PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 1 Executive Summary
BRIEF OF PROJECT REPORT
(INCLUDING MINING PLAN) 1.0 INTRODUCTION
The proposed PR for Pauni-II Expansion OC has been envisaged by expansion
of Pauni-II OC in adjacent Pauni-III geological block which is located west of
Pauni Extension Geological Block and forms the south-western most coal bearing
area of eastern limb of Wardha Valley Coalfield. The geological block is named
as “Area west of Pauni Extn. Block”. The Pauni-II OC mine was envisaged in
Pauni Extension geological block located in the south-western part of eastern
limb of Wardha Valley Coalfield. Pauni Extension Block is located west of Pauni
OC mine. The area falls in the Rajura tehsil of Chandrapur district of Maharashtra
State. The Chandrapur district township is located at the distance of about 25 km
from the block.
The entire geological block is virgin one and no mining activity is in progress. The
nearest working opencast mine i.e. Pauni O.C. is located east of Pauni Extn.
Block.
1.1 BRIEF HISTORY OF EARLIER REPORTS
The Project Report of Pauni-II OC mine was approved by WCL Board on
13.11.2003 in Total Hiring option for 0.60 Mty target capacity with capital
investment of Rs 28.1120 Crores.
The Project Report for Pauni-III OC mine was prepared in March, 2009 for a
target capacity of 1.25 Mty. The Project Report for Pauni-III OCP (updated
February 2010) was placed in the 224th meeting of the Board of Directors of
WCL held on 29.04.2010. After deliberations at length, the Board accorded first
stage approval, i.e., approval of the Mining Plan to facilitate application of forestry
and environment clearance for a capacity of 1.25 Mty at a capital investment of
Rs 360.7987 crores with Departmental Option. The Board directed for entering
into Coal Supply Agreement with prospective consumer on Cost Plus Basis to
yield 12% IRR at 85% target capacity and clearance from CIL.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 2 Executive Summary
Presently Pauni-II OC mine is an on-going project of WCL & land acquisition is
under process. For Pauni-III OC mine, Cost Plus agreement is not finalized till yet
and so the final approval of the PR is yet to be done.
1.1.1 Salient Features of last Approved Reports
The salient features of earlier approved PRs of Pauni-II OC (July,2003) in Total
hiring option & Pauni-III OC (February,2010) in Departmental option are tabulated
below:
Sl. No.
Particulars
Approved PR of Pauni-II OC (July,2003) (Total hiring
option)
Approved PR of Pauni-III OC (Feb., 2010)
(Departmental option)
A Mining Parameters 1 Mineable Reserves (Mt) 4.91 24.11 2 Grade/GCV of coal (kcal/kg) G9/4775 G9/4830
3 OB Volume (Mm3) 31.90 157.57 4 Average S/R 6.49 6.54 5 Mine Capacity (Mty) 0.60 1.25 6 Manpower 110 755 7 Overall OMS (t) 20.66 6.27 B Financial Parameters 1 Total Capital (Rs. In Crores) 28.1120 360.7987 2 Cost of Production (Rs./t)
a) @ 100% of target capacity (Rs./t) 632.72 1376.32
b) @ 85% of target capacity (Rs./t) 662.92 1564.85 3 Av. Selling Price (Notified) (Rs./t) 725.85 1074.50 4 Profit (Rs./t) a) @ 100% of target capacity (Rs./t) 93.13 (-) 301.82 b) @ 85% of target capacity (Rs./t) 62.93 (-) 490.35 5 Financial IRR @ 85% capacity (%) 20.60 NEGATIVE
6 Price to yield 12 % IRR @ 85% capacity (Rs./t)
691.39 1801.65
7 Difference between Avg. Selling Price (Notified) & price to yield 12 % IRR @ 85% capacity (Rs./t)
(+) 34.46 (-) 727.15
1.2 EXPLORATION STATUS
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 3 Executive Summary
Pauni-II OC Block
Total 14 nos. of boreholes have been drilled in quarriable area (upto 120 m depth
of Composite Seam) and adjacent area of Pauni-II OC Block in an area of about
0.54 km2. The total meterage is 1558 and the borehole density works out to 26.
Pauni-III OC Block
Total 43 nos. of boreholes have been drilled in quarriable area and adjacent area
of Pauni-III OC Block in an area of about 2.17 km2. The total meterage is 3724.20
and the borehole density works out to 20.
The borehole density for combined Pauni-II and Pauni-III OC block works out to
21 boreholes per square kilometer in quarriable area of 2.71 km2 (0.54 sq. km +
2.17 sq. km).
1.3 MINING ACTIVITY The PR of Pauni-II OC mine was approved by WCL Board on 13.11.2003 in Total
Hiring Option. It is an on-going project and land acquisition is under process. No
mining activity has been started in this mine. The PR of Pauni-III OC mine is
approved on Cost Plus basis in Departmental Option and final approval is yet to
be done. Thus, no mining activity has been started in both the projects.
1.4 SALIENT FEATURES OF PROJECT REPORT
It was desired by WCL that an Amalgamated PR of both Pauni-II and Pauni-III
OC mines with common infrastructure facilities should be planned for better
economics of the two projects. Accordingly, a Project Report for Amalgamated
Pauni-II & III OC mine was prepared by CMPDI in May, 2015. The target of this
Amalgamated mine was envisaged as 3.25 Mty (0.75 Mty of Pauni-II OC and
2.50 Mty of Pauni-III OC) & maximum possible proved reserves in both the blocks
were considered. Only Total hiring option was detailed in this Amalgamated PR
as project economics is not yielding requisite IRR for approval of PR at notified
price of coal in Departmental Option & Partial hiring Option.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 4 Executive Summary
The salient features of the Project Report for Amalgamated Pauni-II & Pauni-III
OC prepared in May, 2015 for Total Hiring Option are tabulated below:
Sl. No.
Particulars
PR for Amalgamated Pauni-II & III OC (May, 2015)
Pauni-II OC
Pauni-III OC Total
A Mining Parameters 1) Mineable Reserves (Mt) 5.18 25.45 30.63 2) Grade/GCV of coal (kcal/kg) G9/4775 G9/4830 (G-9)/4817 3) OB Volume (Mm3) 31.90 157.57 189.47 4) Average S/R 6.16 6.19 6.19 5) Mine Capacity (Mty) 0.75 2.50 3.25 6) Manpower 242 7) Overall OMS (t) 50.87 B Financial Parameters 1) Additional Capital (Rs. In Crores) 498.8690
2) Existing Capital (as on 31.3.2015) (Rs. In Crores)
15.3094
3) Cost of Production (Rs./t) a) @ 100% of target capacity (Rs./t) 915.40 b) @ 85% of target capacity (Rs./t) 981.14 Power Non power
4) Av. Selling Price (Notified) (Rs./t) 1190.50 1570.50 5) Profit (Rs./t) a) @ 100% of target capacity (Rs./t) 275.10 655.10 b) @ 85% of target capacity (Rs./t) 209.36 589.36 6) Financial IRR @ 85% capacity (%) 12.27% 27.77
7) Price to yield 12 % IRR @ 85% capacity (Rs./t)
1184.70 1184.70
8) Difference between Avg. Selling Price (Notified) & price to yield 12 % IRR @ 85% capacity (Rs./t)
(+) 5.80 (+) 385.80
The above PR was presented in Technical sub Committee of WCL Board at WCL
(HQ), Nagpur on 01.06.2015. The TSC after detailed deliberation directed to
revisit the capital provision of the PR with following observations:
i) The capital provision for residential buildings may be deleted except
provision for Hostel accommodation.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 5 Executive Summary
ii) The land provision made for Pauni-III OC may be finalized in consultation
with Ballarpur Area, WCL.
Based on the recommendations of TSC of WCL Board, the Project Report of
Amalgamated Pauni-II & Pauni-III OC mine was modified in June, 2015. and the
salient features of the PR are as follows :
Sl. No.
Particulars PR of Amalgamated Pauni-II & III OC
(June,2015) Pauni-II OC Pauni-III OC Total
A Mining Parameters 1) Mineable Reserves (Mt) 5.18 25.45 30.63 2) Grade/GCV of coal (kcal/kg) G9/4775 G9/4830 (G-9)/4817 3) OB Volume (Mm3) 31.90 157.57 189.47 4) Average S/R 6.16 6.19 6.19 5) Mine Capacity (Mty) 0.75 2.50 3.25 6) Manpower 242 7) Overall OMS (t) 50.87 B Financial Parameters 1) Total Capital 499.0042 2) Additional Capital (Rs. In Crores) 483.6948
3) Existing Capital (as on 31.3.2015) (Rs. In Crores)
15.3094
4) Cost of Production (Rs./t) a) @ 100% of target capacity (Rs./t) 910.73 b) @ 85% of target capacity (Rs./t) 975.53 Power Non power
5) Av. Selling Price (Notified) (Rs./t) 1190.50 1570.50 6) Profit (Rs./t) a) @ 100% of target capacity (Rs./t) 279.77 659.77 b) @ 85% of target capacity (Rs./t) 214.97 594.97 7) Financial IRR @ 85% capacity (%) 12.67 28.13
8) Price to yield 12 % IRR @ 85% capacity (Rs./t)
1182.05 1182.05
9) Difference between Avg. Selling Price (Notified) & price to yield 12 % IRR @ 85% capacity (Rs./t)
(+) 8.45 (+) 388.45
The proposal for grant of TOR for above Project report was presented in 55th
EAC meeting held on 11-13 May, 2016 at MOEF, New Delhi for getting
Environmental Clearance. The committee, after deliberations noted the following:
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 6 Executive Summary
(i) Earlier there was a proposal for Pauni-III OCP for which the ToR has been
obtained in 2011. However, since that proposal was not pursued, the EAC
noted the ToR for Pauni-III OCP had lapsed. In effect, therefore, the EAC
of the view that Pauni-III OCP did not actually exist as of now. Agreeing
with this, the project proponent clarified that the present proposal was
actually the expansion of Pauni-II by amalgamating the areas under the
erstwhile Pauni-III ToR.
(ii) The erstwhile Pauni-III OCP involved 12.07 ha of forest land for which they
had earlier also applied for FC, and accordingly shown it in the
documentation submitted to this EAC meeting. The project proponent
were advised to name their proposal and considering the same as an
expansion of Pauni-II without reference to erstwhile Pauni-III. This was
important because the entire documentation submitted by the project
proponent in the present meeting continuously referred to Pauni-II and
Pauni-III features which need to be amalgamated.
(iii) The proposal was accordingly deferred for want of the above clarification
from the project proponent and resubmission of fresh documentation.
While doing so, the project proponent was also advised to reduce land
degradation, and to consider sequential mining to reduce the land for
external OBD, excavation and void area. The project proponent was
requested to study MoC guideline on mine plan towards this.
Hence, considering above recommendations of EAC, the Amalgamated PR
for Pauni-II & Pauni-III OC mine is being renamed as Pauni-II Expansion OC
mine in this report in which no change has been made in mine economics
of approved PR (June,2015). Thus, this project report is expansion of Pauni-
II OC in adjacent Pauni-III geological block.
As recommended by EAC of MOEF, while preparing PR for Pauni-II Expansion
OC mine, backfilling of OB has been considered in Quarry-II (Pauni-III OC) as the
geo-mining parameters permit simultaneous backfilling of OB. However, in
Quarry-I (Pauni-II OC) backfilling of OB has not been proposed due to limited
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 7 Executive Summary
strike length and other geo-mining parameters. Quarry-I will be further extended
in dipside in future. After final extraction of extended Quarry-I, the void of Quarry-I
will be considered for backfilling of OB in future.
WCL is planning to enhance coal production to 60 Mty by 2019-20 which requires
opening of new projects as well as expansion of existing projects. Accordingly,
PR for Pauni-II Expansion OC mine has been prepared with simultaneous
working in both the quarries of the mine i.e. Quarry-I and Quarry-II to get the
enhanced production of 3.25 Mty. Therefore, sequential mining is not possible as
the proposed target production cannot be achieved by sequential mining.
1.5 JUSTIFICATION OF PROJECT REPORT FOR PAUNI-II EXPANSION OC MINE
Many of the existing opencast mines of Ballarpur Area (Pauni OCM, Gauri OCM)
are reaching near to its approved limits. The exhaustion of these mines would
create additional gap between Demand & Supply & therefore opening of new
projects like Pauni-II Expansion OC is very essential to bridge this gap of demand
& supply. Presently Pauni-II OC mine is an on-going project of WCL & land
acquisition is under process. However, due to increase in land cost by
Maharashtra Govt. & introduction of new R&R policy of CIL, it is not possible to
complete the land acquisition of this project within sanctioned capital of PR. The
PR of Pauni-III OC has been approved on Cost Plus basis and Cost Plus
agreement is yet to be done. As both quarries are adjacent, common
infrastructure can be shared by both the quarries thus optimizing the capital and
revenue cost. Thus, the proposed PR of Pauni-II Expansion OC mine by
expanding Pauni-II OC in the adjacent ‘West of Pauni Extension block’ can be
planned economically viable in notified price by sharing the common
infrastructure as well as by enhancing the target capacity of the projects.
Moreover, following new guidelines of project formulation have to be incorporated
in the PR.
1. Administrative cost per tonne to be considered as 10% of last audited
accounts of WCL which is Rs.16.85/t. This is as per decision of 310th
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 8 Executive Summary
CIL Board meeting held on 08.11.2014 subject to vetting by Institute of
Cost Accounts of India.
2. In pursuant to Central Credit Rules intimated by WCL, Service Tax is to be
excluded while calculating hiring rates for OB removal / coal extraction.
3. Mid-point of Basic to be considered for estimation of salaries and wages.
4. While estimating mineable reserves, 10% geological losses and 5%
mining losses have to be considered.
Thus to make both the projects economically viable in notified price of coal by
sharing common infrastructure, enhancing the target capacity and incorporating
various new guidelines, preparation of PR for Pauni-II Expansion OC mine is
essential.
The present proposal would work as replacement mine to depleting opencast
mines of Ballarpur Area and help in partially bridging the gap between demand &
supply of coal. The proposed PR would also help in gainful utilization of existing
men and machinery of existing OCMs after exhaustion of approved reserves of
mines like Pauni OCM, Gauri OCM etc.
