phase 111 final report re-engineering tre rufs work plan
TRANSCRIPT
U. S. DEPARTMENT OF ENERGY OAKLAND OPERATIONS OFFICE
LABORATORY FOR ENERGY RELATED HEALTH RESEARCH DAVIS, CALIFORNIA
PHASE 111 FINAL REPORT
RE-ENGINEERING TRE RUFS WORK PLAN
April 14,1995
INFORMAL NOTE
TO: LEHR Core Team
FROM: S. Golim. EM-22
DATE: April 14, 1995
Enclosed is the most current sue conceptual model and sunmmy notes from our meeting on April 4&5. 1995. Table 3 has been revised and an appendix prepared which outline additional information needs and actions rquqcd to b e p r more detailed evaluation of t h e likely rupow actions idenufied by the team.
Below I have outlined sow thoughts for your considartion on how you m y m t to proceed over the next K V C ~ week.
o Initiuc r more detailed evaluation of the rrspocue options dimmed in our meeting u king the most rppmpriac, i.e., 1) crpping of Imdfik on-site dupovl of non-djrcent arcs into r RCRA- type cell; 2) crppbg of laadfib md off-site drsposrl of aon-djacat a. Team will also need to fiarlizc a decision rrgrrdins the chrnacrintioa of the laudfillr md the appropriateness of capping than in wordurce with state md Fedenl mammdWions. Should you elect to consider otha options tha capping for thc Imdfillr. thir would serve to conniturc a third or fourrh altanrtive with either on-site or ofbite disposl of mrteriJI in rhc hndfih. VOTE: relutd to these e v a l u t i w will k the consideration of auman rt m lppopiur or possibly q u i d respow md the Univenivs desk to look a! tbe possibility of fimrrr rrrcuth optioru on my wutt remaining at tfre site; with rrspect to uafmcnt needs, I haw asked Jeff, Liz md Steve to begin dnAing some thougho on implementing truemat contiagcocia during excavation].
o Begin evaluating the potential timing of response doru (e.6, removal of tfre dog peas and Goldmra's box this h c d year, sign interim action ROD for sourca in d y FY% with medial action in late FY96 or early FY97?????)
o Begin compuiog identified dam needs (Table 3 d Appendix A) agrinrt the cumnt draft of the RVFS w o d ~ l m to erurPe dl net- dam will k collected d my unnecessuy dam collection k e l [NOTE: fix mart &tier, oeceuuy dam collation mry not k defined until the rh* action jtcmJ in Table 3 arc a d k s d ]
o Compile md organize existing ground wuer dam to fsciliote the genaation of a "picnuc" of the cumnt conditions d whu tbe mnahbg ground wrm dam needs mry k.
o GeamW a 'user-~cndiy" site mtp identifying known xwca with m womprnying able which descrikr whp is cun'catly known about each some. Particularly wful for ach source would be a c a p u b a of c o a m h n t levels (eitha hm u m p l u or known release quantities) against the EPA rrd Strtc prciummy rrwdi.tioa goals d d d a levels.
o Revisit rhs public p r r t i c i m mrtegy in light of thc dircctioo thc team is now moving i.e.. should a public meeting k held to 1) Mnmuize known cobditionr (tbe site mrp, accompanying
c,5@- tabla, and site coDceparrl modcl would k helpful to bciliaoc communicttion); 2) review the P' teams' initial screen& of rttcmrtiva and supporting n t i h (the " 1st ctn" FS adyses would be
wful here); 3) identify wbm dtamthu arc d u i i to k m dcPil, and 4) outline the possible timing of rrspow dous. Such a meeting would dl thc public to inform you of other options thy m y want to have coosided or concerns t h y have with th ahnatives k i n g evrhuted 5-
I klieve the majority of the activities discus& above arc "desk-top" papa e x m i s a tbu could k cornpletsd o v a the next four to six we&. If you think it would k helpful, wc could bold one more
meeting together in lue May or early June to wrap up the uncertainty discussions and dau nee& for all sourcer, umblisb ground water dau needs and investigation mzutgy, timing of response actions, and develop dccuion rules for potential maanent contingencies, rtc.
Please let me know how you would like to proceed. Thurk you again for your participation wth the smtegic milestone mview initiative.
To: Duncan Austin Cal EPA / DTSC Jim Linlejohn DOE-OAK Julie McNeal UC Davis Lida Tan U.S. EPA Susan Timrn RWQCB
CC : Salem Aniga Ed Bailey Elizabeth Dodge Steve Golian Tony Kluk Jeff Smyth Joe Niland Steve W ilhelrn Don Williams
PNL RHB CH2M HILL DOE-HQ DOE-HQ PPC Dames & Moore EG&G Environmental DOE-HQ
n. Workshop Summa y Notes
I. Cover Memo 11. Workshop Summary Notes 111. Agenda For LEHR Strategic Milestone Initiative Meetings IV. Development of Conceptual Site Model and Likely Response Actions
1. Describe the basis of the conceptual model (from the Draft RI/FS Work Plan) 2. Expected Site Conditions Based on Existing Information 3. Likely Response Actions Based on Expected Site Conditions 4. Display of results of the conceptual model development in table and figure 5 . Display of results of likely response action development in table 6. LEHR site map
V. Development of Data Needs 1. Describe Approach 2. Display of Data/Information Needs in Tables by Likely General Response Action
VI. Approximate Cost Comparison of Selected Alternatives 1. Rationale and Limits 2. Sensitivities 3. Incompleteness of Cost Estimate 4. Alternatives 3. Results
Appendix A: Revisions to Summary Notes
LII. Agenda For LEHR Strategic Milestone Initiative Meetings
1. Develop a conceptual site model based on existing information by identifying likely source areas, pathways, and receptors Goal: Come to an agreement on how site works and remaining uncertainties
2. Identify site concerns '
Goal: Come to agreement on priorities for response .
3. Identify likely general response actions and land use Goal: Focus the feasibility study to a discrete set (2-3) of viable alternatives
4. Identify remaining data netds, manageable uncertainties, and requirements for a risk assessment Goal: Come to agreement on what data must be collected before response(s) and what data may be collected during response(s)
5. Develop a site management strategy 1. Sampling/Analysis plan 2. Typflirning of response 3. Public particidation plan Goal: Appropriately remediate the site as efficiently and effectively as possible
IV. Development of Conceptual Site Model and Likely Response Actions
The conceptual model described in the Draft RI/FS W ~ r k Plan (Figure I) was used as the staning point for discussions held in Oakland on March 15th and 16th. This conceptual model was revised based on the following:
Use of existing information from LEHR hstorical and current data) Consensus of LEHR core project team (Duncan Austin, CaUEPA Department of Toxic Substances Control; Jim Littlejohn, DOBOAK; Julie m e a l , U.C. Davis; Alice Tackett, U.C. Davis; Lida Tan, U.S. EPA; Susan Timm, Regional Water Quality Control Board) with regards to site conditions
The revised conceptual model (Figure 2) is the result of these discussions and represents only current site conditions. Probable or expected conditions arc shown with solid lines. Uncertain conditions which were felt to be reasonable possibilities are shown with dotted lines. Table 1 summarizes the changes made to the ori@ RYFS conceptual model and the rationale for those changes.
Exmted Site Conditiou
Following a consensus on how the site was c m t l y working, the extended LEHR team discussed site problems, expected conditions, and likely general response actions. Three site problems were identified:
. ,
1) Continuous releases to soil subsurface &om sources that leach to the upper and lower hydrostatigraphic units. The sources include:
Radium-226 leach field DOE box Strontium-90 leach field/lmhoff Disposal trenches underground tanks LandfiUunits#l,2,and3 Forty-nine waste holes Chemical dispensing area Southwest trenches Seven septic systems Solid waste trenches adjacent to Southwestan dog pens soils landfill unit #2
2) Groundwater contamhalion that is known to exceed MCLs at specific points (both spalial and temporal). This includes contaminaton of both the upper and lower hydrostaligraphic units. This site problem has uncertainty associated with it because Mknown sources may contribute to groundwater c o n ~ o n
3) U o w g "spills" to soil surfact that have &own . . of being resuspended
by wind and storm water and being transported to ofiite receptors, on-site workers. and Putah Cmk. This includes intrusion into LmdfiU unit #3 and the southwestern trenches.
The tekn ranked the groundwater as the primary overall concern of these three site problems, but agreed that the fint priority for considering general response actions should be the problem of continuous releases from the sources to the sub-surface soil. This decision was based on two key factors:
The groundwater will continue to be affected as long as the sources are releasing contaminants to the sub-surface soil because the contaminants leach to the upper and lower hydrostatigraphic units; and Current data indicates that the groundwater contamination does not demand immediate attention or an emergency action.
Under these circumstances, the primary concern is for the long-term protection of the groundwater. This can only be accomplished by addressing the problem at the sources. Any
. remediation of cumntly contaminated groundwater is a second priority for considering general response actions.
Likely Resmnse Actions
Consequently, the extenaed LEHR team focused the remaining time at the March 16th meeting discussing the site problems contributing to the continuous releases to the sub-surface soil. Table 2: Site Problems and Likely Response Actions at LEHR sum,marks the sources contributing to this site problem, the expected conditions and the likely general response actions identified by the extended LEHR team. Please note that disposal signifies either on-site or off-site disposal.
Figure 1 Conceptual Model Found in the RUFS Work Plan
naruporl Mechanism
Pathwry Receptor
Human Biota EXPOSURE Cwca R M ~ , A ,
1. Ra&-226 R a d m c ~
L e d Fidd
C Rdimtiml Inpa# 2. Slralli~-90
a ~aeb ~ddr + Rdiarctive a lnhrlria
3. FayaLw W e
Curca S i k whir
a a
v Cknird qaVrral Conrvl
FUIWC
RCS*C;MS
a a
e a a
F ~ w c SIIC
WocLcca
a a
Hda Y d o r l l ~ r c u M
4. Wid Wrw P -
w 106- Surf= & J I U ~ ~ J ~
Tro&r Ingatim W Pacabion '-t Soil (<6- b p ) @ a a a
5. MIU 82 (19 a a a T N S C ~ ~ S ) I
6. Lmdfd 81 (w h a ) a a a I
7. LmdfJl83 Crak
a
~ C ~ C U I I ~ I
a
A~UIIC
a
(sI.uow Piu) - w t laguciocl a
D O E a p Y l qg-- Bor UppaHyMqphrc +kb~.ria l ulrit(sM4. fed k p ,
9. lrbA rvaye lm u 25'. cQII.c( a
a a
a a a - -
c - g My cuuhlui* is Trtc 9 I l W 4 -1
10. Cbclnicrl
a
a
a Pardation ~ r y ~ ( # a - Ihh" l 11. 7scpic ~ m ~ e r ~ ~ ~ i y r p h i c
SF-'" Uni~ (Waw 80 feu dccp.
a a
average Lhicknc~ u w. Conwl a a
12. Dog Pau r v n * d v i c y i s - 3.2x10"4 k)
a
Table 1 - Revisions to the Conceptual Model
Type of Change
Source (Number 10 in Figure 1)
Source (Numbers I & 2 in Figure 1)
Source (Number 1 1 in Figure 1)
Source (Number 9 in Figure 1)
Release Mechanism
Release Mechanism
-
Change
Eliminated the chemical dispensing area as a discrete source.
