pile installation methods_bhushan

Upload: bhushan1107

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Pile Installation Methods_Bhushan

    1/36

    Methods of Construction of

    Pile Foundations

  • 7/28/2019 Pile Installation Methods_Bhushan

    2/36

    Outline of Presentation

    1. Methods of installation of piles

    a. Driven Piles

    b. Bored Piles2. Case study:- Piling work at

    Bandra - Worli sea link ( BWSL )

    4/19/2013 2

  • 7/28/2019 Pile Installation Methods_Bhushan

    3/36

    Methods of installation

    The methods of installation of piles are mainly

    divided into two types

    1. Pile Driving:- In this method the pile (Precast

    or cast in situ) is driven into ground by meansof automated pile driving machines.

    2. Pile Boring:- In this method the pile (Mostly

    Precast) is bored into ground by means of by

    hand operated or automated augers.

    4/19/2013 3

  • 7/28/2019 Pile Installation Methods_Bhushan

    4/36

    a. Driven Piles

    The piles types which are installed using pile

    driving methods includes:-

    Timber piles

    Steel piles Precast concrete piles

    Prestressed concrete piles

    Cast-in-situ piles

    4/19/2013 4

  • 7/28/2019 Pile Installation Methods_Bhushan

    5/36

    a. Driven Piles

    Driven piles are installed by means of a driving

    hammer or a vibratory driver. The various types

    hammer types includes:-

    1. Drop hammer,

    2. Steam or air hammer,

    3. Diesel hammer

    4. Hydraulic hammer.

    Use of these hammer types are classified as

    percussive piling, which is subject to the requirementsof Noise Control Ordinance (HKSARG, 1997).

    The use of noisy diesel, pneumatic and steam

    hammers for percussive piling is generally banned in

    built-up areas surrounded by noise sensitive receivers4/19/2013 5

  • 7/28/2019 Pile Installation Methods_Bhushan

    6/36

    a. Driven Piles

    Driven Piles consists of assembly

    1. Dolly,

    2. helmet

    3. packing or pile cushion

    The purpose of the assembly is tocushion the pile from the hammer

    blows and distribute dynamic stresses

    evenly without allowing excessive

    lateral movements during driving.

    In addition, the life of the hammerwould be prolonged by reducing the

    impact stress. Pile cushion

    (or packing) is generally not

    necessary for driving steel piles4/19/2013

    6

  • 7/28/2019 Pile Installation Methods_Bhushan

    7/36

    Drop hammers

    A drop hammer (8 to 16 tonnes) is liftedon a rope by a winch and allowed to fall

    by releasing the clutch on the drum.

    The stroke is generally limited to about

    1.2 m except for the case of 'hard

    driving' into marble bedrock where

    drops up to 3 m have been used inHong Kong.

    The maximum permissible drop should

    be related to the type of pile material.

    The drawback to the use of this type of

    hammer is the slow blow rate, thedifficulty in effectively controlling the

    drop height, the relatively large

    influence of the skill of the operator on

    energy transfer, and the limit on the

    weight that can be used from safety

    considerations.4/19/2013 7

  • 7/28/2019 Pile Installation Methods_Bhushan

    8/36

    Steam hammers

    Steam or compressed airhammers are classified as

    single-acting

    double-acting

    depending on whether the

    hammer falls under gravity or is

    being pushed down by a second

    injection of propellant.

    A chiselling action is produced

    during driving as a result of thehigh blow rate. Some single-acting

    steam hammers are very heavy,

    with rams weighing 100 tonnes or

    more.

    4/19/2013 8

  • 7/28/2019 Pile Installation Methods_Bhushan

    9/36

    Steam hammers

    Single acting Hammer Double acting Hammer

    4/19/2013 9

  • 7/28/2019 Pile Installation Methods_Bhushan

    10/36

    Diesel Hammer

    In a diesel hammer, the weightis lifted by fuel combustion. The

    hammer can be either single-

    acting or double-acting.

    Due to the high noise level andpollutant exhaust gases

    associated with diesel hammers,

    the use of diesel hammers has

    been phased out in populated

    areas.

    The ram weight of a diesel

    hammer is generally less than a

    drop hammer but the blow rate

    is higher.4/19/2013 10

  • 7/28/2019 Pile Installation Methods_Bhushan

    11/36

    Hydraulic hammer

    A hydraulic hammer is lessnoisy and does not produce

    polluting exhaust.

    The ram of the hammer is

    connected to a piston,

    which is pushed upward anddownwards by hydraulic power.

    Some complex models have

    nitrogen charged accumulator

    system, which stores significantenergy allowing a shortened

    stroke and increased blow rate.

    4/19/2013 11

  • 7/28/2019 Pile Installation Methods_Bhushan

    12/36

    Hydraulic Hammer (contd)

    As such, the kinetic energy of the hammer depends not

    only on the height of the stroke but also the acceleration

    due to the injection of hydraulic pressure.