1.6 CONSTRAINTS / RISK IN MINING
Major constrains / risks associated with the project are as follows:
a) Diversion of Lendi Nalla and Seasonal nala
Lendi nala is passing through coal bearing area of Quarry-II, which is proposed to
be diverted as per route shown in Quarry and Surface Layout Plan. The
proposed diverted length of Lendi nala is 1.50 km and proposed to meet in Sakhri
nala. The seasonal nala are proposed to divert and meet in Lendi nala. However,
no capital provision has been made for diversion of seasonal nala.
b) Diversion of Sakhri Nala
Sakhri Nala is passing through coal bearing area of Quarry-I and Quarry-II, which
is proposed to be diverted as per route shown in Quarry and Surface Layout
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 9 Executive Summary
Plan. The proposed diverted length of Sakhri nala is 2.00 km and proposed
to meet in Pauni nala.
c) Diversion of 66 kV power line, 11 kV power line & other rural feeders
66 kV HT line, 11 kV power line and other rural feeders passing over the quarry
area are proposed to be diverted. As per discussion with Ballarpur Area officials,
temporary diversion of 66 kV HT line has also been proposed. The temporary &
permanent diversion of 66 kV HT line has been proposed as per route shown in
Quarry & Surface layout Plan.
d) Diversion of Chincholi- Sakhri road
Chincholi- Sakhri road is passing through property of Quarry-I which is proposed
to be diverted. As per discussion with Ballarpur Area officials, temporary
diversion of Chincholi-Sakhri road has also been proposed. The temporary &
permanent diversion of Chincholi-Sakhri road has been proposed as per route
shown in Quarry & Surface layout Plan.
e) Land Acquisition
Land acquisition will be a major challenge. 21.61 ha land which is already
acquired for Pauni OC mine has to be transferred to proposed Pauni-II Expansion
OC by boundary readjustment. Acquisition of land (305.80 ha) for Quarry-I is in
advanced stage. For Quarry-II, 825.25 ha land is proposed for acquisition. Out of
825.25 ha land for Quarry-II, 12.07 ha forest land is to be acquired in Phase-II
and remaining land is to be acquired in Phase-I which is a critical activity.
2.0 MARKETABILITY & JUSTIFICATION
The mines of WCL are under constant pressure to meet the increasing
demand of non-coking coal for power plants and other bulk consumers from
Western as well as Southern part of country. The justification of this mine has
been studied in the light of estimated demand for coal from WCL and production
forecast from existing, completed, ongoing and future projects of WCL.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 10 Executive Summary
Following table shows the deficit in availability of coal, including middlings from
the various Existing, Completed, On-going, and Future Projects of WCL:
Sl.
No. Sector
Projections of Surplus / Deficit of Coal (Mt)
2015-16 2016-17 2017-18 2018-19 2019-20
1 Demand for coal 69.08 69.28 70.08 70.58 70.58
2 Availability of coal 45.000 48.00 50.00 55.00 60.00
3 Surplus / Deficit (+/-) (-) 24.08 (-) 21.28 (-) 20.08 (-) 15.18 (-) 10.58
The availability of coal shown above includes the coal production from proposed
Pauni – II Expansion OC mine. From the above table, it is clear that the deficit in
supply of coal from WCL as a whole will be (-) 24.08 Mt in 2015-16 which will
be narrowed down to (-) 10.58 Mt in 2019-20 provided WCL achieved the target
of 60.00 Mt production in 2019-20. New mines/ projects have to be opened or
expansion of existing operating mines has to be done by WCL in order to meet
the ever increasing demand of coal. There is a deficit in supply of coal from the
mines of WCL and therefore a ready market exists for the coal produced from
proposed Pauni - II Expansion OC mine.
Thus, there will be no problem in marketing of 3.25 Mty coal from Pauni-II
Expansion OC mine in view of large deficit in availability of coal from the mines of
WCL.
3.0 PROJECT SITE INFORMATION 3.1 LOCATION & COMMUNICATION
The proposed mine area falls in the Rajura tehsil of Chandrapur district of
Maharashtra State. The Chandrapur district township is located at the distance of
about 25 km from the block. The area of Pauni-II Expansion OC block is bounded
by latitudes N 190 48’ 19” and 190 49’ 27” and Longitude E 790 13’ 48” and 790
16’ 13”. The block is covered in the survey of India Toposheet No.- 55 M/5 .
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 11 Executive Summary
The approach to the area at present is via Sasti Colliery or Rajura, Mathra, Gauri,
Pauni and Sasti villages by a fair weathered road, which is passing from north of
the block boundary. The area is free from village population, since no village exist
within the area of the block. Waroda village is located in the north-west outside
the block boundary and connected with all-weather metal road with Rajura tehsil.
Delhi-Madras Grand Chord Railway line passes through Ballarpur township which
is located in the NE of the block at a distance of about 10 km. Ballarshah Railway
Station is located in the NE at about 10 km from the area.
3.2 TOPOGRAPHY & DRAINAGE
The altitude of the area ranges between 183.25 m and 200.29 m. A 66 kV High
Power Tension Line is passing through the southern part of the area. Few
seasonal nallas are passing through the block and joining easterly flowing Pauni
nala in the north, which ultimately joins Wardha river near Sasti village. The
general slope of the area is from west to east. The main drainage of the area is
controlled by the Wardha river which is flowing southerly and is located about 10
km east from the area.
Few seasonal nalas are passing through the block and their flow direction is from
west to east. Lendi nala is passing through the middle part of the Quarry-II and
Sakhri nala is passing through property of proposed Quarry-I. These nalas join
easterly flowing Pauni nala in the north which ultimately joins Wardha river near
Sasti village.
4.0 GEOLOGY AND DEPOSIT APPRAISAL 4.1 INTRODUCTION
4.1.1 Geological Reports prepared for the blocks under reference
The following Geological Reports have been prepared for the two blocks – 1. Geological Report on Quarriable Potentiality of Pauni Extension Block,
Wardha Valley Coalfield, Dist. Chandrapur, Maharashtra, March, 2002.
2. Geological Report of Area West of Pauni Extension Block (Pauni-III) Wardha
Valley Coalfield, Dist. Chandrapur, Maharashtra, November, 2006.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 12 Executive Summary
4.1.2 GEOLOGICAL BLOCK BOUNDARY
Pauni Extension Block (Pauni-II block) The Gelogical block boundary.of Pauni Extension Block are as follows : -
North - Fault F1-F1 (below Kamthi)
South - Fault F2-F2 (Floor of Bottom Section)
East - 170 m depth line
West - Subcrop of Composite Seam.
West of Pauni Extension Block
The area west of Pauni Extn. Block is 2.52 km2 and is located in the south-
western part of eastern limb of Wardha Valley Coalfield. The limits of area west of
Pauni Extn. Block are as follows :
1. North - Fault F2 (PE) – F2 (PE) (at the floor of Composite Top Section)
2. South - Fault F9 - F9 (at the floor of Composite Bottom Section & F10-
F10 (below Kamthi) and subcrop of Composite Seam
(below Kamthi)
3. East - Fault F2 (PE)- F2 (PE) (at the floor of Composite Top Section)
4. West - Subcrop of Composite Seam (below Kamthi) and faults F3–F3
& F10–F10 (Below Kamthi)
4.2 EXPLORATION STATUS
The exploration details of the proposed Pauni Extension Block (Pauni-II block)
and West of Pauni Extension Block are tabulated below :
Sl. No.
Block Name No. of Boreholes
Meterage Area of Block (km2)
Borehole Density
1. Pauni Extension Block (Pauni-II)
14 1558 0.54 26
2. West of Pauni Extension Block
43 3724.20 2.17 20
Overall 57 5282.20 2.71 21
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 13 Executive Summary
4.3 GEOLOGICAL STRUCTURE OF THE BLOCK 4.3.1 Strike & Dip Pauni – II block
The general strike of the coal seam as determined from the floor contour and roof
contour plans of Composite Seam is ENE-WSW dipping towards south. The dip
of the formation ranges 8o-9o (1 in 6 to 1 in 7).
West of Pauni Extension Block
The general strike of the coal seam as determined from the floor contour plans of
Composite Top and Bottom Sections is WSW – ESE with minor swing to NNW –
SSE in the north western part of the area. However, local minor swing in the
strike has also been observed in the area. The dip of the strata ranges from 6.50
to 140 (gradient 1 in 4 to 1 in 8.5) and dipping towards east. The northern and
southern part of the area generally having less gradient (1 in 8.5) as compare to
remaining part of the block.
4.3.2 Faults Pauni – II block
A total of 2 nos. normal faults (F1-F1 & F2-F2) have been interpreted in Pauni-II
Block. Fault F1-F1 demarcate the northern limit and fault F2-F2 demarcate the
southern limit of the block. The details of these faults are furnished in the
following Table.
Description of Faults (Pauni-II Mining Block)
Fault No.
Trend Throw Evidence Direction Amount
F1-F1 NW-SE SW About 70 m
Omission of Top Section in CMWG-59 and omission of Bottom Section in CMWG-114.
F2-F2 NW-SE to NNW-SSE
SW to SSW
About 100 m
Omission of Composite Seam in CMWG-104 & 116.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 14 Executive Summary
West of Pauni Extension Block The area of the block is traversed by 12 numbers of faults. All the faults are
oblique faults, cutting across the strike of the strata. The major fault F2 (PE) - F2
(PE) is continuing from the eastern adjoining block i.e. Pauni Extension Block and
its fault number has been retained as mentioned in the geological report prepared
by CMPDI. This major fault F2 (PE) – F2 (PE) also demarcates northern / eastern
the limit of the block.
The details of the individual faults are given in the following Table :
DESCRIPTION OF FAULTS (AREA WEST OF PAUNI EXTN. BLOCK)
Sl. No.
Fault No.
Extent of faults
(m) Trend
Throw Evidence Direction Amount
(m) 1. F1 –F1 750 m NW -
SE SW 0-20 Difference in floor reduced
level on both sides of the fault.
2. F2 (PE)–
F2
(PE) (Pauni Extn. Block)
3300 WNW-ESE
WSW About 80-150
Talchir and Vindhyan contact is faulted in CMWG – 173, Composite Top + Bottom Sections are omitted in CMWG – 124, 181 & 207 and Composite Top Section omitted and roof of Composite Bottom Section is faulted in CMWG -211.
3. F2 –F2
1300 WNW-
ESE NNE About
90 Composite Top Section omitted and roof of Composite Bottom section is faulted in CMWG–119 & Composite Top & Bottom Sections are omitted in CMWG - 106
4. F3 –F3 1000 NW –
SE
NE 0 – 40 Difference in floor reduced
level on both sides of the
fault.
5. F4 –F4 700 E - W N 0 - 15 Roof of Composite Top
Section is faulted in
CMWG – 107 and
Composite Bottom Section
is omitted in CMWG -154.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 15 Executive Summary
Sl. No.
Fault No.
Extent of faults
(m) Trend
Throw Evidence Direction Amount
(m)
6. F5 –F5 500 N - S E 25 – 60 Floor of Composite
Bottom Section is faulted
in CMWG – 170 &
difference in FRL on both
sides of the fault.
7. F6 –F6 350 NW -
SE
NE 70 - 80 Difference in floor reduced
level on both sides of the
fault
8. F7- F7 500 E - W S 0 - 15 Roof of Composite Top
Section is omitted in
CMWG – 164.
9. F8 –F8 350 NW -
SE
NE 50 Difference in floor reduced
level on both sides of the
fault.
10. F9 –F9 1100 E - W S About
40
Difference in floor reduced
level on both sides of the
fault and floor of
Composite Top Section is
faulted and Composite
Bottom Section is omitted
in CMWG – 101.
11. F10 –
F10
400 NW –
SE
NE About
60
Composite Bottom Section
is omitted in CMWG -165.
12. F11 –
F11
675 NNW
- SSE
WSW About
10
Roof of Composite Top
Section is faulted in
CMWG – 142.
4.4 DESCRIPTION OF COAL SEAMS
The details of coal seams in Pauni-Extension Block (Pauni-II Block) and West of
Pauni Extension Block are described below :
Pauni –II block
The major part of Wardha Valley Coalfield is characterized by presence of one
thick Composite Seam varying in thickness from 15 m to 20 m composed of
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 16 Executive Summary
mainly 2 to 3 correlatable sections separated by well defined partings. In Pauni-II
OC Mining Block, the Composite Seam having thickness ranging from 17.65 m
(CMWG-80) to 20.79 m (CMWG-118) including all dirt bands and parting occurs
in the middle part of the Barakar Formation. The study of seam structure of
Composite Seam reveals that prominent fine grained sandstone, alternate shale
and sandstone and carb. Shale, etc occurring within the seam divides it into two
sections i.e. Top and Bottom.
For proving the quarriable potentiality of Pauni-II Mining Block, both the sections
i.e. Top Section & Bottom Section of the Composite Seam have been considered
as single coal bed horizon after excluding the parting between both sections. The
details of seam description for the individual seam sections i.e. Top Section and
Bottom Section as well as for the Composite Seam in the proposed Pauni-II OC
mining area (upto 120m depth at the floor of bottom section) are as follows :-
SEAM DETAILS (PAUNI-II BLOCK)
Sl. No.
PARTICULARS TOP SECTION BOTTOM SECTION
COMPOSITE SEAM
1 Depth (Roof) i) Minimum 19.80 m
(CMWG-109) 27.92 m (CMWG-111)
19.80 m (CMWG-109)
ii) Maximum 83.91m (CMWG-118)
111.60m (CMWG-110)
83.91 m (CMWG-118)
2 Floor Reduced Level i) Minimum 180.55m
(CMWG-118) 170.70m (CMWG-118)
170.70m (CMWG-118)
ii) Maximum 255.99m (CMWG-109)
247.88m (CMWG-109)
247.88m (CMWG-109)
3 Full seam thickness i) Minimum 10.72 m
(CMWG-118) 2.55 m (CMWG-80)
13.50 (CMWG-80)
ii) Maximum 10.95 (CMWG-80)
4.30 (CMWG-118)
15.02 (CMWG-118)
4 Parting (with Top/ Bottom section) i) Minimum 2.23 m
(CMWG-111) 2.23 m (CMWG-111)
ii) Maximum 5.55m (CMWG-118)
5.55 m (CMWG-118)
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 17 Executive Summary
West of Pauni Extension Block
SEQUNCE OF COAL SEAMS, AREA WEST OF PAUNI EXTN.BLOCK
Coal seam/ Parting
Thickness range (m) Generalised thickness
range (m) Minimum Maximum Composite Top Section
5.56 (CMWG – 151)
13.99 (CMWG – 174))
8.00 - 12.00
Parting 1.33
(CMWG – 174) 5.13
(CMWG – 180)
Composite Bottom Section
2.05 (CMWG – 174)
6.00 (CMWG – 176)
2.00 - 6.00
4.4.1 QUALITY OF COAL
Quality of coal has been assessed for both the quarries separately as well as for
combined OC based on the borehole data available within the quarry area.
Pauni – II OC block The minimum and maximum range of analytical data for quality of coal for
composite seam is as given below:
Parameters Range Minimum Maximum Moisture % 8.0 (CMWG-118) 8.1 (CMWG-80) Ash % 26.5 (CMWG-80) 27.3 (CMWG-118) GCV (kCal/kg) (excluding Parting)
4470 4826
Average GCV (kcal/kg)
4755 kCal/kg (G-9)
West of Pauni Extension Block
The minimum and maximum range of analytical data for quality of coal for bottom
section & top section is as given below:
Parameters Range
Minimum Maximum
Bottom Section
Moisture % 6.3 (CMWG-187) 9.5 (CMWG-96)
Ash % 18.7 (CMWG-164) 34.7 (CMWG-128)
GCV (kCal/kg)
(excluding Parting)
4072 5339
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 18 Executive Summary
Parameters Range
Minimum Maximum
Top Section
Moisture % 5.7 (CMWG-155) 9.0 (CMWG-153)
Ash % 20.2 (CMWG-167) 40.0 (CMWG-155)
GCV (kCal/kg)
(excluding Parting)
3796 5073
GCV (Composite
Seam)
4830 kCal/kg (G-9)
OVERALL QUALITY
The overall quality of composite seam (top & bottom section combined) for Pauni
– II Expansion OC mine, on average basis, works out to 4817 kCal/kg ( G-9).
