Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Upload: lorena-sharp

Post on 18-Jan-2018

221 views

Category:

Documents


0 download

DESCRIPTION

Renewable Energy Act of 2008 Republic Act No An Act Promoting the Development, Utilization and Commercialization of Renewable Energy Resources and For Other Purposes December 16, 2008

TRANSCRIPT

Page 1: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Philippine Feed-In Tariff System

ImplementationSharon O. Montañer

Chief- Office of the Executive DirectorMember – RE Technical Working Group

Page 2: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

2

Chapter IV - Regulation of the Electric Power Industry

Section 38. Creation of the Energy Regulatory Commission. There is hereby created an independent, quasi-judicial regulatory body to be named the Energy Regulatory Commission (ERC). xxx

Section 41. Promotion of Consumer Interests. xxx and ensure the adequate protection of consumer interests. Xxx

Section 43. Functions of the ERC. The ERC shall promote competition, encourage market development, ensure customer choice and discourage/penalize abuse of market power in the restructured electricity industry. xxx

Energy Regulatory Commission

Page 3: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Renewable Energy Act of 2008

Republic Act No. 9513

An Act Promoting the Development, Utilization and Commercialization of Renewable Energy Resources and For

Other Purposes

December 16, 2008

Page 4: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Renewable Energy Act of 2008

On-Grid Renewable Energy DevelopmentRenewable Portfolio StandardsFeed-In Tariff SystemRenewable Energy MarketGreen Energy OptionNet-metering for Renewable Energy

Off-Grid Renewable Energy DevelopmentMinimum RE generation capacities

4R.A. 9513

Page 5: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

* Section 6 of the RE Law 5

Defined as “a market-based policy that requires electricity suppliers to source an agreed portion of their energy supply from eligible RE resources”

The NREB shall set: Minimum percentage of generation from

eligible renewable energy resources Which sector RPS shall be imposed on a

per grid basis

Renewable Portfolio Standards

Page 6: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

* Section 8 of the RE Law 6

The DOE shall establish the REM Direct PEMC to implement changes to the WESM

rules in order to incorporate the rules specific to the operation of the REM under the WESM

PEMC, under DOE supervision, establish a Renewable Energy Registrar Issue, keep and verify RE Certificates

Renewable Energy Market (REM)

Page 7: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

* Section 9 of the RE Law 7

The DOE shall establish a Green Energy Option program which provides end-users the option to choose RE resources as their sources of energy

End-users may directly contract from RE facilities their energy requirements

TRANSCO, DUs, PEMC and all relevant parties are hereby mandated to provide the mechanisms for the physical connection and commercial arrangements necessary to ensure the success of the Green Energy Option

ERC to develop regulatory framework

Green Energy Option

Page 8: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

* Section 10 of the RE Law 8

Net Metering for RE

DUs may enter into Net-Metering agreements with qualified end-users

The ERC, in consultation with the NREB shall develop Net-metering interconnection standards and pricing methodology and other commercial arrangements

The DOE, ERC, Transco, DUs, PEMC and all relevant parties are mandated to provide mechanisms for physical

connection and commercial arrangements

Page 9: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Section 7: Feed In Tariff System Mandate ERC, in consultation with the NREB For emerging renewable energy resources to be used in

compliance with the renewable portfolio standard Wind Solar Ocean Run-of-river Hydro Biomass

Priority connection to the grid Priority purchase and transmission of, and payment for, such

electricity by the grid system operators Fixed tariff by technology Mandated number of years, not less than 12

Page 12: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

The FIT to be Paid to RE Developers

Based on cost of a representative project Technology-specific20 years durationSubject to degression and adjustments Subject to review

NREB ERC FIT

Page 13: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

ERC-Approved FITs

NREB(in PhP/kWh)

ERC-Approved(in PhP/kWh)

ROR Hydro 6.15 5.90Solar 17.95 9.68Wind 10.37 8.53Biomass 7.00 6.63

Note: Decision on OTEC FIT deferred

ERC Case No. 2011-006 RM

Effectivity“Payment of the approved FIT rates to the eligible RE Developers shall commence upon the effectivity of the Feed-in Tariff Allowance (FIT-All), which shall be determined by the Commission at a later date after due proceedings thereon.”

