pb_visit_report_bangladesh_for power plant site report

24
Parsons Brinckerhoff Business Management System Systems Management Report Template SM-202-F03 Copyright Parsons Brinckerhoff Printed copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version. EHII - Bangladesh IPP for BPDB Visit report – June 2010 June 2010 Parsons Brinckerhoff (Middle East) Limited Legends Headquarters Building First Floor, Emirates Road PO Box 4512 Dubai UAE Telephone +971 4 360 0090 Facsimile +971 4 374 3939

Upload: mohiuddin-ahmed-ranju

Post on 27-Mar-2015

199 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PB_Visit_Report_Bangladesh_for power plant site report

Parsons Brinckerhoff Business Management SystemSystems Management

Report Template SM-202-F03

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

EHII - Bangladesh IPP for BPDBVisit report – June 2010

June 2010

Parsons Brinckerhoff (Middle East) Limited

Legends Headquarters BuildingFirst Floor, Emirates Road

PO Box 4512Dubai UAE

Telephone +971 4 360 0090Facsimile +971 4 374 3939

Page 2: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page iCopyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Visit Report – EHII Bangladesh IPP for BPDB (June 2010)

Revision

Reviewed ApprovedRev Date Details

Name Signature Name Signature

A 05/07/2010 Draft Rob Higgo

Prepared by:Parsons Brinckerhoff (Middle East) Limited

PO Box 4512Dubai, United Arab EmiratesTel: +971 4 360 0090Fax: +971 4 374 3939

Page 3: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page iiCopyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

ContentsPage Number

Executive summary ...............................................................................................................................1

1. Meeting Notes.................................................................................................................................21.1 EHII Led Delegation 21.2 Bangladesh Power Development Board 21.3 Bangladesh Oil, Gas and Mineral Corporation (Petrobangla); 61.4 Power Grid Company of Bangladesh (PGC); 71.5 Meghnaghat Independent Power Plant 8

2. Power Plant EPC ..........................................................................................................................112.1 Alstom 11

3. Conclusion ...................................................................................................................................123.1 Site for the proposed IPP 133.2 Primary Energy 133.3 EPC Contractor 133.4 Option 13

List of appendices

Appendix ASite Possibilities for the Proposed EHII IPP

Appendix BMeghnaghat IPP – select images

Appendix CVisit Business Cards

Page 4: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 1Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Executive summaryOverview

A delegation representing Energy Holdings International Inc. (EHII) visited Dhaka, Bangladesh betweenSunday 20 June 2010 and Wednesday 23 June 2010 inclusive.

The primary purpose of the visit was to commence working with Bangladesh Power Development Board(BPDB) and establish the team, who would involve itself in the development of the proposed IPP, tobe financed, specified, built and operated by EHII and its Partners.

Successful meetings were held with various stakeholders in Bangladesh, and progress was made incommencing with the proposed IPP project.

A potential site has been identified as the primary site of choice for the IPP; and the IPP adjacent to thissite was visited by Parsons Brinckerhoff to establish general background on their experiences inoperating an IPP in Bangladesh.

Key Stakeholders Visited

Key Stakeholders visited included:

Advisor to the Honourable Prime Minister of Bangladesh and to the Chairman of BPDB;

Bangladesh Power Development Board (BPDB);

Bangladesh Oil, Gas and Mineral Corporation (Petrobangla);

Power Grid Company of Bangladesh (PGC);

Independent Power Plant (IPP) Unit, BPDB;

Meghnaghat Power Limited.

Page 5: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 2Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

1. Meeting Notes

1.1 EHII Led DelegationThe following parties formed part of the EHII led delegation to Bangladesh:

1. Mr Fahad Abdullah BuNuhayan; Chairman of Advance Energy;2. Mr Jalal Al Ghani; Director and Chief Financial Officer of EHII;3. Mr Muhammad Fuad Abdul Rahman; Manager for Wasatah Capital;4. Mr Rob Higgo; Director for Power & Water, Parsons Brinckerhoff, Middle East.