4.5 GEOLOGICAL RESERVES
Pauni-II block
Only one Composite workable seam in two sections designated as Top and
Bottom section occurs in the area under report. A total of 13.56 Mt of proved
quarriable reserves of Composite Seam have been established in Pauni
Extension Geological Block.
Out of 13.56 Mt Proved Geological Reserves in Pauni Extension Geological
Block, geological reserves upto 120m depth is 6.06 Mt and rest 7.50 Mt lies
beyond 120m depth.
West of Pauni Extension Block The sectorwise, depthwise and gradewise quarriable net proved reserves for
area west of Pauni Extension block are given in following table:
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 19 Executive Summary
SECTORWISE, DEPTHWISE AND GRADEWISE QUARRIABLE NET PROVED RESERVES, AREA WEST OF PAUNI EXTN. BLOCK
Grade Depth (m) Total
reserves (Mt.) Upto 50 50-100 100 - 150 150 - 200 > 200
SECTOR - A
i) Subcrop Zone 1.257 0.131 -- -- -- 1.388
ii) Full Thickness 0.050 14.037 8.769 2.550 0.093 25.499
TOTAL SECTOR – A 1.307 14.168 8.769 2.550 0.093 26.887
SECTOR – B i) Subcrop Zone
0.494 -- -- -- -- 0.494
ii) Full Thickness 0.270 0.517 -- -- -- 0.787
TOTAL SECTOR– B 0.764 0.517 -- -- -- 1.281
SECTOR – C
i) Subcrop Zone 0.095 -- -- -- -- 0.095
ii) Full Thickness 0.186 0.838 -- -- -- 1.024
TOTAL SECTOR – C 0.281 0.838 -- -- -- 1.119
SECTOR – D i) No Subcrop Zone
ii) Full Thickness -- -- 3.045 8.921 2.398 14.364
TOTAL SECTOR – D -- -- 3.045 8.921 2.398 14.364
SECTOR-E NIL
TOTAL SECTOR A+B+C+D+E
A. SUBCROP ZONE
1.846
0.131
--
--
--
1.977
B. FULL SEAM THICKNESS
0.506 15.392 11.814 11.471 2.491 41.674
G. TOTAL 2.352 15.523 11.814 11.471 2.491 43.651
West of Pauni Extension mining block has been projected in Sec - A, Sec - B
and Sec - C. Geological reserves estimated in this mining block is 29.287 Mt.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 20 Executive Summary
5.0 MINE BOUNDARY, MINEABLE RESERVES, TARGET & LIFE
5.1 MINE BOUNDARY DELINEATION
The proposed Pauni-II Expansion OC mine has been envisaged as expansion of
Pauni-II OC (Quarry-I) in Quarry-II. The mine boundaries of both quarries are as
follows:
Quarry-I
The proposed Quarry-I has been planned in Pauni Extension Geological block
which is bounded in north by fault F1-F1 (70m throw) and in south by another
fault F2-F2 (100m throw). Thus these two faults form the natural mine boundary
at the floor of coal seam of proposed Quarry-I in northern and southern side.
The top and bottom sections of composite seam subcrop in western side. The
subcrop of top section forms the mine boundary (in coal) in the western side
where bottom section also exists. The subcrop of bottom section has been
excluded because of high cut off ratio due to non-existence of top section at that
place.
In the eastern dip side, coal reserves have been proved upto a depth of 170m of
the floor of composite seam. However, in this report the dip side limit of quarry
has been fixed up to a depth of 120m at the floor of composite seam.
Thus the quarry boundaries (in coal) of the proposed Quarry-I OC are as follows:
Particulars North East South West
Proposed
Mine
Boundary
Fault F1-F1. 120m depth line at
the floor of bottom
section of composite
seam
Fault
F2-F2
Subcrop of
top section
of
composite
seam
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 21 Executive Summary
Quarry-II
The Pauni-III geological block is bounded by faults in three directions & sub-crop
of seam in fourth direction. The block is divided in to five sectors i.e. ‘A’, ‘B’, ‘C’,
‘D’ & ‘E’ as detailed in para 4.6. The proposed mine is envisaged to mine coal in
sectors ‘A’,’B’ & ‘C’ only, considering the geo-mining parameters, stripping ratio,
etc. Exploration is being carried out near sector ‘D’ and no geological reserves
have been projected in sector ‘E’ as it is having negligible width bounded with two
major faults.
The mining reserves in sector ‘A’, ‘B’ & ‘C’ have been considered upto dip side
major fault F2-F2 (max. depth about 200m). Faults namely F5-F5, F6-F6 & F8-F8
which exist towards east side of the property, make the eastern boundary of the
proposed mine. Reserves east of these faults (in Sector D) have not been
considered in this report as the extension of eastern side is still under geological
investigation. Subcrop of the bottom section of seam makes the southern &
western boundary of proposed mine.
The Mine boundaries of proposed Quarry-II OC are tabulated below :
5.2 MINEABLE RESERVES
Quarry-I The total in-situ geological reserves in entire Pauni Extension Geological Block
is 13.56 Mt, out of which 6.06 Mt is available upto 120m depth at floor of bottom
section. The net mineable reserves available in the proposed Quarry-I OC mine
is 5.18 Mt. While estimating the net mineable reserves, 10% geological losses
(0.61 Mt) and 5% mining losses (0.27 Mt) have been excluded from the proved
geological reserves.
Particulars North East South West
Proposed
mine
Boundary
Fault F2-
F2
Fault F5-
F5, F6-F6 &
F8-F8
Sub crop of
bottom section
Sub crop of bottom
section & Fault F1-F1
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 22 Executive Summary
Name Of
Seam
Floor Area
Considered
In Ha.
Thickness
Variation
'M'
Geological
Reserves
(Mt)
Geological
Losses
(Mt)
Mining
Losses
(Mt)
Mineable
Reserves
(Mt)
1 2 3 4 5 6 7
BOTTOM
SECTION
26.60 2.55m –
4.30m
6.06
0.61
0.27
5.18
TOP
SECTION
26.60 10.72m –
10.95m
Quarry-II
The total in-situ geological reserves in quarriable area of West of Pauni Extension
Geological Block is 29.76 Mt. The net mineable reserves available in the
proposed Quarry-II OC is 25.45 Mt. While estimating the net mineable reserves,
10% geological losses (2.98 Mt) and 5% mining losses (1.33 Mt) have been
considered.
Name Of
Seam
Floor Area
considered in
Ha.
Thickness
Variation
'M'
Geological
Reserves
(Mt)
Geological
Losses
(Mt)
Mining
Losses
(Mt)
Mineable
Reserv.
(Mt)
1 2 3 4 5 6 7
Bottom
Section
148.50 2.05 To
6.00
9.16 0.92 0.41 7.83
Top
Section
141.50 5.56 To
13.99
20.60 2.06 0.92
17.62
Total 29.76 2.98 1.33 25.45
Thus, the net mineable reserves assessed in Pauni-II Expansion OC Mine are
30.63 Mt (5.18 Mt in Quarry-I OC and 25.45 Mt in Quarry-II OC mine).
5.3 TARGET PRODUCTION & MINE LIFE
The proposed report has been prepared for a target capacity of 3.25 Mt/annum
from Quarry-I OC (0.75 Mty) and Quarry-II OC (2.50 Mty). The parameters of
opencast mine field and technical conditions of its development make this target
feasible with normal indices namely length, width & depth of the excavated block,
thickness of coal seam, seam gradient, method of mining etc.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 23 Executive Summary
The life of Pauni – II Expansion OC mine works out to 14 years considering
annual target production of 3.25 Mty and mineable reserves of 30.63 Mt.
The break-up of mine life is as under:
Period Quarry-I Quarry-II Pauni – II Expansion
OC mine Pre construction period 1 Year 2 Years 1 Year Construction/Production
Build-up period 2 Years 3 Years 4 Years
Target capacity period 5 Years 9 Years 3 Years Tapering capacity
period 1 Year - 6 Years
Total life 9 Years 14 Years 14 Years
6.0 METHOD OF MINING
6.1 MINE PARAMETERS The different Mine parameters of proposed Quarry-I and Quarry-II are as follows:
Sl. No. Particulars Quarry-I Quarry-II Total
1. Area of the Quarry a) On floor (ha) 26.60 148.50 175.10 b) On surface (ha) 63.45 231.90 295.35 2. Depth (m) [upto floor of
bottom section]
a) Initial 28-30m 27 27 b) Final 120m 200 200 3. Gradient of Seam 1 in 6 to 1 in 7 1 in 6 1 in 6 to
1 in 7 4. Average thickness of
seams
a) Top Section 10.72m – 10.95m 10 b) Bottom Section 2.55m – 4.30m 4 5. Strike length (m) on floor of
composite seam 400 2500
6. Strike length (m) on surface
600 950
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 24 Executive Summary
6.2 SELECTION OF MINING METHOD
The target of proposed quarry has been envisaged as 3.25 Mty. Production is
proposed from multi sections (two sections) of composite seam. Property of
Quarry-I is having limited strike length, steep gradient (1 in 6 to 1 in 7) and
property of Quarry-II has several faults hence, deployment of Surface miner is
ruled out in the proposed PR. Deployment of dragline has not been proposed
considering the geo-mining conditions and lesser mine life (13 years revenue
life). Underground mining has been ruled out considering conservation of coal in
thick seam and better economics in an opencast compared to underground
mining.
Presently shovel-Dumper combination is being practiced very successfully in
existing mines of WCL. Hence, in proposed Pauni-II Expansion OC mine also
shovel-dumper combination has been proposed.
6.3 EQUIPMENT SELECTION
The proposed Pauni-II Expansion OC mine has been planned for Total Hiring
option and the entire coal and OB will be extracted by hiring / out-sourcing
agency.
Sl. No. Particulars Quarry-I Quarry-II Total
7. Width on surface (m) [dip rise]
1050 750
8. Width on floor (m) [dip rise] 825 750
9. GCV (kCal/kg) and Band of GCV
4755 ( G-9)
4830 (G-9)
4817 (G-9)
10. Mineable Reserves (Mt) (considering 5% mining losses)
5.18 25.45 30.63
11. Total OB (Mm3) including access trench
31.90 157.57 189.47
12. Average stripping ratio (m3/t)
6.16 6.19 6.19
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 25 Executive Summary
Some Common departmental equipment have been proposed in the mine which
are as follows :
Sl. No. HEMM (For Common) Nos. 1. Fire Fighting Truck 1 2. 8-12 t crane 2 3. 2.8 m3 Backhoe 2 4. 3.1-4.6 m3 Front End Loader 1 5. Water Sprinkler 2
6.4 MINING SYSTEM & SYSTEM PARAMETERS 6.4.1 Width & height of benches
The height of benches in OB has been considered as 10m while height of
benches in coal has been considered as per thickness of seam. However,
maximum height of bench in coal seam has been considered as 5 m. The width
of working and non-working benches for top overburden removal have been
considered as 30m and 20m respectively. The height of benches for parting
removal has been considered as per thickness of parting. The width of coal and
parting bench has been considered as 20m. The height and width of uppermost
two benches in OB has been considered as 5m.
6.4.2 Slope of benches & quarry
i) During mining operation The slope of topmost two OB benches in quarry has been considered as 450. The
slope of Individual OB and coal benches has been considered as 700. The rise
side quarry slope has been considered as 370 and dipside working slope of
quarry has been considered about 220 during mining operation.
ii) At the end of quarry
At the end of quarry, the slope of topmost two OB benches has been considered
as 450 whereas the slope of individual OB benches in hard strata and coal
benches has been considered as 700. Quarry slope has been considered as 370
in rise side & dip side of quarry.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 26 Executive Summary
It is proposed in this Project Report to carry out scientific study for slope and
design of benches in quarry. Based on above scientific study, bench and quarry
profile may change.
7.0 MINING AND DUMPING STRATEGY 7.1 CONSTRAINTS ON MINE DEVELOPMENT
Major constrains / risks associated with the project are as follows:
a) Diversion of Lendi Nalla and Seasonal nala
Lendi nala is passing through coal bearing area of Quarry-I, which is proposed to
be diverted as per route shown in Quarry and Surface Layout Plan. The proposed
diverted length of lendi nala is 1.50 km and proposed to meet in Sakhri nala. The
seasonal nala are proposed to divert and meet in Lendi nala. However, no capital
provision has been made for diversion of seasonal nala.
b) Diversion of Sakhri Nala
Sakhri Nala is passing through coal bearing area of Quarry-I and Quarry-II, which
is proposed to be diverted as per route shown in Quarry and Surface Layout
Plan. The proposed diverted length of Sakhri nala is 2.00 km and proposed to
meet in Pauni nala.
c) Diversion of 66 kV power line, 11 kV power line & other rural feeders 66 kV HT line, 11 kV power line and other rural feeders passing over the quarry
area are proposed to be diverted. As per discussion with Ballarpur Area officials,
temporary diversion of 66 kV HT line has also been proposed. The temporary &
permanent diversion of 66 kV HT line has been proposed as per route shown in
Quarry & Surface layout Plan.
d) Diversion of Chincholi- Sakhri road Chincholi- Sakhri road is passing through property of Quarry-I which is proposed
to be diverted. As per discussion with Ballarpur Area officials, temporary
diversion of Chincholi-Sakhri road has also been proposed. The temporary &
permanent diversion of Chincholi-Sakhri road has been proposed as per route
shown in Quarry & Surface layout Plan.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 27 Executive Summary
e) Land Acquisition Land acquisition will be a major challenge. 21.61 ha land which is already
acquired for existing Pauni OC mine has to be transferred to proposed Pauni-II
Expansion OC mine by boundary readjustment. Acquisition of land (305.80 ha)
for Quarry-I is in advanced stage. For Quarry-II, 825.25 ha land is proposed for
acquisition. Out of 825.25 ha land for Quarry-II, 12.07 ha forest land is to be
acquired in Phase-II and remaining land is to be acquired in Phase-I which is a
critical activity.
7.2 MINING STRATEGY
7.2.1 Quarry & Access Trench
The proposed Pauni-II Expansion OC mine has two quarries namely Quarry-I &
Quarry-II.
In Quarry-I, the Access Trench is proposed to touch the composite coal seam
near the sub-crop of Bottom section near fault F2-F2 (where top section also
exists). Slight variation in the position of fault F2-F2 cannot be ruled out and it is
therefore proposed in this report to make confirmatory boreholes prior to making
the Access Trench to confirm the sub-crop of composite seam near the touching
point of Access Trench as well as to confirm the position of fault F2-F2.
Similarly, in Quarry-II, Access trench would be driven at a gradient of 1 in 16 to
touch at subcrop of bottom section of seam (where thickness is 2.0m) in sector
‘A’. The Access Trench would be driven through the rise side batter to optimize
the OB excavation. Another Access trench is proposed to be driven for Sector ‘B’
& ‘C’. Part of this access trench would be common for both the sectors.
7.2.2 Cut-wise Coal, OB & Stripping Ratio
Both the quarries of Pauni-II Expansion OC have been divided into various Cuts.