Page 14: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

ERC-Approved Degression RatesERC-Approved(in PhP/kWh)

ROR Hydro 0.5% after year 2 from effectivity of FIT

Solar 6% after year 1 from effectivity of FIT

Wind 0.5% after year 2 from effectivity of FIT

Biomass 0.5% after year 2 from effectivity of FIT

Page 15: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Section 2.5: FIT Rules

Uniform ₱/kwh charge Payable by all electricity users Periodically calculated and set Based on forecasted RE deliveriesProceeds go to a fund administered by

Transco from where the RE payments will be sourced

TRANSCO ERC FIT-ALL

Feed-In Tariff Allowance (FIT-All)

Page 16: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Other Provisions: FIT Rules

Sec. 2.6 of the FIT Rules provides that NREB shall establish more detailed guidelines for the collection & disbursement of the FIT-All Fund.

Sec. 2.9 of the FIT Rules provides that ERC may consider the issuance of additional guidelines governing the dispatch and settlement of the FIT.

Page 17: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

RULES ENABLING THE NET-METERING PROGRAM FOR RENEWABLE ENERGY

Renewable Energy – Technical Working Group

Page 18: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Introduction Resolution No. 9, Series of 2013 - A Resolution

Adopting the Rules Enabling the Net-Metering Program for Renewable Energy

Components: Rules Enabling the Net-Metering Program (Annex A) Net-Metering Interconnection Standards (Annex A-1) Net-Metering Agreement Template (Annex A-2)

Approved on May 27, 2013

Effectivity on July 24, 2013

18

Page 19: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Legal Basis

Section 10 of R.A. 9513 and Section 7 of its IRR provides that the ERC, in consultation with

NREB, shall establish the net-metering interconnection standards and pricing

methodology.

19

Page 20: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Scope, Applicability & Qualification Applicable to on-grid systems. Only for installation of < 100kW. For eligible RE Technologies such as wind, solar,

biomass or biogas or other RE systems capable of being installed in the QE’s premises.

End-user should be in good credit standing in the payment of electric bills to the DU.

The RE System must be compliant with the standards set in the PEC, PDC, DSOAR and the Net-Metering Interconnection Standards.

20

Page 22: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Pricing Methodology Interim pricing for export energy is the DU’s

monthly charge based on its blended generation cost.

This cost shall be automatically included in the DU’s total generation cost to be recovered from all its customers.

22

Page 24: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Net-Metering Charge

Net-metering charge is equivalent to PhP/customer/month supply and metering rates; plus the ERC-approved PhP/kWh metering rate based on export energy.

DUs may file for a different net-metering charge, if necessary.

24

Page 25: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Billing Charge

Billing Charge:PhP for import energy

Less: PhP export energyPhP credited in previous monthTOTAL

If positive: QE shall pay this amount to DUIf negative: DU shall credit this amount to QE’s next bill

25

Page 26: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Net-Metering Interconnection Standards

Annex A-1

Page 27: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Interconnection Standards

General Guidelines Application for Interconnection System Parameters System Protection Operations & Maintenance Metering Testing & Commissioning

27

Page 28: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

General Guidelines Design, installation, operations and maintenance shall be in

consultation with the DU, since all specifications shall be of DU’s standards.

System requirements shall be met at the Connection Point. The DU shall only allow interconnection of RE facilities with up to

100kW capacity per QE account. The DU shall conduct inspections and shall remove the

generation from DU system at any time due to maintenance, test, repair and emergency conditions.

QE to be liable for any damages of the DU should the QE execute changes to the RE facilities without first informing the DU.

28

Page 29: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Application for Interconnection

QE and DU to enter

into a Net-Metering Agreement.

QE to send a letter requesting DU for interconnection.

DU to provide information

to QE.

QE to complete and file an application.

DU to acknowledge within 10 business days from receipt.

ACKNOWLEDGEDU to determine whether DIS and/or DAS is necessary.

If yes:DU shall provide

results of study.

DU, with QE to conduct on-site inspection.