Combined radium-226 and strontium-90 leach fields as one source area
Eliminated septic system #1 from the septic systems source area.
Eliminated the Imhoff underground tanks as a discrete source.
Deletion of the radiation1 radioactive decay release mechanism h m the sources to the air.
M.ltration/Percolation release mechanism redefined as intrusion
Rationale
Combined with the solid waste trenches because of proximity in location and similarity of probable response actions.
Combined the leach fields because of proximity in location, similarity of probable response actions, and similarity of probable contaminants. Although the leach fields received primarily either radium or strontium, some overlap in dispensing existed.
1
Added septic system #1 to the leach fields source area because of proximity in location and similarity of probable response actions. \
Combined with the radium and strontium leach fields source area because of proximity in Iocation, similarity of probable response actions, and similarity of probable contaminants.
Samples show no indication of contamiaation from this release mechanism. The only problem observed with radon is following rains, which is considered normal. Radioactive materials will not get into the air unless it is attached to volatiles.
Intrusion more adequately describes the possible release of contaminants from the sources. The consensus was that there was a possibility that sources could contaminate the surhcc soil because of historical dibances , but not via infiltration or percolation.
Type of Change
Pathway
Source/Release Mechanism
Transp~rt Mechanism
Receptors
Change
The pathway via intrusion was defined as uncertain.
A number of sources were eliminated as possible contributors to contamination to the surface soil once the release mechanism was redefined as intrusion.
The transport of contaminants fiom the surface soil to the air was changed to an uncertainty, and chemical diffusion was eliminated as a transport mechanism.
Future site workers and future site residents were eliminated as receptors.
Rationale
Data do not show any indication of contamination of the surface soil. However, there are reports of historical disturbances into Landfill unit #3 and the southwestern trenches, which could result in contamination via this pathway. Therefore, the entire pathway of contaminants being released via intrusion is considered an uncertainty.
Past disturbances (e.g., digging) could have redeposited contaminants so that surface soil is a potential secondary source. There is an indication that two sources were disturbed: the southwest trenches and landfill unit #3. Although the pathway is uncertain, these two sources arc dqlayed in the conceptual model as possible contaminators via intrusion. All other sources were eliminated as contributors to the surface soil. Consensus was that these sources were not contributing via infiltration, percolation, or inmion. - Although data does not indicate that the air is contaminated, uncertainty exists because of historical disturbances which could have redistributed contaminants in the surface soils. However, consensus was that these contaminants would travel via volatilization or resuspension into the air, but not via chemical diffusion.
For the purposes of this conceptual model, future receptors wen eliminated. This conceptual model reflects only the current condition of the site.
Type of Change
- Source
Exposure Route
Release Mechanism
Transport Mechanism
Transport Mechanism
Change
Surface water was eliminated as part of the pathway for contaminants to reach receptors.
Inhalation was eliminated as an exposure route for contaminants that could be in Putah Creek.
Leaching was redefined as dispersion.
Volatilization was eliminated as a transport mechanism from the subsurface soil to the surface soil.
Volatilization was added as an uncertain transport mechanism into the surface soil of contaminants dispersing from the sources. and
Rationale
Surface water does not exist on-site except under storm conditions. In such a case, excess storm water would discharge into Putah Creek. The only place where surface water collects in along the western trenches. Consensus was that thls is not a problem and that the only possible receptors of surface water contamination were exposed via Putah Creek.
Consensus was that inhalation was not a viable exposure route for possible contaminants in Putah Creek.
Dispersion better describes the release of contaminants !?om the sources. It includes leaching, but also includes the movement of contaminants via release mechanisms that arc not associated with water.
Contaminants in the upper hydrostatigraphic unit volatilize into the sub-surface soil, but the probable transpon of these contaminants to the surface soil was eliminated. There is no indication from existing data that this is occurring. The soil is tight, which makes transport unlikely, and the quantities of contaminants makes this pathway insigntficant.
Consensus of the group was that volatilization could not be eliminated as a transport mechanism of contaminants to the surface soil. The volatilization is shown h m the dispersion release mechanism to the surface soil so as not to indicate that contaminants volatilize from the groundwater through the sub-surface soil to the surface soil.
Type of Change
Receptors
Change
Groundwater was changed from a tertiary source to a receptor.
Rationale
The State of California considers groundwater to be a receptor, per groundwater antidcgredation policy .
Revised Conceptual Model
Relase Stconbmy Pathway Mecbamirm Sov~ccr MbcLutn
9 . S W D q P m 4 Soil
Rcctptor Human Biota
KEY:
Expected Pathway
) - - - - - - - -. Uncertain Palhway
- - - - - - I WW/lNJpIbr
1 Aj, r - - - - - - - - - - - - - - -
EXPOSURE R m
h-ia
t -
. - C m A RuiQ, .
- - - - - - - - I b u d * I ; - - - - - - - - - - I - - - - -
1 -* M(<6.b) c z = = ; - - - - - - - - - - - - - - - - - - - - - - - - + - C(
1 r - - - * L - - - - - - - I I t I ~Slan Wora F h
; - - - - - . I 1
. ~ I m d II I ;- - - - - - -
I I , - , - a I
I I I -- , *l P* L - - - - - - - - - - - - - I- - I - 1
m w . . I - - - - - - a I I DmJ
I . . . I ' I
I
'Jppcr HydraulqgLic hi( ( 5 0 4 0 C a c d s s p . ~
Tiu-LrrQ-in ~ ~ ~ % I P a m l b ~ r ~ l p p c r ~ ~ C H ~ ) dai* lav#v OCA Q NO, DC+ Td-: hi@krataaddmd ~ ' . r d ~ l 4
c a n * ) C r o r d w r l e r b c o d d e d r RECEFIXIR by t k u r l e dC.Ykm&
CUICU S i r - .
T m
. Agruc
A . . .
Revised Conceptual Model
6. LmdW 13 (SYaw Pb)
Rcccpbr H u m Biota -
EXPOSURE curar C r r a A S*r T- AQ.& Raid tau Ykta
KEY:
Expected Pnlhway
) - - - - - - - -. Uncertain Palhway
Table 2 Site Problems and Likely Response Actiens at LEHR
Continuous Releases to Sgil Sub-surface
Draft- 1 1
Likely General Response Action
1. No action 2. Removal, treat and disposal 3. In-situ treatment or containment
1. Removal, treat and disposal 2. Removal and disposal 3. In-situ treatment or containment 4. No action
1. Removal, treatment and disposal 2. Removal and disposal 3. In-situ treatment or containment 4. No action
Sources Contributing to
Site Problem
Radium and Strontium leach fields
Expected Conditions
Radium leach field: No VOCs and very low levels of radium-226 and strontium- 90 are expected. A total of 3 millicuries of radium was r e l e d to these systems. Consists of 3 dry wells, each arc approx.30n in diameter and 40' deep; a trench, which is approx. 9 1 ' long, 3' wide, and 14' deep. Public concern exists because of clogging of the system may have xsulted in spills- No sampling was done inside of the trenches, dry wells, or directly underneath the trenches. Strontium leach field: This area consists of 2 fields, a box, and lines. The ori@ leach field is located under a building. An estimated 2.5 millicuriu of strontium-90 was discharged. 1 millicurie of plutonium-23 1 was discharged. Cesium was also detected. The hhof f u n d w u n d norage tanks and septic system # 1 (sec Figure 3). which processed sanitary waste, art included as part of the RalSr leach systems.
Division of Problem for
Response Actions
Soils
cobbl# (includes trench and dry wells)
Strum (inclder distribution box, tanks, piping,
and septic system # 1)
Draft- 12
Sources Contributing to
Site Problem
Forty-nine waste holes
Disposal Trenches
Expected Conditions
Radiological materials are expected, including: 17 different radionuclides, 8 of whlch where long-lived isotopes, and mtium. Records show that higher levels of tritium and bottles containing chemicals were disposed in the waste holes. Documents indicate that a total of 1.7 curies of radionuclides were disposed. One wipe sample detected a lpb .:dionuclides. The dimensions of the waste holes arc approximately 4'x4'~8- 10'.
Potential mixed waste, very low levels of chloroform and radium have been detected. Reported to be approx. 120 ' long and oriented roughly in a northlsouth direction. The exact number, location and depth of the trenches is not known. This category includes the chemical dispensing area Chlordane is a possible contaminant.
Division of Problem for
Response Actions
No division required
Southwestern trenches
Intrusion resulting in surf= contamination (uncertain)
Likely General Response Action
1. Removal, treat, and disposal 2. Removal and disposal 3. Selectivdhot spot removaYcapping
1. Removal, segregate and 00s 2. Removal, segregate, treat, and dispose 3. Selectivehot spot rcmovaVcapping
1. Removal, segregate and dispose 2. Removal, segregate, mat, and dispose 3. Selective/hot spot rcmovaL/capping
Draft- 13
Sources Contributing to
Site Problem
Disposal Trenches (Continued)
Landfill unit # 1
Landfill unit #2
Expected Conditions
Chloroform is expected in the solid waste trenches adjacent to landfill unit #2. Containers with pesticides have been found. The trenches were typically 2' wide, ranged in length h m 33' to 270', and estimated to be between 8-10' deep.
Received waste h m campus and sludge h m the wastewater treatment plant Recent data has showed that landfill unit # 1 is probably about 30' larger than ongu l ly expected. There is more of a random dumping pattern in landfill unit # 1 than in either #2 or #3. A small quantity of mixed waste is possible. Chromium has been detected in the groundwater that may have come from landfill unit #l.
Trench and fill technique was used Often the chemicals were burned to reduce the volume. Mixed waste is uncertain. The quantity of wastes disposed in #2 is estimated at 19,260 cubic yards.
Divhion of Problem for - Response
Actions
Solid waste trenches (both radiological and chemical)
No division required
No division r t q d
Likely General Response Action
1. Removal, segregate and dispose 2. Removal, segregate, trea6 and dispose 3. Selectivehot spot removallcapping
1. Capping 2. Selective removal, segregation, pat, dispose 3. Entire removal and disposal
1. Capping 2. Selective removal, segregation, trtat, dispose 3. Entire removal and dqosal
Draft- 1 4
Sources Contributing to
Site Problem
Landfill unit 83
DOE disposal box
Septic systems numbered 2-7 (See Figure 3)
Soil underneath the southwestern dog Pens (below gravel)
Expected Conditions
Located off-site and only used for about 4 years. A trench and fill techmque was used to dispose. Mixed waste is uncertain.
The combined total acreage for the three disposal artas is estimated at approximately 6 acres
A metal box is ex,-,;ed. No contamination has been detected in adjacent soil, but radiologic, and possibly mixed, waste is expected in the box.
Septic system #2 is at least partially under a building and may have been destroyed. Septic system #4 may contain x-ray chemicals Septic system #5 is cut by utilities Septic system #7 may not exist
Some chlordane and some low levels of radiation arc expected. The expectation is for shallow contamination.