1.2 Bangladesh Power Development BoardMeetings were held with BPDB on 21 and 22 June 2010.

1.2.1 Dr. Tawfiq-e-Elahi Chowdhury, Advisor to the Honourable Prime Minister ofBangladesh and to the Chairman of BPDB. {21st June 2010}

Courtesy meeting, and to obtain Dr Tawfiq’s support for follow-on meetings with BPDB andothers.

General discussion included Bangladesh plans for procuring LNG from Qatar; general gasshortages in Bangladesh and the perceived need for IPP to be duel-fuel capable as a resultof gas shortages currently being experienced.

Mr Higgo requested support in being able to visit one of the existing IPP’s in Bangladesh,and Dr Tawfiq referred him to visit Meghnaghat IPP, as this was located in close proximityto Dhaka.

Dr Tawfiq went on to secure a meeting with the Chairman of BPDB for 22 June 2010.

1.2.2 Chairman: Bangladesh Power Development Board (BPDB). {22nd June 2010}

Those present at the courtesy meeting, but not limited to, include: Engr. A.S.M. Alamgir Kabir; Chairman. Engr. Md. Mostafa Kamal; Member (Generation). Engr. Masum Al-Beruni; Chief Engineer (Planning & Design).

General discussion related to the IPP, with a focus on siteing of the IPP.Delegation was referred to discuss siteing with the Chief Engineer (Planning & Design).

Page 6: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 3Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Additional meetings were discussed, and Chairman assisted the delegation in securing thefollowing meetings, along with his staff present:

Petrobangla; Power Grid Company; Head of IPP unit, BPDB; IPP, being Meghnaghat site.

In general terms, the delegation was referred to discuss IPP related matters (PPA andrelated Agreements) with the IPP unit of BPDB;Transmission and Grid related matters to be discussed with PGC;Gas provision and fuel supply and planning to be discussed with Pertobangla.

1.2.3 Chief Engineer (Planning & Design); Engr. Masum Al-Beruni. {22nd June 2010}

Primarily discussed siteing of the potential IPP; based on access to fuel, transmission andwater resources.

Several sites identified, as can be seen in Appendix A: Site Possibilities for the ProposedEHII IPP, which have been superimposed onto the Grid Diagram for Bangladesh.

After some discussion with those present, two sites appeared most likely to be favoured,those being the site prepared adjacent to the existing Meghnaghat IPP, which is able ofdeveloping and accommodating four new IPP projects in the scale of 450 ME OCGT; and asite identified in Chittagong, due to its location close to the sea-port and therefore, liquid fuelto support duel-fuel firing configuration.

The preferred site however, when considering ready infrastructure, transmission gridstrength and water, leaves in reality, only the site at Meghnaghat.

It was also highlighted that a grid strengthening project has been approved, and EPCcontracts placed, for the construction of a 400kV power line to augment the grid systemcurrently at Meghnaghat site, being 230kV, but not sufficient for additional IPP capacity.

1.2.3.1 Identified Sites

1.2.3.1.1 Meghnaghat site, lat: 23.608782° and lon: 90.596882° with elevation: 0m.

1.2.3.1.2 Chittagong site, lat: 22.297686° and lon: 91.800888° with elevation: 0m.

1.2.3.1.3 Keranigany site, lat: 23.654583° and lon: 90.338867° with elevation: 0m.

1.2.3.1.4 Others; not considered further.

Page 7: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 4Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Meghnaghat siteHigh level statistics (un-proven) on this site:

Fuel (natural gas): Gas line exists; but beware potential gas shortage; Fuel (HFO): No; Transmission: Yes at 230kV; but needs augmentation;

o 400kV augmentation approved and EPC contracts placed Water: Yes, on river; Access: Yes, road and river; Site: Rehabilitated land, 10 years old and industrial suited; Suitability: Excellent.

Chittagong siteHigh level statistics (un-proven) on this site:

Fuel (natural gas): No; Fuel (HFO): No; Transmission: Yes at 132kV; but needs major augmentation; Unsure of how close

transmission network is from the proposed site; Water: Yes, on river; Access: Limited, river access; No road; Site: Virgin; greenfield; Suitability: Second Choice.