    Most new hydraulic hammers are equipped withelectronic sensors that directly measure the velocity of

    the ram and calculate the kinetic energy just before

    impact.

    The energy transfer ratio of hydraulic hammers ranges

    between 0.8 and 0.9

    4/19/2013 12

  • 7/28/2019 Pile Installation Methods_Bhushan

    13/36

    Vibratory hammers A vibratory driver consists of a static

    weight together with a pair of contra-rotating eccentric weights such that the

    vertical force components are additive.

    The vibratory part is attached rigidly to

    the pile head and the pulsating force

    facilitates pile penetration under thesustained downward force.

    The vibratory driver may be operated at

    low frequencies, typically in the range of

    20 to 40 Hz, or at high frequencies

    around 100 Hz (i.e. 'resonance piledriving').

    Vibratory drivers are not recommended

    for precast or prestressed concrete piles

    because of the high tensile stresses that

    can be generated.4/19/2013 13

  • 7/28/2019 Pile Installation Methods_Bhushan

    14/36

    b. Bored Piles

    Bored piles are mostly formed by machineexcavation. Excavation of the pile bore may also

    be carried out by hand-digging in the dry known

    as hand-dug caissons . When constructed in water-bearing soils which

    are not self-supporting, the pile bore will need to

    be supported using steel casings, concrete rings

    or drilling fluids such as bentonite slurry,polymer mud, etc.

    4/19/2013 14

  • 7/28/2019 Pile Installation Methods_Bhushan

    15/36

    Machine Dug Bored Piles

    The Machine dug piles are mainly divided

    into:-

    a.Mini Piles

    b.Socketed H-Piles

    c.Continuous Flight Augur piles

    d.Large dia. Bored Piles

    4/19/2013 15

  • 7/28/2019 Pile Installation Methods_Bhushan

    16/36

    Mini Piles

    Mini-piles are in a range of 100 mm

    to 400 mm in dia. and can be

    constructed to a depth of 60 m

    depth or more, but verticality

    control becomes more difficult at

    greater depths.

    They can be used for sites with

    difficult access or limited

    headroom and for underpinning.

    In general, they can overcome

    large or numerous obstructions

    in the ground.

    A mini-pile usually has four 50 mm

    diameter high yield steel bars and

    has a load-carrying capacity of

    about 1 375 kN.

    4/19/2013 16

  • 7/28/2019 Pile Installation Methods_Bhushan

    17/36

    Socketed H-piles

    Socketed H-piles are formed by inserting asteel H-pile section into a pre bored hole in

    rock. The hole should have a diameter

    adequate to accommodate the steel section

    plus any necessary cover for corrosionprotection.

    Cover to the pile tip is generally

    unnecessary and the H-pile section can be

    placed directly on the rock surface of the prebored hole. The common size of the pre

    bored hole is about 550 mm. The hole is

    then filled with non-shrink cement grout.4/19/2013 17

  • 7/28/2019 Pile Installation Methods_Bhushan

    18/36

    Socketed H-piles

    4/19/2013 18

  • 7/28/2019 Pile Installation Methods_Bhushan

    19/36

    Continuous flight auger piles

    Sizes of CFA piles range from 300 mm to 700 mm indiameter and their lengths are generally less than 30 m.

    Once concreted, reinforcement bars or a steel H-pile

    section may be inserted to provide resistance to lateral

    load or to increase the load-carrying capacity.

    These piles can be installed with little noise and

    vibration and are therefore suited for sites in urban

    areas.

    However, this type of piles cannot cope with boulders.

    The lack of penetration under continuous rotation due toa hard layer or an obstruction can lead to soil fighting upthe auger causing ground loss and settlement.

    4/19/2013 19

  • 7/28/2019 Pile Installation Methods_Bhushan

    20/36

    Continuous flight auger piles

    4/19/2013 20

  • 7/28/2019 Pile Installation Methods_Bhushan

    21/36

    Continuous flight auger piles

    4/19/2013 21

  • 7/28/2019 Pile Installation Methods_Bhushan

    22/36

    Large Dia. Bored piles

    Large-diameter bored piles are used to supportheavy column loads of tall buildings and

    highways structures such as viaducts.

    Typical sizes of these piles range from 1 m to 3

    m, with lengths up to about 80 m and workingloads up to about 45 000 kN ( 4.5 Lakh tonnes ).

    The working load can be increased by socketing

    the piles into rock or providing a bell-out (bulb) at

    pile base. The pile bore is supported bytemporary steel casings or drilling fluid, such as

    bentonite slurry.

    4/19/2013 22

  • 7/28/2019 Pile Installation Methods_Bhushan

    23/36

    Large Dia. Bored piles

    4/19/2013 23

  • 7/28/2019 Pile Installation Methods_Bhushan

    24/36

    Manual Dug Bored Piles

    Hand-dug caisson is a very simple and low cost to formlarge-size bored pile due to the following reasons:

    No heavy equipment is required except powered tools

    Requires very little working space

    Can work for a number of piles at the same time Can work at very difficult condition such as steep slope

    Boulder inside the bore can be cut fairly easily by human

    worker.