Division of Problem for
I Response Actions
Landfill -
Intrusion resulting in surface contamination (uncertain)
No division r e q d
Soils
Structures
No division required
Likely General Response Action
1. Capping 2. Selective removal, segregation, treat, dispose 3. Entire removal and disposal
1. Capping 2. Selective removal, segregation, treat, dqose 3. Entire removal and disposal
1. Remove/excavate and disposal
1. No action 2. Removal and disposal 3. In s i t . treatment
1. No action 2. Removal and disposal 3. Grout in place
1. No action 2. Removal and disposal
---------- 7
Septic Systos 116 J
LEllll SllE DOUNDAnV
SlramUumDO lmhon Tmho
I I
bndllll Dlnpoad Unll I 3 Approrlmrlrly WO Fort Ems1 -
A ,ln,lar( rrn.... L
FORMER WASTE DISPOSAL AREAS
RllFS Work Plan LEI IF\ Erlvironmenlal Resloralion
Davls. Calllor~lla
V. Development of Data Needs
The extended LEHR project team met in Oakland on April 4th and 5th to: Review the summary sheets of the prior LEHR meeting, and Discuss data needs for probable general response actions identified for sources of contamination at the site.
Corrections and modifications to the March 15th and 16th summary package have been incorporated into the previous sections and are summarized in Appendix A: Revisions to Summary Notes. These changes are based on the consensus of LEHR core project team (Duncan Austin, CaYEPA Department of Toxic Substances Control; Jim Littlejohn, DOUOAK; Julie M'Weal, U.C. Davis; Lida Tan, U.S. EPA; Susan Timm, Regional Water Quality Control Board).
Following a consensus on revisions to the summary sheets of the March 15th and 16th meetings, discussions were held to determine data needs for the likely general response actions. The fm sources discussed were landfill units # 1,2, and 3. The discussion focused on establishing criteria (i.e., what information is necessary) for detch ' ' g whether entire removal (i.e., excavation) of the landfills or capping is more appropriate. These discussions wen largely inconclusive becaee of the n a h ~ ~ of characterization uncertainties (i.e., determining when the landfills have been s-ciently characterized).
In the intmst of time, the following compromise was proposed and accepted Generally, thm an three types of uncertainties related to determining data needs:
1. Characterization uncertainties, 2. Regulatory uncertainties, and 3. Technical uncertainties.
In the case of the landfills discussion, the con group was trying to resolve characterization uncertainties. For landfills, resolving regulatory and technical uncertainties may resolve characterization uncertainties. Then an two primary reasons for this:
EPA and the Regional Water Quality Control Board technically have set precedents for capping landfills, and EPA and the Regional Water Quality Control Board have regulations and guidance that cap landfills as a preference.
As a result, the core p u p agreed to the following approach of discussing data needs:
To shift their disc.ussion of data needs to focus on uncertaintiddata needs of other sources To evaluate regulatory and technical uncertainties to d a d c if reasons exist that would not allow the LEHR landfills to be capped and would quire a response action different than the precedent
Draft- 16
During the remaining time, the team discussed the technical data needs of identified likely response actions. The discussions are summarized in Tables 3-9. Due to time constraints, the team was unable to discuss data needs for in-situ and ex-situ treatment.
Draft- 17
Table 3 Likely General Response Action: No Action
Sources for which alternative has been designated likely: Radium & Strontium Leach Fields (soils and cobbles), Septic Systems n u m b e d 2-7 (soils and structures), and Soil underneath the Southwestern Dog Pens (below gravel).
Uncertainty
Is fbture land-use consistent with no-action?
Are contaminant levels above action levels?
-
Additional Information Required Prior to Resolving
Action-Item
None
None
Existing Information
UC Davis would like to have limited use of LEHR.
Sufficient soil contamination data exists to make initial screen. (See table of expected conditions).
a
Action Required
UC Davis needs to determine long- term land use for LEHR
Use action levels to conduct a preliminary risk screening: 1. Compare expected conditions by source to EPA Region 1X Preliminary Remediation Goals (PRGs) 2. Use PRG values in Regional WQCB's Water Board's Designated Level Methodology (DLM) methododlogy to develop Regional WQCB action levels 3. Compare expected conditions by source to DLM values 4. Use action levels to distinguish which units cannot be considered for the no action alternative.
Table 3 Likely General Response Action: No Action
Uncertainty
For sources that have contaminant levels below action levels, what additional data are required to support the no action alternative?
What is the cost of colltcting data to support a no action alternative vs. the cost of excavation?
Existing Information
Sufficient soil data is expected to exist for the newer strontium-90 leach field to fiuther support the no action alternative. Other sources do not have sufficient information.
Sufficient data exists to do a preliminmy cost analysis. The public would prefer an action alternativt. If the cost to suppport a no action alternative is comparable in cost to an action alternative, action is preferable.
Additional Information Required Prior to Resolving
Action-Item
None
None
Action Required
If the prefered allernalive is no action, DQOs must be developed 10
determine what cons~itu~es sufficient information to support no action. This may be necessary for the following locations: the old Sr- 90 leach field, the Ra-226 leach field, septic system # I leach field, along the dry wells, along the trenches, and below the tanks. Other sources are not being considered for no action. '
Determine if no action is cost- effective alternative by comparing relative costs of no action and action alternatives. Specifically, 1. Data collection to support a no action alternative (see above), and 2. Excavation and disposal Prior analysis discussed above must be completed before performing this analysis.
Table 3 Likely General Response Action: No Action
Uncertainty
Is no action a feasible alternative when considering interacting components?
Existing Information
Some sources art divided into separate components for the purpose of evaluating alttnratives. If one component requires action, a no action alternative may no longer be feasible for other components of the source.
Additional Information Required Prior to Resolving
Action-Item
None
Action Required
I . Determine if no action is the likely preferred ahernative for all components of a divided source. 2. If no action is not the likely preferred alternative for all of (he components, evaluate how the components of the source influence or interact with each olher to determine if a no action alternalive is still.feasible for some of the components of the source.
Table 4 Likely General Response Action: Excavation
Sources for which alternative has been designated as likely: Radium dr Strontium Leach Fields (soils, cobbles, and structures), Fony- nine waste holes, Disposal Trenches (southwestern trenches, area of intrusion, and solid waste trenches), DOE Disposal Box, Septic
Systems numbered 2-7(soils and structures), and Soil underneath theSouthwestem Dog Pens (below gravel).
Uncertainty
Are there health and safety issues associated with excavation?
What are the approximate dimensions of needed excavations for use in feasibility study and design?
Existing Information
Contaminants of concern for H&S issues and ranges of levels expected are known
Varies. For some sources, location and general dimensions are known. For other sources, even location is not exactly known.
Additional Information Required Prior to Resolving
Action-Item
None
None
Action Required
Confirm uncertainties are manageable. Proposed con tingnecy plan is to start at Level B and drop down to Level C if appropriate.
Develop order of magnitude volume/costs. Sufficient information exists to make relative, but not absolute, cost comparisons. This information will be used to determine if existing information can support FS-level definition and evaluation of alternatives.
Table 4 Likely General Response Action: Excavation
Uncertaioty
When should excavation bc stopped?
What ARARs exist that affect the excavation alternative?
Will a CEQA analysis of the excavation will bc rquircd?
Existing Information
Enough information is available io facilitate FS-level and design-level calculations of excavation volumes. Actual extent of contamination is not known for any source. Actual dimensions cannot be determined with great confidence prior to excavation.
State has PRG type cleanup rules that may bc ARARs for the excavation
State has indicated preliminarily that a CEQA analysis will bc rcquircd
Additional loformation Required Prior to Resolving
Action-Item
None
None
None
Action Required
There will always be surprises with volumes. This uncertainty is manageable with a contengency plan to guide the excavation. To assess the feasibility of this approach, use existing information to develop concentiation profiles. The profiles are used to estimate depths and Iengths/widths of required excavations with wficient accuracy to determine when excavation methods would change.
Preliminary ARARs analysis to determine when to'stop excavation. Use State/EPA PRGs as a first step in this determination
Preliminary ARARs analysis to identify regulatory (e.g., CEQA) issues that the Stat?, EPA, and DOE must resolve
Table 5 Likely General Response Action: On-Site Disposal
Sources for which alternative has been designated as likely: Radium and Strontium Leach Fields (soils, cobbles, and struct~es), Forty-Nine Waste Holes, Disposal Trenches (southwestem trenches, area of intrusion, and solid waste trenches), DOE Disposal Box,
Septic Systems Numbered 2-7(soils and structures), and Soil underneath the Southwestern Dog Pens (below gravel)
Dra ti--23
Uncertainty
Is future land-use consistent with on-site disposal?
What is the cost of constructing an on-site landfill?
What regulations could impact on-site disposal?
will h e majority of the cornunity accept on-site disposal?
Existing Information
UC Davis has indicated acceptance of on-site disposal
Sufficient data exists to do a preliminary cost analysis (e-g., sizing and construction costs) of on-site disposal.
Radioactive materials are expected in most of the sources listed above
Community preference is for off-site disposal. However, the majority of the community will base its acceptance on technical data and risk analysis.
Additional Information Required Prior to Resolving
Action-I tern
None
None
None
Lcvel of community acceptance with on-site disposal
Action Required
I . Location for on-site disposal 2. UC Davis' final land-use designation
1. Develop preliminary cost 2. Determine volume sensitivity of costs
ARARs analysis to determine radiological waste disposal requirements
Go to the public as early and as often as possible. Commit to public participation in the alternative selection process. 'public opinion is one of many factors that will deternline the final remediation strategy.
Table 5 Likely General Response Action: On-Site Disposal
Uncertainty
Arc here permitting issues that could impact on-site disposal?
Additional Information Required Prior to Resolving
Action-Item
None
Existing Information
The State has indicated that it may waive the land ban ARAR
CA mles and regulations are being developed for building a mixed waste facility
Action Required
, ARARs analysis in first-cut FS to determine: I . Land ban restrictions 2. Feasibility of disposing mixed or radiologic waste on-si te 3. May need to meet substantive requirements that are being developed in CA for building a mixed waste facility
Table 6 Likely General Response Action: Off-Site Disposal
Sources for which alternative has k e n designated as likely: Radium and Strontium Leach Fields (soils, cobbles, and structures), Forty-Nine Waste Holes, Disposal Trenches (southwestern trenches, area of intrusion, and solid waste trenches), DOE Disposal BOX,
Septic Systems Numbered 2-7 (soils and slructures), and Soil underneath the southwestern Dog Pens (below gravel)
Uncertainty
What criteria must waste meet to be shipped off- site?
What is the cost of shipping waste to an off- site disposal facility vs. the cost of on-site disposal or hot spot removal and capping?
what other quirements (e.g., rtgulations, paperwork requirements) could impact off-site disposal?
Existing Information
Existing information is sufficient to evaluate. DOE- OAK has waste acceptance criteria (WAC) for Hanford and Envirocare.
Sufficient data exists to develop a preliminary cost analysis of off-site disposal for both Hanford and Envirocare.
Existing information is sufficient to evaluate
Additional Information Required Prior to
Resolving Action-Item
None
None
None
Action Required
Compare WAC at likely disposal sites to expected conditions
Develop preliminary cost estimate of off-site disposal. ,
Evaluate paperwork requirements for off-site disposal
Tablt 6 Liktly Gtntral Rtsponst Action: Off-Sitt Disposal
Unctrtainty
To which off-site disposal facility will LEHR send waste?
Existing Information
LEHR has previousily shipped waste to Hanford. DOE has access to COE contract for Envirocare.
Additional Information Rtquirtd Prior to
~ u o l v i n ~ Action-Item
Cost and contract terms at each disposal facility.