Keranigany site (Dhaka)High level statistics (un-proven) on this site:

Fuel (natural gas): No; Fuel (HFO): No; Transmission: No; Water: Yes, on river; Access: Limited, river access; No road; Site: Virgin; greenfield; Suitability: Poor.

1.2.4 Director: IPP Cell; Engr. Md. Shamsul Hassan Miah {22nd June 2010}

Following general introduction on the purpose of the EHII visit, the background related to theproposed IPP and mention of proposed sites, general discussion on requirements related tothe establishment of an IPP in Bangladesh ensued.

Page 8: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 5Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Mr Miah commenced the meeting by explaining the IPP bid process related to IPP’s inBangladesh; All IPP’s are required to follow a competitive bidding process, and currently,Meghnaghat Phase II1 is out to bid.

When quizzed on pricing, Mr Miah responded with an indicative tariff 0f 2,79c/kWh(levelised tariff) for the Meghnaghat IPP, based on gas firing, and a 22 year PPA term. Itwas further suggested that the gas price was approximately $2.4/Giga-Joule. (1 MCFapproximately 950 btu2)

The delegation then explained the nature of the EHII IPP, and requested feedback onpossible time lines in being able to finalise a Letter of Intent for the IPP. Mr Miah respondedthat Meghnaghat took between 90 and 120 days to finalise (signed PA) after a firm offer hadbeen placed on the table for consideration by the BPDB.

In terms of Grid capacity, Mr Miah confirmed that the Meghnaghat site requires gridstrengthening to evacuate power, and the current 400kV strengthening project is anticipatedto be completed within 2 years. (Keep in mind the current bidding programme forMeghnaghat 2, which could add a further 300 – 450MW to the grid at Meghnaghat).

With respect to the use by a developer of second hand or refurbished power plant andequipment, Mr Miah advised that this would not be permitted, due primarily to the PPAduration (22 years) and the requirement for plant to meet or exceed availability of 90%.

PPA durations are typically 15 years for OCGT power plant; and 22 years for OCGT powerplant.

When considering Primary Fuel, Mr Miah advised that currently, generation capacity wasbeing affected to the value of approximately 600 – 700MW, due to a shortage in gas supply.This is being addressed, however, Mr Miah was not prepared to speculate on gas availabilityrelated to IPP’s, and referred the delegation back to the BPDB proper for advice on fuel.

Mr Miah then proposed that the following process should be followed in seeking anagreement with the BPDB:

Conclude background work and investigation (feasibility study); Make a proposal to the BPDB, that is priced and contains an indicative tariff; Obtain government approval (BPDB); Issue a Letter of Intent (BPDB); Negotiate and sign a PPA.

1 During an internet search, PB resourced the following information: (The Power Development Board (BPDB)

floated the pre-qualification (PQ) document seeking qualified power developers to install a dual fuel 300 to 450 megawatt

power plant in Meghnaghat on 21 January 2010; it was further reported that the PQ for Meghnaghat 2 has some relaxed

criteria to encourage greater participation of bidders). The BPDB was seeking further clearance of two PQ documents

for Bibiyana-2, a 450 MW project, and Bhola 150 MW power projects.

2 To be verified by EHII

Page 9: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 6Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

When asked about the recent contracting of rental generation, Mr Miah advised thatapproximately 920MW of rental power is being contracted by the BPDB; the indicative tariffis 11c/kWh, being based on furnace oil; it was added that approximately 50% of rental unitsare burning gas as a primary fuel, and that 50% are burning furnace oil.

When discussing the PPA particulars, it was confirmed that Fuel is not considered pass-through, but that the PPA is based on heat rate. Capacity payment is based on 365 days ofthe year, and the variable tariff component applies to power actually generated. (There areliquidated damages for not meeting availability targets);

Procurement of fuel remains the responsibility of the IPP, who will be required to source,and procure all fuel required for the IPP.