There are six Cuts in Quarry-I and ten Cuts in Quarry-II. The different Cuts and
their extent along the floor of bottom section are tabulated below :
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 28 Executive Summary
Cut wise quantities for both the quarries are summarized below.
CUT-WISE COAL, OB & STRIPPING RATIO
Quarry-I
Cut No. COAL (Mt) OB (Mm3) S/R (m3/t)
Box Cut 0.40 1.98 4.94 Cut-I 0.35 0.99 2.84 Cut-II 0.71 3.50 4.95 Cut-III 1.00 7.66 7.64 Cut-IV 1.14 10.59 9.29 Cut-V 1.58 7.18 4.53 Total 5.18 31.90 6.16
Quarry-II
Cut No.
COAL (Mt) OB (Mm3) S/R (m3/t)
Bottom Section
Top Section
Total Coal Parting
Top OB Total OB
Box Cut 0.07 0.35 0.42 0.19 3.81 4.00 9.52
Cut-I 0.22 0.75 0.97 0.30 7.93 8.23 8.48
Cut-II 2.05 3.76 5.81 1.29 35.48 36.77 6.33
Cut-III 1.26 3.27 4.53 1.07 21.42 22.49 4.96
Cut-IV 1.29 2.46 3.75 0.85 19.81 20.66 5.51
Cut-V 0.75 1.85 2.60 0.56 21.62 22.18 8.53
Cut-VI 0.56 2.06 2.62 0.44 20.18 20.62 7.87
Cut-VII 0.67 1.52 2.19 0.56 14.17 14.73 6.73
Cut-VIII 0.53 1.01 1.54 0.41 6.23 6.64 4.31
Cut-IX 0.43 0.59 1.02 0.26 0.99 1.25 1.22
Total 7.83 17.62 25.45 5.93 151.64 157.57 6.19
Quarry Cut No.
Description Quarry Cut No.
Description
Quarry-I
Box cut Up to 37m depth Quarry-II
Box cut 30 m along diprise in bottom section for 500m
strike length Cut-I 37m to 45 m depth Cut-I Upto 30m depth Cut-II 45m to 60m depth Cut-II 30m to 50m depth
Cut-III 60m to 80m depth Cut-III 50m to 70m depth
Cut-IV 80m to 100m depth Cut-IV 70m to 90m depth Cut-V 100m to 120 m depth Cut-V 90m to 110m depth
Cut-VI 110m to 130m depth Cut-VII 130m to 150m depth Cut-VIII 150m to 170m depth Cut-IX 170m to dipside limit
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 29 Executive Summary
PAUNI-II EXPANSION OC MINE COAL, OB & STRIPPING RATIO
QUARRY COAL (Mt) OB (Mm3) S/R (m3/t)
Quarry-I 5.18 31.90 6.16 Quarry-II 25.45 157.57 6.19
Total 30.63 189.47 6.19
7.3 DUMPING STRATEGY
As detailed above, entire mining area is divided in 2 quarries namely Quarry-I &
Quarry-II. Due to limited strike length of the quarry in Quarry-I and steep gradient
of seam sections, no internal dumping is proposed in the quarry and therefore the
entire overburden will be dumped externally. The layout of these OB dumps are
shown in Quarry and Surface Layout plan. External Dump ‘D” having dumping
capacity of 25.45 Mm3 and maximum height of 90m for dumping of hard OB of
Quarry-I, has three benches each of 30m height and final angle of slope is
proposed to be kept at maximum 25o. It is proposed to remove soil upto 3m depth
in 120m trench along periphery of proposed external dump ‘D’ to increase the
stability of dump. However, it is proposed in this report to involve some scientific
agency to conduct the study on slope stability and the final angle of slope as
suggested by the above agency will be implemented. Provision for the same has
been made in PR.
Another external dump ‘C’ on coal bearing area between Quarry-I & Quarry-II,
having dumping capacity of 12.80 Mm3 and maximum height of 30m at slope
angle of 370 has been proposed for dumping of Black cotton soil of Quarry-I
(3.63 Mm3), part of black cotton soil of Quarry-II (6.24 Mm3), trench cutting OB
from the site of Dump ‘A’ of Quarry-II (1.88 Mm3) and trench cutting OB from the
site of Dump ‘D’ of Quarry-I (1.05 Mm3). It is proposed to rehandle entire 12.80
Mm3 of black cotton soil dump quantity in void of Quarry-II as shown in Calender
programme of excavation. It is also proposed to construct an embankment (6m
high above HFL & top width of 20m) against Lendi nala, Sakhri nala, Pauni nala
and seasonal nala. 2.82 Mm3 of hard OB from Quarry-I will be used for
construction of this embankment.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 30 Executive Summary
The volume of different OB Dumps for Quarry-I are tabulated below:
DUMP CAPACITY AT QUARRY-I
Sl.
No.
Dump Height Volume of OB
Dump (Mm3)
1. Temp. Black cotton soil dump ‘C’ 30m 3.63
2. Embankment 6m above HFL 2.82
3. Dump ‘D’ 0 – 30m 14.15
30 – 60m 8.22
60-90m 3.08
Sub-Total 25.45
4. Internal Dumping 0.00
Total OB (1+2+3) 31.90
5 Trench cutting OB in dump ‘C’ 1.05
6. Total OB (including trench cutting OB) 32.95
In Quarry-II, external Dump ‘A” having dumping capacity of 76.60 Mm3 and
maximum height of 90m for dumping of hard OB of Quarry-II, has three benches
each of 30m height and final angle of slope is proposed to be kept at maximum
25o. It is proposed to remove soil upto 3m depth in 120m trench along periphery
of proposed external dump ‘A’ to increase the stability of dump. Another external
dump ‘B’ on dipside non coal bearing area having dumping capacity of 6.80 Mm3
and maximum height of 30m at slope angle of 370 has been proposed for
dumping of Black cotton soil of Quarry-II. As mentioned earlier, external dump
‘C’ on coal bearing area between Quarry-I & Quarry-II, having dumping capacity
of 12.80 Mm3 and maximum height of 30m at slope angle of 370 has been
proposed for dumping of Black cotton soil of Quarry-I & part of black cotton soil of
Quarry-II. In Black cotton dump ‘C’ having capacity of 12.80 Mm3, it is proposed
to dump 3.63 Mm3 Black cotton soil (upto 6m depth ) of Quarry-I and balance
quantity 9.17 Mm3 (12.80-3.63) of black cotton soil will be dumped from Quarry-II.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 31 Executive Summary
Internal dumping has also been proposed in the mine towards western side of the
property in the sector A of the proposed mine. It has been projected to backfill
67.93 Mm3 of OB in this dump. Out of 67.93 Mm3 of backfilled OB, 54.11 Mm3 of
OB will be dumped upto surface level and 13.82 Mm3 of OB will be dumped
above surface level. The details of OB dumps have been tabulated in the table
below :-
DUMP CAPACITY AT QUARRY-II
Sl. No. Dump Height Volume of OB Dump
(Mm3)
1. Black cotton soil dump ‘B’ 30m 6.80
2. Black cotton soil dump ‘C’ 30m 6.24
3. Dump ‘A’ 0 – 30m 35.37
30 – 60m 25.60
60-90m 15.63
Sub-Total 76.60
Total external dump (1+2+3) 89.64
4. Internal Dump (excluding rehandled OB
from temporary OB dump ‘C’
67.93
Total OB (1+2+3) 157.57
5. Trench cutting OB in dump ‘C’ 1.88
6 Total OB (including trench cutting OB) 159.45
Thus, Out of total 192.40 Mm3 OB (31.90 Mm3 from Quarry-I, 157.57 Mm3 from
Quarry-II, 1.88 Mm3 from trench cutting at Dump ‘A’ and 1.05 Mm3 from trench
cutting at Dump ‘D’), 124.47 Mm3 OB will be accommodated in External OB
Dump and balance 67.93 Mm3 will be dumped in decoaled void of Quarry-II.
Thus, 64.69% of total OB will be dumped externally and 35.31% OB will be
accommodated in Internal Dump. Thus, the Dump Capacity for Pauni-II
Expansion OC mine is summarised below:
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 32 Executive Summary
DUMP CAPACITY FOR PAUNI-II EXPANSION OC MINE
Sl.
No.
Dump Location Source of OB Volume of OB (Mm3)
A) EXTERNAL DUMP
1) Dump-A In rise side of Quarry-II OC
Quarry-II OC 76.60
2) BC Soil Dump-B In dip side of Quarry-II OC
Quarry-II OC 6.80
3) Dump-D In rise side of Quarry-I OC
Quarry-I OC 25.45
4) Embankment Surrounding Quarry-I OC & Quarry-II OC
Quarry-I OC 2.82
Total (External Dump)
Quarry-I OC
Quarry-II OC
Total
28.27
83.40
111.67
B) Temporary BC
Soil Dump-C
( This entire OB dump will be rehandled &
accomodated in internal dump in decoaled void of
Quarry-II OC
In Coal bearing area between Quarry-I OC &
Quarry-II OC
a) Quarry-I OC Quarry-II OC
b) Trench Cutting at Dump A
c) Trench Cutting at Dump D
Sub-Total (B)
3.63
6.24
1.88
1.05
12.80
C) INTERNAL DUMP
1) De-coaled void of Quarry-II OC
De-coaled void
of Quarry-II OC
Quarry-II OC
b) Rehandling of Temporary BC Soil
Dump C
67.93
12.80
GRAND TOTAL (EXTERNAL+ INTERNAL)
Quarry-I OC
Quarry-II OC
Trench Cutting at Dump sites
TOTAL
31.90
157.57
2.93
192.40
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 33 Executive Summary
8.0 MINING SCHEDULE AND EQUIPMENT PHASING
8.1 DESIGN CRITERIA
Project report for Pauni-II Expansion OC mine has envisaged 330 days of
working in a year based on 7 days schedule of mine working. As per the
prevalent practice in WCL, there will be three working shifts in a day each of 8
hours duration. The excavation category of OB material has been assumed as
50% Category III + 50% Category IV, whereas for Coal it is assumed as Category
IV. The insitu volume weight of OB material has been considered as 2.2 t/m3
whereas for coal it is 1.60 t/m3.
8.2 ANNUAL PRODUCTIVITY OF HEMM WITH DIFFERENT LEAD
The entire coal and OB will be extracted through outsourcing agency and
therefore, the productivity of HEMM will depend on the HEMM to be deployed by
outsourcing agency. However, the lead for coal and for OB has been estimated
based on quarry and dump profile and distance of dump from quarry.
Based on the quarry profile, dump location & distance between different cuts of
quarry & dumps, the following haul distances have been assessed for OB and
coal.
Sl. No. COAL / OB LEAD
A) Quarry-I
i) For Coal (Maximum) 2.50 km
ii) For OB (Average) 2.50 km
B) Quarry-II
i) For Coal (Maximum) 3.50 km
ii) For OB (Average) 2.00 km
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 34 Executive Summary
8.3 CALENDAR PROGRAMME OF EXCAVATION
It is envisaged in this PR of Pauni-II Expansion OC mine that part land of
Quarry-I will be acquired in 1st year. It is proposed to start coal production and OB
removal from 2nd year in Quarry-I. However, coal extraction and OB removal in
Quarry-II will start from 3rd year. Thereafter, both Quarry-I & Quarry-II will be
operated simultaneously.
The separate calendar programme of both the quarries as well as combined
calendar programme is tabulated below :
CALENDAR PROGRAMME OF EXCAVATION (QUARRY-I)
Year
Coal (Mt) Natural OB (Mm3) Programed OB (Mm3)
In Quarry Trench
Cutting
In Quarry Trench
Cutting Total
Yearly Cumm. Yearly Cumm.
Yearly
Cumm.
Insitu RH* Total
1 Land Acquisition
2 0.40 0.40 1.98 1.98 1.05 2.00 0.00 2.00 2.00 1.05 3.05
3 0.60 1.00 2.23 4.21 2.25 0.00 2.25 4.25 2.25
4 0.75 1.75 4.48 8.69 4.50 0.00 4.50 8.75 4.50
5 0.75 2.50 5.82 14.51 6.00 0.00 6.00 14.75 6.00
6 0.75 3.25 6.97 21.48 6.75 0.00 6.75 21.50 6.75
7 0.75 4.00 5.07 26.55 4.76 0.74 5.50 27.00 5.50
8 0.75 4.75 3.40 29.95 2.76 0.74 3.50 30.50 3.50
9 0.43 5.18 1.95 31.90 1.40 0.00 1.40 31.90 1.40
TOTAL 5.18 31.90 1.05 30.42 1.48 31.90 1.05 32.95
Note:* 31.90 Mm3 OB of Quarry-I includes 1.48 Mm3 OB dumped in the dip side
of Quarry-I from nearby Pauni OC mine.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 35 Executive Summary
CALENDAR PROGRAMME OF EXCAVATION (FOR QUARRY-II)
Year
Coal (Mt) Natural OB (Mm3) Programed OB (Mm3) In Quarry Trench
Cutting In Quarry Trench
Cutting Total
Yearly Cumm. Yearly Cumm. Yearly Cumm.
1 Land Acquisition 2 Land Acquisition 3 0.40 0.40 3.79 3.79 1.88 4.00 4.00 1.88 5.88 4 0.80 1.20 6.82 10.61 7.00 11.00 7.00 5 1.50 2.70 9.92 20.53 10.00 21.00 10.00 6 2.50 5.20 15.83 36.36 15.50 36.50 15.50 7 2.50 7.70 15.12 51.48 15.50 52.00 15.50 8 2.50 10.20 12.42 63.90 14.00 66.00 14.00 9 2.50 12.70 12.95 76.85 14.00 80.00 14.00
10 2.50 15.20 13.78 90.63 14.25 94.25 14.25 11 2.50 17.70 20.48 111.11 18.50 112.75 18.50 12 2.50 20.20 19.91 131.02 18.50 131.25 18.50 13 2.50 22.70 17.40 148.42 18.00 149.25 18.00 14 2.75 25.45 9.15 157.57 8.32 157.57 8.32
TOTAL 25.45 157.57 1.88 157.57 1.88 159.45
CALENDAR PROGRAMME OF EXCAVATION (FOR PAUNI-II EXPANSION OC MINE)
Year
Coal (Mt) Natural OB (Mm3) Programed OB (Mm3) Rehan-
dling of BC Soil Dump (Mm3)
In Quarry Trench Cutting
In Quarry Trench Cutting
Total Yearly Cum. Yearly Cum.
Yearly Cum.
