Marschall, P.E.Associate Facilities Program Coordinator
SUNY ESF, Syracuse, NY
Jeffrey L. Robbins, P.E.Senior Principal Engineer
C&S Engineers, Inc., Syracuse, NY
Presented by:
Learning Objectives
1. Recognize the basic concepts of site electrical infrastructure systems.
2. Evaluate opportunities and means for increasing electrical distribution reliability and their impact on costs.
3. Predict when replacement or modifications of the electrical infrastructure primary components must occur.
4. Explore ways to identify value added components to electrical distribution projects.
Agenda
What Triggers Expansion? Campus Planning & Electrical Infrastructure Site Electrical Distribution 101 System Considerations Cost Reduction Measures Value Added Components Construction Issues Lessons Learned
What Triggers Expansion?
Crisis
Opportunity
Program
Crisis
Failures within electrical system Electrical demand capacity
exceeded No expansion capabilities left
Opportunity
Incorporate infrastructure as part of other projects New buildings Building additions Site beautification projects
Works best if utility master-plan is in place
Program
Starts with a master plan of the utilities Should overlay with campus master plan
Provides for orderly upgrade of systems Can set up series of phases for improvements or
replacement of systems
Makes life easier for the Crisis and Opportunity upgrades
Campus Planning
Open communications with all levels of the Campus
Coordinate with Campus Master Plan Buildings getting bigger with more technology Create tandem utility infrastructure plan if possible
Remember buried infrastructure during surface beatification projects
Electrical Site Distribution 101
Basic Distribution Overview Definitions
Radial Network Loop Primary Selective
Review of different configurations Pros & cons
Basic Distribution Overview
Basic components: Utility service Substation (if required) Distribution switchgear Distribution system
DistributionSwitchgear
Substation
Definitions
Radial: A single simultaneous path of power flow to the load.
Network: More than one simultaneous path of power flow to the load.
Loop: Two paths of power flow to multiple loads that can be sectionalized.
Primary Selective (Dual Radial): Two radial feeders to each load.
Radial Feeder Configuration
Bldg. 1 Bldg. 2 Bldg. 3
Bldg. 6 Bldg. 4Bldg. 5
SubstationUtilityService
MH-5MH-3
MH-4MH-2
MH-1
Splice
Loop Feeder Configuration
Substation
Tie
Bus 1
Bus 2
UtilityService
Bldg. 1
NC NC
NCNC
Bldg. 2
NC NC
Bldg. 3
NC NO
Bldg. 6
NCNC
Bldg. 5
NCNC
Bldg. 4
Primary Selective Feeders
Substation
Tie
Bus 1
Bus 2
UtilityService
Bldg. 1
NO NC
NONC
Bldg. 2
NC NO
Bldg. 3
NO NC
Bldg. 6
NCNO
Bldg. 5
NONC
Bldg. 4
MH-1
MH-2
MH-3
MH-4
MH-5
Splice
Radial Feeder Analysis
Pro Least Amount of
Equipment Least Capital CostSimplest configuration
ConAny one failure will take
out entire feederMany splices, usually in
manholesCannot isolate a single
buildingMost susceptible to wide
spread outage
Loop Feeder Analysis
Pro 2 services to each buildingEasy to isolate buildingsHigh reliability Lower capital cost than
Primary Selective Flexible construction
ConOperation ConsiderationsMore equipment than Radial
FeedersHigher Capital Cost than
Radial Feeders
Primary Selective Analysis
Pro 2 services to each buildingHigh reliabilityEasiest to balance loads
on feeders Isolate main busses for
maintenanceAllows for double-ended
substations in buildings
ConMost amount of splices Time consuming to isolate
1 feederMore equipment that
Radial FeedersHighest capital cost
Hybrid Feeder Configuration
UtilityService
Bldg. 4
Substation
Tie
Bus 1
Bus 2
Bldg. 2
NC NO
Bldg. 3
NCNO
Bldg. 5
MH-1
MH-2 MH-3
MH-4
Bldg. 6
NCNONC NC
Bldg. 1
System Considerations
Reliability How much do we really need?
Expansion Review your Campus Master Plan
Existing distribution What do you have?
Public utilities Coordination
How much Reliability do we need?
How long can any one building be down? Are there critical loads?
Critical experiments Research & development Critical life support (hospitals)
Risk assessment How much is reliability worth?