Mr Miah ended by confirming that the government is concerned by the lack of fuel diversity,and that as a result, the BPDB are seeking to increase power generation using primary fuelssuch as coal, renewable energy and liquid fuels, such as furnace oil (HFO). In the case ofEHII’s proposed IPP, it was Mr Miah’s opinion that the IPP should be duel fuel capable.

When requested to comment on the flexibility of the PPA, and to what extent EHII couldpropose alterations to the existing PPA model; Mr Miah stated that there is limited scope forproposing changes to the PPA.

With regard to a visit to the Meghnaghat IPP, Mr Miah arranged with Engr. Retaul Karcium,Executive Engineer of the IPP Cell unit, to escort Mr Rob Higgo to the site on 23 June 2010.For future reference, Engr. Karcium can be contacted on mobile (015 524 05996).

1.3 Bangladesh Oil, Gas and Mineral Corporation (Petrobangla);

1.3.1 Director: Operations and Mines; Dr. Molla Md. Mobirul Hossain. {22nd June 2010}

Following general introduction on the purpose of the EHII visit, the background related to theproposed IPP and mention of proposed sites, general discussion on fuel continued. Thefollowing notes were recorded:

80% of Bangladesh Power is currently generated using natural gas reserves (own);this is perceived to be a major risk, and Bangladesh authorities are now looking forfuel diversification to redress this risk. (i.e Oil, Coal or other primary fuels)

Bangladesh is experience a general natural gas shortage, and this is beingtransferred to the power sector. Petrobangla are working on increasing gasproduction by expanding operations, and increased gas production is expected inthe next two to three years, starting 2012.

Bangladesh is considering augmenting its own gas reserves by importing LNG fromQatar, and degasifying it in Bangladesh for local consumption.

Page 10: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 7Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Recoverable gas reserves in Bangladesh total 12 TCF currently; but there are plansto expand exploration to expand on these reserves.

Bangladesh have large coal reserves, and it was proposed that this could be asource of fuel for future power generation.

It was confirmed that an IPP built in Chittagong would not be able to get natural gassupplied from the existing Bangladesh reserves at this time.

Gas is currently priced at between US$4.00 and US$4.25 per MCF. This is basedon the Japanese Crude Cocktail (JCC) index.

Dr. Hossain estimated that a 450MW IPP would require between 72 and 75 MCFper day dependent on overall efficiency.

In conclusion, it would appear that the Bangladesh Government, through Petrobangla, areworking to augment gas reserves in the country. Whether this gas will be routed to powergeneration or not, is beyond the scope of this report summary. Even with the gasaugmentation, it would seem as though Bangladesh wish to pursue fuel diversification,however, it is unlikely that they will be able to firstly afford the costs of HFO and other liquidfuel sources, considering the logistics that would be required in transporting, handling andstorage of the fuel. Environmental impacts would also add to the difficulty of importing suchlarge HFO and other fuel sources, unless produced locally.

1.4 Power Grid Company of Bangladesh (PGC);

1.4.1 Managing Director; Engr. MD. Ruhul Amin. {22nd June 2010}

Following general introduction on the purpose of the EHII visit, the background related to theproposed IPP and mention of proposed sites, general discussion on transmission integrationand grid strengthening ensued. The following notes were recorded:

Those present at the courtesy meeting in addition to Mr Amin, but not limited to, include: Engr. MD. Rafiqul Islam; Deputy General Manager (Design). Engr. Muhammad Elias; Deputy General Manager (Planning). Engr. Arun Kumar Saha; Manager System Planning. Engr. Pranab Kumar Roy; Manager (M.I.S.)

It was confirmed that the 400kV strengthening of the Meghnaghat site had commenced, andthat the EPC contract for the new transmission line had already been placed. In addition tothis strengthening, a new double circuit 400kV transmission line is being planned to linkMeghnaghat to Chittagong, where it is intended to construct a 1300MW Coal fired powerplant.

In terms of siteing, the delegation from PGC confirmed that from a transmission point ofview, that Meghnaghat is a preferred site for the construction of a new IPP. It is both closeto the Dhaka load centre, but will work well considering the grid strengthening underway.