Insitu RH Total
1 Land Acquisition
2 0.40 0.40 1.98 1.98 1.05 2.00 0.00 2.00 2.00 1.05 3.05
3 1.00 1.40 6.02 8.00 1.88 6.25 0.00 6.25 8.25 1.88 8.13
4 1.55 2.95 11.30 19.30 11.50 0.00 11.50 19.75 11.50
5 2.25 5.20 15.74 35.04 16.00 0.00 16.00 35.75 16.00
6 3.25 8.45 22.80 57.84 22.25 0.00 22.25 58.00 22.25
7 3. 25 11.70 20.19 78.03 20.26 0.74 21.00 79.00 21.00
8 3.25 14.95 15.82 93.85 16.76 0.74 17.50 96.50 17.50
9 2.93 17.88 14.91 108.76 15.40 0.00 15.40 111.90 15.40
10 2.50 20.38 13.78 122.54 14.25 0.00 14.25 126.15 14.25
11 2.50 22.88 20.48 143.02 18.50 0.00 18.50 144.65 18.50 3.20
12 2.50 25.38 19.91 162.93 18.50 0.00 18.50 163.15 18.50 3.20
13 2.50 27.88 17.40 180.33 18.00 0.00 18.00 181.15 18.00 3.20
14 2.75 30.63 9.14 189.47 8.32 0.00 8.32 189.47 8.32 3.20
TOTAL 30.63 189.47 2.93 187.99 1.48 189.47 2.93 192.40 12.80
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 36 Executive Summary
8.4 DUMPING SCHEDULE
The year-wise Dumping Schedule in the proposed Pauni-II Expansion OC mine
is tabulated below :
Year QUARRY / TRENCH CUTTING
(Mm3)
PROG.
OB
(Mm3)
(including
Rehandling)
Dumping (Mm3)
Dump- A
BC Soil Dump-B
Temp. BC soil Dump-C
Dump- D
Embank-ment
Internal Dumping in
void of Quarry-II
1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2
Quarry-I 2.00 0.00 0.00 0.20 0.00 1.80 0.00 Trench Quarry-I
1.05 0.00 0.00 1.05 0.00 0.00 0.00
3
Quarry-I 2.25 0.00 0.00 0.30 0.93 1.02 0.00 Quarry-II 4.00 3.20 0.80 0.00 0.00 0.00 0.00 Trench
Quarry-II 1.88 0.00 0.00 1.88 0.00 0.00 0.00
4 Quarry-I 4.50 0.00 0.00 0.55 3.95 0.00 0.00 Quarry-II 7.00 5.70 1.30 0.00 0.00 0.00 0.00
5 Quarry-I 6.00 0.00 0.00 0.70 5.30 0.00 0.00
Quarry-II 10.00 8.20 1.80 0.00 0.00 0.00 0.00 6 Quarry-I 6.75 0.00 0.00 0.78 5.97 0.00 0.00
Quarry-II 15.50 11.40 2.60 0.00 0.00 0.00 1.50 7 Quarry-I 5.50 0.00 0.00 0.58 4.92 0.00 0.00
Quarry-II 15.50 9.20 0.30 2.50 0.00 0.00 3.50 8 Quarry-I 3.50 0.00 0.00 0.52 2.98 0.00 0.00
Quarry-II 14.00 7.50 0.00 2.50 0.00 0.00 4.00 9 Quarry-I 1.40 0.00 0.00 0.00 1.40 0.00 0.00
Quarry-II 14.00 7.76 0.00 1.24 0.00 0.00 5.00 10 Quarry-II 14.25 8.75 0.00 0.00 0.00 0.00 5.50 11 Quarry-II 18.50 13.00 0.00 0.00 0.00 0.00 5.50
Rehandling 3.20 0.00 0.00 (-) 3.20 0.00 0.00 3.20 12 Quarry-II 18.50 1.89 0.00 0.00 0.00 0.00 16.61
Rehandling 3.20 0.00 0.00 (-) 3.20 0.00 0.00 3.20 13 Quarry-II 18.00 0.00 0.00 0.00 0.00 0.00 18.00
Rehandling 3.20 0.00 0.00 (-) 3.20 0.00 0.00 3.20 14 Quarry-II 8.32 0.00 0.00 0.00 0.00 0.00 8.32
Rehandling 3.20 0.00 0.00 (-) 3.20 0.00 0.00 3.20
Total OB 205.20 76.60 6.80 0.00 25.45 2.82 80.73
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 37 Executive Summary
8.5 EQUIPMENT SCHEDULE ~ SCHEDULE OF EXPENDITURE ON HIRING/ OUTSOURCING OF EQUIPMENT
As described earlier, the entire coal and OB will be excavated by
hiring/outsourcing of equipment. The cost of OB and parting removal and coal
extraction by hiring/outsourcing of equipment depends on type of strata and lead.
In the proposed Pauni- II Expansion OC mine, the strata under consideration is
medium hard strata. The rates for OB by hiring of equipment for the proposed
mine have been estimated on the basis of FD approved rates circulated by WCL,
updated with change in price of diesel for April’2015 (Rs 53.46/litre).
The average rate (Rs./m3) for excavation / rehandling of OB and extraction of
coal (Rs/t) are tabulated below :
Year
COAL OB Trench Cutting Rehandling OB
Prod.
Hiring
Rate
(Rs./t)
Insitu
OB
(Mm3)
Hiring
Rate
(Rs./m3)
Trench
Cutting
(Mm3)
Hiring
Rate
(Rs./m3)
Rehan-
dled OB
(Mm3)
Hiring
Rate
(Rs./m3)
1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 0.40 28.53 2.00 50.78 1.05 51.91 0.00 0.00
3 1.00 28.53 6.25 50.31 1.88 51.91 0.00 0.00
4 1.55 30.05 11.50 53.78 0.00 0.00 0.00 0.00
5 2.25 31.56 16.00 55.83 0.00 0.00 0.00 0.00
6 3.25 32.35 22.25 56.85 0.00 0.00 0.00 0.00
7 3.25 33.15 20.26 58.58 0.00 0.00 0.74 58.58
8 3.25 34.70 16.76 59.56 0.00 0.00 0.74 59.56
9 2.93 36.25 15.40 59.81 0.00 0.00 0.00 0.00
10 2.50 37.04 14.25 52.47 0.00 0.00 0.00 0.00
11 2.50 37.83 18.50 52.47 0.00 0.00 3.20 45.16
12 2.50 39.01 18.50 52.47 0.00 0.00 3.20 45.16
13 2.50 40.18 18.00 52.47 0.00 0.00 3.20 45.16
14 2.75 40.18 8.32 52.47 0.00 0.00 3.20 45.16
TOTAL 30.63 187.99 2.93 14.28
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 38 Executive Summary
Rates for excavation for hiring/ outsourcing of HEMM are being adopted in this
report for planning purpose and economic evaluation of the project. These rates
may vary at the time of actual implementation. The rates include excavation,
transport, drilling, dozing at face & dumps, water spraying and Land Reclamation.
It is also suggested here that before awarding the work to hiring agency,
geological structure should be further confirmed by drilling additional boreholes.
Lead for OB, bench-wise, horizon-wise has been calculated for each cut on
weighted average basis keeping into account the OB dumping programme. The
lead for coal is calculated based on floor RL of each cut to coal stock yard. On
actual implementation of report these rates and lead may vary based on site
conditions. It is suggested to re-assess hiring rates again based on site
conditions while awarding tender.
8.6 DRILLING & BLASTING
Drilling pattern in overburden, with a bench height of 10 m has been envisaged
with the burden as 5.0-6.0 m and spacing as 6.5-7.0 m. The powder factor of
3.65 m3/kg has been considered for overburden for planning purpose.
For coal, depending upon the thickness available in the horizons, bench height of
maximum 5 m is being proposed. For coal bench, drilling pattern with burden
and spacing of 2.5 m & 3.0 m respectively has been proposed. A powder factor
of 5.48 t/kg has been considered for blasting in coal for planning purpose.
However at the time of operation of mine, drilling parameters have to be
optimized on the basis of actual field trial depending upon joint pattern, bedding
plane and local geology of the blast site and accordingly powder factor for OB &
coal may vary after final trial of blasting.
It is proposed that bulk loading explosive may be used. For storage of L.D.
explosive and accessories existing magazine at Pauni OC is proposed to be
used.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 39 Executive Summary
9.0 QUALITY
Quality of coal has been assessed for both the quarries separately as well as for
Combined OC based on the borehole data available within the quarry area.
Quarry-I The minimum and maximum range of analytical data for quality of coal for
composite seam is as given below:
Parameters Range
Minimum Maximum
Moisture % 8.0 (CMWG-118) 8.1 (CMWG-80)
Ash % 26.5 (CMWG-80) 27.3 (CMWG-118)
GCV (kCal/kg)
(excluding Parting)
4470 4826
Overall quality for Quarry-I has been assessed based on borehole wise GCV in
quarriable area which works out to 4755 kCal/kg (G-9).
Quarry-II
The minimum and maximum range of analytical data for quality of coal for bottom
section & top section is as given below:
Parameters Range Minimum Maximum Bottom Section
Moisture % 6.3 (CMWG-187) 9.5 (CMWG-96) Ash % 18.7 (CMWG-164) 34.7 (CMWG-128)
GCV (kCal/kg) (excluding Parting)
4072 5339
Top Section
Moisture % 5.7 (CMWG-155) 9.0 (CMWG-153) Ash % 20.2 (CMWG-167) 40.0 (CMWG-155)
GCV (kCal/kg) (excluding Parting)
3796 5073
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 40 Executive Summary
Overall quality for Quarry-II has been assessed based on borehole wise GCV in
the quarriable area (calculated basis) which works out to 4830 kCal/kg (G-9).
OVERALL QUALITY
The overall quality of composite seam (top & bottom section combined) for PR
for Pauni-II Expansion OC mine, on average basis, works out to 4817 kCal/kg
(Grade G-9).
10.0 PUMPING & DRAINAGE
The Pumping capacity required at the time of five years after reaching the target
has been calculated as under:-
Sl.
No.
DESCRIPTIONS CALCULATED DATA
Quarry-I Quarry-II
1 Maximum exposed area (ha) 53.7 131.5
2 Maximum backfilled area (ha) 0.00 73.5
3 Surface area of mine considered for
excavation (ha)
53.7 205
4 Area beyond excavation (ha),5% of item
(3)
2.685 10.25
5 Run-off co-efficient for
a) Open excavation 0.70 0.70
b) Area beyond excavation 0.10 0.10
6 Rainfall infiltration co-efficient for backfilled
area
0.20 0.20
7 Probable max. rainfall in a day (mm) 172 172
8 Water collected in the quarry due to
exposed area and area beyond excavation
(cum/day)
65117 184741
9 Required pumping capacity to handle the
whole water of the rain water in 100 hrs
(lps)
181 513
10 Seepage due to strata (15% of Item 9) 27 77
11 Total pumping capacity 208 590
12 Depth in target plus five years (m) 120 200
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 41 Executive Summary
Pumping system has been designed for the volume of water accumulated in the
mine at the target plus five year production considering maximum rainfall in a day
as 172mm
Peak pumping capacity worked out as 74884 cum for Quarry-I & 212452 cum for
Quarry-II.
Above volume of water will be dewatered in 5 days at the rate of 20 hrs pumping
per day.
Pumping capacity per day thus worked out as 14977 cum for Quarry-I & 42490
cum for Quarry-II.
10.1 SELECTION OF PUMPS DELIVERY RANGES
Quarry-I (i) Four pumps of 80lps x 150m head have been proposed. Out of four
pumps, one pump is standby.
(ii) Two pumps of 80 lps x 80m head have been proposed.
(iii) One diesel pump of 80lps x 60m head has been proposed.
(iv) Three face pumps of 11lps x 30 m head have been envisaged in this
report.
(v) One delivery range of 312mm dia. has been proposed for main pumps of
80lps x 150m head and maximum two pump will be connected in this
delivery.
(vi) One delivery range of 219mm dia. have been used for main pumps of
80lps x 150m.
(vii) Two delivery ranges of 219mm dia. have been used for auxiliary pumps of
80lps x 80m.
(viii) 80 mm dia. G.I. pipe will be used for face pumps.
(ix) No piping provision have been made for standby pumps.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 42 Executive Summary
Quarry-II
i) Five pumps of 160lps x 250m head have been proposed. Out of five pumps,
one pump is standby.
ii) Three pumps of 80 lps x 150m head have been proposed.
iii) One diesel pump of 80lps x 60m head has been proposed.
iv) Six face pumps of 11lps x 30 m head have been envisaged in this report.
Out of six pumps, one pump is standby.
v) One delivery ranges of 406.4 mm dia. have been proposed for main pumps
of 160lps x 250m head and maximum two pumps will be connected in each
delivery.
vi) One delivery range of 312mm dia. has been proposed for main pumps of
160lps x 150m head and maximum one pump will be connected in this
delivery.
vii) Three delivery ranges of 219mm dia. have been used for auxiliary pumps of
80lps x 160m.
viii) 80 mm dia. G.I. pipe will be used for face pumps.
ix) No piping provision have been made for standby pumps.
11.0 COAL HANDLING ARRANGEMENT
Combined CHP has been proposed for both quarries in this PR to handle the
entire production of coal. Location of the CHP has been proposed near access
trench of proposed Quarry-II. However, exact location will depend upon site
conditions.
Salient Features of CHP are summarized below.
a) There will be two streams. In first stream there will be three numbers of
integrated feeder breaker with secondary sizer for crushing of coal to (-) 100
mm size and discharging crushed coal onto 1400 mm wide belt conveyor. In
second stream there will be one number of integrated feeder breaker with
secondary sizer for crushing of coal to (-) 100 mm size and discharging
crushed coal onto 1200 mm wide belt conveyor.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 43 Executive Summary
b) Conveying of coal by two streams of 1400 mm wide belt conveyors and
1200 mm wide belt conveyor. 1400 mm wide belt conveyors are for first
stream and 1200 mm wide belt conveyor is for second stream.
c) Storage of coal in one no. of 2 x 100 t capacity overhead hoppers in second
stream and in 7000t capacity ground bunker in first stream.
d) Despatch of coal by trucks in second stream and feeding to Cross Country
Conveyor Transportation (CCT) in first stream by the belt conveyors. A CCT
of 1400/1600 mm wide belt width will be installed for Gauri, Pauni and Sasti
group of mines which will collect coal from mines and discharge coal into 20
thousand tonne capacity ground bunker at proposed Rapid Loading system
(RLS) siding at Sasti by tripper conveyor. Coal from ground bunker will be
loaded into reclaim conveyor by plough feeder. Reclaim conveyor will
discharge into elevating conveyor which will discharge into 4000t capacity
silo. From silo coal will be loaded into wagons by RLS. Cost of silo, RLS,
CCT, Ground bunker for silo, siding, other common conveyors and other
common equipment will be provided through a separate scheme, hence
capital provision has not been made in this PR.
e) Dust suppression and fire extinguisher system
f) Power supply, illumination and control systems
g) Civil and structural cost
h) Weighment of coal with the help of road weighbridge for road dispatch.
11.1 RAILWAY SIDING
No financial provision has been made in this report under this head. Railway
siding shall be prepared by a separate scheme.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 44 Executive Summary
12.0 WORKSHOP & STORES
12.1 WORKSHOP
The proposed Pauni-II Expansion OC mine has been planned for Total hiring
option. The entire coal extraction and OB removal will be done by hiring agency.
The HEMM deployed in the mine will be operated and maintained by hiring / out-
sourcing agency. Hence, No provision for excavation workshop has been
made in this report.
E & M workshop E & M Workshop facilities have been proposed in this PR to carry out
maintenance & repair of the CHP, equipment, pumps, LMVs, electrical etc. The
E&M workshop is essentially a unit workshop and will depend on central/regional
workshop for major repair and part manufacture.
12.2 STORES
Unit store will cater the routine needs of consumables, spares, POLs etc.
