pavement basics
TRANSCRIPT
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
I. History of PCC Pavements:•Legislation•Equipment•Interstates•Design Procedures•JointingII. Basics of PCC Pavement•Pavement Types•Basic Components of Concrete Pavement•Design Methods
Pavement Basics - CIMT 210
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Topics covered in this Course*PAVEMENT HISTORY
http://www.pavement.com/Concrete_Pavement/About_Concrete/100_Years_of_Innovation/index.asp
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
First Legislation•1916 President Woodrow Wilson Directed Federal gov’t to cooperate 50/50 with the state (he signed the first “Federal-Aid Highway Act)
•1956 President Eisenhower “National System of Interstate and Defense Highways”(signed the “Federal-Aid Highway Act of 1956)
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Equipment•1946 James W. Johnson and Bert Myers conceptualized the slip form paver•1949 The Iowa Highway Dept. constructed the first slipformed roadway•1955 Quad City Construction developed an improved self-propelled, track mounted slipform paver•At that time on-site mixing was replaced with hauling
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Interstate•1956 Introduction of the interstate• 41 Billion Dollars•41,000 miles•Largest road construction in US history•AASHTO- American Association of State Highway and Transportation Officials was formed to conduct studies•1976 Congress funded the 3R programRestoration, Rehabilitation, and Resurfacing•1981 the fourth R of Reconstruction was added for Interstate projects
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Design Procedures•1920s were the beginning of the “Mechanistic-Empirical” Design Procedure(Related pavement thickness to traffic loading)• The Critical stress was found in slab corners
•Mechanistic –Based on computed pavement response
•Empirical – Calibrated to observe pavement performance
•A design thickness was limited to the stress of ½ the concrete’s Modulus of Rupture (MOR)
•Edges of the concrete were thickened
•1930s Westergaard’s equation was adopted
•1933 PCA (Portland Cement Association) procedure introduced fatigue
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Jointing Practices•Expansion joints were used to relieve compression stresses in heat
• From 1925 to 1945 Contraction joints and transverse expansion joints were employed
•Results of this combination was that expansion joints closed up causing contraction joints to open
•Skewed joints were employed in 1906 and 1918 not allowing wheels to cross joints at the same time
•Skewed Joint Roadway became a common practice for undoweled pavements
•Randomized joint spacing became the standard practice for major roadways due to resonating car vertical responses
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
• Expansion Joint (Not Good Practice with Good Design of Contraction Joint )
Jointing Practices
• Contraction Joint reinforced slab
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
(1) Transverse Contraction Joint - a sawed, formed, or tooled groove in a concrete slab that creates a weakened vertical plane. It regulates the location of the cracking caused by dimensional changes in the slab, and is by far the most common type of joint in concrete pavements. (2) Longitudinal Joint - a joint between two slabs which allows slab warping without appreciable separation or cracking of the slabs. (3) Construction Joint - a joint between slabs that results when concrete is placed at different times. This type of joint can be further broken down into transverse and longitudinal joints. (4) Expansion Joint - a joint placed at a specific location to allow the pavement to expand without damaging adjacent structures or the pavement itself.
Jointing Practices
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
•Missing Contraction Joints
Jointing Practices
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
• Contraction Joints
Jointing Practices
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
•Skewed Contraction Joints
Jointing Practices
Axle with Two Wheels
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
• Longitudinal and Transverse (Construction Joints )
Jointing Practices
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
II. Basics of PCC Pavement
•Pavement Types
•Basic Components of Concrete Pavement
•Design Methods
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Types
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Types
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Types
•Jointed Plain•Undoweled•Doweled
• Jointed Reinforced
•Continuously Reinforced
•Prestressed
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Types•Jointed Plain (JPCP)
•Undoweled•Doweled
Dowels
15-20 ft.
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Types• Jointed Reinforced (JRCP)
Mesh Dowel
25-30 ft.
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Types•Continuously Reinforced (CRCP)
1.5-6.0 ft.
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
II. Basics of PCC Pavement
•Pavement Types
•Basic Components of Concrete Pavement
•Design Methods
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Basic Components of Concrete Pavement
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Basic Components of Concrete Pavement
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Basic Components of Concrete Pavement
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
II. Basics of PCC Pavement
•Pavement Types
•Basic Components of Concrete Pavement
•Design Methods
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Design
•Empirical Design Procedures(The 1993 AASHTO Guide for Design of Pavement Structures. ) Based on observed performance AASHO Road Test
Mechanistic Design Procedure(The 2002 AASHTO Guide for Design of Pavement Structures) Employs the Finite Element Method Based on mathematically calculated pavement responses PCA Design Procedure (PCAPAV) New windows based StreetPave
MEPDG Procedure Mechanistic-Empirical Pavement Design Guide (uses both procedure mentioned above)
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Pavement Design
Empirical Design Equation and Procedures
25.0
75.0
75.0
10
46.8
7
10
101810
42.1863.215
132.1log32.022.4
1
10624.11
5.15.4log
06.01log35.7log
kE
DJ
DCSp
D
PSI
DSZW
c
dctoR
cS
Therefore, the slab depth (D) is required to determine the number of ESALs to design for before the pavement is ever designed. The iterative design process usually proceeds as follows:
1. Determine and gather rigid pavement design inputs (ZR, So, DPSI, pt, Ec, S'c, J, Cd and keff).2. Determine and gather rigid pavement ESAL equation inputs (Lx, L2x, G)3. Assume a slab depth (D).4. Determine the equivalency factor for each load type by solving the ESAL equation using the assumed
slab depth (D) for each load type.5. Estimate the traffic count for each load type for the entire design life of the pavement and multiply it by
the calculated ESAL to obtain the total number of ESALs expected over the design life of the pavement.6. Insert the assumed slab depth (D) into the design equation and calculate the total number of ESALs that
the pavement will support over its design life.7. Compare the ESAL values in #5 and #6. If they are reasonably close (say within 5 percent) use the
assumed slab depth (D). If they are not reasonably close, assume a different slab depth (D), go to step #4 and repeat the process.
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Design CriteriacS
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
Design CriteriacS
CONCRETE INDUSTRY MANAGEMENT TECHNOLOGY
READING ASSIGNMENT /REFERENCES
Training Workshop Modules_Rigid Pavement Types
Training Workshop Modules_Rigid Pavement Basics
Reading Material _NCPTC