    The only drawback is that it is very dangerous for workerworking inside the caisson. Therefore, in 1998, the use of

    hand-dug caisson was banned due to the high accident rate.

    However, under special condition (e.g. work in steep slope),

    approval can still be obtained subject to the fulfilment of

    certain safety requirements.4/19/2013 24

  • 7/28/2019 Pile Installation Methods_Bhushan

    25/36

    Manual Dug Bored Piles

    The Manual dug piles are mainly divided

    into:-

    a.Piles using Caisson

    b.Piles using chisel and grab

    c.Reverse Circulation Method

    4/19/2013 25

  • 7/28/2019 Pile Installation Methods_Bhushan

    26/36

    Piles using Caisson

    4/19/2013 26

  • 7/28/2019 Pile Installation Methods_Bhushan

    27/36

    Piles using chisel and grab

    4/19/2013 27

  • 7/28/2019 Pile Installation Methods_Bhushan

    28/36

    Piles using Reverse Circulation Drilling

    4/19/2013 28

  • 7/28/2019 Pile Installation Methods_Bhushan

    29/36

    4/19/2013 29

  • 7/28/2019 Pile Installation Methods_Bhushan

    30/36

    Foundation design of Bandra-Worli

    Sea Link (BWSL)

    The Bandra-Worli Sea Link is primarily

    meant to provide an alternative to the

    Mahim causeway route that is

    presently the only connection

    between South Mumbai and

    the Western and Central suburbs.

    In the first phase it will connect

    Bandra to Worli whereas in the

    subsequent phases the plans

    are to take it further to Haji Ali

    and then to Nariman Point.

    4/19/2013 30

  • 7/28/2019 Pile Installation Methods_Bhushan

    31/36

    Pile Design of BWSL

    The foundations for the BWSL project consist of1. 120nos of 2.0m piles

    2. 484nos of 1.5m piles

    The project's site geology consists of basalts, volcanic tuffs

    and breccias with some intertrappean deposits The major engineering problems that needed suitable

    solutions before proceeding with the work were as follows:

    Highly variable geotechnical conditions of the foundation

    bed as explained above. Highly uneven foundation bed even for plan area of one pile.

    Presence of Intertidal Zone (Foundation Bed exposed in

    low tide and submerged in high tide).

    4/19/2013 31

  • 7/28/2019 Pile Installation Methods_Bhushan

    32/36

    Problems encountered during

    Pile Driving Reverse Circulation Drilling method is adopted for foundation construction. The

    highly uneven foundation beds and the presence of intertidal zone brought in lots

    of difficulty in terms of Liner pitching.

    This problem was solved by constructing a gabion boundary at the bed level

    around the casing, pouring concrete between the casings to make an artificial

    penetration of the casing. After setting of the concrete under the water, drilling was

    commenced using RCD.

    4/19/2013 32

  • 7/28/2019 Pile Installation Methods_Bhushan

    33/36

    Problems encountered during

    Pile Driving It is interesting to note that loss of water head during continuous

    drilling operation was a major problem while working in the intertidal

    zone. This water head loss lead to very slow production rate and

    very high consumption of drill bits. To overcome this problem, pits

    were made in the low tide at each foundation location using an

    Excavator and the casing was placed at the bottom of the pits.

    Then the casing was placed

    in the pits and was concreted

    to make an artificial penetration,

    maintaining the proper

    water head for continuous drilling.

    4/19/2013 33

  • 7/28/2019 Pile Installation Methods_Bhushan

    34/36

    Problems encountered during

    Pile Driving For several locations, cofferdam construction using steel liner

    and sheet piles, was not possible due to very hard and

    uneven strata.

    Here the problem was solved using circular steel caissons.

    These caissons were fabricated outside and towed to locationusing A-frame barge. The caissons were sunk at the location

    using counterweights.

    The unevenness at the bottom was sealed using the gabion

    method. The benefit of this method was that it completely

    eliminated deployment of resources like Jack up Platform,Crane, Vibro hammer, Compressor, etc. for liner pitching.

    It also eliminated substantial amount of field works and is

    pre-fabricated in principle.

    4/19/2013 34

  • 7/28/2019 Pile Installation Methods_Bhushan

    35/36

    References

    Textual Content Foundation design and construction

    GEO Publication No. 1/2006, Hong Kong

    Foundation analysis and design

    by Joseph E. Bowles Geotechnical Engineering

    by V.N.S.Murthy

    Images:-

    www.images.google.com

    Case Study:-

    Making of BWSL - www.hccindia.com

    4/19/2013 35

  • 7/28/2019 Pile Installation Methods_Bhushan

    36/36

    4/19/2013 36