Action Required
Confirm that waste can be accepted at an off-site disposal facility and determine destination
Table 7 Likely General Response Action: In-Situ Containment
Sources for which alternative has been designated as likely: Radium and Strontium Leach Fields (structures) and Septic Systems Structures (systems numbered 2-7)
Uncertainty
Is the backfilling of systems' structures and the decision to leave them in place consistent with planned future land use?
Will the stability of structures after backfilling be consistent with UC Davis expected land use?
1s backfilling and leaving structures in place protective of human health and the environment?
would in-place backfilling be inconsistent with other actions (e.g., removal of soils under structures)?
Existing Information
University has indicated desire to not prohibit building or transportation over these sources
General information on the sizes and types of structures
Information on materials of construction and conditions of liners. Information on the level of radioactivity is available for some lines.
GRAs identified for the soils around and under the structures
Additional Information Required Prior to Resolving
Action-1 tern
Future land-use
None
Physical samples From structures to determine radiologic constituents/ contamination
None
Action Required
UC Davis to determine long-term future land use for LE t 1 R
Explore backfilling nlethods and stability of structures after backfilling
Action levels analysis using PRGs and DLM
Determine the interactions that have to be considered in evaluating the alternatives
Table 8 Likely General Response Action: Hot Spot Removal
Sources for which alternative has been designated as likely: Forty-nine waste holes and Disposal Trenches (southwestern trenches, area of intrusion, and solid waste trenches)
Uncertainty
Which alternative (i.e., hot spot removaVcapping or entire removal) is more cost effective?
What is a hot spot?
Will the efforts d e d to identify hot spots be cost efftctive?
'
Existing Information
Costs of excavation and disposal is known or can be determined.
Currently a hot spot is defined as anything that does not meet the no action criteria
References are available on this typc of sampling. Limited site information available that would support identification of hot spots.
Additional Information Required Prior to Resolving
Action-I tern
None
None
None
Action Required
Develop cost of excavation & disposal vs. cost of analysis, hot spot excavation & capping
Develop definition of hot spot
Determine sample types and number needed to identi@ hot spot locations (i.e., DQOs).
VI. Relative Cost Comparisons
Introduction l h s package contains initial cost estimates for four general remediation alternatives for the LEHR site at the University of California at Davis. The alternatives were developed based on general guidelines from the extended project team and are intended to bound the range of altematives considered to be "likely". Consideration of the A g e of feasible altematives for the LEHR site is at a very preliminary stage. Initial cost estimates arc useful at this stage in a CERCLA investigation to identify cost ranges for the possible alternatives that might be considered and to focus any additional data collection and evaluation toward the critical factors that determine feasibility, effectiveness, and cost. These initial cost estimates were prepared for initial comparison of relative costs of the altematives. They also provide insight on the factors the final cost estimates will be most determined by, that is, the factors that costs arc most sensitive to. They arc not accurate or complete estimates of total costs that would be incurred to implement the alternatives. B* since they each contain the major cost items that will influence total costs, and because they arc based on consistent assumptions about volumes, unit disposal costs, areas to k remediated, and other major factors, they can k used in relative comparisons. Where the estinat-s for two alternatives differ by a large factor and diffkmces in potential protectiveness are not potentially worth the multiplication of costs, some modification or focussing of the alternatives under consideration might k wamnted.
Limits The costs determined by this estimating effort are not as accurate as required for a CERCLA feasibility study; the latter are "order of magnitude" h a t e s defined & k i n g accurate within + 50% and - 30%. No similar accuracy factor can k reliably attached to the estimates provided here. They are not, as CERCLA cost estimates typically arc, built up from a semidetailed breakout of line items that would k incurred in actually implementing the altematives at a specific site. They are instead based on typical unit costs for large cost items, such as constructing a cap, plus large allowances for the sums of all the smaller cost items that are not broken out in detail. . Cost estimates in a feasibility study arc based on much better defined altematives and arc typically much more detailed k d ekpensive to preparc than is necessary or justifiable at this early stage of exploring alternatives for the LEHR site. More accurate cost estimates will k appropriate later in the process of investigating the LEHR site, when the range - - -
of feasible alternatives is better understood.
More accurate and complete estimates of costs will have to await the development of k t te r engineering descriptions of the alternatives in a feasibility study and perhaps additional information about the site. Baxd on the uncertainties identified in preparing these initial cost estimates, any additional information needed to improve the accuracy and reliability of the cost estimates can k identified. Whether current site information can support cost estimates sufficiently accurate to facilitate selection of remedial actions for the LEHR site needs to be
determined.
Sensitivities The following an large cost determining factors and thus have the potential to sigmficantly affect the total cost estimates:
Actual waste quantities assumed to be excavated. ' (All of the alternatives assume at least partial excavation.) At any level of detail (i.e., preliminary or final) it is always difficult to estimate voluma of waste that will result from excavation, with mon approaching 50% not being uncommon. .
Type of cap assumed for those alternatives that assume at least partial capping of wastes in place. (i.e., Altcmatives 2 and 3). The cost estimates arc based on a RCRA type cap, which is traditionally considered to be a high efficiency and high cost capping method. There is no standard RCRA cap applicable in all settings. However the general features of a RCRA cap arc: approximately five feet total thickness with a flexible 'membrane liner, a compacted clay layer, a sand drainage layer, and a topsoil layer. The entire cap is graded and sloped for chinage. While the exact requirements that would apply at the LEHR site have not been determined, the forgoing is typical and is not inconsistent with the approximate cost assumed for these estimates: S250,000 per acre. Less expensive capping alternatives, that meet minimum California regulatory requirements for closing old landfills, might reduce the unit cost for capping by as much as 40%.
Unit costs for off-site disposal the wastes. The estimates arc based on the cumnt costs for DOE wastes going to a particular facility under a specific cost contract held by another federal agency. These arc the probable costs that would be i n c d However, thew are very favorable costs. L€ for any reason, that contract could not be used, LEHR could reasonably see unit costs twice as high as assumed in these estimates.
Assumed waste designations for the wastes (i.e., hazardous waste, radioactive waste, or mixed waste). The assumed unit cost for transportation and disposal of soil classed is hazardous waste is $300 per cubic yard; for soil c l a d as low-level radioactive waste the same unit cost factor is S400 per cubic yard; for soil classed as mixed waste it is S 1,400. Thus, the designations of the wastes assumed in the costs estimates are vtry large determining fkton.
Incornpleteneu of Cost Estimate - The alternativa estimated here arc not complete. The alternatives address source control actions.
Additional remediation efforts may be required to address deeper soils if they are c o n e e d ; additional efforts that may be naessary address groundwater cannot be designed or estimated at this time.
Deep vadow tone soils. Contaminants have reached the groundwt~r and must have
Draft- 3 0
passed through vadose zone soils to reach that point. Whether there are any areas of concentrated contamination that can or should be excavated or remediated in place has not been determined. The cost estimates do not assume any actions for deeper soils.
Groundwater contamination. The precise needs for groundwater remediation, including general approach, extent, and pumping rates, have not been determined, and may be sipficantly altered by the source control efforts envisioned in the alternatives addressed here. The cost estimates do not address the potential need for groundwater remediation.
The estimates do not fully account for LEHR being a DOE site. The estimates do not account for the higher programmatic, administrative, and procedural costs associated with DOE site remediations. Some of the unit costs are based on limited data available for working on a DOE site; some cost indications are available for capping and excavation on DOE sites, but not for constructing an onsite landfill.
The estimates do not adequately account for differences in costs for handling radioactive, hazardous, and mixed wastes. Some of the unit costs for site work (excavation, capping, transportation, onsite landfihg) may vary sigmficantly between these waste types. No allowances have been made for these differences.
Alternative 1: Remove All Wastes from Their Current Locations and Consolidate in an On-Site, RCRA-Compliant Disposql Facility.
The foIlowing sources would be excavated: .
Radium and Strontium Leach Fields (includes lmhoff tanks and septic system # 1 )
, I . - Forty-nine Wise Holes Disposal Trenches (including the southwest disposal trenches and the chemical dispensing area) Landfill # 2 Landfill# 1 Landfill # 3 DOE Disposal Box Septic System 2 - 7 Western Dog Pen Soils
The total volume of soils and wastes assumed to be excavated and disposed in the RCRA- compliant rmit is 50,000 cubic yards. (For comparative purposes, this volume would, if placed evenly on .a thee acre site, stack up to approximately ten feet deep.)
Volumes of wastes i4 be excavated arc estimated based on known andfor suspected dimensions of the o r i g d disposal units (e.g., trenches, holes), or based on assumed dispersion of the contaminants from the units. Overexcavation and bulking factors are added to the estimated, in-ground volumes of the wastes to better estimate the volumes that will be produced by the excavation activities.
The estimate does not assume any particular action levels, either for excavation or demonstration of remediation completion/success (i.e., excavate until the residual levels are below')[). Available data on the contamination distribution would not allow calculation of the impacts of assuming various action levels.
Landfill 3 is assumed to be excavated only within the areas that showed anomalies on the geophysical surveys, approximately 30% of the total area of the landfill on the available maps. The landfill was operated for only a few years and the entire area of the landfill shown on some maps is not likely to contain wastes.
The Western Dog Pen Soils would be excavated to six inches below the existing, clean gmvel, a total of 2,100 cubic yards. The clean gravel would not be placed in the RCRA landfill.
The landfill would be RCRA compliaa with liners, l e a c h collection, leak de&tion, RCRA cap, monitoring wells, and post4osun care and maintenance. The cost of
constructing, operating, closing, and maintaining the RCRA disposal unit are estimated on a per-cubic-yard-of-disposal-space basis, at $300 per cubic yard. Note that h s assumes that disposing radioactive and mixed waste in a RCRA-type landfill will be acceptable.
No location for the RCRA unit is assumed, but it is assumed that the exact location on the UCD site would not sipficantly affect the cost estimate.
The RCRA landfill would be built first to avoid the need fdr temporary storage of wastes between the time of excavation and the availability of the disposal facility.
Air emissions during remediation are considmd to be manageable without extraordinary means, such as building temporary containment structures. Thus, the cost estimates do not include an allowance for air emissions control during remediation.
Groundwater remediation is not considered in this alternative (or any of the other three alternatives).
Unrestricted use of the site vould be allowed by this alternative, but the remediation is assumed to include only bddilling of the excavations to grade, without any other replacements or modifications of inhstructurc (e-g., roads, buildings).
Sensi tivities
Other than the major cost determinants noted in the Introduction, no additional factors have the potential to significantly affect the total cost of the alternative as estimated here.
Alternative 2: Remove Wastes from Sources Not Adjacent to Landf& 1,2, and 3 and Consolidate in on-Site, RCRA-Compliant Disposal Faciiity. Cap Landfills 1,2, and 3 and Their Adjacent Sources.
The following units would be excavated:
1. Radium and Strontium Leach Fields (includes Imhoff tanks and septic system # 1 )
3. Trenches 1-5 of the Disposal Trenches 7. DOE Disposal Box 8. Septic Systems 2 - 7
The following sources arc considered adjacent to one or more of the landfills for this alternative and would be capped in addition to the capping of the thm landfills:
2. Forty-nine Waste Holes 3. Trenches 6-1 7 of the Disposal Trenches, which includes the SW Disposal
Trenches (i.e., trenches 1 5, 1 6, and 1 7) 9. The Western Dog Pen Soils
The total volume of soils and wastes assumed to be excavated and dtsposed in the RCRA- compliant unit is 1,250 cubic yards. (For comparative purposes, this volume would, if placed evenly on a three acre site, stack up to approximately 3 inches deep.)