13.0 POWER SUPPLY
For the proposed Pauni II Expansion OC Mine, maximum demand of the mine
will be 4636 kVA for Total Hiring Option (Including Township). Initially at the
starting of this project, the power will be made available by extending the 11kV
feeder from existing Pauni mine to Quarry-I. This 11kV feeder will have insulator,
Conductor & pole structure of 33kV rating. When the proposed Pauni II
Expansion OC Mine will reach its production stage this 11kV feeder will be
converted to 33kV feeder.
A 220 kV/33 kV, 2 x 16 MVA central substation is proposed to be installed near or
adjacent to the premises of existing Sasti central 66kV/11kV S/S. It is proposed
to draw approx. 5 km long, 220 kV line from the new 220 kV/33 kV substation,
which is under construction near Ballarpur Paper Mill in Ballarpur township to
Sasti central substation.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 45 Executive Summary
From this proposed 220 kV/33 kV S/S a 33kV feeder, 11 km long, will be drawn
to meet the power requirement of proposed Pauni - II Expansion OC Mine. A 33
kV/3.3 kV, 2 x 5 MVA substation is proposed to be installed near Pauni-II
Expansion OC Mine at a suitable location in non coal bearing area to meet the
power requirement of this proposed mine.
In another option for power supply, if power will be available at 33 kV from nearby
area in Ballarpur then it can be utilized as incoming power source of Pauni-II
Expansion OC Mine. Two situations are being envisaged at this stage. The first
one is the conversion of existing 66 kV incoming line to 33 kV, of Sasti central
substation by MSEDCL which is under consideration. The second one is
availability of power at the new 220 kV/33 kV substation, which is under
construction near Ballarpur Paper Mill in Ballarpur Township.
Salient features of the electrical parameters are given in table below:-
Sl. No. ITEM HEAD TOTAL HIRING
1
Projected Maximum Demand
A) Only Mine 8084 kW
B) Only Township 334 kW
C) Total 8418 kW
2
Specific Energy Consumption
A) With Respect to OB Production NIL
B) With Respect to Coal Production 2.59 kWh/t
C) With Respect to Common Load 2.11 kWh/t
D) With Respect to Total Load 4.70 kWh/t
3 Specific Power Cost 47.87 Rs. /t
4 Fixed Percentage Of Power Cost 44.09 %
5 Variable Percentage Of Power Cost 55.91 %
6 Average Cost Of Purchased Power 10.19 Rs./kWh
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 46 Executive Summary
14.0 CIVIL CONSTRUCTION WORKS
The Building Cost Index for the Maharastra has been worked out to 560 in 2015
(1st half) taking the prevalent rates of materials and labours in Maharastra. This
Building Cost Index is with reference to base 100 in Nagpur as on 1.1.1992.
14.1 SERVICE BUILDINGS
Keeping in view the needs and requirements of this mine, provision for all
necessary service buildings such E & M workshop, Sub–station and other service
buildings have been provided.
14.2 RESIDENTIAL BUILDING
Total manpower proposed for this project is 242. Considering the availability of
quarters at existing colonies of Pauni OC, Gauri OC etc. TSC of WCL Board held
on 01.06.2015 at WCL (HQ), Nagpur directed to delete the capital provision for
residential buildings. Only Hostel type accommodation has been provided in the
proposed PR.
14.3 ROADS & CULVERTS
1.40 km long Haul road for 35T dumper capacity has been provided for
transportation of coal / OB inside quarry. For approaching different Service
Buildings 1.00 km long Sector Road on Stratum `D’ specification with culverts,
drain, tree guards etc. has been proposed.
Temporary diversion of road from Chincholi to Sakhri village for 1.0 km length of
Stratum ‘C’ and Permanent diversion of road (on proposed embankment) from
Chincholi to Sakhri village for 7.5 km length of Stratum ‘C’ has been proposed.
Accordingly, provision for road diversion have been made in proposed PR for
Pauni-II Expansion OC Mine.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 47 Executive Summary
14.4 WATER SUPPLY & SEWERAGE
Water supply arrangements have been envisaged for project only. The total water
requirement for project site has been worked out to 880 kl. Water demand for
project site includes water to be supplied for dust suppression, fire fighting, water
sprinkling on roads, etc.
Sub-soil water has been envisaged as the source. Accordingly, bore-well
provisions have been made. Sub-soil water through bore well has been proposed
to be conveyed to O.H. reservoirs via ground sumps. Further, water from O.H.
reservoir shall be supplied under gravity to different buildings after chlorination.
It is, however, suggested that permanent water supply arrangement should be
formulated after carrying out detailed survey, investigations for the adequate
source of water and detailed engineering. The details and estimated amount for
Water supply in colony use & industrial use is given in PR.
To avoid any discharge of effluent into natural water-courses, sewage disposal
arrangement has been envisaged. Estimated amount for sewage disposal
arrangement for project site along with required surface drains is given in PR.
However, final economical scheme may be formulated after detailed survey &
engineering considering the site parameters.
15.0 SAFETY & CONSERVATION
15.1 SAFETY FROM INUNDATION
Lendi nala, Sakhri nala and some seasonal nalas are passing through proposed
mine area of Pauni-II Expansion OC Mine. The HFL of these nalas are not
known. In this report, if required, it is proposed to make a flood protection
embankment 6m above HFL around the proposed mine wherever necessary. The
top width of embankment is proposed as 20m. During rainy season regular
inspection of embankment shall be done. All precautions as per CMR 126 shall
be taken.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 48 Executive Summary
15.2 DUST SUPPRESSION
For suppression of dust, fixed type water sprinklers may be provided.
Suppression of mine dust may be done by using package bond & dust bond, for
methodology of application DGMS Circular No.8 of 1997 may be referred.
15.3 SAFETY FROM FIRE AND SPONTANEOUS HEATING
No person shall deposit heated material or ashes on any opencast working. No
person shall light a fire or permit a fire to be lighted in any OC working except by
the permission in writing of the Manager and only for a special purpose specified
therein. No coal shall be left exposed in coal benches more than its incubation
period to avoid fire in seam due to spontaneous heating. Proper type of the
extinguisher should be kept in each HEMM ready for use in case of emergency.
In coal stock, coal shall be dispatched on the basis of first in first out.
15.4 SLOPE STABILITY
Proper care for stability of dump slope is required as proposed dumps are 90m
above ground level. Slope stability studies should be done beforehand & its
recommendation should be implemented. Also on dip side of quarry it is
proposed to conduct studies for stability of quarry slope. Again side batter runs
faults. These faults shall be knocked out at the floor of the coal seam to avoid any
bench slope failure due to fault. It is suggested that following action may be taken
to deal with slope stability problem :
i) Vulnerable area may be identified and marked on quarry plan.
ii) Observation of actual alignment of fault planes, its throw, joints, etc. may be
recorded during the process of excavation.
iii) Water drainage system may be properly implemented. Regular monitoring of
tension cracks, horizontal and vertical movement of strata in critical area may be
done.
iv) Mine encounters lot of faults, whenever mine workings approaches to fault plane
proper monitoring may be done. Efforts may be made to reduce load on fault plan
v) Water accumulation at dump top and toe is major cause of dump failure.
Adequate drainage shall be maintained at top and toe of dump.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 49 Executive Summary
15.5 HAUL ROAD MAINTENANCE
In this PR, haul road shall be constructed and maintained from time to time. It will
be maintained by hiring agency. Safe distance between the haul road and the toe
of the backfill shall be maintained.
15.6 PRECAUTIONS FROM BLASTING
Special precautions will be taken while performing blasting operations to avoid
danger from fly rock. Controlled blasting shall be practiced near built up area and
near embankment to avoid any damage to them.
15.7 SAFETY ASPECTS FOR OUTSOURCING / HIRING OF HEMM
Special precaution should be taken while employing contractual machine &
labours in the mine. Before employing contractual workers to the mine proper
vocational training should be imparted based on recommendations of various
Safety Conference. Terms and conditions for deployment of contractual labours
as well as machineries shall be fixed by management. Some of the major aspects
are as follows:
A) For persons :
i) Records in Form-B & Form-E shall be maintained.
ii) Records of VTC driving license of operators shall be kept by
Operators and readily available for inspection by management
iii) Salaries shall be distributed in front of management representative
iv) No person shall be employed unless person holds VTC certificate and
Management is informed.
v) Adequate supervision shall be maintained by competent person.
vi) All persons employed in mine shall obey lawful instructions of mine
supervisors and officials.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 50 Executive Summary
B) For Machineries :
i) All the machineries to be deployed in mines should be passed by the
management.
ii) RTO certificate photo copies of all vehicles shall be submitted to
management.
iii) Daily welding, monitoring, inspection shall be done by contractor's
mechanic as directed by management.
iv) Machine manufacturers should be asked to give risk analysis.
v) Records of daily maintenance breakdown repairs etc shall be
maintained by contractor and shall be available for inspection by mine
officials.
C) General : i) No person/vehicle shall be deployed at any place other than authorized
place.
ii) All employees of contractors should obey lawful instruction of mine
management.
iii) Risk Management Plan by contractor of tipper and excavators may be
made and implemented.
iv) VTC trained Manpower shall only be deployed in the mine.
v) Restricted traffic & traffic control planning shall be done and
implemented.
15.8 CONSERVATION OF COAL
Quarry limits are fixed in such a way to exploit maximum possible coal. Although
for calculation of mineable coal reserves 5% mining losses has been taken
into account, but in practice all efforts would be made to minimise the losses.
OB benches would be kept sufficiently advanced to avoid mixing of coal & OB.
Maximum possible backfilling is proposed in mine.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 51 Executive Summary
15.9 SCIENTIFIC STUDIES
Provision for scientific studies regarding Slope stability & Hydro-geological study
etc. have been made in this PR. It is suggested that before starting of backfilling
operation in Quarry-II, scientific studies have to be conducted for design of
backfill dump and to find out safe distance between working face and toe of
backfilled dump.
16.0 ENVIRONMENTAL MANAGEMENT
Pauni-II OC mine (Quarry-I) is an on-going project of WCL and Environment
Clearances for Pauni-II OC (Capacity 0.60 MTPA) vide letter no J-
11015/71/2005-IA.II (M) dated 02/02/2006 is available. However for enhanced
capacity of Pauni-II Expansion OC Mine (Target capacity of 3.25 Mty and Peak
capacity of 4.06 Mty), Environment Clearance will be required.
Although, the target capacity of the mine has been planned as 3.25 Mty, the mine
may achieve higher or lower than target capacity under following favourable or
unfavourable geo-mining, climatic and other conditions :
i) Availability of larger or smaller strike length and flatter or steep gradient of
seam. In the proposed mine the peak capacity of 4.06 Mty is likely to be
achieved during the period from 7th year to 8th year due to larger strike
length and flatter gradient.
ii) Less or more number of rainy days in particular years.
iii) Timely and efficient working by hiring/out-sourcing agency or vice versa..
iv) Encountering less or more geological disturbances than projected in the
geological report.
v) Upgradation of size and type of HEMM at the time of replacement due to
technological advancement.
Due to above conditions, it is possible that the production from mine may be
more or less than target capacity. In case of higher than target production, the
higher production is catered through cushion available in the system or by
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 52 Executive Summary
increasing workload of out-sourcing agency as departmental capacity cannot be
increased for short and irregular period of such higher than target capacity.
Hence, inclusion of peak capacity in calendar programme is not feasible. But, a
peak capacity of 25% more than target capacity (4.06 Mty) is very likely in some
years of mine life.
16.1 AIR QUALITY MANAGEMENT
Air pollution is likely to be generated due to dust, exhaust from vehicles, blasting
fumes etc. In opencast mines, dust is likely to be produced during blasting,
crushing of coal, handling of overburden and coal, drilling and operation of
HEMM. The following measures have been proposed to control air pollution :
i) Water spraying is to be carried out on haul road at regular interval during
each shift.
ii) Water spraying arrangement at dust generating points in CHP, feeder
breaker, conveyor transfer points etc.
iii) Proper maintenance of all internal combustion engines to reduce smoke and
exhaust fumes.
iv) Dust extractors in working condition in all the drills
v) Tree plantation in rows and blocks along the approach road of the mine and
also along the coal transportation road on both sides.
vi) Perimeter tipping of external overburden dumps. Tree plantation on the
slope of the perimeter dump.
vii) Water spraying mixed with safe and non-toxic dust suppression chemicals
on haul roads during dry months.
viii) Coal transportation in trucks covered with tarpaulin.
ix) Avoiding overloading of trucks.
x) Frequent cleaning of coal transportation road.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 53 Executive Summary
16.2 WATER QUALITY MANAGEMENT
The quantity of mine water pumped out would vary according to the season. The
mine water may contain various impurities like coal dust, traces of grease, oil etc.
in various proportions. The mine water would be allowed to collect in the quarry
sump where primary settling would take place. The mine water would then be
pumped into secondary settling tanks on the surface. Here the water would be
allowed to settle and thereafter part of treated water will be utilized for meeting in
-house water requirement (like dust suppression, watering of plants, washing of
HEMM, potable use etc). Peripheral trenching is recommended near external OB
dumps for coursing the run-off and leached water from the dumps. If required, the
water may be sent to surface settling tanks before discharging it into the drainage
channels.
The used water from the industrial area comprising CHP, Workshop, Garage etc.
may be contaminated with grease, oil, coal dust, dirt etc. This water will be
allowed to settle and suitable treatment will be carried out in oil and grease trap.
Thereafter the treated water will be mostly recycled.
16.3 GROUND WATER MANAGEMENT
Due to proposed project, it is anticipated that the effect on ground water regime
will be pronounced upto around 500 m from mine edge and effect will be
pronounced in the down-dip side and milder in the up-dip side. But this effect will
be temporary in nature and once the project is over, after 2 – 3 rains, the regime
will regain its almost original status. Any shortage of water in the affected villages
during the temporary period will be supplemented through supply of treated water
pumped out from the mine.
16.4 NOISE AND GROUND VIBRATION MANAGEMENT
Existing noise level at the mine site (wrt pre-mining level) is likely to increase and
following measures are being suggested to reduce noise and ground vibration
effects :
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 54 Executive Summary
i) With judicious use of explosives and correct blasting techniques, ground
vibration and noise pollution would be reduced.
ii) Structures prone to vibration or those with moving parts are suggested to be
inspected periodically and source of vibration should be damped to minimize
noise and vibration.
iii) Proper maintenance of HEMM and exhaust silencers.
iv) Vegetation barrier around the service buildings will act as effective acoustic
barrier.
v) Ground vibration and fly rock can be controlled by proper use of delay
detonators. This will help to reduce the noise pollution.
16.5 FLORA AND FAUNA MANAGEMENT
No Changes in the diversity of species or number of any species of animal and
no reduction in the number of any unique, rare or endangered species of animals
are anticipated. Any deterioration to existing fish or wild life habitat due to mining
is ruled out. Similarly, no changes in the diversity of species or number of any
species of plants and also no reduction of the number of unique, rare or
endangered species of plants are anticipated.
Adequate plantation has been proposed with native species to maintain the
diversity and also to attract the fauna.
16.6 LAND RESOURCE MANAGEMENT
Regarding land use during mining, in addition to excavation of quarry for coal,
overburden dump will be created along with development of other mine related
infrastructures. Overburden dump is proposed to be technically and biologically
reclaimed and sufficient greenery will be developed.