Page 11: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 8Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

It was further confirmed that the project Developer would be required to construct theElectrical Special Facilities (High Voltage Switching Yard and Substation) and onceconstructed and commissioned, hand it over to PGC to own and operate into the future.

The standard and specifications that would be required to be followed in constructing theESF, would be those of the PGC; It was mentioned that the developer should attempt to asfar as possible, reduce the amount of common equipment related to the power plant /transmission network, so as to create clear boundaries or battery-limits.

1.5 Meghnaghat Independent Power Plant

1.5.1 Plant Manager; Engr. Riaz Uddin. {23rd June 2010}

Meghnaghat IPP is a 450MW IPP, originally built by AES (Allied Energy Systems) Corp, theUS-based producer; it was subsequently sold to British CDC Globeleq, and has since beenacquired by Pendekar Energy, when they purchased the shares held by Globeleq inGlobeleq Bangladesh Ltd. Pendekar Energy (Labuan) Ltd. operates power plants, of whichthree are in Bangladesh, one in Pakistan and two fuel oil plants in Sri Lanka. PendekarEnergy (Labuan) Ltd. was founded in 2005 and is based in Malaysia. Pendekar Energy(Labuan) Ltd. is a subsidiary of Tanjong Energy Holdings Sdn Bhd.

Mr Uddin welcomed Rob Higgo to the plant, and assured Mr Higgo that he was comfortablediscussing his experiences related to the IPP and relations with BPDB openly; Mr Uddin hadbeen part of the AES team when constructing the IPP, and had gone on to become thePlant manager for Meghnaghat IPP.

Summarising the main points discussed, the following is pertinent to consider wheninvesting in an IPP in Bangladesh:

Payment (by BPDB) is good; no issues, and payment periods of within 30 days arenormal;

Duel Fuel – would be problematic, both in terms of logistics and fuel procurementwithin Bangladesh;

Reflecting on the current magnitude of rental power agreements in Bangladesh, MrUddin felt that the cost of this power would result in the government being unable topay/honour its long term commitments; which could have a direct knock-on effectwrt. A new IPP and payment for power;

o Estimates are that the BPDB are paying between 7 and 14 Taka per kWh;whilst the retail price of electricity is 3 to 4 Taka per unit.

Transmission – currently the grid is not as stable as it should be; however, it is farbetter than when Meghnaghat was first commissioned; Frequency swings between

Page 12: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 9Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

40Hz and 51Hz are common, and power plant must be designed to operatewithin this poor electrical environment; In terms of Voltage levels, the gridvoltage on the 230kV network typically runs at between 190kV and 200kV, also ofconcern to the IPP operator.

o In terms of interaction with BPDB and PGN, Mr Uddin finds that the IPPreceives excellent support from the utility, who genuinely go out of their wayto assist the IPP in resolving issues.

Primary Energy (Natural Gas) is in short supply; during peak periods, the IPP doesnot receive sufficient gas to generate at full load. This has been the case for sometime, and is expected to improve in future;

Staffing is a problem; It is a problem finding engineering and operating staff with therequired skill set to work on an IPP within the local market, due to the broad natureof experience and competence required.

o Meghnaghat recruited young engineers, and have invested heavily in theirdevelopment at site; these engineers are now trained to deal with a broadrange of site related issues, being multi-skilled;

o The total power plant staff, including management is numbered 44; Theseare all Bangladeshi nationals;

In terms of IPP development, Meghnaghat has been the last IPP to be contractedand built in Bangladesh in 9 years; this is ascribed to the difficult environmentrelated to the investment, when considering gas supply, and general ability to cutthrough “red tape” and bureaucracy in making meaningful progress.

o Many IPP developers have visited Bangladesh; have signed MOU’s buthave failed to conclude an IPP / PPA agreement.

Permitting (day to day) – is an issue, but has improved; General permitting will needto be closely managed, and the IPP needs a Government Relations Officer orsimilar resource / agent to progress permits;

o Example used was that for any specialised repair to plant or equipmentoutside of Bangladesh, an export – import permit is required; a fast trackpermit will take 14 days, in which time the plant may be out of servicewaiting on the repair.