Volumes of wastes to be excavated are estimated based on known andlor suspected dimensions of the original' disposal units (e.g., trenches, holes), or based on assumed dispersion of the contaminants from the units. Over-excavation and bulking factors are added to the estimated, in-ground volumes of the wastes to better estimate the volumes that will be produced by the excavation activities.
The estimate does not assume any particular action levels, either for excavation or demonstration of mediation completion/success (i.e., excavate until the midual levels are below X). Available data on the contamination distzibution would not allow calculation of the impacts of assuming various action levels.
Landfill 3 is assumed to be capped only at the areas that showed anomalies on the geophysical w e y s , approximately 30% of the total area of the landfill on the available maps. The 1andfi.U was operated for only a few years and the entire area of the landfill shown on some maps is not likely to contain wastes.
The landfill would be RCRA compliant, with liners, leachate collection, leak detection, RCRA cap, monitoring wells, and post-closure care and maintenance. The cost of
consaucting, operating, closing, and maintaining the RCRA disposal unit are estimated on a per-cubic-yard-ofdisposal-space basis, at $300 per cubic yard. Note that this assumes that disposing radioactive and mixed waste in a RCRA-type landfill will be acceptable.
No location for the RCRA unit is assumed, but it is assumed that the exact location on the UCD site would not significantly affect the cost estimate.
The RCRA landfill would be built first to avoid the need for temporary storage of wastes between the time of excavation and the availability of the disposal facility.
The cap on Landfills 1 and 2, the forty-nine waste holes, the disposal trenches except trenches 1-5, and the southwest arca would be one continuous cap. The arca of this cap is assumed to be approximately 7.1 acns.
The cap is assumed to comply with the standard requirements for a cap on a closed RCRA disposal unit. It would be approximately five f a t thick and incorporate a flexible membrane liner, a compacted clay layer, a sand dramage layer, and a topsoil layer. The entire cover would be graded and sloped for drainage.
Air emissions during remediation arc considered to be manageable without exmiordinary means, such as building temporary containment structures. Thus, the cost estimates do not include an allowance for air emissions control during remediation.
Groundwater remediation is not considered in this alternative (or any of the other three alternatives).
Sensitivities
In addition to the major cost drivers noted in the Introduction, the following factors have the potential to significantly affect the total cost of the alternative as presented hen.
Whether or not the westan dog pen soils arc included in the area to be capped. These soils ah very lightly contaminated, if contaminated at all. Further investigation may indicate that they do not require remediation. The 2,100 cubic yards arc spread over an area of approximately 2 acres, which would cost $500,000 to cap.
Type of cap assumed for the landfills and adjacent a m . A RCRA-type cap is assumed. A simpler, but perhaps equally effective cap could be c o m c t e d at a reduction in cost as high as 40%.
Draft- 3 5
Alternative 3: Remove Wastes from Sources Not Adjacent to Landfdls 1,2, and 3 and Dispose of Off-Site in Appropriate Disposal Facilities. Cap L r n d f i 1,2, and 3 and Their Adjacent Sources.
The following units would be excavated:
1. Radium and Strontium Leach Fields (includes Lmhoff tanks and septic system #I)
3. Trenchesl-SoftheDisposalTrenches 7. DOE Disposal Box 8. Septic Systems 2 - 7
The following sources are considered adjacent to one or more of the landfills for this alternative and would be capped in addition to the capping of the three landfills:
2. Forty-nine Waste Holes 3. Trenches 6- 17 of the Disposal Trenches, which includes the S W Disposal
Trenches (i.e., trenches 15, 16, and 17) 9. The Western Dog Pen Soils
The total volume of soils and wastcs assumed to be excavated and disposed is 1,250 cubic yards. (For comparative purposes, this volume would, if placed evenly on a three acre site, stack up to approximately 3 inches deep.)
Volumes of wastes to be excavated arc estimated based on known andfor suspected dimensions of the original <tspasal units (e.g., trenches, holes), or based on assumed dispersion of the contaminants from the units. Overcxcavation and bul)cmg factors are added tot he esthatd, in-ground volumes of the wastes to better estimate the volumes that will be produced by the excavation activities.
The estimate does not assume any particular action levels, either for excavation or demonstration of remediation completiodsuccess (i.e., excavate until the residual levels an below X). Available data on the con t a m i d o n distribution would not allow calculation of the impacts of assuming various action levels.
Off-site disposal is assumed to be at commercial facilities permitted to receive the types of wastes present at UCD. For purposes of this estimate, each waste unit was designated as containing either hazardous waste, radioactive waste, or mixed waste. The disposal requirements and disposal costs for these thm types of wastes vary substantially (i.e., $300, S400, and S1,400 per cubic yard) and have a very si@cant impact on the overall
cost estimates for this alternative.
Landfill 3 is assumed to be capped only at the areas that showed anomalies on the geophysical surveys, approximately 30% of the total area of the landfill on the available maps. The landfill was operated for only a few years and the entire m a of the landfill shown on some maps is not likely to contain wastes.
The cap on Landfills 1 and 2, the forty-nine waste holes, the disposal trenches except trenches 1-5, and the southwest area would be one continuous cap. The area of this cap is assumed to be approximately 7.1 acres.
The cap is assumed to comply with the standard requirements for a cap on a closed RCRA disposal unit. It would be approximately five feet thick and incorporate a flexible membrane liner, a compacted clay layer, a sand dramage layer, and a topsoil layer. The entire cover would be graded and sloped for dramage.
Air emissions during remediation are considered to be manageable without extraordinary means, such as building temporary containment structures. Thus, the cost estimntcs do not include an allowance for air emissions control during mediation.
Groundwater remediation is not considered in this alternative (or any of the other three alternatives).
Sensitivities
In addition to the major cost drivers noted in the Introduction, the following factors have the potential to significantly affect the total cost of the alternative as presented here.
Whether or not the western dog pen soils arc included in the area to be capped. These soils arc'very lightly contaminated, if contaminated at all. The 2,100 cubic yards are spread over an area of approximately 2 acres, which would cost S500,OOO to cap. Further investigation may indicate that they do not require remediation.
Type of cap assumed for the landfills and adjacent areas. A RCRA-type cap is assumed. A simpler, but perhaps equally effective cap could be constructed at a reduction in cost as high as 40%.
Alternative 4: Remove All W l s t u from Their C u m n t Locations and Transport to Appropriate Off-Site Disposal Facilities for Disposal
The following sources would be excavated:
1. Radium and Strontium Leach Fields (includes Imhoff tanks and septic system # 1)
2. Forty-nine Waste Holes 3. Disposal Trenches (incluchg the southwest disposal tmches and the
chemical dispensing area) 4. Landfill # 2 5. Landfill # 1 6. Landfill # 3 7. DOE Disposal Box 8. Septic Systems 2 - 7 9. Western Dog Pen Soils
The total volume of soils and wastes assumed to be excavated and disposed in .the RCRA- complian. - A t is 50,000 cubic yards. (For comparative purposes, this volume would, if placed evenly on a three acre site, stack up to approximately ten feet deep.)
Volumes of wastes to be excavated arc estimated based on known andlor suspected dimensions of the o r i w disposal units (c.g., trenches, holes), or based on assumed dispersion of the con taminants from the units. Ova-excavation and bulking factors are added to the estimated, in-ground volumes of the wastes to bmer estimate the volumes that will be produced by the excavation activities.
No action levels for excavation or demonstration of remediation completion/success are assumed. Available data on the contamination distribution do not allow calculation of the impacts of various action levels.
Landfill 3 is assumed to be excavated only within the areas that showed anomalies on the geophysical surveys. The landfill was operated for only a few years and the entire area of the 1- shown on some maps is not likely to contain wastes.
The Western Dog Pen Soils would be excavated to six inches below the existing, clean gravel. The clean gravel would not be disposed of ofiite.
Off-site disposal is assumed to be at commercial facilities permitted to receive the types of wastes present at UCD. For purposes of this estimate, each waste unit was designated as containing either hazardous waste, radioactive waste, or mixed waste. The disposal
requirements and disposal costs for these three types of wastes vary substantially (i.e., $300,5400, and $1,400 per cubic yard) and have a very significant impact on the overall cost estimates for this alternative.
Air emissions during remediation are considered to manageable without extraordinary means, such as building temporary containment structures.
Groundwater remediation is not considered in this alternative (or any of the other three alternatives).
Unrestricted use of the site would be allowed by this alternative, but the remediation is assumed to include only backfilling of the excavations to grade, without any other replacements or modifications of inh tmcture (e.g., roads, buildings).
Sensitivities
Other than the major cost detcminants noted in the Introduction, no additional factors have thc potential to significantly affect the total cost of the altemative as estimated h a .
LEHR COST ESTlMAl €(preliminary) Cost Summary for Restoration Alternatlves
ALTERNATIVE ALT 1 -- onsite Landfill
ALT 2 -- Cap and Onsite andf fill
ALT 3 -- cap &d 0 f f J i ~ ~ ~ " d f i u
ALT 4 -- Offsite Landfill - ALT 4 -- Offsile Landfill
COST $23,000,000
$10,000,000
$10,000,000
$31,000,000 $137,000,000
COMMENTS . . - - . . . . . . . . . - - . Excav. all areas incl. 70% of iFi h ~i'#2,'a;rb . . . 30% of LF 13
Excav. . RalSr . leach, - . &-me SW . - Irenches, . - . . W E box, septic sys 112 lo 7
.- . - - . - Excav. RalSr leach, some SW trenches, WE*box, seplic sys #2 lo 7
Landfills 1,2, and 3 as Hazardous Wasle Landfills 1,2, and 3 as Mixed Wasle
LEHR COST ESTIMATL ,preliminary) - Unit Costs
Page 1
UNIT COSTS TranspoNdispose mixed waste (soil) Transport /dispose mixed waste debris TranspoNdispose rad waste (soil) TranspoNdispose . . . . . - - . . rad - waste . . . . . debris . . . . - TranspoNdispose haz waste -
RCRA Cap
Waste Type . MWS MWD RWS RWD HW ---
Excavate h a ~ , rad, or mixed waste -- Onsite Landfill -- large - - - - . - - - &site Landfill -- small
Comments Appro;. 750 mi haul '
Approx. 750 mi haul Approx. 750 mi haul Approx. .- 750 mi haul . . . . . Approx. 250 mi haul
Unit . cost $2,000 $3,700
$430 $980 $300
$325,000 Soil excav. 6 analyses;H&S, air monit, backfill construction, handling, placement, closure construction, handling, placement, closure
Unit & .
cy cy cy . - - cy Ac
$75 $150 $250
cy cy cy
LEHR COST ESTiMATE(prelirnlnary) -- Quantity Spreadsheet
SITE AREA ALT 2 cap' - Area (auer)
ALT 3 oiisiie LF Volumes (cy)
50(]
ALT 3 ALT 4 . . - . - . - ALT 5 ALT 5 WASTE TYPE Commenls - . .. . .