16.7 ENVIRONMENT MANAGEMENT SYSTEM
To have a close watch on the environmental condition and implementation
of various measures suggested, a multi- disciplinary approach is essential. At
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 55 Executive Summary
present WCL headquarter acts as apex body which supervises the activities
relating to environment at project level through the General Manager. General
Manager of the area coordinates the activities of various disciplines in the area to
render all necessary assistance at the implementing level i.e. the project. Area
Nodal Officer (Environment) monitors all aspects of environment on behalf of the
General Manager. He also takes suitable steps for generation of environment
data alongwith its analysis and interpretations. As far as plantation is concerned
horticulturist with suitable backup staff is provided in the area for undertaking the
plantation jobs including raising of a nursery. Sub-Area Manager is responsible
for mechanical reclamation of the area. He is also responsible for biological
reclamation with assistance of GM’s office.
16.8 CAPITAL PROVISION
A capital provision of Rs. 97.09 lakhs has been made against environment
protection.
In addition to this, Rs. 6.00/t has been considered in the report for revenue
expenditure related to environmental activities in the mine.
17.0 LAND REQUIREMENT
The TSC of WCL Board held on 01.06.2015 in WCL(HQ), Nagpur directed to
revisit provision of land requirement for Quarry-II in consultation with Ballarpur
Area. Accordingly, Land provision for Quarry-II has been made in the proposed
PR. The total land requirement for Pauni-II Expansion OC Mine is 1152.66 ha out
of which the land requirement for proposed Quarry-I and Quarry-II is 327.41 ha
and 825.25 ha respectively. Out of 327.41 ha land for Quarry-I, 21.61 ha land
which is already acquired for Pauni OC has to be transferred to Pauni-II
Expansion OC by boundary readjustment. For economic evaluation, one time
monetary compensation in lieu of employment (@ Rs. 5 lakh/Acre) for 50% of
Tenancy land has been considered in this PR. However, it is envisaged that WCL
may offer jobs as per the New R&R policy of CIL to land losers who are not
willing to take monetary compensation in lieu of employment.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 56 Executive Summary
17.1 TYPE OF LAND
The type of land for proposed Pauni-II Expansion OC is as follows:
21.61 ha land is already acquired for nearby Pauni OC mine which will be
transferred to Pauni-II Expansion OC mine by boundary adjustment. Total
additional land required for the PR for Pauni-II Expansion OC mine is 1131.05 ha
(1152.66-21.61). It is proposed to acquire above additional land in two phases i.e.
Phase-I & Phase-II. In Phase-I, it is envisaged to acquire 1118.98 ha land
(1029.38 ha tenancy land and 89.60 ha Government land) and in phase-II, it is
envisaged to acquire 12.07 ha forest land.
Initially, Environmental Clearance will be taken for Phase-I of Pauni-II Expansion
OC mine. In the meantime, the application for getting forest clearance for
acquisition of 12.07 ha forest land under Quarry II OCP will be processed under
the name Pauni-II Expansion OC (Phase-II). After getting forest clearance, the
EC for Pauni-II Expansion OC (Phase-II) will be processed.
17.2 LAND USE PATTERN
Total 1152.66 ha land is required for the proposed Pauni-II Expansion OC mine.
The land required for the project for various activities is as follows:
Sl. No.
Particulars Land (ha)
Quarry-I Quarry-II Total Land
Existing Land (acquired for Pauni OC)
Additional Land
Total land
Additional Land
1) Tenancy land
21.61 281.03 302.64 748.35 1050.99
2) Govt. land 0.00 24.77 24.77 64.83 89.60 3) Forest
land 0.00 0.00 0.00 12.07 12.07
Total 21.61 305.80 327.41 825.25 1152.66
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 57 Executive Summary
Sl. No. Particulars Area (ha)
1. Quarry Area 295.35 2. External OB dump 308.90 3. Infrastructure 10.00 4. Area needed for rationalization 336.41 5. Area needed for blasting zone 200.00 6. Colony land (Hostel only) 2.00
Total Land 1152.66
Note: Out of 1152.66 ha land, provision of 21.61 ha land has been made in the
approved PR of Pauni OC which has to be transferred to proposed Pauni-II
Expansion OC by boundary readjustment.
18.0 MINE CLOSURE PLANNING
Mine closure planning has to be carried out at the starting of the mine and
needs periodic reviewing and revision during its life cycle to cope with the geo-
technical constraints, safety and economic risks, social & environmental
challenges. In the proposed Pauni-II Expansion OC Mine, necessary provision
has been kept towards mine closure based on latest guidelines of MOEF. The
closure cost works out to Rs. 42.14/t.
The mine closure cost will cover the closure activities for which a corpus fund will
be created by opening an escrow account with the coal controller organization in
nationalised bank. In case of occurrence of acid mine drainage, post closure acid
mine drainage management cost shall also be included in the total closure cost.
An amount @ Rs 6.00 lakhs per Ha of the project area will be deposited in this
account for final mine closure. Progressive mine closure will be done with the
fund provided in approved report.
The above rate has been taken from Circular No. 55011-01-2009-CPAM,
Government of India, Ministry of Coal, Dated 27 August, 2009 duly updated on
7th January, 2013.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 58 Executive Summary
Type of Mine : Open Cast.
Life (start of mining activity i.e., 1st year to end of mine life i.e. 14th year) : 14 years
Total project area of the mine including 21.61 ha
land already acquired for Pauni OC : 1152.66 ha
Land for mine closure plan in this PR :1131.05 ha
The financial provision for closure of Project Report for Pauni-II Expansion OC
Mine for the entire mine life comes to around Rs. 129.0878 Crores (based on
March, 2015 WPI @ Rs 6 lakh/ Ha and 5% escalation each year. The break-up of
closure cost for Pauni-II Expansion OC Mine is tabulated below.
1) Mining should be carried out in a phased manner initiating afforestation/
reclamation work in the mined out area of quarry and dumps done during
previous years.
2. Upto 80% of the total deposited amount including interest accrued in the
ECSROW account may be released after every 5 years. The amount
released should be equal to expenditure incurred on Progressive Mine
closure in past 5 years or 80% whichever is less.
3. The cost/expenditure of mine closure activities will be met from the corpus
fund deposited in the escrow account by the mine operator. However, the
additional amount beyond the escrow account will be provided by the mine
operator after estimating the final mine closure cost (as per the mine closure
guideline).
4. The amount indicated separately under each head in the following table is
indicative only and based on actual expenditure the amount may change.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 59 Executive Summary
BREAK-UP OF CLOSURE FUND FOR VARIOUS MINE CLOSURE ACTIVITIES
Sl. No.
Activity % of Total Mine closure
Cost
Amount (Rs.in Lakhs)
Remarks
A Dismantling of structures To be included in final mine closure plan.
Service Building 0.2 25.82 Residential Building 2.67 344.66 Industrial Structures like, Workshop, Field
substation, etc. 0.3 38.73
B Permanent Fencing of mine void and other dangerous area
To be included in final mine closure plan. Random rubble masonry of height 1.2
meter including leveling up in cement concrete 1:6:12 in mud mortar
1.5 193.63
C Grading of highwall slopes To be included in final mine closure plan.
Levelling and grading of highwall slopes 1.77 228.49
D OB Dump Reclamation
Handling/Dozing of OB Dump into mine void and preparation of Internal dump for reclamation.
88.66 11444.92 71% for progressive and 17.66% for final mine closure.
Technical and Bio-reclamation including plantation and post care.
0.4 51.64 Equal Weightage throughout the life of the mine.
E Landscaping
Landscaping of the open space in leasehold area for improving its aesthetic and eco value.
0.3 38.73 Equal Weightage throughout the life of the mine.
F Plantation
Plantation over cleared area obtained after dismantling.
0.5 64.54 To be included in final mine closure plan.
Plantation around the quarry area and in safety zone.
0.2 25.82 Equal Weightage throughout the life of the mine.
Plantation over the external OB Dump 0.02 2.582 Equal Weightage throughout the life of the mine.
G Post Closure Env Monitoring/Testing of Parameters for three years.
For three years after mine closure
Air Quality 0.22 28.40 Water Quality 0.2 25.82
H Entrepreneurship development (vocational/ skill development) Training for sustainable income of affected people.
0.26 33.56 Equal Weightage throughout the life of the mine.
I Miscellaneous and other mitigative measures.
2 258.18 Equal Weightage throughout the life of the mine.
J Post Closure Man power cost for supervision
0.8 103.27 To be included in final mine closure plan.
TOTAL 100% 12908.78
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 60 Executive Summary
ESTIMATE OF PROPOSED ESCROW FUND
The total area involved in proposed Pauni-II Expansion OC Mine is 1152.66 Ha.
Out of this area, provision for mine closure plan of 21.61 ha land is already made
in nearby Pauni OC mine. Hence, in this PR, provision for mine closure plan has
been made for 1131.05 ha land only. So the corpus based on August, 2009 rate
is 67.863 crores @ Rs 6.0 Lakh /ha of project Area. The wholesale price Index in
August, 2009 is 129.6 and the WPI for the month of March, 2015 available in the
website of Office of Economic Adviser, Ministry of Commerce, Government of
India is 176.1(provisional). So the current value of corpus for 2015-16 is Rs.
67.863*176.1/129.6 crores which comes to Rs.92.2120 crores. This corpus is to
be divided by the life of mine which is 14 years in case of Pauni-II Expansion OC
Mine (starting from the year when mining activity is started, i.e. 1st year till the end
of the mine i.e. 14th year). The mine is proposed to start production from 2nd year
(2016-17), however, the activities like consent of opening of mine and Escrow
account opening will have to be completed in 1st year (2015-16). So dividing by
14 years, the annual corpus comes to Rs 6.5866 crores. The above annual
corpus amount calculated for 1st year will be deposited in escrow a/c in 1st year
of mine i.e. 2015-16. Thereafter in each subsequent year, the annual corpus
amount will be deposited by escalation @ 5% per annum.
Annual Corpus Fund to be Deposited in Escrow Account
Project Year Financial Year Amounts (Rs. ‘000) 1 2015-16 65866
2 2016-17 69159
3 2017-18 72617
4 2018-19 76248
5 2019-20 80060
6 2020-21 84063
7 2021-22 88266
8 2022-23 92680 9 2023-24 97314
10 2024-25 102179 11 2025-26 107288
12 2026-27 112653
13 2027-28 118285
14 2028-29 124200 Total Corpus Fund 1290878
Closure Cost per tonne Rs. 42.14/t
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 61 Executive Summary
19.0 MANPOWER & PRODUCTIVITY
The manpower requirement for proposed Pauni-II Expansion OC Mine is 242 in
total hiring option. The manpower requirement for proposed project has been
calculated on the basis of 3 shift operation for 330 days in a year. The
manpower requirement for this project has been detailed in Appendix-B
and B.1 of the project report. The OMS including Welfare manpower works out
to 50.87 t.
Manpower Requirement
Sl. No. Particulars Total Hiring Option
1. Executives 28
2. Non-executives:
i) Monthly rated staff 81
ii) Daily rated staff 133
3. Total 242
20.0 PROJECT IMPLEMENTATION SCHEDULE
The proposed Pauni-II Expansion OC Mine is expansion of Pauni-II OC in West
of Pauni Extension block. Pauni-II OC (Quarry-I) is on-going project and land
acquisition is under process. In this PR, initial one year (2015-16) has been
earmarked for land acquisition in Quarry-I and coal production has been
envisaged from 2nd year (2016-17) onwards. Quarry-I will achieve target capacity
of 0.75 Mty in 4th year.
In Quarry-II, land will be acquired in initial two years (2015-16 & 2016-17) and
coal production will start from 3rd year (2017-18) onwards. The mine will achieve
target capacity of 2.50 Mty in 6th year.
Thus, the Pauni-II Expansion OC Mine as a whole will start production in 2nd year
(2016-17) and will achieve target production of 3.25 Mty in 6th year. As this is a
Greenfield project, all the infrastructural facilities have been provided
independently in order to ensure its proper development.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 62 Executive Summary
The two main phases in project construction would be Pre - Sanction and Post -
Sanction phases. Some major activities under both heads are detailed in
following table.
PRE AND POST SANCTION ACTIVITIES BEFORE STARTING EXCAVATION
Pre Sanction Activities Post Sanction activities before
starting excavation
Detailed surveying of the area
Preparation of budgetary estimates
for construction of various
infrastructural facilities like ,
Workshop, VTC Building, Approach
Road etc.
Dialogue with State Government and
other appropriate authorities to
expedite various statutory clearances.
Posting of core management group.
Dialogue with MAHAGENCO to
finalise sources of power supply and
diversion of power line passing over
the Property.
Getting various statutory clearances.
Soil investigation for construction
work.
Procurement of HEMM and OPM
equipment. Creating facilities for
erection and commissioning of
equipment.
Preparation and submission of EMP Starting construction of permanent
approach road.
Dialogue with State Government and
other appropriate authorities for
diversion of road
Starting construction of workshop, pit
office etc.
Dialogue with State Government and
other appropriate authorities for
diversion of Nalas
Selection and training of manpower
for the project as per manpower
budget.
Proposal for various scientific studies.
Construction of Railway siding
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 63 Executive Summary
21.0 PROJECT ECONOMICS
Considering recommendations of EAC of MOEF, the Amalgamated PR for
Pauni-II & Pauni-III OC mine is being renamed as PR for Pauni-II Expansion
OC mine. No change has been made in mine economics of approved PR
(June,2015). Thus, this project report involves expansion of Pauni-II OC in
adjacent Pauni-III geological block and is named as PR for Pauni-II
Expansion OC mine.
Proposed PR for Pauni-II Expansion OC Mine has been prepared for Total Hiring
Option considering leasing/out sourcing of HEMM for excavation, transport,
drilling, dozing, Dumping etc. for Top OB, coal and Parting. Blasting, surface
illumination, pumping, CHP, supervision etc. would be done departmentally. Mine
target is 3.25 Mty and the weighted average GCV of coal works out to 4817
kCal/kg (calculated).
21.1 EXISTING CAPITAL AND ADDITIONAL CAPITAL WITH PHASING
The total estimated capital investment for the proposed Pauni-II Expansion OC
Mine, having an annual capacity of 3.25 Mty of coal and 22.25 Mm3/y of Peak
OB, works out to Rs. 499.0042 crores (including existing assets as on 31/3/2015
worth Rs. 15.3094 crores). Additional capital requirement for proposed Pauni-II
Expansion OC Mine works out to Rs 483.6948 crores. The phasing of capital has
been given in Appendix- A. The summarised form of Appendix-A is given in Table
below.
