pebs newsletter no. 7 - cordis · pebs newsletter no. 7 bgr federal institute for geosciences and...

2
PEBS Newsletter No. 7 BGR Federal Institute for Geosciences and Natural Resources Stilleweg 2, 30655 Hannover phone +49.511.643.2246 fax +49.511.643.3660 e-mail [email protected] This newsletter provides information about the final phases of specific laboratory work and outlines the final event of the project. Laboratory experiments at CIEMAT The PEBS project aims to gain an understanding of the behaviour of the EBS and to assess its long-term safety functions in a multi-disciplinary and integrated approach, with experimentalists and modelers from various disciplines working in an interactive and coordinated manner. The experimental work is carried out at different spatial and time scales, from long-term (several years), large-scale in situ tests to shorter-term, small-scale laboratory tests. Mock-up tests. The FEBEX mock-up test is an experiment at almost full scale, which has been running at the CIEMAT facilities (Madrid) under controlled boundary conditions since February 1997. Its main components are (Figure 1): a stainless steel confining structure that simulates the gallery, through which hydration takes place; the heater system, composed of two electric heaters that simulate the heat generation of the waste canisters; a hydration system that supplies granitic water to hydrate the bentonite mass at a constant controlled pressure of 0.5 MPa; a 63-cm thick engineered barrier composed of compacted FEBEX bentonite blocks surrounding the heaters; more than 500 sensors installed within and outside the buffer material to monitor the boundary conditions and the system behaviour (temperature, total pressure, pore pressure, water injection Figure 1: General layout of the mock-up test, including instrumented sections pressure, relative humidity and strains); and a monitoring and control system that records the data. At the same time, the Geochemical Advanced Mock-up Experiments (GAMEs, Figure 2) are being conducted, with the aim of investigating the changes that may occur in the buffer material as a result of thermo-hydraulic and geochemical processes in granite and clay host rock concepts. Concrete blocks are used in the mock-up as hydration surfaces, simulating the clay host rock concept, and corrosion is enhanced at the heater surface in both mock- ups. The chemistry of the hydration water matches that expected in each host rock. To simulate the prevailing long-term conditions, the degree of saturation of the bentonite is high (saturation was forced from the beginning of operation), and the temperatures low (below 40 °C). Laboratory tests. The performance of large-scale tests is complicated and time-consuming and boundary conditions in such tests are not always well controlled and known. Laboratory tests in thermo-hydraulic cells that simulate the conditions of the sealing material during operation are therefore a valuable alternative for identifying and quantifying processes. In these cells, the sealing material can be subjected simultaneously to heating and hydration. The cells are cylindrical and designed to be hermetic and non- deformable. The heat generated by the radioactive decay of the wastes in the containers is simulated by an electric heater and simulated groundwater is injected. EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm Pressurized water line EN0203B.CDR 6000mm 806 mm 1625 mm 750 mm ext. 340 mm 881 mm 1000 mm 1259 mm 48 Hydration system nozzles 186 Sensor nozzles Confining structure Bentonite blocks Heaters Instrumented sections Geotextile layer N 2 Pressure line Heaters power line Temperature (328), pressure (80), and relative humidity (40) sensors in the instrumentation seccions Temperature (20), injection pressure (2) and displacement (19) sensors in the confining structure 18 Temperature sensors in the heaters Water tanks weighting Room temperature A12 A11 A10 A9 A8 A7 A6 A5 A4 A3 A2 A1 AB B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12

Upload: others

Post on 13-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PEBS Newsletter No. 7 - CORDIS · PEBS Newsletter No. 7 BGR Federal Institute for Geosciences and Natural Resources Stilleweg 2, 30655 Hannover phone +49.511.643.2246 ... Mock-up

PEBS Newsletter No. 7

BGR Federal Institute for Geosciences and Natural ResourcesStilleweg 2, 30655 Hannover

phone +49.511.643.2246fax +49.511.643.3660

e-mail [email protected]

This newsletter provides information about the final phases of specific laboratory work and outlines the final event of the project.

Laboratory experiments at CIEMATThe PEBS project aims to gain an understanding of the behaviour of the EBS and to assess its long-term safety functions in a multi-disciplinary and integrated approach, with experimentalists and modelers from various disciplines working in an interactive and coordinated manner. The experimental work is carried out at different spatial and time scales, from long-term (several years), large-scale in situ tests to shorter-term, small-scale laboratory tests.

Mock-up tests.

The FEBEX mock-up test is an experiment at almost full scale, which has been running at the CIEMAT facilities (Madrid) under controlled boundary conditions since February 1997. Its main components are (Figure 1): a stainless steel confining structure that simulates the gallery, through which hydration takes place; the heater system, composed of two electric heaters that simulate the heat generation of the waste canisters; a hydration system that supplies granitic water to hydrate the bentonite mass at a constant controlled pressure of 0.5 MPa; a 63-cm thick engineered barrier composed of compacted FEBEX bentonite blocks surrounding the heaters; more than 500 sensors installed within and outside the buffer material to monitor the boundary conditions and the system behaviour (temperature, total pressure, pore pressure, water injection

Figure 1: General layout of the mock-up test, including instrumented sections

pressure, relative humidity and strains); and a monitoring and control system that records the data.