Cap - Ohsite LF ~ o n s o ~ ~ a ~ Cap Rad.Haz.Mixed '
I RADlUMlSr LEACH FIELDS
2 . 4 9 WASTE HOLES - .
ind wl LF I 2 ind wl LF I 2 400 indwlLF I 2 RWS
3. SOLID WASTE TRENCHES
-
4 LANDFILL I 2 -
- - - . . - . - - - 5. UNDFILL I 1
6. LANDFILL I 3 I I I
26001 0 . 2 1 ~ iAn as Mixed waste I ' 5 0 Vdums allowance 7. DOE DISPOSAL BOX
8. SEPTIC SYSTEMS 2 THRU
9. SW MX; PEN SOILS
lnuemental Cap from wnroli --
2.1 2100 2.1 RWS
- 0 2
TOTALS --- -- Soil Bulkrnp Factor
Overexcavation Fbctor
LEHR COST ESTlr. E (preliminary) Alternative 1 -- ExcavatelOnsite Landnll
Page 1 3124195 3 .09 PM
AREUCosl llem -. - GENERAL COSTS
ln~s lga l i ons
Site Preporalion
SYe Conlrols
Tempocary Facilities - - - - - - - - 1. RADlULUSr LEACH FIELDS
Exuvate
Onsite LondW - . 2 .49 WASTE HOLES -- - - - - Exuvale .
Onrye LandfJl - - . . - - -- -. 1. SOLID WASTE TRENCHES Exuvale
-.-
~ n r i l e ~ a n d r ~ l
4. LANDFILL 1 2
Exuvale
Onsite Landfill - - - 6. LANDFILL I 1 -
Exuvole
Onsile Landf~ll -- 6. LANDFILL I 3 - - Exuvale
Onrite LandrJl
7. DOE OlSPOSAL BOX
E x u l .
ollS&. Landfin 8. S E P W SYSTEMS 2 THRU 7
Exuval. --
Onsite Landrill 0. SW DOG PEN SOILS
~ x u v o l e
Onrile Landfill ______. - GROUNDWATER ____.__ Eflrocl&n w ~ U ~nslallalion(Cr) ______-_ . . . . .
Grwndwaler Trea~menl Syslem _ - . D~scharge Line
QUANTITY
1
1
1
- - -
500 - -- 500 . - - - - -. . - -
400 400
- - - - - 2=
22000
22000 - - -- -
~~
-- 64mI sooOcy
-.
--- 400
--- 400
2100
2100
- -
. . .
. . . . .
UNITS ...
Is
Is
Is l h -- -. - ---
!2-- 2- -- - - - - - cy
cy-- - . - CY
2 5 o O c Y
cy -- cy
- CY
cy- --
-- CY
SOcy SOcy
cy
CY
-.
cy
cy .-
. .
UNIT COST . .
$ 1.000.000
$200.000
$200.000
$200,000 - -
$75 -- $150
- - -
--- $75 $150
f 75
$150
$75
$150
$75
$150
$75
$150
$75
$150
$75
$150
$75
$150
. . -- -. -
. --
- - . - -. .. - - . -
COST TOTAL . . . ..... -
$ 1.000.000
$200.000 . . .
$200.000 . . . . - $200,000
$38.000 $75.000-
- - $30,000
wJ.Oo0
$166.000 $375.000
-- S 1,850,000
$3.300.000
- $1,500,000
s3,000,000
- $450,000
$900,000
s4,oa)
-- sa.000
$30,000
S60.000
-- $158.000
$315,000
- - . - .. .- - .
............. - - -
. . . - . - - .. - - . - - - .
COMMENTS . . . . . . - - -
p;ehln=ry albwanca (2x olfsile bndrJl AN. 4)
Prehbary akwancs (2x offsite landlii AN. 4) . .
Prelilnary alorrsnca (2x offsite lsndl l All. 4) - . . . . . . . . . . Prehlnary akwance (2x offsite lsndrJl All. 4) - Trenches, lmhoU Irnk.,Septk syslem I 1
Soil exuvalbn and ma)yrss;hd. --- ak monloring and heolh and safely cosls
-- Soil excavalion a d 8~)yrer;Lnd. a& rnonitotlng and her lh and safely cosls - -. - - - - - - -
Sod exuvalkn a d 0naIyaes;lnd. a i monitoring and heolh and safely coals
Assuned oxuvale 7 W , SOU a ~ l y a a s , r k monitoring. H I S
Assumed exuvrl. 70%. SOH analyses, ak monitwhg, H I S
h s u n e d exuvr le 30%. sod matyses. a& monitotlng. H I S
. .
Exuvale 6 i~lches over entire aroa;gravel no1 hd.
---- Nd lnduded in prelbnlnrry eslimole - - - --
- - - wens. Ovg &pvI ea =
- - - - --- gpm syslem;Cr(6) reduclionlppl and 1X - - - - - - - - - - - -. - . - - - - - - -. - . - .
LEHR COST ESTIMATE (preliminary) Alternative I - ExcavatelOnsite Landfill
ARENCosl llem . . Moniloring Wen InslaNalion
E x l r ~ l m n Well InslaYalion[CHCI3)
Grwndwaler Trealrnenl Syslem . . Discharge Line - - - - - - - - - - - Moni(otlng Well lnslahlion p-
VADOSE ZONE REMEDIATION - . - - - - - - - - Soil V w ExlradionlOffqas T r M - - - - . - . - . . - - - - - - - - . , . . - - . .
. - CONSTRUCTION SUBTOTAL --.- MobUrlbnldernoHizrIion - Sile Preporalbn and Uilily Hookups
Bonding and Insurance - - Permitlhg and Legal ----
QUANTITY
--
- - . - . - - - - - . - . . - - - -
--.--
- --
UNITS
--
- - - -
. - -
- . - . - --
t b l b l h - - l h --
She Abninislrolbn -
- Cotredive Adion PbnrlDesigns
Services During Conslrudbn
Is
Is
l h
1 ---- 1
---
UNIT COST ...
SITE REMEDIATION SUBTOTAL ---- Conlingency - REMEDIATION CONSTRUCTION
COST . . - . . . TOTAL
... . .
C 0 n l r . d ~ *La .6nln; Prelimlnory alowrncr (2x offsire b n d r i AH. 4)
PreUmhar) *owanat (2r dftL lrndHAl. 4) Preliminary rlowrnca (21 offshe IandlWI All. 4)
$200,000 s 1,000.000
$2m-J,000
- -- -
- -1 '9- TOTAL - -
COMMENT&,
Addlbnal wsls --. . - . . . .
- web, aug depth e r = . . . . . . . . .
- gpm syslem. GAC .. .. . . - ... . . . . -
-- - --
$200,000
$1,000,000
- $200,000
-- 30%
.---
-- Nol Muded h preliminary eslhale -- - -- - . - - -
... ____ __
-- - - - - -
. -
- Akmnc;. Allowance No( hd. h pnhh.ry es lh r l e
Not hd. h prelWnuy e s h r l e
--- -- -------- -
---- - - - . - - - - - - -
$ 17,200.000 -- $5,200,000 $ 22,ooo.ooo
-
.-
$20.000 $20.000
$€I
18.m
-- $4,000
----- S 52.000 $ l5 .W
S67.m
ANNUAL O I M
L M J I cap monitoring, m8inlenance
Gromdwaler m o n l h g
(iroundwrler Trerlrnenl OaM - SVE syslem OhM Silo Admiislralbn
Owrsle Senticas
Annual O I M Sub(&l
C~Ung6nCY __ AnnuaJ O I M Tola1
.- . -
U F . O O O $200,000
$ 1 ,000.000 -
3 0 - ~ r O I M Present Worth - --
-- - $13.700,000
~00 ,000
$200,000 $1,000,000
15.372
$20,000
$2o,ooo
-- 20%
-- 10%
- 30% - - -
_ _ - -- - . 1
--A
-- -
-__
-- - --
Prelwninary a~ (2x offsite MI AI. 4)
Prellminwy okwrncr (2x offale landtill All. 4) PrelLnhary rlowonce (2x dfrl le IandM All. 4)
--.- -- $1,010,000 Al5% dhunur( rrle - Is
l b
l b
--
l b
l h -- --
l h -_- ___
Preliminary rlowrnco (2x offsile Irndi~ll All. 4) $500.000
$23,000,000 _ - _ _ . _ _ . . .
i o h l Presenl Worth
-- $500.000
. . . - -
LEHR COST ESTI. E (preiiminary) Alternative 2 -- Cap and. Onsite Landfill
ARENCosl Ilem
GENERAL COSTS
Inveslqalions I ISII~ Prepanlion
Site Conlrolr
Exuvale - - - . - - - Onrile Landfill
2.49 WASTE HOLES - - - - - - - - - - - Cep- - - . - - . - - - - 3. SOLID WASTE TRENCHES - -. -- Excavale
-. -- Onrile Landfill
4. LANDFILL l 2
COP 5. LANDFILL I 1 --
csp 8. LANDFILL I 3
c . p -- 7. DOE DISPOSAL BOX
Exuvale Hol Spds ---- - - Onrile Landf~U -
8. SEPTIC SYSTEMS 2 THRU 7
Excavale Hd Spd8
Onrile Landfi
S. SW DOG PEN SOILS
C'P - GROUNDWATER
Exlraclion WeW Inslallalbn(Cr)
Groundwater Treatmnl Syslem
Discharge Line -
Groundwaler Trealmenl Syslem
D~scharge Line
QUANTITY UNlT I UNIT COST COST TOTAL COMMENTS .. . . - . . . - - - - . - . . . - - . . - - . . . . . . . . I $750.000 $750,000 Preliminary albwancs ( 1 . 5 ~ onsite landfill All. 4)
s 150.000 . . . $150,000 . Preliminary .- albwincs -. ... . . ( 1 . 5 ~ . - offrile kndfi~ . . . All. 4)
$ 150.000 . $150.000 Preliminary atlawance (1.5~ offshe _ tandMAll. _ _ _ 4) _ _ . .. -. . - .
f 150.000 $150,000 Preliminary allowanca ( 1 . 5 ~ offrile landfil AH. 4)
Trenches, ImhM lank, Seplk ryslem I 1
Soil exuvalion and analywr;lnd. rlr moniloring and heanh and safely wsls
$125,000 --
$ 325.000 $0 Incl. wilh IandfiY I 2 cop - - - - -- - Trenches 1 lhru 5 only; 6 lhru 17 ind. wilh LF I 2 u p - ---- <I -. - - $2::: - - . Soil excavation and mdywr$~I. ab rnonilorhg and heatlh and safely w r l s
wells. avg deplh ea = gpm ryrlern;Cr(6) redudbnlppl and IX
- I p i t i o n a l wells - - - - - - - - - . - . . - - - - - - - - - - . . - - - - - . - - . - - - - --I
. . - - - . - - - - - - . - - . - - - . - - - - - - . - - - - . . . . . - - - - - - - - - - -- - . - - - wens. avg deplh ea = - - - - . - - - - - - - - - - . - - -. - - - - - - - - - - - . - I I_ gpm syslem. GAC . - - . - . . - - - - - - . . - - -. - - - - - . - - -- - . - - - -- I
Page 1
LEHR COST ESTIMATE (preliminary) Alternative 2 - Cap and Onsite Landfill
1
ARENCosl llem
Monilormg Well Inslallalion
VADOSE ZONE REMEDIATION . . .