In terms of the actual Meghnaghat Power Plant, some of the salient points include:

Cooling Water for the power plant is taken from the adjacent river; No permittingissues have been experienced;

o Need to adhere to World bank standards as regards effluent and otherdischarge and plant/environmental parameters;

o Average water temperature – 26C; ranges from 20C in winter through32/33C in summer;

Page 13: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 10Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

o Maximum temperature rise is 2C in Bangladesh; outfall discharge is 1kmdown stream from the power plant; the discharge channel can be seen onthe Google Earth picture of Meghnaghat contained in Annexure B.

Plant Availability averages 92% plus;

o Two Siemens V94.2 OCGT’s;

o Air-cooled generators from Ansaldo Energia s.p.a. affixed to the OCGT’s;

o Steam turbine supplied by Fuji. (FUJI triple-pressure (HP, IP and LP),reheat, condensing, down exhaust type steam turbine with a two-polegenerator being totally enclosed and water-to-air-cooled);

o Korean manufactured and erected HRSG. (HHI (Hyundai Heavy Industries)triple-pressure, natural-circulation Heat Recovery Steam Generators usesupplementary firing).

Gas provided by the authority requires an on-site Compressor Booster Station,which is operated and maintained by the IPP as part of their equipment;

The power plant runs at base load; and all available power is purchased by BPDB;

Power frequency trip settings – IPP is set to disconnect from the grid at 51.5Hz;whilst the system setting is 52Hz;

The plant includes full on-line monitoring of steam condensate and other criticalwater systems; has a fully functional laboratory (chemist) on site dealing with routineplant samples; have small electrical and mechanical workshops, water treatmentplant etc. i.e. The IPP is a fully functional, stand alone power plant.

1.5.2 Operations Manager; Mr Sushanta Kumar Paul. {23rd June 2010}

Following the meeting with the Plant Manager, Mr Paul kindly escorted Rob Higgo on a tourand walk-about on the IPP.

The power plant was in excellent visual condition, and as good as any power plant of similarage in western countries visited by Rob Higgo. House keeping was good, plant cleanlinessgood and the overall impression was that the plant is well managed, operated andmaintained.

Page 14: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 11Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

1.5.3 Visuals of the power plant

Unfortunately, the taking of photographs is forbidden on site. No photographs were taken asa result, however, in the Annexure B to this report; several photographs from file have beenobtained to give a general pictorial overview of the IPP itself.

2. Power Plant EPC

2.1 AlstomFollowing the visit to Bangladesh, and considering development options for the power plant,PB contacted and established a meeting with Alstom, to discuss the IPP opportunity ingeneral.

Alstom representative:

Mr Dieter Buck Senior Business Sales Manager Email: [email protected]

Tel: +41 56 205 6106Mobile: +41 173 660 4281

The primary reason that PB have suggested that EHII consider direct discussions withAlstom, is that Alstom have the capacity to not only manufacture and supply the IPP andgeneration plant required to construct the power plant (including the Electrical SpecialFacilities), but are also in a position to do this on an EPC “turn-key” basis, providing EHIIwith a fully integrated solution for the IPP.

Alstom will be able to specify the power plant, whilst in addition, optimise the major plantsystems to optimise efficiency, particularly in the area of the OCGT, Steam Turbine andHeat Recovery Steam Generator.

Some aspects to keep in mind include:

Alstom do not manufacture power plant able to burn Heavy Fuel Oil or furnace oil;

o Alstom gas turbines can only fire on diesel fuel or gas;

Considering the state of the network (frequency, voltage and general stability) themost likely equipment to be specified for robustness would be Class E machines asopposed to Class F machines. These are smaller machines as opposed to a singlelarge machine (F Class); increasing operational flexibility for unforseen systeminduced problems.

Page 15: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 12Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

The most likely plant configuration for this project would be a 2-into-1 configuration,comprising two Gas Turbines each coupled to a Heat Recovery Steam Generator,whose combined steam would be routed to a single Steam Turbine; producingapproximately 500MW ISO.