29

Page 30: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Application for Interconnection

QE and DU to enter

into a Net-Metering Agreement.

QE to send a letter requesting DU for interconnection.

DU to provide information

to QE.

QE to complete and file an application.

DU to acknowledge within 10 business days from receipt.

ACKNOWLEDGEDU to determine whether DIS and/or DAS is necessary.

If yes:DU shall provide

results of study.

DU, with QE to conduct on-site inspection.

Pro forma agreements Application form

• Description of proposed connection• Relevant Standard Planning Data • Other data required by DU• Completion date

Technical requirements Specifications Listing of certified equipment Application fee information Applicable rate schedules Metering requirements 30

Page 31: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

System Parameters Voltage Level - should be the same level as the DU with automatic

method of disconnecting. Frequency – 60 Hz with automatic method of disconnecting. Power Quality

Limitation of DC injection – not to inject current greater than 0.5% of the full load rated output current at connection point.

Flicker severity – not to exceed 1.0 unit for ST and 0.8 units for LT.

Harmonics – within limits in Sec. 3.2.4 of PDC Power Factor – not less than 85% lagging measured at the

Connection Point.

31

Page 32: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

System Protection Synchronization – QE to provide synchronizing devices with typical

limits in the NM Standards. Islanding – QE system should detect islanding and disconnect within 2

seconds from formation. Integration with DU’s Distribution System Grounding – shall be

grounded in accordance to PEC. Protective Control Devices

Disconnect device – visible for use by the DU within 10 feet from connection point.

Protective relays – protective relays provided in NM Standards Reclosing – immediate disconnection from the DU system when the

system is down.

32

Page 33: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Operations & Maintenance Facility should operate in parallel with the DU. QE must inform the DU if it is going to

synchronize. If the DU system is down, the facility should

automatically disconnect. QE to provide DU with contact numbers. QE shall maintain the facility in a safe manner

as approved by the DU.

33

Page 34: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Metering MSP shall own and shall be responsible for the

operations and maintenance of the meter in accordance with Sec. 2.11 of DSOAR.

QE to provide space for the metering facilities. Metering facilities shall be installed in an

accessible and visible area for reading and testing of both QE and DU.

34

Page 35: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Commissioning Test shall include the following:Verification and

inspectionsProduction Test

Response to abnormal voltage

Response to abnormal frequency

SynchronizationUnintentional islanding

functionality testCease-to-energize

functionality test

Testing and Commissioning Commissioning test shall be

conducted after the interconnection system is installed.

DU has the right to witness the testing and commissioning.

RE facility shall be equipped with whatever equipment is required to perform the test.

35

Page 36: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Net-Metering Agreement

Annex A-2

Page 37: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

Net-Metering Agreement

Parties: DU and Qualified End-user

Mirrors the provision in the Rules Enabling the Net-Metering Program (i.e. Compliance Standards, Interconnection Set-Up, DU Inspection, Meter Readings, Pricing and Other Charges).

To be submitted to ERC, DOE & NREB within 5 days from execution.

Deemed approved and effective upon submission to ERC.

37

Page 38: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

ISSUES

Page 39: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

ISSUES

1. DUs are not precluded under the Rules from paying out in cash its accumulated peso credit at the end of each calendar year.

2. QE is an entity distinct from that of an SGF and IPP, thus:– It is not covered by the imposition of the universal charge

required of SGF.– It shall apply for COC as QE.

3. Customer who intends to install beyond 100kW:– Must comply with the PDC and DU Standards– Must apply for COC as SGF, if generation is for own use – Must enter into PSA with a DU for ERC’s approval, if it will sell to

a DU

39

Page 40: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

UPDATES

1. The ERC already received two (2) Net-Metering Agreements submitted by MERALCO.

– 5.4 kWp installation in Manila– 2.5 kWp installation in Rizal

2. The ERC has conducted a public consultation on 28 January 2014 on the Amended Certificate of Compliance Guidelines covering the COC compliance of Qualified Net-Metering Customers.

40

Page 41: Philippine Feed-In Tariff System Implementation Sharon O. Montañer Chief- Office of the Executive Director Member – RE Technical Working Group

THANK YOU