S d V a p Exlracl~orJOfl~as Trlml . . . . . . . . . . . . - . - . . . . . . -
CONSTRUCTION SUBTOTAL
MobilizrUonMemobdizaUorr
S b Preporalion and U I U y Hookups ---- B o d q and Insurance
Pmmilthg and Legal
S io Mminlrlralion ----- Cotredha A& PlanJDesignr -- Senhxs During Conslrudkm - -
SITE REMEDIATION SUBTOTAL
QUANTITY
- . . .
----
1
--- ---
..- --
--- ---
UNITS
Is l b l b ---.
l b -- t b -- l b -. l h
- -
-- C o n t i n g g - -
REMEMATION CONSTRUCTION
ANNUAL oau LandfJVcap monitoring, mainlenance
Groundwaler moniloring Gtoundwsler Trsalmenl ObM
S M s y d m 06M SYa M m h b l r r l h
O~efS&e S ~ N ~ C ~ S - -
Annw l OILY Subtotal
Contingency Annual O I M Total
30-Yr O I M Pnsan l Worth
-----
Is .-
--
-- Is
l h
--
Is -- l h .--- -
I h
l b
1
-- TOTAL
1
.--.-
- - 1
--.-
---
-
----.
.---
UNIT COST
. . . . . . . . . .
- $300.000 $1 50.000 $750,000 - $37~.000'
$150,000 - S 750,000 $150,000
Tolal Present Worth
30%
--
SlO,ooO,OOO
$2,000.000
$ O , ~ , ~
COST TOTM
.....
$4.ooO.000 $300,000 $1 50,000 $750.000 $375,000
SlSfJ.000 - $750.000
$1 50.m
w.m.oOo
COMMENTS --. . . . . . . -. . .
Nd . . . W e d in prelimhuy . . . eslimale
- . - . .- - - --. ... .. . .. . . . . . . - . - . . . . . . . . .
Preliminary aIkwanu (1.5~ oNrWa L.ndM M. 4)
PreYmh.ry .lowmnca (1.51 ofhilo W M UI. 4)
Prehhary aMowwx (1.51 olhila W H A&. 4)
P r e h i n q ~kwurar (1.5~ ofts~a W I AR. 4) -- Contrador offike d m h ; pYmhuy 8lbuma (1.51 offsle hndri A&. 4) P~eYmhuy allowance (1.5~ l r n M M. 4)
~ t e ~ m l n r r y ~ k m n c a (1.5~ olhila l rndn M. 4)
- . -- $20.000 $15.000 Alkwance
$20.000 $20,000 Akwancs - $0 No( M. h pellr.thary e l l ha le
No4 M. h prahhuy a r l h u l r -.
20% $7,000 . 10%
50%
-
15.372
--
-- S 3.500
- $45,500 $22.750
$68.250
$1,050,000
-
-
N 5 % dbcount rala
- --
LEHR COST ESTL. .E(preliminary) Alternallve 3 -- Cap and Offsite Landfill
ARENCosl llem TYPE UNIT COST COST TOTAL COMMENTS .. - ... -. ._ _ , . .. . .
GENERAL COSTS . . . . .
Inveslqalions $650.000 $650,000 Preliminary allowance ( I .5x oflsile landtii AN. 4) . . .
Sde Prepanlion S 130.000 S 130.000 Prelimhary allowance ( I .5x offrile landfill All. 4) Si(e Conlrols . . .
. - -. . Temporary Facilities -- 1. RADlUWSr LEACH FIELDS Trencher, lmhofl tank, Septk system I 1 Exuvale -- $38.000 Soil excmvatbn a d 8nalyaer;lnd. alr moniloriq and health and safely coats Oltrite Landfdl $2 15.000 2.4s WASTE HOLES
~ - - - -
c o p - . . - $0 Ind. wilh bndf t #2 up
- .-- Trencher 1 WN 5 only; 6 thru 17 Lnd. with LF I 2 u p Excavale $23.000 SON excmvalkm a d 8nalysor;ind. air monlorhg and health and safety costs onsite o and^ urn $1 zs.000
4. LANDFILL l 2
cap I 2 . & r l - -b3~-
7. DOE DISPOSAL BOX
Excavale Hot Spols 50 cy _ - _ _ _ __ _ .. _ $4.000 Volume -- atkrvana -- .- Onsde Landf~U 50 cy MWD - - - - - . - - - - s3.7w --- $ 185,000
I $780,000 I I
I. LANDFILL ll
Cap :- - { -- - -- 2.61~1y . -. . - - - 6. LANDFILL I 3 -
cap -- -- 0.2 Ac $325,000
I. SEPTIC SYSTEMS 2 THRU 7 $30,000
OnrYe LandfW - $430 $172.000
0. SW DOO PEN SOILS - cap $325.000
--. $683,000
I GROUNDWATER . Ndlnduded h prehlnary erltnate
Extradbn W e l InslaYaUon(Cr) - ~ l h . 8Vg ea = Groundwater TreaWnf Syrtem - gpm ryrlemiCr(6) redudbnlppl and i)[
Dbcharge L h - -- - MonYwlng Wen lnrtaaalion Mdilional wsh - -- -
~845.000
$65.000
---
, --
Discharge Line I I I I I I
k x ~ n c ~ i o n Wen Inshllalion(CHCIJ) _ _. -- Groundwaler Trealmenl Sy~ lem ___ _--__ -- . -
Page 1
_ _ _ .__
_ _ _ .- . .
__. _- _ . - . _
- - . - - -. . . . -
-__ _ _ - . - . . . - - -
---
_ - - - - -
- - - - - - - - .- - - __ wells, avg depth ea = - - -- - - .
- gpm ryrlem. GAC -. - - . - - . - --
LEHR COST ESTIMATE(pre1iminary) Alternative 3 - Cap and Offsite Landfill
ARWCosl llem .. - - ..... . . . . . . . h i l o r i n g Well lnslalrllon . . .
VADOSE ZONE REMEDIATION
soil vapor ~ x ~ r a c l l o n l ~ t i ~ a s Trim1 . . . . . . . . .
CONSTRUCTION SUBTOTAL
Mobiliralionldemobialion Sle Preparalion and Uildy Hookups
Bonding and Insurance
Permitlirq and Legal
Sile Abninhlralion
Corredive A d h PlanrlDsslgns
S m h s During Conrlrudbn
-. SITE REMEDIATION SUBTOTAL -- Cmlingency
REMEDIATION C0NSTRUCTK)N -
ANNUAL O I M - Cap monitotlng. mainlenonce
Groundwater monitoring Groundwaler Trealmenl OhM
SVE syslem OhM
SHm MmWstralbn
Overale S e h r -
h n m l O & M SuMo(ll
C m q p n c y Annual O&M To(d
30-yr O&M Prmrrnt Worth
Total Praaant Worth
QUANTITY . . . . . .
1
1
--- ---
- 1
TOTAL . ---
1
1
- 1
--
----- ----- 1
--
UNITS ...
-
Is
l h -- ls
l b
l h
l b
l b
ls
-
Is
Is
Is
l b
l h
Is
--
-
TYPE -.
-.-.
-
--
-
--
----
--
UNIT COST
. . . .
$300.000 S 150.000
$750.000
_ _ _ _ COST TOTAL
. . . .
S4.200,000
$ 300,000
$150.000 . $750,000
COMMENTS _ _ _ _ _ _ _ _ - . .
Nd hdudsd In prehlnary eslirnale
. . - . . . . . . . . . . . . . . . . . . .
PreYminary allowance (1 .51 d a l e bndM M. 4) PrrYmInrry akwonce (1.5~ d l r Y m bndtil M. 4) - PreYmlnrry akmnc;. (1 .Sx ollr le hndM M. 4)
$375,000
$150,m
$750,000 $150.000
-
--- 30%
- S1O.OOO
$20,000
20% 10%
50%
15.372
$375,000
$150.000
$750,000
$150.000
W * e O o , ~ $2.000.000
-- $@,ooo,ooo
$lO,OOO
$20,000
$0
$6,000 $3,000
$39,000
SlB.500
$56.500
Prelimhity o h a n c s (1.5~ *Ym LrndRl M. 4)
Contradof offka 16nh; pfehlnrry 8Nowana (1.51 onrile landid AH. 4)
PreLlmh.ry abwmca (1 .Sz ohhe ludn Al. 4)
Pfehlnrry .kwrnce (1.Sx o(ldle bndtil M. 4)
-
-- M o w a m
Akwrncs No4 hd. In prehlrury eathale
No( h- - ' h p r e h h u y esllnak
-
.
$900,000
$10,ooo,ooo
At 5% dlscounl rrle
--
LEHR COST ESJ TE (preliminary) Alternative 4 -- ExcavatelDispose Offsite:
AREAICost Item - - - - . . . . - . . QUANTITY UNITS . . . - - - . . . - - _ . _ . _ _ _ _ . . - .
GENERAL COSTS - - . . prelim . allowance . . . . . . . prelim allowance - . - . - . - . . - . . - . . - . - . prelim allowance
- - - . - - . -. -. -- - - . - - . - - Prelim allowance
Sile Controls
Temporary Facilities
1. RADlUWSr LEACH FIELDS
Excavate
Trenches, lmhoff lank. Septk system I1 I Soil exuvation and 8natysos;M. alr monilodq and heaWh and safety costs
Transpod appro-ely 750 m k s and dhpow I~ranrpoct and Dispose
I 2.49 WASTE HOLES
Excavate SoU excavatbn and ~ 8 l y w s ; h d . ah rnoni(ohg and health and safety costs
$430 Transport r p p r o x h l d y 750 mibs and d w Transpod and Dispose
Transport and Dispose
$75 5188,000 Soil e x m a l b n ud an8iyms;hd. air monlorlng and heaWh and safety costs
$430 S 1,075.000 Transpon .pptoxlmalely 750 mibs and dlsposo
4. LANDFILL I 2 --- Excavate
Transport and Dispose 1- 5. LANDF ILL I1 --
Assumed exuvale 70%, s d l anatyses, alr rnonloring. H I S
Transpoll qprox. 250 ml. W H u Waste. 750 ml. H Mlxed Wasle
Asswned excavate 70%. SOH analyses. alr monitorha. H I S Excavate
Transpod and Dispose - 6. LANDFILL I 3 --- Excavate
Transpod and Dispose
7. DOE DISPOSAL BOX
Excavate
Transpod and Diipose
8. SEPTIC SYSTEMS 2 THRU 7
Excavate
Transport and Dispose
Transpod approx. 250 mi. # H u Wasle. 750 ml. U W e d Waste
Assumed excavale 30%. soil analyses, air rnonloring. H I S --
Transpon ~ o x . 250 ml. U Haz Waste. 750 ml. If Mlxed Waste
- - A - -- - 400 cy RWS -- --
4m/a- --
9. SW DOG PEN SOILS
Excavate
Transpod and Dispose .. -- $4 30
$158.000 ' ~ x u v a t e 6 hches over entire area; ravel n d hd. MI=- Not Included In prellmlnary eslirnate -- - -. -. . . - - web. avg dplh ea P -- - - - - - . - - gpm system;Cr@) reductionlppl and IX
GROUNDWATER - _ ._ _ _ _ - Exlndion WeU Inslallation(cr) . - __ . -- - - -
Groundwaler Treatment System - _ _ __ - - -
I ~ i s c h a c ~ e Line I I I 1 I I I
Page 1
LEHR COST ESTiMATE (preliminary) Alternative 4 - ExcavatelDispose Offslte: . .-..