Alstom can as part of their turn-key services, construct the Electrical SpecialFacilities; this being done by “Alstom Grid”, Alstom’s power network companyacquired on 7 June 2010 through the take-over of Areva T&D’s transmissionbusiness.

Alstom is able to following commissioning and going commercial, offer fullOperating and Maintenance (O&M) services on an on going basis to the IPP.

When discussing Bangladesh specifically, Mr Buck stated that he was familiar with thecountry, and had in fact, provided Westmont Power with a proposal some years ago, for acombined cycle gas fired IPP power plant. Mr Buck was also familiar with the MeghnaghatIPP, and the proposed site for the new IPP, immediately adjacent to Meghnaghat IPP.

Mr Buck estimated a development time line as follows:

From “Down-payment” or contract signing, 24 – 26 months for first power on theOpen Cycle Gas generators;

For completion of the Combined Cycle power plant, 42 months from contractsigning.

This is based on Alstom providing the power plant on a turn-key basis, andconsidering the country being Bangladesh.

It was agreed that Mr Buck would revert to his principals in Switzerland, and would advisePB and EHII on a high-level, budget priced proposal for consideration in relation to theproposed EHII IPP for Bangladesh.

3. ConclusionIn general, the prospect for developing an IPP in Bangladesh exists. This is largelydependent on their being adequate Primary Energy available for the power plant, and at thistime, the primary energy of choice being natural gas.

A second consideration is that the establishment of an IPP in Bangladesh will be subject toEHII’s ability to cut through government and in general, red tape and bureaucracyconcerned with the establishment of a contract, PPA and IPP in general.

Page 16: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Page 13Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

3.1 Site for the proposed IPPMeghnaghat is a suitable site, provided that the network expansion continues as has beenadvised by BPDB and PGN. During the short visit, other sites were superficially evaluated,but at this juncture, it is recommended to pursue Meghnaghat as the preferred IPP site forthis proposed project.

3.2 Primary EnergyIt is proposed that at this time, EHII concentrate their efforts on unlocking gas as the primaryenergy of choice for the IPP.

Duel fuel is a very viable, and feasible option, however, the logistics associated withprocuring, storage and in general, firing on liquid fuel detract from the IPP opportunity itself.Duel fuel as an option will need rigorous Due Diligence prior to such a decision being madein this regard.

3.3 EPC ContractorAt this stage of the opportunity, it is suggested that EHII work with Alstom on a negotiatedbasis, to derive the most optimised and viable turn-key option for a IPP power plant forBangladesh. Alstom are both competent, and believed commercially viable in this regard,and have the necessary pedigree to deliver.

3.4 OptionConsidering the amount of both gas and liquid fuel being burnt in less than efficient powerplants in Bangladesh (such as old OCGT power plants and/or rental equipment), it may beworth conducting a high level feasibility study related to the opportunity that could exist, byre-routing the allocation of this fuel to a new, and more efficient, reliable IPP whenconstructed in for example, three years time.

Aspects of the study would include existing fuel contracts, and PPA contracts if these exist;as the assumption may be that these power plants are government owned, andtherefore/possibly over staffed, under maintained, have poor levels of availability andperformance in general and inefficient thermally.

It may be an attractive option therefore for the BPDB to re-allocate gas to a new IPP as aresult.

Page 17: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Appendix A

Site Possibilities for the ProposedEHII IPP

Page 18: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Meghnaghatsite

Chittagongsite

Keraniganysite

FaruqueWestmontGroup site

AnotherSite notconsidered

Page 19: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Proposed Meghnaghat IPP site

Page 20: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Appendix B

Meghnaghat IPP – select images

Page 21: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Select Images of the Meghnaghat IPP, Dhaka, Bangladesh

Page 22: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Page 23: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF

Appendix C

Visit Business Cards

Page 24: PB_Visit_Report_Bangladesh_for power plant site report

Visit ReportEHII Bangladesh IPP for BPDB

June 2010

Copyright Parsons BrinckerhoffPrinted copy is uncontrolled and only valid at the time of printing. Always refer to the electronic copy as the latest version.

PARSONSBRINCKERHOFF