Initial Capital Investment (Total Hiring Option)
A/c Head
Particulars
Capital Provisions ( in Rs. Crores )
Total Capital (Existing
+Additional)
Existing as on
31.3.2015
Additional Capital
01 Land 318.5859 0.0000 318.5859 02 Service & Residential 3.6556 0.0000 3.6556
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 64 Executive Summary
Buildings
A/c Head
Particulars
Capital Provisions ( in Rs. Crores )
Total Capital (Existing
+Additional)
Existing as on
31.3.2015
Additional Capital
03 Plant & Machinery 84.6888 0.0000 84.6888 04 Furniture & Fittings 0.3000 0.0000 0.3000 05 Railway Siding 0.0000 0.0000 0.0000 06 Vehicles 0.2724 0.0000 0.2724 07 Prospecting & Boring 12.8946 12.5626 0.3320 08 Mine Development 74.0576 1.9665 72.0911 09 Revenue Expenditure
Capital. 4.5493 0.7803 3.7690
Total 499.0042 15.3094 483.6948
21.2 BASIS OF PRICE OF P&M & CIVIL WORKS
The pricing of P&M is based on the standard price list of August, 2014 (Updated
upto April’2015) circulated by the specialist cell of CMPDI, Ranchi. The cost of
civil works has been estimated on the basis of Cost Index of 560 at
Maharashtra as on 1st half of the year 2015 with a base of 100 in Delhi as on
1.1.1992. The other cost indices taken in costing are as under:-
Indices AICPI WPI Diesel Cost
for Hiring rate Electricity
Cost Value 5767.34 for the period
1.12.14 to 28.2.15 for non Executives
176.1 (prov.
March’2015)
Rs. 53.46 /lit.
(April,2015)
Rs. 10.19/kWh
21.3 OPENING OF REVENUE ACCOUNT AND COMMERCIAL READINESS
The mine is proposed to be in revenue from 2nd year.
Commercial Readiness
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 65 Executive Summary
A project will be treated to have reached the stage of commercial readiness to
yield production on a sustainable basis, from the year when all the following
criteria have been achieved :
i) 30% of the total volume of excavation (coal and OB) envisaged in the
target year
ii) The land required for the project upto target year has been acquired.
Within the above mentioned construction period, the project is in commercial
readiness, as it would be able to yield production on sustainable basis and most
of the infrastructure facilities like Road, CHP, Workshop, Service Building, Power
Supply, Water Supply and Development activities for mine operation, would be
completed and accordingly, capital provision has been made. In this Proposed
Project, the mine will have cash surplus in the 2nd year of operation (including
one year for land acquisition).
21.4 REPLACEMENT CAPITAL Yearwise replacement capital is indicated in cash flow statement (App.-D)
21.5 SOURCES OF FINANCE: INTERNAL RESOURCES OR LOAN The source of finance will be through internal resources.
21.6 COMPLETION COST
The completion cost for the project works out to Rs. 573.3813 crores. (excluding
existing assets of Rs. 15.3094 crores.)
21.7 COST OF PRODUCTION AT DIFFERENT LEVEL OF PRODUCTION:
A) SALARIES & WAGES COST
The detail of category-wise /scale-wise manpower requirement and year-wise
estimated wages cost is given in appendix-B.1. The estimated salaries & wages
cost works out to Rs. 70.31/t at 100% target capacity.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 66 Executive Summary
B) STORES COST
Stores cost has been estimated taking into account provision for repair &
maintenance, POL, explosive, and miscellaneous stores cost. The estimated
stores cost has been worked out to Rs. 89.26/t at 100% target capacity.
C) POWER COST
The average power cost per tonne of coal production works out to Rs. 55.88/t at
100% capacity.
D) MISC. EXPENDITURE
This cost has been estimated to cover expenditure on printing & stationary,
postage, telephone, repair & maintenance of assets other than P&M, workshop
debit, ins. & taxes for vehicles and other repairs and a further provision has been
made for deterioration of coal stock. The miscellaneous cost per tonne of coal
production works out to Rs. 55.48 at 100% level of operation.
E) ADMINISTRATIVE CHARGES
As per decision taken in 310th meeting of CIL Board, administrative charges shall
be taken as 10% of Administrative overhead as communicated by WCL for
financial year 2014-15. Accordingly the administrative cost works out to Rs.
16.85/t at 100% capacity. However, the above decision of CIL Board is subject to
vetting by Institute of Cost Accountants of India.
F) HIRING / OUTSOURCING COST
The average outsourcing cost per tonne of coal production works out to Rs.
376.80 at 100% level of operation.
G) INTEREST ON WORKING CAPITAL
Interest on working capital (@ 14.50%) works out to Rs. 34.45/t at 100%
capacity.
H) DEPRECIATION
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 67 Executive Summary
Straight line method of depreciation has been considered to arrive at depreciation
cost per tonne of coal production. The depreciation cost works out to Rs. 113.56
per tonne at 100 % capacity.
I) INTEREST ON LOAN CAPITAL
Interest @ 11.50% on loan capital has been computed based on given debt
equity mix. Interest on loan capital works out to Rs. 50.00 /t.
J) ENVIRONMENT RELATED COST
Rs. 6.00/t of coal has been provided for environmental related cost in the project
at 100% capacity utilization.
K) MINE CLOSURE COST
Rs. 42.14 /t have been provided in the project against mine closure cost at 100%
target production.
L) COST OF PRODUCTION
Total cost of production works out to be Rs. 910.73/t and Rs. 975.53/t at 100%
and at 85% of target capacity respectively.
21.8 GRADE OF COAL & WEIGHTED AVERAGE SELLING PRICE
The weighted average GCV of coal works out to 4817 kCal/kg (Grade G-9)
(calculated). The selling price of coal of G-9 Grade is Rs.1190.50/t. for Power
Fertilizer and Defense sector, whereas for Other than Power, Fertilizer and
Defence Sector the selling price is Rs. 1570.50/t.
- TRANSPORTATION / LOADING / SIZING CHARGES
Rs. 79.00/t. has been considered for sizing charges for coal upto (-) 100 mm size.
- DESPATCH OF COAL & POINT OF SALE.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 68 Executive Summary
Coal from the face would be dispatched to coal stock yard. From stock to CHP it
will be transported by tippers. Capital provision for railway siding has not been
made in this PR. Railway siding/Silo will be constructed through separate
scheme.
21.9 PROFITABILITY (PROFIT/LOSS)
The profit with average sale value of coal as Rs. 1190.50/t for power fertilizer
and defense sector works out to be Rs. 279.77/t and Rs. 214.97/t at 100%
and 85% target capacity respectively. The Profit with average sale value of
coal as Rs. 1570.50/t for other than power, fertilizer and defence sector works
out to Rs. 659.77/t and Rs. 594.97/t at 100% and 85% capacity respectively.
21.10 MANPOWER & OMS
The total requirement of manpower works out to 242 giving OMS of 50.87 t. This
includes provision for leave/ sickness. Details of manpower requirement and
manpower analysis are given in Appendix-B and B.1of this report.
21.11 EMS
The overall EMS works out to Rs. 3288.21 based on CMPDI norms. The salary
& wages works out to Rs. 70.31/t.
21.12 FINANCIAL IRR
The IRR of the project at 100% and 85% capacity works out to 17.71% &
12.67% for power sector.
The IRR of the project at 100% and 85% capacity works out to 34.40% &
28.13% for Non-Power sector.
21.13 DESIRED SELLING PRICE:
The desired selling price to yield 12% IRR at 100% and 85% of target production
works out to Rs.1182.05/t and Rs.1087.40/t respectively. Appendix-C shows the
estimates of cost of production at various production levels.
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 69 Executive Summary
21.14 SENSITIVITY ANALYSIS
Risk analysis and its impact on IRR, NPV (@ 12%) and Desired selling price at
discounting rate of 12% have been studied due to change in different parameters
such as Land capital cost, Mine development capital cost, Salary and wages
cost, Store cost, Power cost, Operating cost, sales realization and capacity
utilization etc. The risk analysis for power Sector is given in table below:
RISK ANALYSIS FOR POWER SECTOR
PARAMETERS 0% 5% 10% 15% 20% 25% 50% 100%
INCREASE IN LAND
IRR 17.71% 17.03% 16.37% 15.74% 15.15% 14.57% 12.04% 8.14% NPV 130.4111 117.4852 104.5594 91.6336 78.7078 65.7820 1.1530 -128.1051
Sale Price for 12% IRR (Rs,.t) 1082.54 1093.24 1103.94 1114.64 1125.34 1136.04 1189.55 1296.55
INCREASE IN MINE
DEVELOP -MENT EXP
( A.8.1)
IRR 17.71% 17.62% 17.52% 17.43% 17.33% 17.24% 16.77% 15.87% NPV 130.4111 128.5242 126.6374 124.7505 122.8637 120.9769 111.5427 92.6743
Sale Price for 12% IRR (Rs,.t) 1082.54 1084.10 1085.66 1087.22 1088.79 1090.35 1098.16 1113.78
INCREASE IN CAPITAL
IRR 17.71% 16.74% 15.83% 14.97% 14.16% 13.40% 10.12% 5.38% NPV 130.4111 111.7282 93.0454 74.3625 55.6797 36.9969 -56.4173 -243.2457
Sale Price for 12% IRR (Rs,.t) 1082.54 1098 1113.47 1128.94 1144.40 1159.87 1237.21 1391.87
INCREASE IN WAGES/ SALARIES
IRR 17.71% 17.51% 17.31% 17.11% 16.91% 16.71% 15.70% 13.66% NPV 130.4111 125.7598 121.1085 116.4572 111.8059 107.1546 83.8982 37.3853
Sale Price for 12% IRR (Rs,.t) 1082.54 1086.39 1090.24 1094.09 1097.94 1101.79 1121.04 1159.55
INCREASE IN STORE
COST
IRR 17.71% 17.47% 17.23% 16.99% 16.75% 16.51% 15.28% 12.77% NPV 130.4111 124.7420 119.0730 113.4039 107.7349 102.0658 73.7206 17.0301
Sale Price for 12% IRR (Rs,.t) 1082.54 1087.23 1091.92 1096.62 1101.31 1106.00 1129.47 1176.40
INCREASE IN POWER
COST
IRR 17.71% 17.56% 17.41% 17.25% 17.10% 16.95% 16.17% 14.61% NPV 130.4111 126.8274 123.2438 119.6602 116.0766 112.4930 94.5750 58.7390
Sale Price for 12% IRR (Rs,.t) 1082.54 1085.50 1088.47 1091.44 1094.40 1097.37 1112.20 1141.87
INCREASE IN OPERATING
COST
IRR 17.71% 15.72% 13.67% 11.55% 9.36% 7.06% -6.97% -57.61% NPV 130.4111 83.7126 37.0142 -9.6843 -56.3827 -103.0812-336.5734 -803.5578
Sale Price for 12% IRR (Rs,.t) 1082.54 1121.20 1159.86 1198.52 1237.18 1275.84 1469.14 1855.74
INCREASE IN SALES
REALISATION
IRR 17.71% 20.61% 23.38% 26.03% 28.59% 31.08% 42.63% 63.32% NPV 130.4111 202.3129 274.2147 346.1165 418.0184 489.9202 849.4294 1568.4477
Sale Price for 12% IRR (Rs,.t) 1082.54 1023.01 963.49 903.96 844.44 784.91 487.29 -107.96
DECREASE IN CAPACITY UTILISATION
IRR 17.71% 16.09% 14.41% 12.67% 10.86% 8.97% -2.46% NPV 130.4111 91.7919 53.1728 14.5537 -24.0655 -62.6846 -255.7803
Sale Price for 12% IRR (Rs,.t) 1082.54 1115.63 1146.99 1182.05 1158.12 1198.60 1623.73
DECREASE IN SALES
REALISATION`
IRR 17.71% 14.65% 11.37% 7.82% 3.88% -0.60% -49.05% NPV 130.4111 58.5092 -13.3926 -85.2944 -157.1963 -229.0981-588.6073
Sale Price for 12% IRR (Rs,.t) 1082.54 1142.06 1201.59 1261.11 1320.64 1380.16 1677.79
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 70 Executive Summary
21.15 CONCLUSION
Considering recommendations of EAC of MOEF, the Amalgamated PR for
Pauni-II & Pauni-III OC mine is being renamed as PR for Pauni-II Expansion
OC mine. No change has been made in mine economics of approved PR
(June,2015).
This PR of Pauni-II Expansion OC Mine has been prepared for a target capacity
of 3.25 Mt for Total Hiring option. The entire workload of OB and coal extraction
would be catered by hiring of HEMM. Total Cost of Production is Rs. 975.53/t at
85% of target capacity. Average Sale Price of coal (Grade G-9) is Rs.1190.50/t
for Power Sector and Rs. 1570.50/t for Non Power Sector. IRR works out to
12.67% for power sector at 85% of target capacity and 28.13% for non- power
sector at 85% of target capacity in Total hiring option. The Desired Selling Price
to yield 12% IRR at 85% of target capacity is Rs. 1182.05/t.
The Project Report in Total Hiring option is yielding 12.67% IRR (> 12.00%) at
85% of target capacity for power sector, hence this option with total capital of Rs
499.0042 crores (including existing capital of Rs 15.3094 crores) may be
considered for approval by competent authority as this mine is economically
viable for approval on notified price.
The other related mining and financial parameters are as tabulated below:-
Sl. No. Particulars
Approved PR of
Pauni-II OC (July,2003) (Total hiring
option)
Approved PR of Pauni-III OC (Feb., 2010)
(Departmental Option)
Pauni-II Expansion OC Mine ( June, 2015)
Quarry-I Quarry-II Total
A Mining Parameters 01 Mineable Reserves (Mt) 4.91 24.11 5.18 25.45 30.63 02 Grade/GCV of coal (kcal/kg) G9/4775 G9/4830 G9/4775 G9/4830 (G-9)/4817 03 OB Volume (Mm3) 31.90 157.57 31.90 157.57 189.47 04 Average S/R 6.49 6.54 6.16 6.19 6.19 05 Mine Capacity (Mty) 0.60 1.25 0.75 2.50 3.25 06 Manpower 110 755 242 07 Overall OMS (t) 20.66 6.27 50.87 B Financial Parameters 01 Total Capital (Rs. In Crores) 499.0042
PR FOR PAUNI-II EXPANSION OC MINE ( JUNE’ 2015) CMPDI
Job No.4101802 Page - 71 Executive Summary
02 Additional Capital (Rs. In Crores) 28.1120 360.7987 483.6948
03 Existing Capital (as on 31.3.2015) (Rs. In Crores) 0 0 15.3094
04 Cost of Production (Rs./t) i at 100% of target capacity 632.72 1376.32 910.73 ii at 85% of target capacity 662.92 1564.85 975.53
Sl. No. Particulars
Approved PR of
Pauni-II OC (July,2003) (Total hiring
option)
Approved PR of Pauni-III OC (Feb., 2010)
(Departmental Option)
Pauni-II Expansion OC Mine ( June, 2015)
Power Non power
05 Av. Selling Price (Notified) (Rs./t)
725.85 1074.50 1190.50 1570.50
06 Profit (Rs./t)
i @ 100% of target capacity (Rs./t)
93.13 (-) 301.82 279.77 659.77
ii @ 85% of target capacity (Rs./t)
62.93 (-) 490.35 214.97 594.97
07 Financial IRR @ 85% capacity (%)
20.60 NEGATIVE 12.67 28.13
08 Price to yield 12 % IRR @ 85% capacity (Rs./t)
691.39 1801.65 1182.05 1182.05
09
Difference between Avg. Selling Price (Notified) & price to yield 12 % IRR @ 85% capacity (Rs./t)
(+) 34.46 (-) 727.15 (+) 8.45 (+) 388.45
************