ARWCosl llem . . .
Monilormg Wen Installation
Ertraclion - . Well Insta~ation(CHCI3) . . . ..
Grwndwalsr Treatment System . . - - . -. . . - . . . - - . - Oircharge - Line
LAonlwing Wen Instabtion --
VADOSE ZONE REMEDIATION -- Sod Vapor EdndbdOf fgas Ttiml
- - CONSTRUCTION SUBTOTAL .- Mob~zationldemoMLLslbn S Y ~ Preparath and UiWy Hodtups
Bonding and Insunncs .- -
Permilling and Legal .
Silo Mmlnistralbn - Cotredive A d b n PlsnrlDesLgnr - -. Services During Conrlruclbn
SITE REMEDIATION SUBTOTAL
ConUllgency
REMEDIATION CONSTRUCTION
ANNUAL OaM Groundwater rnonlwing
Gr&ler Trealmenl OIM
SVE system O I M She Mminhlratbn
OvenHe Services ---
Ann4 OaM StJb(dr1
C~UnOency _.
Annual OUM Total
3 0 - ~ r OUM Present Wodh.
-- Total Present Wodh
QUANTITY -
--
-----
- - .
---. - - - - -- -
1
t - ---
1 ---
----
TOTAL
t
-
_ - - __
-
UNITS . . . .
--
--.-
. - . - .-
l k
l b
l k - Is -- Is --
l h --- Is --
-. lh
-- .-.
Is -
---- ---- l b
l h
-- l h
1 ' s . - .
- -
TYPE
.
--
-
-
- -
- - -
- -
UNlTCO ---- --.- --- - . _ _ _ _ _ - _ _ M d h a l wsls - - - - . - . .
- web, avg &plh e r = . . . . .------.. . . - - - . . .
.. - . . . .. - -- - gpm system, GAC _ - .. - ..... .. . . . -
-
.
- $200.000 -- $100.000 SS00.000
TiiGGi-- $100,000
$500.000
$100,000
3W
$5.000
- 20%
1 o n
50%
15.372
- ---.
$22,000,000
$200,000 $100.000
$500,000
$250.000
$100.000
$500,000 $100,000
$23,MK),ooO $7,100,000
$31,000,000
$5,000
- SO
- s 1.000
$500
.- S6.500 $3.250
$9.750 - $1 60,000
$31,000,000
.
- -
Nd includ8d in preliminary estimate
preliminary a l b * n m - preliminary alowanor
prelimhrry a l o w a w
prehhary alowsnor
Contrador bld and home office odmh;preliinary rlbwanca -- -.
prelbnhuy alowsnco
imlimhary a k m m
Mowance -- - -- - - Nol Ind. h prelknhrry er thate - --
NoLind. h preUmhry erllmale --
, . -- -- ---
M 5% dircwnl rate --
--
LEHR COST ESTlh.. . (€(preliminary) Alternative 4 -- ExcavatelDispose Offsite:
AREAlCosl Item
GENERAL COSTS
Inwstgations 1
S~ le Preparation 1
Sde Conlrols . . . . . . 1
Temporary Facililks 1
1. RADlUWSr LEACH FIELDS
UNITS
Is
Is
Is
Is . -
Excavate --
Transpod and Dispose
2.49 WASTE HOLES
Excavate
ironspod and Dispose --- 3. SOLID WASTE TRENCHES
Excavate - Transport and Dispose
landfills as mixed waste l3
' I .- . '
. I-- .-. .
. . . . - - . . - . . Sl00.000 S 100.000 prelim allowance - ---
-- Trenches. lmhofi tank. Seplic syslem I 1
$75 $38,000 Soil excavation and analys8s;ind. air monitoring and heahh and safety costs $430 . f 21 5.000 Transport approximately 750 rnibs and dispose
- - - - - - - - . - - -- .- $30.000 Soil ercovatbn and a ~ ) y n s ; l n d . ak monitoring and heat~h and nlety costs
RWS - 1 $172.000 ilans,n approximately 750 miles and dispoae
- $188,000 Soil excavaUon and matyse8;lnd. ak moniloring and heanh and safely costs
RWS -- $430 S 1,075,000 Transpod approrlnately 750 mils8 and dispose
5. LANDFILL I 1
Excavate $75 $1,500,000 Assumed exuvale 70%. soil analyses, ak monilorhg. H6S
Transport and Dispose MWS - $2.000 $40.000,000 Transpod approx. 250 ml. If H u Waste. 750 mi. Y Mixed Waste
4. UNDFILL 8 2
Excavate
Transport and Dispose -
6. UNDFlLL 83 --
$450.000 Assumed excavate 30%. SOY analyses, ak monilorlng. H6S --
$12,000,000 Transporl ~ o x . 250 mi. If Haz Waste. 750 ml W Mixed Waste
Page 1
- 22aUIfl $I1 22000cy MWS $2.000 ----
$1,650.000
$44.000.000
Assumed excaval. 70%. SOU analyses. alr rnonitorlng, H6S - Transport approx. 250 mi. if Haz Waste, 750 mi. W W e d Waste
LEHR COST ~ ~ ~ ~ ~ ~ ~ ~ ( ~ r e l i r n i n a r ~ ) Alternative 4 -- ExcavatelDispose Offsite:
AREAlCost llern - . . - - - . . - QUANTITY UNI . . - -
Moniloring We# Inslallalion -. . .
Groundwaler Treatment Syslem . . . - - . -. Discharge Line ---- - Moni(wina WeU Inslaklion
VADOSE ZONE REMEDIATION
. Soil Vapor ExlraclbdOflq_ss Tdml
. --. CONSTRUCTION SUBTOTAL - - - - - - . - Mobiliz allonldemobilizaIion l k
Site Preparatkn and Uli l iy Hookups l b
Bond9 and Insurance l h
Perm i l l 4 and Legal 1 Is -- --- Sile MmWslralion 1 Is
Conediva Adion Pknr/Designs 1 Is -- %~ices During Conslrudkn 1 -- Is
I SITE REMEDIATION SUBTOTAL
Conlqency
Gromdwaler monkwing ---- -- Groundwrler Trealmenl O IM --- --
SVE s f l m 06M -- .- She M m h k l r a l h -- Ovrrsilr Services I h
Annual O l M SuMolr l --- 1 Is - - - - - - . - -
Annual O l M Tolal _ _ . .. - - -.. -
30-Yr ObM Prasrnl Worth 1 Is
_ _. . _ - . .
Tolal Pressnl Wort11
lendiills as mixed waste TYPE UNIT COST COST TOTAL COMMENTS - . - -- .. ..-- _ _ _ - . . - . . - . . - . - - ..
walls, avg deplh ea = . I-. - . .. . .... . . .
$1 00.000 ConIradoc lkld and home o K i rbnln;pfellntnary a b a n c s
$500,000 ~~~~~ h a -
$100,000 $100,000 p r e h h r y alowrncs
-- !a% .
$9.750 - - - - - - . - - - - - - - - - - - - . - - - - - - . - - - - - . . - - - - - - 15.372 $1 60,000 A1 5% diswunl rale - - - - - - - - -
Appendix A Revisions to Summary Notes
Document Changed
Figure 2: Revised Conceptual Model
Figure 2: Revised Conceptual Model
Table 1 : Revisions to the Conceptual Model
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Type of Change
Modification to upper and lower HSUs
Modification to upper and lower HSUs
Correction to a type of change
Modification to Radium and Strontium leach fields
Modification to Radium and Strontium leach fields
Change
Replace the average hydraulic conductivity numbers (located in the descriptions of the hydrostatigraphic units) with relative descriptions of conductivity
Note which contaminants have been detected in the upper and lower HSUs and their relative concentrations, but do not distinguish between those that have been detected over or under MCLs
Refer to surface water as a source, rather than a tertiary source.
Add no action as an alternative for Radium and Strontium leach fields: cobbles
Replace in-situ treatment or containment with containment as an alternative for Radium and Strontium leach fields: structures
Rationale
Uncertainty exists in the actual numbers and it is more important to convey the relative hydraulic conductivities of the two hydrostatigraphic units
The core group agreed to reflect facts that are unrypllable in the conceptual model.
I
Tertiary sources were not delineated as such in Figure 1.
No action is a likely general response action for this source
In-situ treatment is not a likely general response action for this source. However, containment remains a viable response action for the tanks and septic systems.
Document Changed
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Type of Change
Modification to Radium and Strontium leach fields
Modification to 49 waste holes and disposal trenches
Correction to disposal trenches
Modification to disposal trenches
Modification to Landfill unit #1
Change .
Delete no triatment (should have read no action) as an alternative for Radium and Strontium leach fields: Strucms
Add capping to the Selective/hot spot removal altcmative for the forty-nine waste holes and the disposal trenches
M w the expected conditions section of the disposal trenches to correct errors
Add a division to the Disposal Trenches to reflect the area where intrusion m y have resulted in surfkc contamination
Add to the expected conditions of Landfill unit #1 that a small quantity of mixed waste is possible and that chromium, which may have originated in the landfill, has been detected in the groundwater
- Rationale
No action is not a likely general response action for this source.
Hot spot removal, or selective removal is not a likely general response action without capping included as a part of the action
Sections of the southwestern and the solid waste trenches descriptions w m switched and thm wen mors in the expected contaminants
The area of the disposal trenches where intrusion may have resulted in surface contamination should be looked at separately as a diffkrcnt general response action may be appropriate
Additions clarify the expected conditions
Document Changed
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Type of Change
Correction to Landfillunit #2 and 49 waste holes
Modification to Landfill unit #3
Modification to Landfill units #2 and 3
Modification to DOE disposal box
Modification to septic SystUns numbered 2-7
M d c a t i o n to septic systems numbered 2-7
Change
Move the sentence begin.ing,"Records show ..." from the expected conditions of Landfill unit #2 to the expected conditions of the 49 waste holes
Add a division to Landfill unit #3 to reflect the arca where intrusion may have resulted in surface contamination
Change wording in the expected conditions of Landfill units #2 and 3 to read that mixed waste is uncertain
M w the expected conditions to read that the metal box is expected to contain radiological contaminauts
Divide the source into soils and structures
The likely general response actions for the soils should be: 1. No action 2. Removal and disposal 3. In situ treatment
Rationale
Description was in the wrong location
The area of Landfill unit #1 where intrusion may have resulted in surface contamination should be looked at sepamtely, as a different general response action may be appropriate
The Expected Conditions section should reflect that mixed waste is an uncertainty in landfill units #2 and 3 rather than an expected waste
More accurate
There arc different likely general response actions to be considmd for the soils and the structures of the septic systems
The likely general response actions are different for the soils than for the structures
1
Document Changed
Table 2: Site Problems and Likely Response Action at LEHR
Table 2: Site Problems and Likely Response Action at LEHR
Type of Change
Modification to septic systems numbered 2-7
Modify the soil underneath the S W dog pens
Change .
The likely general response actions for the soils should be: 1. No action 2. Removal and disposal 3. Grout in place
Include that the soil is k low the gravel
Rationale
The likely general response actions are different for the structures than for the soils
Clarification