Reliability of utility company’s service
Review Campus Master Plan
What projects are anticipated that will increase load?
What are your anticipated loads?
Critical nature of facilities? Adding critical life safety Adding research & development
Scheduling of projects?
Where are new facilities going to be located?
Existing Distribution System?
What is the capacity, condition & age? Substation, cables, ductbanks, bldg. transformers
Existing loads and where are they? Load profile Identify choke points in distribution
What configuration exists? Spare capacity in ductbanks? Hazardous material?
Asbestos (ductbanks, fire proof., insulation) PCB’s (Trans., switches, cables, potheads) Lead (cable sheathing)
Public Utility Coordination
What can the utility provide? Service voltage Service capacity Independent services
Any special tariffs? Voltage migration Co-generation surcharges Crossing public thru-fares
Cost associated with any changes? Utility service reliability? Distributed generation on campus?
Additional Considerations
Reliability requirements will drive system configuration Reliability has to be balanced with what you can afford
(cost vs. benefit) Can we and/or should we salvage any of the existing
system?SubstationCablesBuilding transformersDuctbank system
Additional Considerations (cont.)
What voltage should be used? Can the existing voltage be utilized?
Maintain existing substation if adequateMaintain existing building transformersUtilize existing cables
Higher the voltage, smaller cables can be usedCan save moneyMay have to replace all building transformersWhat can campus electrical personnel handle?Larger equipment size
Substation required?
Additional considerations (cont.)
What is the best configuration to use? Again, driven by reliability, followed by cost Radial – least expensive/least reliable Loop – reliable, flexible, expandable, easiest to construct Primary selective – reliable, flexible, allows for double
ended substations in buildings Combination – hybrid system
How will system upgrades/replacement be completed? Single project Phase project Incorporated into other projects
System Sizing
Look at existing loads plus future growth
If substation, transformers should be designed for n+1 configuration for reliability and redundancy Estimated load + 10 MVA 1 – 10 MVA xfmr + 1 – 10 MVA backup, total 2 xfmrs 2 – 5 MVA xfmrs + 1 – 5 MVA backup, total 3 xfmrs
For loop and selective primary systems, each side should be designed to carry full load of circuit
Ductbank Layouts
Configurations: Radial feed – Spline through campus with offshoots to
buildings Primary selective – similar to radial, sometimes with
separate manholes for each feeder. Loop system – loop around campus, try not to double
cable back in themselves for separation.
Existing utilities and electric room locations can dictate layout
Need good utility survey Ground penetrating radar (GPR) good for locating depths
of utilities
3 Loop Distribution
Cost Reduction Measures
First, need to look at cost vs. benefit
Can existing ductbank be reused: In proper location? In good condition? Right size and spares available?
Reuse of existing equipment
Downsize equipment
Voltage level
Construction in phases Build future capacity later
Value Added Enhancements
Sidewalks
Roads
Plaza Areas
Landscaping
Drainage
Communications
Other Utilities
Campuswide metering
Campus Communications
Early and frequent communications with administration, faculty, staff and students. Communications started a year prior to construction Campus briefings:
Outlined goals, benefits, scope, and impact on buildings
Departmental briefings:Focus departmental needs through department liaisons
Individual meetings Emails Websites
Preparation for Construction
Buildings will be shut down!
Required to be unoccupied during construction Impractical and costly in most cases to temporarily power
entire buildings. Some occupancy may be required
Researchers attend to flora and fauna
Try to schedule shutdowns on breaks, summer, holidays
Coordinate temporary work provisions
Schedule shutdowns as early as possible
Temporary Power Provisions
Identify critical electrical loads Department meetings On-line surveys Building walk-throughs with occupants and trades staff Protect critical research Chemical storage
Maintain critical services University police, student health Central receiving, mail Vehicle maintenance and fueling
Expect last minute additions to lists
Construction Issues
With existing radial systems, multiple shutdowns required at most buildings Building shutdown schedule dictated in contract documents
Maintain fire detection and alarm systems
Temporary generators/transformers Backfeed through breakers in existing switchgear Temporary distribution panels
Construction Issues
Campus and building Access, Parking Maintain handicap parking and building access
Coordination with fire department for access
Lessons Learned
Building occupants will consider project a nuisance, however, will soon forget.
Communications is key from concept through construction. Communicate early and frequently.
Have contingency plans during construction.
Plan now to avoid crisis mode or take advantage of an opportunity.
Plan for growth, it will happen.