At the same time, the Geochemical Advanced Mock-up Experiments (GAMEs, Figure 2) are being conducted, with the aim of investigating the changes that may occur in the buffer material as a result of thermo-hydraulic and geochemical processes in granite and clay host rock concepts. Concrete blocks are used in the mock-up as hydration surfaces, simulating the clay host rock concept, and corrosion is enhanced at the heater surface in both mock-ups. The chemistry of the hydration water matches that expected in each host rock. To simulate the prevailing long-term conditions, the degree of saturation of the bentonite is high (saturation was forced from the beginning of operation), and the temperatures low (below 40 °C).

Laboratory tests.

The performance of large-scale tests is complicated and time-consuming and boundary conditions in such tests are not always well controlled and known. Laboratory tests in thermo-hydraulic cells that simulate the conditions of the sealing material during operation are therefore a valuable alternative for identifying and quantifying processes. In these cells, the sealing material can be subjected simultaneously to heating and hydration. The cells are cylindrical and designed to be hermetic and non-deformable. The heat generated by the radioactive decay of the wastes in the containers is simulated by an electric heater and simulated groundwater is injected.

 

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

A12 A11 A10 A9 A8 A7 A6 A5 A4 A3 A2 A1 AB B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

A12 A11 A10 A9 A8 A7 A6 A5 A4 A3 A2 A1 AB B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

A12 A11 A10 A9 A8 A7 A6 A5 A4 A3 A2 A1 AB B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

Pressurized water line

EN0203B.CDR

6000mm

806

mm

1625 mm 750 mm

ext. 340 mm

B12 B4B5B6B7B8B9B10B11 ABB1B2B3

881

mm

1000

mm

1259

mm

48 Hydration system nozzles

186 Sensor nozzles

Confining structure

Bentonite blocks HeatersInstrumented

sections Geotextile layer

N2 Pressure line

Heaters power line

Temperature (328), pressure (80), and relative humidity

(40) sensors in the instrumentation seccions

Temperature (20), injection pressure (2) and

displacement (19) sensors in the confining structure

18 Temperature sensors in the heaters

Water tanks weighting

Room temperature

A12 A11 A10 A9 A8 A7 A6 A5 A4 A3 A2 A1 AB B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12

Page 2: PEBS Newsletter No. 7 - CORDIS · PEBS Newsletter No. 7 BGR Federal Institute for Geosciences and Natural Resources Stilleweg 2, 30655 Hannover phone +49.511.643.2246 ... Mock-up

BGR Federal Institute for Geosciences and Natural ResourcesStilleweg 2, 30655 Hannover

phone +49.511.643.2246fax +49.511.643.3660

e-mail [email protected]

 Figure 2: GAME mock-up (barrier length 1 m, thickness 22-30 cm).

To simulate the whole thickness of the barrier in different reference concepts, Teflon cells with an internal diameter of 7 cm are used, whose modular configuration can be changed so as to have columns of 10 to 60 cm length. To avoid the deformation of the cells through bentonite swelling, their outside is covered with semi-cylindrical steel sections. The water intake can be measured online, as can the relative humidity and the temperature inside the sealing material. The most recent version of these cells includes: the insertion of a load cell at the top, to measure the pressure exerted by the material on saturation; the measurement of the heater power; and an extra external insulation around the cell body (necessary when working with materials of very low thermal conductivity, such as materials with low initial degrees of saturation). These new cells are being used to simulate the conditions of the HE-E in-situ experiment (Figure 3, left). The duration of the tests in this kind of cells ranges from 0.5 to more than 9 years.

Figure 3: Thermo-hydraulic cells

Smaller cells (Figure 3, right) were designed for the study of the corrosion processes at the canister/bentonite interface and the processes at the concrete/bentonite interface (see Newsletter No. 6).

The final event of the PEBS project “International Conference on the

Performance of Engineered Barriers”The PEBS project will end with an international conference, as a platform for technical and scientific discussions related to engineered barrier systems.

Conference objectives

The objectives of the conference are to discuss, document and disseminate the current state of research on the performance of engineered barriers in geological repositories for high-level nuclear waste. Sessions are rounded up with discussions, aiming at bringing together views from experimentalists, modelers, and safety assessors. The outcome of the PEBS project plays a central role, but it is put in context through presentation of the outcome and status also from other projects and activities.

Main Topics

The conference focuses on the evaluation of engineered barrier performance as the basis for long-term safety of geological repositories for the disposal of radioactive waste. Abstracts are invited on the following subjects: • New insights through laboratory and in-situ

experiments of engineered barriers • Recent developments in numerical modelling of

THM(-C) processes in engineered barriers • Improvements in long-term performance

prediction and potential impacts on safety assessment

Important deadlines

Authors October 6, 2013 Abstract submission October 31, 2013 Authors’ notification November 29, 2013 Extended abstracts

Attendees September 2, 2013 Registration opens November 8, 2013 Early bird registration (120 €) December 31, 2013 Late registration (150 €)

Contents of the next NewsletterThe following Newsletter will report on some major results of the project.

For more detailed information, see the PEBS web site:

http://www.pebs-eu.de